LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Wednesday, February 14, 2024

Whether the impugned judgment of the High Court negating the plea of land owner seeking ‘lapse’ of the acquisition proceedings in terms of s. 11-A of the Land Acquisition Act is liable to be interfered with; whether decision of Nagpur Improvement Trust refusing to grant alternative plot, as directed by the High Court, requires interference; and what suitable relief could be granted to land owner on account of delay caused in determination of compensation despite time bound directions by the High Court.

[2023] 12 S.C.R. 159 : 2023 INSC 818

LOONKARAN GANDHI (D) THR. LR.

v.

STATE OF MAHARASHTRA AND ORS.

(Civil Appeal No. 2644 of 2016)

SEPTEMBER 06, 2023

[SURYA KANT AND J.K. MAHESHWARI*, JJ.]

Issues for consideration: Whether the impugned judgment of

the High Court negating the plea of land owner seeking ‘lapse’

of the acquisition proceedings in terms of s. 11-A of the Land

Acquisition Act is liable to be interfered with; whether decision of

Nagpur Improvement Trust refusing to grant alternative plot, as

directed by the High Court, requires interference; and what suitable

relief could be granted to land owner on account of delay caused

in determination of compensation despite time bound directions

by the High Court.

Land Acquisition Act, 1894 – s. 11-A – Nagpur Improvement

Trust Act, 1936 – Acquisition under the State Act-NIT Act with

the aid of LA Act – Applicability of s. 11-A in the acquisition

proceedings under the NIT Act – On facts, notification issued

u/s. 39 of the NIT Act in 1962, possession was taken in the

year 1970 and the road was constructed, in the year 1986

award passed in case of the other land owners and in 2013

an ex-parte award passed – Plea of lapsing of acquisition

proceedings by the land owner:

Held: Provisions of s. 11-A of LA Act which provides for lapsing of

the land acquisition proceedings, would not be applicable where

acquisition was made under NIT Act – In view thereof, no error

committed by the High Court in negating the plea of lapsing of

acquisition proceedings as raised by land owner. [Paras 13 and 15]

Land Acquisition Act, 1894 – Nagpur Improvement Trust Act,

1936 – Rejection of the request of the land owner for grant

of alternate piece of land by the Nagpur Improvement Trust,

as directed by the High Court – Interference with:

Held: By the impugned order passed by the High Court, directions

were issued to NIT to consider the prayer for the grant of alternate

land to the land owner – Said prayer was rejected by the NIT, inter-

* Author

160 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

alia stating that grant of alternate land in lieu of compensation was

not possible in the absence of any provisions in the Act – Said

plea does not have any statutory backing under NIT Act, thus,

refusal made by NIT does not warrant any interference – After the

rejection of the representation to grant alternate land particularly

in absence of any statutory backing, there is no inclination to

entertain the said plea – Nonetheless, the said prayer was not

seriously pressed by the land owner and prayer was confined to

grant of adequate compensation. [Para 16]

Land Acquisition Act, 1894 – Nagpur Improvement Trust Act,

1936 – Delay caused in determination of compensation despite

time bound directions by the High Court – Publication of

preliminary notification in 1962, the possession of the subject

land taken in 1970 and the road was constructed which is in

public use since then – Award passed in 1986, in the case

of other land owners, discriminating the instant land owner

wherein even after directions of the High Court in 2009 to pass

an award, prayer for the grant of alternate plot was rejected by

NIT, and ‘ex-parte’ award was passed in 2013 during pendency

of the instant appeal and as such land owners could not get

compensation of the land since last five decades – Grant of

suitable relief to the land owner:

Held: In view of the said chain of events, the delay cannot be

attributed to the land owner – Value of the land which may be

on the date of preliminary notification cannot be equated on the

date of passing of ‘ex-parte’ award – As per s. 48-A of LA Act,

if the award is not passed within a period of two years from the

date of final notification, compensation for the damages suffered

due to delay is to be determined as prescribed therein – Thus,

to meet the ends of justice, it is appropriate to mould the relief –

‘Ex-parte’ award would not be given effect to – Land Acquisition

Officer to determine the compensation afresh taking the market

value of the subject land as on the date of passing of ‘ex-parte’

award – Land owner also entitled to all other statutory benefits

as per the provisions of the LA Act to be calculated from the date

of preliminary notification, as also be entitled to compensation

for damages suffered in view of delay. [Paras 21, 27, 34 and 35]

Land Acquisition Act, 1894 – Nagpur Improvement Trust

Act, 1936 – s. 67 – Award of tribunal how to be determined

– Acquisition of land under NIT Act – Determination of 

[2023] 12 S.C.R. 161

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

compensation – Passing of an award – Applicability of the

said provisions of the LA Act:

Held: s. 67 makes it clear that for determining the compensation

and to pass an award, the provisions of the LA Act would be

applicable – Thus, LA Act has its application to such extent for land

acquired by the NIT subject to the modifications made under the

NIT Act – Applicability of s. 11 of LA Act which deals with enquiry

and award, and s. 16 of LA Act which deals with power of Collector

to take possession, even in acquisition under the NIT Act is ‘sine

qua non’ – While making an inquiry u/s. 11, the applicability of s.

9 which deals with issuance of notice to persons interested, is an

integral procedure in the proceedings – Thus, for determination

of compensation to pass an award in case of acquisition of land

under NIT Act, the applicability of the said provisions of the LA

Act has been duly recognised in s. 67 of the NIT Act. [Para 17]

Land Acquisition Act, 1894 – Nagpur Improvement Trust Act,

1936 – Compulsory acquisition of land – Inordinate delay

in granting compensation to the land owner from the date

of taking over of possession – Duty of the State and the

authorities:

Held: Eminent domain of the State cannot be doubted – Right

of the land owner enshrined u/Art. 300-A and Art. 31-A has been

recognized as a human/civil right , thus if any individual is to be

divested or deprived of the said right by the State, it ought not

be done without giving compensation in accordance with law for

the land so acquired for public purpose – While striking a balance

between eminent domain of the State and human/civil rights of an

individual, an obligation is on the State and its authorities to pass

an award within a reasonable time – On compulsory acquisition

of land, if the award is not passed within a reasonable time duly

compensating such an individual, it would cause grave hardship

and it would adversely affect the livelihood of the land loser – Delay

in determining compensation uproots the land losers, however, to

meet the ends of justice and to rationalize the equity, switching

the date of market value in determining compensation is found

necessary. [Para 32]

