LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Saturday, May 4, 2024

SUPREME COURT RULES, 2013 - Order XII, Rule 3 – Scope thereof, explained – Filing of applications after disposal of the statutory appeal: Held: Impermissible – A post disposal application for modification and clarification of an order shall lie only in rare cases, where the order passed by the Supreme Court is executory in nature and the directions of the Supreme Court have become impossible to be implemented because of certain subsequent events or developments – After disposal of an appeal / petition, the Supreme Court becomes functus officio and does not retain jurisdiction to entertain any application. [Para 20] SUPREME COURT RULES, 2013 – Practice and Procedure – Application projected as an application for clarification, though it was registered as a miscellaneous application – Practice deprecated. Code of Civil Procedure, 1908 – Order XXIII, Rule 1 – Scope thereof, explained.

* Author

[2024] 3 S.C.R. 1023 : 2024 INSC 213

Jaipur Vidyut Vitran Nigam Ltd. & Ors.

v.

Adani Power Rajasthan Ltd. & Anr.

Miscellaneous Application Diary No. 21994 of 2022

In

Civil Appeal Nos. 8625 – 8626 of 2019

18 March 2024

[Aniruddha Bose* and Sanjay Kumar, JJ.]

Issue for Consideration

When can a litigant apply for modification of a judgment or an

order in a matter which stands finally concluded; and can a party

file an application after disposal of the statutory appeal by invoking

inherent powers of the Supreme Court.

Headnotes

SUPREME COURT RULES, 2013 - Order XII, Rule 3 – Scope

thereof, explained – Filing of applications after disposal of

the statutory appeal:

Held: Impermissible – A post disposal application for modification

and clarification of an order shall lie only in rare cases, where the

order passed by the Supreme Court is executory in nature and

the directions of the Supreme Court have become impossible

to be implemented because of certain subsequent events or

developments – After disposal of an appeal / petition, the Supreme

Court becomes functus officio and does not retain jurisdiction to

entertain any application. [Para 20]

SUPREME COURT RULES, 2013 – Practice and Procedure –

Application projected as an application for clarification, though

it was registered as a miscellaneous application – Practice

deprecated.

Code of Civil Procedure, 1908 – Order XXIII, Rule 1 – Scope

thereof, explained.

Held: There are two Orders in the Supreme Court Rules, 2013

which permit review of a judgment or an order of the Supreme

Court, Orders XLVII and XLVIII – The former Order, contained in 

1024 [2024] 3 S.C.R.

Digital Supreme Court Reports

Part IV of the 2013 Rules, relates to “Review of a Judgment” and

the latter relates to “Curative Petition” – There is no other provision

in the 2013 Rules, whereby a litigant can apply for modification of

a judgment or an order of the Supreme Court in a matter which

stands finally concluded – By taking out a Miscellaneous Application,

the applicant cannot ask for reliefs which were not granted in the

main judgment itself. [Para 10]

Through this miscellaneous application, the applicant seeks a

direction upon the Rajasthan Discoms for making payment of

Rs.1376.35 crores – The present application has been captioned

as “APPLICATION FOR DIRECTIONS ON BEHALF OF THE

RESPONDENT NO.1/APPLICANT (ADANI POWER RAJASTHAN

LIMITED)” in the said appeals which stood disposed of by a

common judgment of a three-Judge Bench of the Supreme

Court delivered on 31.08.2020 – Review petitions filed against

this judgment by the Rajasthan Discoms stood dismissed on

02.03.2021. [Para 2]

In the course of hearing, it was projected as an application for

clarification, though the same was registered as a miscellaneous

application – The reliefs asked for in this application do not refer

to any clarification. [Para 9]

The applicant had expressed its desire to withdraw the present

application on the last date of hearing, i.e., 24.01.2024 – The

Supreme Court, however, decided not to permit such simpliciter

withdrawal – Even if an applicant applies for withdrawal of an

application, in exceptional cases, it would be within the jurisdiction of

the Supreme Court to examine the application and pass appropriate

orders – So far as the present proceeding is concerned, an important

question of law has arisen as regards jurisdiction of the Supreme

Court to entertain an application taken out in connection with a set

of statutory appeals which stood disposed of – Judgment of the

Supreme Court in Supertech Limited v. Emerald Court Owner

Resident Welfare Association & Others, (2023) 10 SCC 817

deals with this question and the ratio of the said judgment would

apply to the present proceeding as well. [Para 19]

The Supreme Court becomes functus officio and does not retain

jurisdiction to entertain an application after the appeal was disposed

of by the judgment of a three-Judge Bench of the Supreme

Court – This is not an application for correcting any clerical or

arithmetical error – Neither it is an application for extension of 

[2024] 3 S.C.R. 1025

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

time – A post disposal application for modification and clarification

of the order of disposal shall lie only in rare cases, where the

order passed by the Supreme Court is executory in nature and the

directions contained in the judgment may become impossible to

be implemented because of subsequent events or developments–

The factual background of this Application does not fit into that

description. [Para 20]

SUPREME COURT RULES, 2013 - Order XII, Rule 3 read with

Rule 6 of Order LV – Filing of applications after disposal of the

statutory appeal by invoking inherent powers of the Supreme

Court – Held, impermissible.

Held: The maintainability of the present application cannot be

explained by invoking the inherent power of the Supreme Court

either – The applicant has not applied for review of the main

judgment – In the contempt action, it failed to establish any wilful

disobedience of the main judgment and order – Now the applicant

cannot continue to hitchhike on the same judgment by relying on

the inherent power or jurisdiction of this Court. [Para 13]

Code of Civil Procedure, 1908 – Section 152 read with Order XII,

Rule 3 of the SUPREME COURT RULES, 2013 – Rectification

of an arithmetic order – permissibility thereof.

Held: A miscellaneous application had been filed for modification

of the content of judgment dated 1st September 2020 passed

in M.A. (D) No. 9887 of 2020 in Civil Appeal Nos. 6328-6399

of 2015 – In the said proceeding, clarification was also sought

on the aspect that the judgment did not bar the Union of India

from considering and rectifying the clerical/arithmetical errors

in computation of certain dues – This was an order permitting

rectification of an arithmetic error, which is implicit in Section 152

of the CPC read with Order XII Rule 3 of the 2013 Rules. [Para 18]

Code of Civil Procedure, 1908 – Section 148 read with Section

112 - Power of the Supreme Court to extend time.

Held: The power to extend time beyond that fixed by a Court on a

legitimate ground is incorporated in Section 148 of the CPC – If the

time to do something requires to be extended, it would be within

the inherent jurisdiction of the Supreme Court to go beyond the

maximum period of 30 days prescribed in the aforesaid Section,

after sufficient reason is shown – Section 112 of the Code itself

provides that nothing contained in the CPC shall affect the inherent 

1026 [2024] 3 S.C.R.

Digital Supreme Court Reports

powers of the Supreme Court under Article 136 or any other

provision of the Constitution. [Para 17]

SUPREME COURT RULES, 2013 - Order XII, Rule 3 – Imposition

of costs on filing of applications after disposal of the statutory

appeal.

Held: The Supreme Court dismissed the present application and

imposed costs of Rs. 50,000/- to be paid by the applicant to be

remitted to the Supreme Court Legal Aid Committee as it was

listed several times. [Para 23]

Case Law Cited

Ghanashyam Mishra & Sons Private Limited v.

Edelweiss Asset Reconstruction Company Limited,

[2021] 13 SCR 738 : M. A. No. 1166 of 2021 in CA

No. 8129 of 2019 – relied on.

Supertech Limited v. Emerald Court Owner Resident

Welfare Association & Others [2021] 10 SCR 569 :

(2023) 10 SCC 817 – Relied on.

State (UT of Delhi) v. Gurdip Singh Uban and Others

[2000] Suppl. 2 SCR 496 : (2000) 7 SCC 296; Sone

Lal and Others v. State of Uttar Pradesh (1982) 2 SCC

398; Ram Chandra Singh v. Savitri Devi and Others

[2003] Suppl. 4 SCR 543; (2004) 12 SCC 713; Common

Cause v. Union of India and Others (2004) 5 SCC 222;

Zahira Habibullah Sheikh and Another v. State of Gujarat

and Others [2004] Suppl. 2 SCR 571 : (2004) 5 SCC

353; P.N. Eswara Iyer and Others v. Registrar, Supreme

Court of India [1980] 2 SCR 889 : (1980) 4 SCC 680;

Suthendraraja alias Suthenthira Raja alias Santhan

and Others v. State through DSP/CBI, SIT, Chennai

[1999] Suppl. 3 SCR 540 : (1999) 9 SCC 323; Ramdeo

Chauhan alias Raj Nath v. State of Assam [2001] 3 SCR

669 : (2001) 5 SCC 714; Devendra Pal Singh v. State

(NCT of Delhi) and Another [2002] Suppl. 5 SCR 332

: (2003) 2 SCC 501; Rashid Khan Pathan in re (2021)

12 SCC 64 – referred to.

Energy Watchdog v. Central Electricity Regulatory

Commission and Others, MA Nos. 2705 – 2706 of 

[2024] 3 S.C.R. 1027

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

2018 in Civil Appeal Nos. 5399 – 5400 of 2016;

Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. V. Adani

Power (Mundra) Limited, MA (D) No. 18461 of 2023 in

Civil Appeal No. 2908 of 2022; Kalpataru Properties

Pvt. Ltd. v. Indiabulls Housing Finance Ltd., MA No.

2064 of 2022 in Civil Appeal No. 7050 of 2022;

Supertech Limited v. Emerald Court Owner Resident

Welfare Association & Ors., MA No. 1918 of 2021

in Civil Appeal No. 5041 of 2021; Union of India v.

Association of Unified Telecom Service Providers of

India and Ors., MA No. 83 of 2021 in MA (D) No.

9887 of 2020 in Civil Appeal No. 6328-6399 of

2015] – distinguished.

List of Acts

Code of Civil Procedure, 1908; Supreme Court Rules, 2013.

List of Keywords

Miscellaneous Application, Clarification Application, Modification

Application, Costs, Inherent Powers, Maintainability, Post Dismissal

Application.

Case Arising From

CIVIL APPELLATE JURISDICTION : Miscellaneous Application Diary

No.21994 of 2022

In

Civil Appeal Nos.8625-8626 of 2019

From the Judgment and Order dated 31.08.2020 in C. A. Nos.8625-

8626 of 2019 of the Supreme Court of India

Appearances for Parties

Dushyant Dave, Sr. Adv., Kartik Seth, Anshul Chowdhary, Prashanth

R. Dixit, Ms. Arushi Rathore, Abhishek Kandwal, Amit Goyal, Mahesh

Bhati, Saurabh Chaturvedi, M/s. Chambers of Kartik Seth, Advs. for

the Appellants.