Nagpur Improvement Trust v. Vasantrao and Others,

(2002) 7 SCC 657 : [2002] 2 Suppl. SCR 636; Bankatlal

v. Special Land Acquisition Officer and Another, (2014)

15 SCC 116 : [2014] 7 SCR 879 – relied on.

162 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

Tukaram Kana Joshi and Others through Power-ofAttorney Holder v. Maharashtra Industrial Development

Corporation and Others, (2013) 1 SCC 353 : [2012]

13 SCR 29; Bhimandas Ambwani (Dead) through LRs

v. Delhi Power Company Limited, (2013) 14 SCC 195

: [2013] 1 SCR 996; Delhi Airtech Services Pvt. Ltd.

and Another v. State of U.P. and Another, (2022) SCC

Online SC 1408; K. Krishna Reddy and Others Vs.

Special Deputy Collector, Land Acquisition Unit II, LMD

Karimnagar, Andhra Pradesh, (1988) 4 SCC 163:[1988]

2 Suppl. SCR 853 – referred to.

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2644 of 2016.

From the Judgment and Order dated 29.09.2009 of the High Court

of Bombay at Nagpur in WP No. 2022 of 1992.

Shekhar Naphade, Sr. Adv., Gagan Sanghi, Ms. Farah Hashmi,

Ms. Aishwarya Dash, Dr. Prashant Pratap, Rameshwar Prasad Goyal,

Advs. for the Appellant.

Dama Sheshadri Naidu, Sr. Adv., Satyajit A. Desai, Abhinav K.

Mutyalwar, Gajanan N. Tirthkar, Vijay Raj Singh Chauhan, Ms.

Anagha S. Desai, Sachin Patil, Siddharth Dharmadhikari, Aaditya

Aniruddha Pande, Bharat Bagla, Ms. Kirti Dadheech, Geo Joseph,

Risvi Muhammed, Durgesh Gupta, Advs. for the Respondents.

The Judgment of the Court was delivered by

J. K. MAHESHWARI, J.

1. This appeal has been filed against the order dated 29.09.2009 passed

in Writ Petition No. 2022 of 1992 by the High Court of Judicature of

Bombay at Nagpur Bench. The said Writ Petition was filed by the

father of the appellant/land owner (now deceased) seeking writ in

the nature of mandamus to declare the action of the respondents in

taking over possession of the subject land owned by him pursuant to

acquisition made by respondent no. 2 as illegal, arbitrary and without

any authority of law. The land owner also sought compensation @

Rs. 400-500/- per sq. ft. with commensurate damages caused on

account of mental agony suffered in last several years, or in alternate,

allotment of plot of equal dimension in the same vicinity. During the

pendency of the petition, the original writ petitioner died and his legal

heir (appellant herein) was substituted. 

[2023] 12 S.C.R. 163

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

2. The High Court observed that possession of land was taken in 1970

and the award in case of other land owners was passed in year 1986,

separating the case of appellant. Therefore, partly allowing the writ

petition, High Court directed respondent nos. 2 and 3 to complete

the exercise for grant of alternate plot on or before 31.01.2010 or

otherwise determine compensation on or before 30.04.2010 and

pay damages as per Section 48-A of the Land Acquisition Act, 1894

(hereinafter referred to as ‘LA Act’) in accordance with law.

3. For ready reference and convenience, hereinafter we shall refer

the deceased father of the appellant as ‘land owner’; his legal

heir as ‘appellant’; Respondent No. 1/State of Maharashtra as

‘State’; Nagpur Improvement Trust/Respondent No. 2 as ‘NIT’ and

Respondent No. 3/Special Land Acquisition Officer as ‘SLAO’.

4. The facts succinctly stated are that, in an auction dated 26.02.1943

held by the Commissioner Court of Wards, the landowner purchased

two plots bearing No. 8 admeasuring 9800 sq. ft. of Khasra No. 35/8

and No. 18 admeasuring 7248 sq. ft. of Khasra No. 35/9 at Mouza

Khamla, District Nagpur, Maharashtra on payment of Rs. 880/-. The

said plots previously belonged to ‘Ex-Malguzar Pande’. The sale

deeds of both the plots were executed by the representative of the

Court of Wards in favour of the landowner on 02.03.1944. Vide order

dated 09.05.1962 passed by S.D.O., Nagpur, the revenue records

were corrected and those plots were mutated in the name of the

landowner. NIT required the said land for ‘Ajni Street Scheme’

(hereinafter referred to as ‘Scheme’) for which the notification under

Section 39 of Nagpur Improvement Trust Act, 1936 (hereinafter

referred to as ‘NIT Act’) akin to Section 4 of the LA Act was published

on 12.07.1962 specifying Khasra Nos. 35/1 and 35/2 only. The

final declaration under Section 45 of the NIT Act akin to Section 6

of the LA Act was published on 16.01.1969. After final declaration,

NIT vide letter dated 10.10.1969 requested the State for transfer of

Khasra Nos. 35/1 and 35/2 to it for the Scheme, as it presumed the

land to be Government Nazul land. Sometime in the year 1970, NIT

constructed the road on 5390 sq. ft. of land of Khasra No. 35/8 which

included plot No. 8 belonging to the land owner. Thus, admittedly,

after taking of possession of subject land, road was constructed in

1970 on it and is in public use since then.

164 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

5. In reply to letter dated 10.10.1969 written by NIT, the Collector, District

Nagpur on 31.05.1972 informed that transfer of land of Khasra Nos.

35/1 & 35/2 is not possible because it is not Government land; in

fact, the said land belonged to and was occupied by Ex-Malguzar

Pande. Therefore, NIT was instructed to submit valuation report of

the remaining land. The land owners also received ‘no objection’ to

sell other plot No. 18 of Khasra No. 35/9 from NIT on 21.02.1976

and sold it to one Anil Hinge on 08.03.1976. For the sake of clarity,

it is only ‘plot No. 8’, i.e., Khasra no. 35/8 which is the subject land

in the present appeal and not plot No. 18 of Khasra No. 35/9.