Dr. A.M. Singhvi, Sr. Adv., Mahesh Agarwal, Ms. Poonam Sengupta,

Arshit Anand, Shashwat Singh, Ms. Sakshi Kapoor, Saunak Rajguru,

Sidharth Seem, E. C. Agrawala, Advs. for the Respondents/Applicants.

1028 [2024] 3 S.C.R.

Digital Supreme Court Reports

Judgment / Order of the Supreme Court

Judgment

Aniruddha Bose, J.

The applicant, Adani Power Rajasthan Limited (APRL), is a generating

company as per Section 2(28) of the Electricity Act, 2003 (“2003

Act”). It operates a thermal power plant in the State of Rajasthan.

There were three appellants (1 to 3) in the main set of appeals, in

connection with which the present application has been taken out,

being the distribution licensees of the State of Rajasthan as per the

provisions of the 2003 Act. They shall, henceforth in this judgment,

be collectively referred to as “Rajasthan Discoms”. Rajasthan Urja

Vikas Nigam Limited was the 4th appellant in the main set of appeals.

It appears to have been formed by the Government of Rajasthan for

the purpose of coordination among the aforesaid three Discoms, as

also other distribution licensees of the State.

2. Through this miscellaneous application, the applicant seeks a direction

upon the Rajasthan Discoms for making payment of Rs.1376.35

crore towards Late Payment Surcharge (“LPS”). This claim has been

raised by the applicant citing Article 8.3.5 of the Power Purchase

Agreement dated 28.01.2010 (“PPA-2010”) entered into between

the Rajasthan Discoms and the applicant. The present application

has been captioned as “APPLICATION FOR DIRECTIONS ON

BEHALF OF THE RESPONDENT NO.1/APPLICANT (ADANI

POWER RAJASTHAN LIMITED)” in the said appeals which stood

disposed of by a common judgment of a three-Judge Bench of this

Court delivered on 31.08.2020. Review petitions filed against this

judgment by the Rajasthan Discoms stood dismissed on 02.03.2021.

3. The appeals arose out of a dispute involving certain additional

payments claimed by the applicant as per the PPA-2010. Under the

agreement, the applicant was to supply electricity to the Rajasthan

Discoms, which had to be generated by the applicant. For this

purpose, the PPA-2010 postulated domestic coal as the primary

source of energy, while imported coal was to be used as a backup

option. The applicant’s complaint was that, due to non-availability

of sufficient domestic coal, it could not be allocated a domestic coal

linkage by the Government of India and it was compelled to rely on

imported coal from Indonesia, which had a higher cost. Claim for

compensation of loss, caused on account of non-supply of domestic 

[2024] 3 S.C.R. 1029

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

coal, was raised by the applicant before the Rajasthan Electricity

Regulatory Commission (“RERC”), invoking the change in law clause

of the PPA-2010. Change in law was one of the conditions under

the PPA-2010, for which tariff adjustment payment could be made

by the seller of electricity following the procedure stipulated in the

aforesaid agreement. By an order dated 17.05.2018, RERC held

that the applicant would be entitled to relief on account of change

in law, which was held to be the difference between actual landed

cost of alternative/imported coal (as certified by the auditor) and

actual landed cost of domestic linkage coal. This was recorded in

an order passed on 25.02.2022 by a Coordinate Bench of this Court

in a contempt action brought by the applicant [Contempt Petition

(Civil) No(s) 877-878 of 2021]. We shall refer to the said proceeding

later in this judgment. We also need not delve into the question of

eligibility of the applicant to get additional sum on account of change

in law, as that question stands finally decided in the main judgment.

4. The applicant had also raised another claim for additional payment

before the RERC, under the head of carrying cost which was

disallowed by the RERC. Rajasthan Discoms, being aggrieved by

the grant of change-in-law compensation, as also the applicant, being

aggrieved by rejection of the claim for carrying costs appealed against

the order of the RERC before the Appellate Tribunal for Electricity

(“APTEL”). By a common decision dated 14.09.2019, the APTEL

found that the applicant’s claim based on “change in law” was valid

and opined that the applicant was entitled to compensation for the

loss caused to it because of change in law under a subsequent coal

supply scheme, termed as the SHAKTI scheme, which failed to provide

domestic coal linkage. The APTEL further found that the applicant

would also be entitled for payment towards applicable carrying cost.

The Rajasthan Discoms had appealed against the common decision

of APTEL before this Court. The three-Judge Bench of this Court,

by the judgement dated 31.08.2020, dismissed the appeals with the

following observations and directions: -

“66. Considering the facts of this case and keeping in

view that the RERC and APTEL have given concurrent

findings in favour of the respondent with regard to change

in law, with which we also concur, we may now deal with

the question of liability of appellants-Rajasthan Discoms

with regard to late payment surcharge. In this regard, the 

1030 [2024] 3 S.C.R.

Digital Supreme Court Reports

following Articles 8.3.5 and 8.8 of PPA, which are relevant

for the present purpose, are extracted hereunder:

“8.3.5. In the event of delay in payment of a Monthly Bill

by the Procurers beyond its Due Date, a Late Payment

Surcharge shall be payable by such Procurers to the Seller

at the rate of two percent (2%) in excess of the applicable

SBAR per annum, on the amount of outstanding payment,

calculated on a day to day basis (and compounded with

monthly rest), for each day of the delay. The Late Payment

Surcharge shall be claimed by the Seller through the

Supplementary Bill.

8.8 Payment of Supplementary Bill

8.8.1 Either Party may raise a bill on the other Party

(supplementary bill) for payment on account of:

i) Adjustments required by the Regional Energy

Account (if applicable):

ii) Tariff Payment for change in parameters,

pursuant to provisions in Schedule 4; or

iii) Change in Law as provided in Article 10, and

such Supplementary Bill shall be paid by the

others party.

8.8.2 The Procurers shall remit all amounts due

under a Supplementary Bill raised by the Seller to

the Seller’s Designated Account by the Due Date and

notify the Seller of such remittance on the same day

or the Seller shall be eligible to draw such amounts

through the Letter of Credit. Similarly, the Seller shall

pay all amounts due under a Supplementary Bill

raised by Procurer(s) by the Due Date to concerned

Procurer’s designated bank account and notify such

Procurer(s) of such payment on the same day.

For such payments by the Procurer(s), Rebate as

applicable to Monthly Bills pursuant to Article 8.3.6

shall equally apply.

8.8.3 In the event of delay in payment of a

Supplementary Bill by either Party beyond its Due 

[2024] 3 S.C.R. 1031

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

Date, a Late Payment Surcharge shall be payable

at the same terms applicable to the Monthly Bill in

Article 8.3.5.

8.9 The copies of all; notices/offers which are required

to be sent as per the provisions of this Article 8, shall

be sent by a party, simultaneously to all parties.”

Liability of the Late Payment Surcharge which has been

saddled upon the appellants is at the rate of 2% in

excess of applicable SBAR per annum, on the amount of

outstanding payment, calculated on a day to day basis

(and compounded with monthly rest) for each day of the

delay. Therefore, there shall be huge liability of payment

of Late Payment Surcharge upon the appellants-Rajasthan

Discoms.

67. With regard to the question of interest/late payment

surcharge, we notice that the plea of change in law was

initially raised by APRL in the year 2013. A case was also

filed by APRL in the year 2013 itself raising its claim on

such basis. However, the appellants-Rajasthan Discoms

did not allow the claim regarding change in law, because

of which APRL was deprived of raising the bills with effect

from the date of change in law in the year 2013. We

are, thus, of the opinion that considering the totality of

the facts of this case and in order to do complete justice

and to reduce the liability of the appellants-Rajasthan

Discoms, payment of 2 per cent in excess of the applicable

SBAR per annum with monthly rest would be on higher

side. In our opinion, it would be appropriate to direct the

appellants-Rajasthan Discoms to pay interest/late payment

surcharge as per applicable SBAR for the relevant years,

which should not exceed 9 per cent per annum. It is also

provided that instead of monthly rest, the interest would

be compounded per annum.

68. We accordingly direct that the rate of interest/late

payment surcharge would be at SBAR, not exceeding 9

per cent per annum, to be compounded annually, and the

2 per cent above the SBAR (as provided in Article 8.3.5

of PPA) would not be charged in the present case. 

1032 [2024] 3 S.C.R.

Digital Supreme Court Reports

69. Before we part with the case, we may notice that

Shri Prashant Bhushan, raised the submission with

respect to over-invoicing. He attracted our attention to the

investigation pending before the DRI. He has submitted

that 40 importers of coal are under investigation by the DRI

concerning alleged over-invoicing. The letter of rogatory

was issued. However, leamed counsel conceded that there

is no ultimate conclusion in the investigation reached so far.

Thus, we are of the opinion that until and unless there is

a finding recorded by the competent court as to invoicing,

the submission cannot be accepted. At this stage, it cannot

be said that there is over-invoicing. We have examined

the case on merits with abundant caution, and we find

that there are concurrent findings of facts recorded by the

RERC and the APTEL. With respect to the aspect that

bid was premised on domestic coal, we find that findings

recorded do not call for any interference.”

5. The applicant had filed contempt proceedings alleging disobedience

of the said judgment and order, which were registered as Contempt

Petition (C) Nos. 877-878 of 2021. We have already referred to this

proceeding. In the contempt proceeding, the applicant’s position

gets reflected in the submissions of its learned senior counsel,

recorded in paragraph 6 of the order passed on 25.02.2022 (One

of us, Aniruddha Bose, J., was a party to this order). The relevant

portion of that order is reproduced below:-

“6. Shri Abhishek Manu Singhvi, learned Senior Counsel

appearing for the petitioner has submitted that the only

dispute which was to be resolved by RERC, APTEL and

this Court was with regard to the payment due because of

“change in law”, which was held to be the actual landed

cost of alternate coal/imported coal as certified by the

auditor minus landed cost of domestic linkage coal. There

was no other dispute which was to be resolved by this

Court. Learned Senior Counsel has submitted that it is

now contended by the respondents that certain payments

have been made by the respondents which, according to

the learned Senior Counsel, was towards regular payment

on the basis of domestic linkage coal and nothing else.