6. The first notice dated 18.07.1974 issued by SLAO under Section

9(3) of LA Act was served to landowner and second notice dated

07.09.1974 was also served, however, none of the said notices

specified that Khasra No. 35/8 is also under acquisition. Nevertheless,

the land owner without prejudice to his rights, filed his statement of

claim in Revision Case No. 82-86/71-72. The NIT in reference to its

previous letter dated 10.10.1969, again wrote to SLAO on 02.02.1977,

requesting him to determine the interests of land owners on Khasra

nos. 35/1 and 35/2. Thereafter, third notice dated 18.10.1977 under

Section 9(3) of the LA Act was served to the landowner, however,

again there was no mention of Khasra no. 35/8. In the said scenario,

the landowner in reply to the notice, requested SLAO to discharge

his land from the acquisition proceedings primarily on the ground that

Khasra No. 35/8 was not reflected in all three notices. The said prayer

was opposed by NIT by response dated 19.04.1979, contending that

Khasra No. 35/8 was part of Khasra Nos. 35/1 and 35/2. However,

the SLAO vide order date 01.08.1981 separated the papers of the

land owner. It is also on record that NIT in furtherance to its letter

dated 02.02.1977, informed SLAO on 03.11.1981 that proposal for

acquisition of Khasra Nos. 35/1 and 35/2 had been submitted and

the interest of various persons shall be determined including the

land owner, however, the proposal with respect to Khasra No. 35/8

was still not submitted.

7. The land owner awaiting a proposal from NIT, filed a claim on

25.11.1981 requesting grant of alternate plot in the same vicinity on

the ground that the possession of his land was taken in 1970 and as

on date, road is already constructed on the same. In response, NIT

vide letter dated 02.06.1982 asked the land owner to prove his title

without considering its own reply dated 19.04.1979. Meanwhile, on 

[2023] 12 S.C.R. 165

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

22.09.1986, SLAO passed an award for adjoining pieces of land in

Khasra Nos. 35/3 and 35/4 and since the papers of land owner were

separated, no award was passed with respect to Khasra No. 35/8.

Corrected city survey record dated 26.09.1986, recording name of

land owner in Khasra No. 35/8 was supplied to him. In view of the

corrected records, landowner again submitted a representation to NIT

on 17.01.1987 and requested for alternate plot. In reply letter dated

06.03.1987, NIT informed landowner that plot No. 8 in Khasra No.

35 belonging to land owner was under acquisition, and alternate plot

cannot be allotted. The land owner was directed to approach SLAO

for compensation for the said plot. Having no clear response, the

land owner sent a legal notice dated 02.09.1987 to NIT and sought

details of acquisition proceedings under which his land was acquired,

however, it was of no avail. In the meantime, the land owner made

a representation to the Guardian Minister seeking allotment of an

alternate plot, which was forwarded to NIT. Pursuant thereto, NIT vide

reply dated 19.12.1988 to Guardian Minister admitted that the land

of the land owner is under acquisition but grant of alternative plot is

not possible. Be that as it may, correspondences were exchanged

and finally NIT vide letter dated 15.01.1990 apprised the land owner

regarding pending acquisition proceedings of his land. Land owner

again submitted representation dated 25.07.1990 and 09.04.1991

for grant of alternate plot as compensation, but again to no avail.

8. Aggrieved by the inaction of authorities and delayed response to his

representations, on the advice of the advocate, land owner filed a

complaint before Consumer Forum, Nagpur, which was withdrawn

for want of jurisdiction. Thereafter, the land owner on 29.04.1992

filed ‘Writ Petition No. 2022/1992’ before High Court of Bombay,

Nagpur Bench praying the above said reliefs. The State did not file

any reply, however, SLAO filed a reply and did not dispute the land

acquisition notification for the Scheme. The issuance of three notices

under Section 9(3) of LA Act; the order dated 01.08.1981 passed

by SLAO separating the papers of land owner as evident from the

records; the passing of the award dated 22.09.1986 in the case of

landowners of other Khasra Nos. 35/3 and 35/4 were neither denied

nor disputed. More so, the SLAO in its reply did not raise any plea

of delay and laches in filing the writ petition by landowner.

9. So far as stand of NIT before the High Court is concerned, the

issuance of notifications for land acquisition was not controverted. 

166 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

It was stated that Khasra No. 35 mentioned in the final Notification

consisted of total area of 8.56 acres of Khasra Nos. 35/1 and 35/2

out of which, 6.56 acres was Government land and the remaining

land was of Ex-Malguzar Pande. It was stated that the west side of

High Court Road was laid down in the compelling public need for the

city of Nagpur. All the communications between NIT, State, SLAO and

land owner were not disputed. It was stated that the request for a

grant of the alternate plot was rightly declined and the order passed

by SLAO on 01.08.1981 was not an order of discharge. Therefore,

the land owner on the anvil of said order cannot contest that his land

was not acquired. The passing of the award on 02.09.1986 for the

land of other land holders was not denied. With respect to prayer

for grant of compensation @ Rs. 400 to Rs. 500 per. sq. ft., it was

said that the actual value of land may hardly be Rs. 125 to Rs. 150

per sq. ft. at relevant time, hence, the compensation as sought is

on the higher side. It was lastly submitted that the writ petition has

been filed after inordinate delay, therefore, it ought to be dismissed

on the ground of laches.

10. The High Court by the impugned order partly allowed the writ

petition as referred above. Being aggrieved, the appellant is before

this Court assailing the said judgment. After notice in this appeal,

NIT filed counter affidavit, whereas, the prayer of the State to file

counter affidavit was declined vide order dated 07.12.2012 with the

liberty to file additional documents. During the pendency, the counsel

for appellant on 03.07.2013 without prejudice gave up his claim of

alternative plot provided NIT is prepared to pay compensation as

per current market rate. On request, time was granted to counsel for

NIT to seek instructions. In reply, additional affidavit was filed by NIT

stating that compensation as per market rate is not possible, since

it is a public body and informed the award granting compensation

@ Rs. 54,717/- has been passed.

11. The appellant filed additional affidavit along with a valuation report

dated 16.07.2013 showing the current market value of land as in

the year 2013 as Rs. 3,93,45,696/-. In view of the inordinate delay

in passing of award from the date of notification and taking over of

possession, prayer is made to mould the relief in exercise of the

powers under Article 142 of the Constitution of India. 