Since, the “change in law” ground of the petitioner has been 

[2024] 3 S.C.R. 1033

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

accepted by all the authorities i.e. RERC, APTEL and this

Court and also confirmed by the dismissal of the Review

Petition filed before this Court, the question cannot now be

reopened at this stage. It is, thus, submitted that since the

actual landed cost of alternate coal/imported coal as was

submitted by the petitioner has been duly certified by the

auditors, which has not been disputed by the respondents,

the payment, as claimed, ought to have been made and

since the same has not been paid, the respondents are

liable for contempt. The further contention of the learned

Senior Counsel of the petitioner is that the claim of the

respondents that they had paid certain amount towards

energy charges regularly month by month, which included

certain amount of price of alternate coal/imported coal

charges cannot be accepted, as at that stage i.e. in the

year 2013, the respondents had not accepted the claim

of the petitioner with regard to “change in law”, and the

assertion now being made by the respondents that they had

paid certain amount after partially accepting the “change

in law” theory cannot be accepted, as this issue had never

been raised by respondents in any proceedings earlier, as

the respondents had, in fact, throughout contested that

the petitioner is not entitled to the “change in law” benefit.”

6. The allegations of non-compliance with the judgment of the threeJudge Bench were dealt with by the Coordinate Bench in the aforesaid

order passed on 25.02.2022. It was, inter-alia, observed and directed

in the said order:-

“9. Firstly, what we have to consider is only the effect of

“change in law”, which as per RERC, API’EL and this Court

would be the actual landed cost of alternate coal/ imported

coal minus the landed cost of domestic linkage coal. The

question of any claim which the respondents may have

against the petitioner, is not an issue before us. As per the

principle laid down by RERC and affirmed up till this Court,

the petitioner has claimed an amount of Rs.5344. 75 crores

up to March, 2021. The said principle having been affirmed

by the APTEL as well as by this Court and even in Review

Petition, cannot be reopened now. It cannot be disputed

that after March, 2021 also, the petitioner would be entitled 

1034 [2024] 3 S.C.R.

Digital Supreme Court Reports

to payment on the basis of the same calculation, which up

to November, 2021 comes to Rs.130.69 crores. As such,

the due amount up to November 2021 would be Rs.5344.

75 + Rs.130.69 = 54 75.44 crores. Out of this amount of

Rs.54 75.44 crores, the petitioner has been paid a sum

of Rs.2426.81 crores in terms of the interim order passed

by this Court. Hence, as per the petitioner, the balance

amount of Rs.3048.63 crores would remain due to be

paid up to November, 2021. The interest at the maximum

rate of 9% per annum, as capped by this Court vide its

judgment and order dated 31.08.2020, is to be applied on

the said amount, from the date the amount became due,

till the date of actual payment. The further claim of late

payment surcharge, amounting to Rs.2477.70 crores, as

per the petitioner, would be a subject matter which the

petitioner, if so advised, can claim before the appropriate

forum, as the same is not the subject in question in the

present proceedings, regarding which no directions have

also been issued by this Court.

10. As such, considering the totality of facts and

circumstances of this case, prima face we are of the

opinion that the respondents are liable for contempt for

not complying this Court’s order dated 31.08.2020. We,

thus, direct the respondents to pay to the petitioner, the

principal amount (as per the terms/norms laid down in the

judgment of this Court dated 31.08.2020) minus Rs.2426.81

crores deposited by the respondents in terms of the interim

order dated 29.10.2018 (which, as per the petitioner, the

balance payable amount would be Rs.3048.63 crores)

along with interest as per the applicable SBAR for the

relevant years, which should not exceed 9% per annum

(to be compounded annually), from the date the amount

became due till the date of actual payment, within four

weeks from today, failing which the respondents shall

appear before this Court in person, on the next date, so

as to enable this Court to frame charges.”

7. The contempt petitions were subsequently directed to be closed by

another Coordinate Bench of this Court and order to that effect was

passed on 19.04.2022. In this order, it was, inter-alia, observed:-

[2024] 3 S.C.R. 1035

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

“With regard to the first question it may only be observed

that by order dated 25.02.2022 passed in these contempt

petitions, this court, in paragraph no. 9, has observed as

under:

“The further claim of late payment surcharge,

amounting to Rs.2477.70 crores, as per the

petitioner, would be a subject matter which

the petitioner, if so advised, can claim before

the appropriate forum, as the same is not the

subject in question in the present proceedings,

regarding which no directions have also been

issued by this Court.”

As such, since according to the respondent(s) the payment

made is only towards the principal amount plus 9% interest

per annum, we are not inclined to pass any further orders

as we have already left the question of late payment

surcharge open, which the petitioner, if so advised, can

claim before the appropriate forum.

As regards the second question of the alleged noncompliance, by the respondents after November, 2021

of the judgment and order dated 31.08.2020, we would

not like to make any observation as there is neither. any

material before us with regard to that nor the same was

in question when the contempt petitions were filed. As

such, we leave this question open to be agitated by the

petitioner, of it is so advised.

With regard to the last issue raised by the respondents,

which is to the effect that the claim of the Rajasthan

Utilities against the petitioner outside the judgment dated

31.08.2020 be permitted to be made, we would only like to

observe that the same cannot be a matter to be considered

in a contempt petition and as such neither we are inclined

to grant any such relief nor stop them from raising any

such issue, if the respondents are so advised and found

entitled under the law. With the aforesaid observations,

we close these contempt petitions.”

8. After institution of the present application on 19.07.2022, it was heard

from time to time and finally on 24.01.2024, when this matter was 

1036 [2024] 3 S.C.R.

Digital Supreme Court Reports

called on for hearing, Dr. Abhishek Manu Singhvi, learned senior

counsel, appearing for the applicant, sought leave to withdraw the

application. Mr. Dushyant Dave, learned senior counsel appearing for

the Rajasthan Discoms, however, opposed such prayer and his case

was that the present application, having been taken out in an appeal

which stood disposed of, did not lie and it should be dismissed on

the ground that it is not maintainable. Mr. Dave drew our attention

to paragraph 67 of the judgment of the three-Judge Bench, which

we have quoted above. The issue of LPS has been dealt with by

the three-Judge Bench in the said passage.

9. In the course of hearing, it was projected as an application for

clarification, though the same was registered as a miscellaneous

application. The reliefs asked for in this application do not refer to

any clarification. We have referred to the substance of the reliefs

prayed for in this application earlier in this judgment.

10. Order XII Rule 3 of the Supreme Court Rules, 2013 (“2013 Rules”)

framed in pursuance of Article 145 of the Constitution of India,

stipulates:-

“3. Subject to the provisions contained in Order XLVII of

these rules, a judgment pronounced by the Court or by

a majority of the Court or by a dissenting Judge in open

Court shall not afterwards be altered or added to, save for

the purpose of correcting a clerical or arithmetical mistake

or an error arising from any accidental slip or omission.”

There are, however, two chapters in the 2013 Rules which permit

review of a judgment or order of this Court, being Order XLVII and

XLVIII. The former Order, contained in Part IV of the 2013 Rules

relates to “Review of a Judgment” and the latter relates to “Curative

Petition”. There is no other provision in the 2013 Rules, whereby a

litigant can apply for modification of a judgment or an order of this

Court in a matter which stands finally concluded. On rare occasions,

a litigant may apply for clarification of an order if the same is ex-facie

incomprehensible, but we do not expect any judgment or order to

bear such a character. So far as the applicant is concerned, it did

not apply for review of the judgment delivered by the three-Judge

Bench. Neither in the contempt action initiated by the applicant, did

this Court find that any case of willful disobedience of the judgment

of the three-Judge Bench was made out on the question of LPS. 

[2024] 3 S.C.R. 1037

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

This would be apparent from the orders passed by this Court in

the contempt petitions which have been reproduced earlier in this

judgement. The judgment of the three-Judge Bench has already

examined the question of LPS and by taking out a Miscellaneous

Application, the applicant cannot ask for reliefs which were not

granted in the main judgment itself.

11. In the case of Ghanashyam Mishra & Sons Private Limited -vsEdelweiss Asset Reconstruction Company Limited [M.A. No. 1166

of 2021 in CA No. 8129 of 2019], a two-Judge Bench of this Court

in its judgment delivered on 17th August 2022 observed and held:-

“4. Having heard learned senior counsel for the parties

and having perused the relevant materials placed on

record, we are of the considered view that the present

applications are nothing else but an attempt to seek review

of the judgment and order passed by this Court on 13th

April 2021 under the garb of miscellaneous application.

5. We find that there is a growing tendency of

indirectly seeking review of the orders of this Court

by filing applications either seeking modifications or

clarifications of the orders passed by this Court.

6. In our view, such applications are a total abuse of

process of law. The valuable time of Court is spent in

deciding such application which time would otherwise

be utilized for attending litigations of the litigants who

are waiting in the corridors of justice for decades

together.”

(emphasis supplied)

12. Subsequently in the judgment of this Court in the case of Supertech

Limited-vs- Emerald Court Owner Resident Welfare Association

& Others [(2023) 10 SCC 817], a two-Judge Bench of this Court

examined the maintainability of miscellaneous applications “for

clarification, modification or recall” and was pleased to observe the

following in the context of that case:-

“12. The attempt in the present miscellaneous application is

clearly to seek a substantive modification of the judgment

of this Court. Such an attempt is not permissible in a

miscellaneous application. While Mr Mukul Rohatgi, learned 

1038 [2024] 3 S.C.R.

Digital Supreme Court Reports

Senior Counsel has relied upon the provisions of Order

LV Rule 6 of the Supreme Court Rules, 2013, what is

contemplated therein is a saving of the inherent powers of

the Court to make such orders as may be necessary for

the ends of justice or to prevent an abuse of the process

of the Court. Order LV Rule 6 cannot be inverted to bypass

the provisions for review in Order XLVII of the Supreme

Court Rules, 2013. The miscellaneous application is an

abuse of the process.”

The authorities which were cited in the said Judgment by the

Coordinate Bench are the cases of State (UT of Delhi) -vs- Gurdip

Singh Uban and Others [(2000) 7 SCC 296], Sone Lal and Others

-vs- State of Uttar Pradesh [(1982) 2 SCC 398], Ram Chandra

Singh -vs- Savitri Devi and Others [(2004 12 SCC 713], Common

Cause -vs- Union of India and Others [(2004) 5 SCC 222], Zahira

Habibullah Sheikh and Another -vs- State of Gujarat and Others

[(2004) 5 SCC 353], P.N. Eswara Iyer and Others -vs- Registrar,

Supreme Court of India [(1980) 4 SCC 680], Suthendraraja alias

Suthenthira Raja alias Santhan and Others -vs- State through

DSP/CBI, SIT, Chennai [(1999) 9 SCC 323], Ramdeo Chauhan

alias Raj Nath -vs- State of Assam [(2001) 5 SCC 714], Devendra

Pal Singh -vs- State (NCT of Delhi) and Another [(2003) 2 SCC

501] and Rashid Khan Pathan in re, [(2021) 12 SCC 64]. These

authorities broadly stipulate that multiple attempts to reopen a

judgment of this Court should not be permitted. Hence, we do not

consider it necessary to deal with these authorities individually.