[2023] 12 S.C.R. 167

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

12. After having heard learned counsel for the parties and in the facts of

the case, in our view, the following questions arise for consideration:

i) Whether the impugned judgment of the High Court negating the

plea of appellant seeking ‘lapse’ of the acquisition proceedings

in terms of Section 11-A of LA Act is liable to be interfered with?

ii) Whether decision of NIT refusing to grant alternative plot, as

directed by the High Court, requires interference in this appeal?

iii) Whether in the peculiar facts of the case, delay caused in

determination of compensation despite time bound directions by

the High Court, what suitable relief can be granted to appellant?

IN REFERENCE TO QUESTION NO. 1

13. It is not in dispute that the notification was issued under Section 39

of the NIT Act on 12.07.1962. Although the said notification is not on

record, but looking at the material brought, it is clear that the land

of Khasra No. 35/1 and 35/2 only, without mentioning Khasra No.

35/8 in the said notification was proposed for acquisition. The final

notification was issued with same details. The possession of Khasra

No. 35/8 was taken in the year 1970 and the road was constructed on

5390 sq. ft. utilising the entire land of 9800 sq. ft of the said Khasra.

It is relevant to note that vide Act of 68 of 1984, amendment in the

LA Act was introduced adding Section 11-A, whereby passing an

award determining the compensation within period of two years was

made necessary. In case the award has not been passed within the

specified period, it shall result in lapsing of acquisition proceedings.

In the present case, the acquisition was under the State Act, i.e.,

NIT Act with the aid of LA Act, however, it’s applicability in such

acquisition requires consideration.

14. The said issue of applicability of Section 11-A of the LA Act in an

acquisition proceeding carried under NIT Act has been decided by

this Court in the case of “Nagpur Improvement Trust Vs. Vasantrao

and Others, (2002) 7 SCC 657”, wherein it was clarified that the

subsequent amendment made by Act No. 68 of 1984 will have no

effect on the acquisition made under the State Act, which means the

lapsing provision under Section 11-A introduced by Act of 68 of 1984,

does not apply to acquisition of land by Nagpur Improvement Trust

under NIT Act. The same principle has been reiterated in “Bankatlal 

168 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

Vs. Special Land Acquisition Officer and Another, (2014) 15 SCC

116”, wherein it was held that the NIT Act is a complete code in itself,

except to apply the provisions of the LA Act that stood legislatively

incorporated in the said Act, and other provisions would not apply. It

was held that the subsequent amendment made by Act 68 of 1984

inserting Section 11-A would have no effect on the acquisition made

under NIT Act.

15. In view of the above, we are of the considered opinion that the

provisions of Section 11-A of LA Act which provides for lapsing of

the land acquisition proceedings, would not be applicable where

acquisition was made under NIT Act. In view of the foregoing

discussion and settled law, we are of the considered opinion that

the High Court has not committed any error in negating the plea of

lapsing of acquisition proceedings as raised by the appellant.

IN REFERNECE TO QUESTION NO. 2

16. By the impugned order dated 29.09.2009 passed by the High Court,

directions were issued to NIT to consider the prayer for the grant of

alternate land to the appellant. The said prayer was rejected by the

Chairman, NIT on 31.12.2009, inter-alia stating that grant of alternate

land in lieu of compensation is not possible in the absence of any

provisions in the Act. The said rejection has not been separately

challenged by the appellant and has attained finality. In our view also,

the said plea does not have any statutory backing under NIT Act,

therefore, refusal made by NIT does not warrant any interference.

Be that as it may, on 03.07.2013, counsel for the appellant without

prejudice to his right made a statement that to amicably resolve the

controversy, the appellant was willing to give up the claim of grant

of alternate plot provided NIT is prepared to pay the current market

price as on 03.07.2013. Thereafter, time was sought by counsel for

NIT to seek instructions. After instructions, NIT filed its response on

02.08.2013 wherein the grant of an alternative plot was denied. As

discussed, after the rejection of the representation to grant alternate

land particularly in absence of any statutory backing, we are not

inclined to entertain the said plea. Nonetheless, the said prayer

was not seriously pressed by the appellant and prayer was confined

to grant of adequate compensation. Therefore, question no. 2 is

answered accordingly. 

[2023] 12 S.C.R. 169

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

IN REFERNECE TO QUESTION NO. 3

17. In the case at hand, compulsory acquisition of the subject land was

initiated issuing preliminary notification in 1962 and final notification

in January 1969 under the provisions of NIT Act with the aid of LA

Act. As per Section 59 of NIT Act, for any scheme, the NIT may

acquire the land with the previous sanction of the State Government

under the LA Act as modified by NIT Act. As per Section 61(b) of

NIT Act, for the purpose of acquiring the land, the provisions of LA

Act shall apply subject to further modifications as indicated in the

Schedule. As per Section 67 of the NIT Act, the provisions of the

LA Act are made applicable for determination of award for the land

so acquired. The Schedule as referred to in Section 61 has made

the modification in the LA Act. Some of the modifications made in

clause 6 adding Section 17-A and clause 14 adding Section 48-A are

relevant for the purpose of this case, in addition to other provisions

as referred hereinabove. Therefore, for ready reference, they are

reproduced as thus –

“17-A. Transfer of land to Trust –

In every case referred to in section 16 or section 17, the Collector

shall, upon payment of the cost of acquisition, make over change of

the land to the Trust and the land shall thereupon vest in the Trust,

subject to the liability of the Trust to pay any further costs which may

be incurred on account of its acquisition.”

“48-A. Compensation to be awarded when land not acquired

within two years –

(1) If within a period of two years from the date of the publication

of the declaration under section 6 in respect of any land, the

Collector has not made an award under section 11 with respect

to such land, the owner of the land shall, unless he has been to

a material extent responsible for the delay, be entitled to receive

compensation for the damage suffered by him in consequence

of the delay.

(2) The provisions of Part III of this Act, shall apply so far as may

be, to the determination of the compensation payable under

this section.”

170 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

Section 67 of the NIT Act makes it clear that for the purpose of determining

the compensation and to pass an award, the provisions of the LA Act would

be applicable. Thus, LA Act has its application to such extent for land

acquired by the NIT subject to the modifications made under the NIT Act.

In view of the provisions of the NIT Act, the preliminary notification of the

land acquisition shall be under Section 39, and the final Notification shall

be under Section 45 for compulsory acquisition as specified in Section 59

of the NIT Act. It is to be noted here that, Section 16 of the LA Act deals

with the power of Collector to take possession of the land after he has

made an award under Section 11 and the said land shall thereupon vest

absolutely in the Government free from all encumbrances. Section 17

of LA Act deals with the special powers in case of urgency, but the said

provision is not relevant in the facts of the present case. Further, Section

17-A of the LA Act as modified in the Schedule referred to in Section

61 of NIT Act adopts the procedure specified in Section 16 or 17 of the

LA Act. Section 17-A prescribes that the Collector upon payment of the

cost of acquisition shall make over change of the land to the Trust and

the land shall thereupon vest in the Trust subject to discharge of liability

and payment of any further cost which may be incurred on account of

acquisition. Therefore, the applicability of Section 11 of LA Act which deals

with enquiry and award, and Section 16 of LA Act which deals with power

of Collector to take possession, even in acquisition under the NIT Act is

‘sine qua non’. While making an inquiry under Section 11, the applicability

of Section 9 which deals with issuance of notice to persons interested,

is an integral procedure in the proceedings. Hence, for the purpose of

determination of compensation to pass an award in case of acquisition

of land under NIT Act, applicability of the said provisions of the LA Act

has been duly recognised in Section 67 of the NIT Act.

18. As per Section 16 of the LA Act, the Collector on making an award

may take possession of the land to vest it in the Government. Similarly,

under Section 17-A added to Schedule of NIT Act, passing of an

award is a necessary pre-condition to vest the land with NIT. Further,

Section 48-A specifies that if award is not passed by the Collector

within a period of two years from the date of final notification, the

land owner, if not responsible for delay to a material extent, shall

be entitled to receive compensation for damages suffered by him in

consequence of delay. The said damage would be determined as

per the provisions of Part-III of LA Act. 

[2023] 12 S.C.R. 171

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

19. In view of the said basic provisions if we see the facts of this case,

then it is not in dispute that the subject land was occupied by ExMalguzar Pande. The land owner purchased the land in auction

and sale deed was executed in his favour by the Court of Wards.

As per the order dated 09.04.1962 passed by the SDO, Nagpur,

the revenue records were corrected recording his name before

issuance of preliminary notification. In the said notification as well

as in the final notification dated 16.01.1969, Khasra No. 35/8 was

not mentioned. The NIT had taken possession and constructed the

road on the west side entrance of the High Court which is in public

use. After final notification, statutory notice under Section 9 of LA

Act was issued to all the persons interested. As per the mandate

of law, such notice shall contain particulars of the land needed for

acquisition with an intent to ask the affected parties to submit their

respective claims and interests.

20. In the instant case, three notices were issued to the land owners

including deceased land owner Loonkaran Gandhi on 18.07.1974,

07.09.1974 and 18.10.1977. However, as stated above, the said

notices did not mention Khasra No. 35/8. Since Khasra No. 35/8 was

not mentioned, land owner filed the application seeking discharge

from acquisition proceedings. Pursuant thereto, SLAO separated

the claim of land owner from other claimants emanating out of

same notification. It is pertinent to note that NIT vide letter dated

10.10.1969 informed the Collector, Nagpur that Khasra Nos. 35/1

and 35/2 are Government Nazul land and asked for transfer of such

land in favour of NIT for the Scheme. In reply, the Collector, Nagpur

on 31.05.1972 informed that such land cannot be transferred since

it is not a government land and belongs to Ex-Malguzar Pande.

Therefore, the Collector requested NIT to submit a valuation

report of the remaining land. The NIT vide letter dated 02.02.1977

acknowledged and requested the SLAO to determine the interest of

the persons from Khasra Nos. 35/8 to 35/12. Later, NIT submitted

proposals for Khasra No. 35/1 and 35/2, but it is not on record why

the proceedings to determine compensation of Khasra No. 35/8 of

the land owner were not commenced.

21. The correspondence also reflects that in absence of initiation of

proceedings for determination of compensation, land owner submitted

a representation to allot alternate land equal to the land of Khasra

No. 35/8 in the same locality which was denied on 06.03.1987. As 

172 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

per material placed, in cases of other landowners, the award was

passed on 22.09.1986 by SLAO with respect to Khasra Nos. 35/3

and 35/4. Thus, it is apparent that possession was taken from land

owner without payment of compensation and the prayer for alternate

piece of land was rejected. It is also apparent that even up to filing

the writ petition, proceedings to award compensation of the land of

Khasra No. 35/8 were not commenced. On filing the Writ Petition,

even during its’ pendency, action to determine compensation was not

started. Therefore, the High Court by the impugned order directed NIT

to consider the prayer for the grant of an alternate plot, otherwise,

SLAO to pass award on or before 30.04.2010. As directed by the

High Court, prayer for the grant of alternate plot was rejected by

NIT, but the award was not passed within the time given in the order

by the High Court.

22. In the given facts, the appellant filed this Special Leave Petition,

wherein, notice was issued on 22.03.2010. The NIT filed its counteraffidavit on 18.06.2012 contesting the case. On 03.07.2013, this

Court passed an order as under –

“Shri Shekhar Naphade, learned senior counsel appearing for the

petitioner made a statement that without prejudice to his rights and

with a view to amicably resolve the controversy, his client is willing

to give up his claim provided the competent authority of the Nagpur

Improvement Trust is prepared to pay the current market price.

Shri Satyajit A. Desai, learned counsel appearing for the Nagpur

Improvement Trust requests for an adjournment to seek instructions

from the concerned authorities.

Put up after two weeks.”

23. Later, on 22.07.2013, the NIT further sought time to seek instructions

in view of the statement made by the counsel for the appellant.