13. Rule 6 of Order LV of the 2013 Rules stipulates: -

“6. Nothing in these rules shall be deemed to limit or

otherwise affect the inherent powers of the Court to make

such orders as may be necessary for the ends of justice

or to prevent abuse of the process of the Court.”

The maintainability of the present application cannot be explained by

invoking the inherent power of this Court either. The applicant has

not applied for review of the main judgment. In the contempt action,

it failed to establish any willful disobedience of the main judgment

and order on account of non-payment of LPS. Now the applicant

cannot continue to hitchhike on the same judgment by relying on

the inherent power or jurisdiction of this Court. 

[2024] 3 S.C.R. 1039

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

14. Appearing on behalf of the applicant, Dr. Singhvi, learned Senior

Counsel, relied on five orders of this Court in which post-disposal

applications were entertained. The first one was an order dated

29.10.2018 in the case of Energy Watchdog -vs- Central Electricity

Regulatory Commission and Others, [MA Nos.2705-2706 of 2018

in Civil Appeal Nos.5399-5400 of 2016]. In that case, an application

for impleadment on behalf of the State of Gujarat was allowed, upon

going through a High Power Committee’s report, which was given

after the judgment was delivered. The judgment disposing of the

Civil Appeal was delivered on 11.04.2017, but in the miscellaneous

application, the applicant was given liberty to approach the Central

Electricity Regulatory Commission for approval of the proposed

amendments to be made to a power purchase agreement. That

was a case where this Court, after the judgment was delivered,

considered certain events which accrued subsequently and had a

bearing on the main decision. The subsequent event was taken into

account for modifying the order but there was no substantive change

in the judgment itself.

15. The next order, on which Dr. Singhvi placed reliance, was passed

on 04.05.2023 in the case of Uttar Haryana Bijli Vitran Nigam Ltd.

& Anr. -vs- Adani Power (Mundra) Limited [MA (D) No. 18461 of

2023 in Civil Appeal No.2908 of 2022]. The substantive part of the

order is contained in Paragraph 2 thereof and this paragraph reads:-

“2. As agreed by the learned counsel for the parties, the

words “As per the details given in the PPA, the mode of

transportation is through railway” shown in paragraph 32

of the judgment dated 20.04.2023 passed in C.A. No. 2908

of 2022 be read as “As per the details given in the FSA,

the mode of transportation is through railway”.

But this order appears to be in the nature of correcting an error

which was clerical in nature and the Code of Civil Procedure, 1908

(“the Code”) itself provides for such correction under Section 152

thereof, as also Order XII Rule 3 of the 2013 Rules.

16. The third order relied on by Dr. Singhvi was passed on 09.12.2022 in

the case of Kalpataru Properties Pvt. Ltd. -vs- Indiabulls Housing

Finance Ltd. [MA No.2064 of 2022 in Civil Appeal No.7050 of 2022].

The applicant therein had approached this Court contending that he

was not heard when the civil appeal was decided. In that case, the 

1040 [2024] 3 S.C.R.

Digital Supreme Court Reports

appellant had approached this Court against an Order passed by

NCLAT in Company Appeal (AT)(Insolvency) No. 880/2021 and the

said appellant sought to withdraw the appeal on deposit of certain

amount by the first respondent in the said appeal. The request was

accepted by this Court and by the Order passed on 26.09.2022, the

appeal pending before the NCLAT was also disposed of by this Court.

The applicant was an intervenor before the NCLAT and his submission

was that in the appeal before the NCLAT which was disposed of,

he also sought to raise some grievances before the NCLAT, in his

capacity as an intervenor. His case was that he should have been

given the liberty to be heard as an intervenor before the NCLAT. A

Coordinate Bench of this Court entertained that application and held: -

“We do believe that this controversy should be resolved

by the NCLAT itself i.e. whether on the appellants seeking

to withdraw the appeal, there can be any impediment in

withdrawal of the appeal and is the NCLAT really required

to comment on the merits of the order of the NCLT at the

behest of an intervener. We further make it clear that we

are not expanding the array of parties before the NCLAT

as a number of entities seems to have jumped into the

picture as the matter has gone on before the Court. We

make it clear that only the parties/existing interventionist

before the NCLAT will have the right of hearing.

In view of the orders passed in Civil Appeal No. 9062/2022,

this appeal will also to be listed before the Bench presided

over by the Chairman.

In view thereof, the final picture which would emerge would

be before the NCLAT and to that extent the order passed

by us on 14.11.2022 would be kept in abeyance till the

NCLAT resolves the issue.”

Again, this Order was in the nature of a review order by the applicant

who was a party to the proceeding before the NCLAT. All the appeals

before the NCLAT were disposed of without hearing him. The context

is entirely different from the one in which the applicant has presently

approached this Court.

17. The fourth order on which the present applicant relied was passed

on 12.08.2022 in the case of Supertech Limited -vs- Emerald 

[2024] 3 S.C.R. 1041

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

Court Owner Resident Welfare Association & Ors. [MA No.1918

of 2021 in Civil Appeal No.5041 of 2021]. The Coordinate Bench

of this Court granted extension of time, as sought by the applicant

therein, in effecting demolition of two building towers which were

approved by the Court while disposing of the civil appeal. The power

to extend time beyond that fixed by a Court on a legitimate ground is

incorporated in Section 148 of the Code. If the time to do something

requires to be extended, it would be within the inherent jurisdiction of

this Court to go beyond the maximum period of 30 days prescribed

in the aforesaid Section, after sufficient reason is shown. Section

112 of the Code itself provides that nothing contained in the Code

shall affect the inherent powers of the Supreme Court under Article

136 or any other provision of the Constitution.