Thereafter on 02.08.2013, NIT filed additional affidavit in which

reference to ‘ex-parte’ award passed on 30.04.2013 was made for

the first time and it was stated that a sum of Rs. 54,717/- has been

awarded to the appellant. On 21.10.2013, during arguments, this

Court found that there was an inordinate delay in passing the award

dated 22.09.1986 in the case of other land owners. Therefore, an

explanation was sought for delay of 17 years, 8 months and 13

days. The said order dated 21.10.2013 is relevant and therefore

reproduced as thus –

[2023] 12 S.C.R. 173

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

“After the arguments were heard for some time, Shri Uday Dube,

learned counsel for the State of Maharashtra made a request for

short adjournment to enable his client to file an additional affidavit

to explain 17 years 8 months and 13 days delay between issue of

notification under Section 45 of the Nagpur Improvement Trust, 1936

and passing of the award. Shri Dube further stated that he shall

instruct the concerned officer to explain as to why appropriate award

was not passed within the time specified in order dated 29.09.2009

passed by the High Court.

The request of Shri Dube is accepted and the case is adjourned to

1.11.2013..”

24. In view of the above order, time to file additional affidavits and to

explain the delay was allowed to SLAO and NIT, which were filed by

them on 11.11.2013 and 04.12.2013 respectively. In the said additional

affidavits, the SLAO and NIT, both attributed delay to each other and

also against the appellant. Therefore, the Court after hearing passed

the order on 03.01.2014, which is reproduced as under –

“The case was taken up on 21st October, 2013, the Court had passed

the following order:

“After the arguments were heard for some time, Shri Uday

Dube, learned counsel for the State of Maharashtra made a

request for short adjournment to enable his client to file an

additional affidavit to explain 17 years, 8 months and 13 days

delay between issue of notification under Section 45 of the

Nagpur Improvement Trust, 1936 and passing of the award.

Shri Dube further stated that he shall instruct the concerned

officer to explain as to why appropriate award was not passed

within the time specified in order dated 29.09.2009 passed by

the High Court.

The request of Shri Dube is accepted and the case is adjourned

to 1.11.2013.”

Pursuant to the said order, explanation has been filed by the State

which shows that there was disputes between the respondents due to

which there was a delay of 17 years, 8 months and 13 days between

issue of notification under Section 45 of the Nagpur Improvement

Trust, 1936 and passing of the award. 

174 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

In the circumstances, respondents are directed to explain as to why

this Court will not grant suitable relief to the petitioners by directing

the respondents as to allot equivalent alternative plots in the adjoining

area or to pay the compensation on the basis of market value as on

the date of award with solatium and interest, as per law.

Affidavit may be filed within three weeks. Reply, if any, be filed within

two weeks thereof.

Post the matter after six weeks.”

25. In response to the order, neither the State Government nor SLAO

submitted any explanation. It is only NIT who filed an additional

affidavit on 25.01.2014, inter-alia, stating that allotment of alternate

plots in the adjoining area is not possible and denied the payment of

compensation as per market value as existing on 03.07.2013. It was

stated that it is only the appellant who can be blamed for inordinate

delay. In the said affidavit, the causes of delay were crystallized in

three slots, viz. between the issuance of notifications till filing of writ

petition; delay during the pendency of writ petition; and delay between

the date of order in the writ petition and passing the award. On filing

the said explanation and upon hearing the parties on 22.07.2014,

this Court passed the following order –

“Heard Mr. Shekhar Naphade learned senior counsel and Mr. Gagan

Sanghi, learned counsel for the petitioner. Mr. Marlapalle learned

senior counsel for Respondent No. 1 and Mr. Pallav Shishodia,

learned senior counsel for Respondent No. 2 in part.

The learned counsel for the parties shall file respective charts precisely

putting forth why there was enormous delay in passing the award.

We have asked learned counsel for the parties to undertake this

exercise as we are of considered opinion that the compensation that

is allowable under Section 48-A of the Nagpur Improvement Trust

Act, 1936 may be applicable if a case is made out.

List on 5th August, 2014.”

26. In furtherance to the said order, it is only the appellant who filed

the chart and explained as to how and in what manner, the delay is

caused. It was further stated that only respondents are responsible

for not passing the award despite time bound directions given by

the High Court. Conversely, the SLAO passed an ex-parte award 

[2023] 12 S.C.R. 175

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

that too without any intimation or notice as mandated by Section

12(2) of LA Act.

27. After hearing the parties and upon perusal of the averments made in

the additional affidavits filed in furtherance of orders dated 03.07.2013,

21.10.2013 and 22.07.2014, it is clear that Respondents have taken

more than six and half years to issue final notification which was

published on 16.01.1969. The possession had been taken immediately

and the three notices under Section 9 of LA Act were issued on

18.7.1974, 07.09.1974 and 18.10.1977 respectively. The award was

passed in the case of other land owners on 22.09.1986, leaving

the case of land owner/appellant herein. Thus, it is apparent that

the period of seven years has been taken to issue the notice under

Section 9 to the appellant after the date of taking the possession and

the award was passed in the case of other land owners after more

than 17 years, separating the claim of the appellant. In view of the

said chain of events, the delay cannot be attributed to the appellant.

More so, the writ petition filed by land owner before High Court on

29.04.1992 was decided on 29.09.2009, i.e., after about 17 years.

During the pendency of the writ petition, the delay, if any, occurred,

cannot be attributed to the appellant, but it may reflect on conduct of

respondents for not passing the award even during such pendency.

It is not out of place to observe that the High Court has not outrightly

disregarded the claim of the appellant for grant of alternate plot in

adjoining area and directed the NIT to take a decision. In case, the

allotment of plot was not possible, respondents were directed to pass

an award within the time frame. The NIT denied the alternate plot,

but even thereafter, the award was not passed within the time limit

fixed by the High Court. The award on record was passed by SLAO

only when this Court had taken cognizance in the matter. Therefore,

even after the order of the High Court, there is a delay of more than

three years in passing of the award. Thus, in our considered opinion,

the delay cannot be said to be attributable to the appellant.

28. As per discussion made above and in the facts of this case, what

amount of compensation may be directed to the appellant herein

needs to be looked into. In this regard, in the case of compulsory

acquisition of land, the eminent domain of the State cannot be

doubted. Simultaneously, right of the land owner enshrined under

Article 300-A and Article 31-A of the Constitution of India which

has been recognized as a human/civil right cannot be overlooked. 

176 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

Therefore, if any individual is to be divested or deprived of the said

right by the State, it ought not be done without giving compensation

in accordance with law for the land so acquired for public purpose.

29. In the above context, we can profitably refer the judgment of this Court

in the case of “Tukaram Kana Joshi and Others through Powerof-Attorney Holder Vs. Maharashtra Industrial Development

Corporation and Others, (2013) 1 SCC 353”. In the said case,

this Court had the occasion to consider the principles of eminent

domain, absolute power and deprivation of the rights to property

of an individual. The relevant paragraphs of the said judgment are

reproduced as thus –

“11. …..There is a distinction, a true and concrete distinction, between

the principle of “eminent domain” and “police power” of the State.

Under certain circumstances, the police power of the State may be

used temporarily, to take possession of property but the present case

clearly shows that neither of the said powers have been exercised.

A question then arises with respect to the authority or power under

which the State entered upon the land. It is evident that the act of

the State amounts to encroachment, in exercise of “absolute power”

which in common parlance is also called abuse of power or use of

muscle power. To further clarify this position, it must be noted that

the authorities have treated the landowner as a “subject” of medieval

India, but not as a “citizen” under our Constitution.

* * * *

17. Depriving the appellants of their immovable properties was a clear

violation of Article 21 of the Constitution. In a welfare State, statutory

authorities are bound, not only to pay adequate compensation, but

there is also a legal obligation upon them to rehabilitate such persons.

The non-fulfilment of their obligations would tantamount to forcing

the said uprooted persons to become vagabonds or to indulge in

anti-national activities as such sentiments would be born in them on

account of such ill-treatment. Therefore, it is not permissible for any

welfare State to uproot a person and deprive him of his fundamental/

constitutional/human rights, under the garb of industrial development.

18. The appellants have been deprived of their legitimate dues for

about half a century. In such a fact situation, we fail to understand

for which class of citizens the Constitution provides guarantees and 

[2023] 12 S.C.R. 177

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

rights in this regard and what is the exact percentage of the citizens

of this country, to whom constitutional/statutory benefits are accorded,

in accordance with the law.

19.…..Even under valid acquisition proceedings, there is a legal

obligation on the part of the authorities to complete such acquisition

proceedings at the earliest, and to make payment of requisite

compensation……”

30. The said judgment has been referred in the case of “Bhimandas

Ambwani (Dead) through LRs Vs. Delhi Power Company

Limited, (2013) 14 SCC 195”, wherein this Court had considered

the aspect of inordinate delay of about five decades in not granting

the compensation to the land loser from the date of taking over of

possession and directed the respondent to make the award treating

the date of Section 4 notification as on the date of order passed by

this Court. For ready reference, the relevant paragraph is reproduced

as thus –

“14. The instant case is squarely covered by the aforesaid judgment

in Tukaram case [(2013) 1 SCC 353] and thus, entitled for restoration

of possession of the land in dispute. However, considering the fact

that the possession of the land was taken over about half a century

ago and stood completely developed as Ms Ahlawat, learned counsel

has submitted that a full-fledged residential colony of the employees

of DESU has been constructed thereon, therefore, it would be

difficult for Respondent 1 to restore the possession. In such a fact

situation, the only option left out to the respondents is to make the

award treating Section 4 notification as, on this date i.e. 12-2-2013

and we direct the Land Acquisition Collector to make the award

after hearing the parties within a period of four months from today.

For that purpose, the parties are directed to appear before the Land

Acquisition Collector c/o the Deputy Commissioner, South M.B. Road,

Saket, New Delhi on 26-2-2013. The appellants is at liberty to file a

reference under Section 18 of the Act and to pursue the remedies

available to him under the Act. Needless to say that the appellants

shall be entitled to all statutory benefits.

31. Recently, the similar approach was adopted in the case of “Delhi

Airtech Services Pvt. Ltd. and Another Vs. State of U.P. and

Another, (2022) SCC Online SC 1408”, wherein 3-Judge Bench

of this Court in a reference while dealing with the divergent views of 

178 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

two Judges relating to taking over of possession without following the

mandate of Section 17 of the LA Act, vis-a-vis violation of constitutional

guarantee to a citizen under Article 300-A of the Constitution of India,

the Court answered the said reference as thus –

25. On weighing all aspects of the matter, we deem it appropriate that

it will serve the ends of justice to direct the respondents to determine

the market value insofar as the appellant’s land is concerned by

reckoning the relevant date as 09.06.2008 (i.e. the date on which

the award was ultimately passed), by applying the yardstick under

Act, 1894. It is made clear that only the market value be determined

as on that date but for awarding the statutory benefits, it shall be

calculated from the date of the original notification since admittedly

the appellant has been dispossessed on 04.02.2003 pursuant to

the notification dated 17.04.2002. Further, from the date on which

the fresh award is passed pursuant to this judgment, the appellant

would get the cause of action for seeking reference if dissatisfied

with the quantum of compensation awarded. It is made clear that the

determination of compensation, in this case, shall not give rise to any

right in favour of any other land loser whose land was acquired under

the same notification, to seek for re-determination of compensation

where the same has already attained finality.

 * * * *

27. In the result, we pass the following order:

(i) The provision contained in Section 11A of Act, 1894 shall be

applicable to cases in which the acquiring authority has not

complied with the requirement of sub-section (3A) to Section

17 of Act, 1894 by tendering and paying eighty per centum of

the estimated compensation before taking possession since

possession in such cases cannot be considered to be taken in

accordance with law and the vesting is not absolute.

(ii) If the requirement is complied and possession is taken after

tendering and paying eighty per centum, though there is need

to pass an award and pay the balance compensation within a

reasonable time, the rigour of Section 11A of Act, 1894 will not

apply so as to render the entire proceedings for acquisition to

lapse in the context of absolute vesting. The right of land loser

in such case is to enforce passing of the award and recover

the compensation. 

[2023] 12 S.C.R. 179

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

(iii) In the instant case though Section 11A of Act, 1894 has become

applicable, in the changed circumstance we deem it proper to

mould the relief instead of holding the acquisition to have lapsed.

Hence for the reasons stated above, we direct as follows:

(a) The respondents shall construe 09.06.2008 as the relevant

date and determine the market value prevailing as on that

date applying the yardstick under Act, 1894 in respect of the

acquired land.