18. The fifth order referred to by the applicant was passed on 23.07.2021

in the case of Union of India -vs- Association of Unified Telecom

Service Providers of India and Ors. [MA No.83 of 2021 in MA

(D) No. 9887 of 2020 in Civil Appeal No.6328-6399 of 2015]. A

miscellaneous application had been filed for modification of the

content of judgment dated 1st September 2020 passed in M.A. (D)

No. 9887 of 2020 in Civil Appeal Nos. 6328-6399 of 2015. In the

said proceeding, clarification was also sought on the aspect that

the judgment did not bar the Union of India from considering and

rectifying the clerical/arithmetical errors in computation of certain

dues. This was again an Order, in substance, permitting rectification

of an arithmetic error, which is implicit in Section 152 of the Code

read with Order XII Rule 3 of the 2013 Rules.

19. We have indicated in the earlier part of this judgment that Dr. Singhvi

had expressed his desire to withdraw the present application on

the last date of hearing, i.e., 24.01.2024. Ordinarily, we would not

have had set out the background leading to the filing of the present

application and the course of the application that was taken before

this Court in view of such submission. Any plaintiff would be entitled

to abandon a suit or abandon part of the claim made in the suit at

any time after institution of the suit, as provided in Rule 1 of Order

XXIII of the Code. We, however, decided not to permit such simpliciter

withdrawal, as the Rajasthan Discoms sought imposition of costs.

Secondly, in our opinion, the provision which pertains to a suit would

not ipso facto apply to a miscellaneous application invoking inherent

powers of this Court, instituted in a set of statutory appeals which 

1042 [2024] 3 S.C.R.

Digital Supreme Court Reports

stood disposed of. Even if an applicant applies for withdrawal of an

application, in exceptional cases, it would be within the jurisdiction

of the Court to examine the application and pass appropriate orders.

So far as the present proceeding is concerned, an important question

of law has arisen as regards jurisdiction of the Court to entertain an

application taken out in connection with a set of statutory appeals

which stood disposed of. Judgment of this Court in Supertech

Limited (supra) deals with this question and in our opinion, the ratio

of the said judgment would apply to the present proceeding as well.

20. We felt it necessary to examine the question about maintainability of

the present application as we are of the view that it was necessary

to spell out the position of law as to when such post-disposal

miscellaneous applications can be entertained after a matter is

disposed of. This Court has become functus officio and does not

retain jurisdiction to entertain an application after the appeal was

disposed of by the judgment of a three-Judge Bench of this Court

on 31.08.2020 through a course beyond that specified in the statute.

This is not an application for correcting any clerical or arithmetical

error. Neither it is an application for extension of time. A post disposal

application for modification and clarification of the order of disposal

shall lie only in rare cases, where the order passed by this Court

is executory in nature and the directions of the Court may become

impossible to be implemented because of subsequent events or

developments. The factual background of this Application does not

fit into that description.

21. Our attention was drawn to an order passed on 14.12.2022 in which

a Coordinate Bench was of the prima facie opinion that the applicant

may be entitled to LPS as per Article 8.3.5 of PPA-2010, at least

from 31.08.2020, till the actual payment was made pursuant to the

order passed by this Court in the contempt proceedings. This prima

facie view was expressed in the course of hearing of the present

application only. We have examined the issue in greater detail. As

we have already indicated, the applicant, after the three-Judge Bench

decision was delivered, did not file any petition for review. On the

other hand, it was the Rajasthan Discoms that had filed the review

petitions which stood dismissed. In the contempt action instituted by

the applicant, the question concerning payment of LPS was raised,

but the Bench of this Court found that the same was not the subject

in question in the contempt proceedings regarding which no direction 

[2024] 3 S.C.R. 1043

Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.

Adani Power Rajasthan Ltd. & Anr.

had been issued by this Court. Hence the Coordinate Bench decided

not to address that question in the contempt proceedings. In this

judgement, we have already quoted the observations regarding the

question of LPS made by the Contempt Court on 25.02.2022 and

19.04.2022. Despite that question being left open by the Contempt

Court, we are of the view that a miscellaneous application is not the

proper legal course to make demand on that count. A relief of this

nature cannot be asked for in a miscellaneous application which was

described in the course of hearing as an application for clarification.

22. So far as the observations made in the order passed in the present

proceedings on 14.12.2022 are concerned, they were made only at

a prima facie stage and do not have binding effect at the hearing

stage. Moreover, the question whether such a prayer could be made

in an application labeled as a “Miscellaneous Application” taken

out in connection with a set of appeals which have been finally

decided, does not appear to have been considered by this Court at

the time of making of the order dated 14.12.2022. The order of this

Court does not reflect any discussion on the issue of maintainability

of the present application. It also does not appear to us that the

maintainability issue was raised at that stage. Thus, mere making

of such observations cannot be construed to mean that this Court

found such application to be maintainable.

23. We, accordingly, dismiss the present application. This application was

listed before us on several occasions and for that reason we impose

costs of Rs. 50,000/- to be paid by the applicant to be remitted to

the Supreme Court Legal Aid Committee.

Headnotes prepared by: Result of the case:

Raghav Bhatia, Hony. Associate Editor Application dismissed

(Verified by: Abhinav Mukerji, Sr. Adv.)