(b) To calculate the statutory benefits on such amount including

interest, the same shall be determined by taking into consideration

the date of the Section 4 notification dated 17.04.2002 since

the appellant was dispossessed on 04.02.2003 pursuant to

the same.

(c) The date on which the fresh award is passed pursuant to this

judgment and communicated shall be the date of cause of action

for seeking enhancement of compensation if the appellant is

dissatisfied with the quantum of compensation offered.

(d) The compensation determined in this case shall not give

the cause of action to any other land loser whose land is

acquired under the same notification to seek re-determination

of compensation.

(e) The appellant shall be entitled to the cost incurred in these

proceedings.”

32. In view of the judgments referred above, this Court while striking a

balance between eminent domain of the State and human/civil rights

of an individual, has put an obligation on the State and its authorities

to pass an award within a reasonable time. It is observed that, on

compulsory acquisition of land, if the award is not passed within

a reasonable time duly compensating such an individual, it would

cause grave hardship and it would adversely affect the livelihood of

the land loser. In the said judgments, because of inordinate delay in

passing the awards, the Court had changed the date of preliminary

notification ordinarily applicable in determining the market value

of land for assessing amount of compensation, to the date of the

judgment of the Court, and/or the date of award passed belatedly. This

Court has recognized the right of the citizen after taking possession 

180 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

of the land without payment of compensation. As observed, the delay

in determining compensation uproots the land losers, however, to

meet the ends of justice and to rationalize the equity, switching the

date of market value in determining compensation by the orders of

the Court is found necessary.

33. In the case of “K. Krishna Reddy and Others Vs. Special Deputy

Collector, Land Acquisition Unit II, LMD Karimnagar, Andhra

Pradesh, (1988) 4 SCC 163”, this Court has conceptualized the effect

of non-determination and payment of compensation immediately to

a land loser. The Court observed that if there is inordinate delay in

determination as well as payment of compensation, it diminishes the

purchase power as well as value of Rupee due to rising inflation.

Therefore, the utility to compensate such land loser with equal value

cannot be ruled out. In the said case, the Court has observed as

thus –

“12. …..After all money is what money buys. What the claimants

could have bought with the compensation in 1977 cannot do in 1988.

Perhaps, not even one half of it. It is a common experience that the

purchasing power of rupee is dwindling. With rising inflation, the

delayed payment may lose all charms and utility of the compensation.

In some cases, the delay may be detrimental to the interests of

claimants. The Indian agriculturists generally have no avocation.

They totally depend upon land. If uprooted, they will find themselves

nowhere. They are left high and dry……..”

34. If we take clue from the above referred judgments and the observations

made, the principles as enunciated squarely applies in the case on

hand. For the sake of clarity and at the cost of repetition, looking to

the records before us, it is clear that the preliminary notification was

published on 12.07.1962 followed by final notification on 16.01.1969.

The possession of the subject land was taken in 1970 and the road

was constructed which is in public use since then. In the case of other

land owners, award was passed on 22.09.1986, discriminating the

land owner/appellant herein. Even after directions of the High Court

in order dated 29.09.2009 to pass an award by 30.04.2010, it was

passed ‘ex-parte’ after three years on 30.04.2013 during pendency

of this appeal without adhering to the mandate of Section 12(2) of

the LA Act. Consequently, appellant could not get compensation of 

[2023] 12 S.C.R. 181

LOONKARAN GANDHI (D) THR. LR. v. STATE OF MAHARASHTRA

AND ORS.

the land since last five decades. In view of the said conduct, we are

of the considered view that the value of the land which may be on

the date of preliminary notification cannot be equated on the date of

passing of ‘ex-parte’ award. As per Section 48-A of LA Act, which is

legislatively applicable as per the Schedule of NIT Act, it is clear that

if the award is not passed within a period of two years from the date

of final notification, compensation for the damages suffered due to

delay is required to be determined as prescribed therein. Therefore,

in the peculiar facts of this case and to meet the ends of justice, we

deem it appropriate to mould the relief and direct that the SLAO shall

pass a fresh award taking market value as on the date when the

‘ex-parte’ award was passed, i.e., 30.04.2013. Needless to observe

that, other statutory benefits shall be reckoned and payable from the

date of preliminary notification as per the provisions of the LA Act.

We are also of the firm view that the appellant shall be entitled for

compensation for damages due to delay as specified under Section

48-A of the LA Act within a period of four months.

35. Accordingly, in view of the foregoing discussion, the appeal is allowed

in part with the following directions –

1. As the land has been acquired under the NIT Act, therefore,

in view of judgment of Nagpur Improvement Trust (supra) &

Bankatlal (supra), the benefit of Section 11-A of LA Act (lapse

of land acquisition proceedings), shall not be available to the

appellant and the findings in this regard recorded by the High

Court are hereby affirmed.

2. The rejection of request of appellant for grant of alternate piece

of land by NIT, does not warrant any interference in the facts

of this case.

3. The ‘ex-parte’ award dated 30.04.2013 shall not be given effect to

and the SLAO is hereby directed to determine the compensation

afresh. For the said purpose, SLAO shall take the market value

of the subject land as on the date of passing of ‘ex-parte’ award,

i.e., 30.04.2013 and determine the compensation affording an

opportunity to the appellant and NIT.

4. The appellant shall also be entitled to all other statutory benefits

as per the provisions of the LA Act which shall be calculated

from the date of notification as prescribed by law.

182 [2023] 12 S.C.R.

SUPREME COURT REPORT: DIGITAL

5. The appellant shall also be entitled to compensation for damages

suffered in view of delay as per Section 48-A of LA Act as

modified by Schedule of NIT Act.

6. The said exercise be completed by the SLAO within a period of

four months from the date of appearance, for which the parties

are directed to appear on 25.09.2023.

7. Pursuant to this judgment and on passing the award as

directed, if the appellant is dissatisfied, the cause of action

to seek reference for enhancement shall be from the date of

communication of the fresh award.

8. The other land owners whose land were acquired under the

same notification and who have received compensation will not

be entitled to seek re-determination of compensation in view

of this judgment.

36. All the pending applications, if any, shall stand dismissed. No order

as to costs.

Headnotes prepared by: Nidhi Jain Result of the case : Appeal partly allowed.