LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws. This blog is only for information but not for legal opinions

Just for legal information but not form as legal opinion

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Saturday, November 21, 2026

Electricity Act (36 of 2003), Ss. 10, 29(4), 38, 61, 62, 79 — CERC (Terms and Conditions of Tariff) Regulations (2014), Regns. 3(53), 4(3) — LILO inclusion in transmission tariff and liability of generator for delayed DTL. Where LILOs on both circuits of the Tuticorin JV–Madurai line at the Tuticorin Pooling Station formed an approved part of the Southern Region transmission strengthening plan and BPTA, were placed in "Regular Service" on 04.01.2015 and 08.01.2015 upon RLDC trial-operation certification and CEA compliance, and actually routed evacuated power through the pooling station to the distribution licensee (TANGEDCO), the assets were used and operational; lack of "beneficial use" cannot be invented to deny tariff, and the generating company delaying its statutory duty under Section 10 to construct its DTL until 27.10.2016 is liable for transmission charges during the intervening period on a non-PoC basis (PGCIL v. M.P. Power Transmission Co. Ltd., (2025) 8 SCC 705; PTC India Ltd. v. CERC, (2010) 4 SCC 603; Energy Watchdog v. CERC, (2017) 14 SCC 80). (Paras 15–20, 22, 34–37, 42–49)

 Case Title: Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors. (with connected appeal)


Citation: 2026 INSC 1237 | Civil Appeal Nos. 14780–14781 of 2025 (with Civil Appeal No. 13153 of 2026) | Decided on November 18, 2026

Bench: J.B. Pardiwala, J. and K. Vinod Chandran, J.

Facts of the Case

  • Transmission System & LILOs: Power Grid Corporation of India Ltd. ("PGCIL"), the Central Transmission Utility ("CTU"), established two Line-In Line-Out ("LILO") elements (Assets 1 and 2) on the two circuits of the Tuticorin JV–Madurai 400 kV D/C (Quad) transmission line at the Tuticorin Pooling Station as part of the Southern Region transmission plan approved in Standing Committee Meetings (including the 29th and 30th SCMs) and reflected in the 24.02.2010 Bulk Power Transmission Agreement ("BPTA") (amended 08.09.2011). Generating company Moxie Power Generation Limited (formerly Coastal Energen Pvt. Ltd.) commenced generation on 23.12.2014, evacuated power routed to TANGEDCO, and commissioned its Dedicated Transmission Line ("DTL") directly to the Tuticorin Pooling Station on 27.10.2016, while upstream lines from Tuticorin to Salem and Madhugiri Pooling Stations were commissioned later. (Paras 1–2, 7, 15–19, 27–37)

  • CERC Order: Based on RLDC trial-operation/charging certificates, CEA safety compliance certificates, and operationalisation of a 1x80 MVAR bus reactor at Tuticorin Pooling Station, the Central Electricity Regulatory Commission ("CERC") (by order dated 29.07.2016) accepted Commercial Operation Dates ("COD") of 04.01.2015 and 08.01.2015 for the two LILOs (without condoning time overrun at that stage, leaving proof for truing-up) and directed transmission charges for the LILOs until commissioning of the generator's DTL to be borne by the defaulting generating companies (50% PoC / 50% by generator in the tariff arrangement noted). (Paras 2–3, 10–13, 33–34, 41)

  • APTEL Orders & Supreme Court Appeals: On appeal over non-PoC charges of ₹15,43,26,909/- for 04.01.2015–27.10.2016, the Appellate Tribunal for Electricity ("APTEL") treated the LILOs as permanent but held they were not put to "beneficial use" and questioned CERC's COD procedure under Regulation 4(3)(ii) of the CERC (Terms and Conditions of Tariff) Regulations, 2014 ("Tariff Regulations"), remanding COD consideration in review. PGCIL appealed both the original and review orders. (Paras 2, 14, 20, 46–48)

Headnotes

Electricity Act (36 of 2003), Ss. 10, 29(4), 38, 61, 62, 79 — CERC (Terms and Conditions of Tariff) Regulations (2014), Regns. 3(53), 4(3) — LILO inclusion in transmission tariff and liability of generator for delayed DTL.

Where LILOs on both circuits of the Tuticorin JV–Madurai line at the Tuticorin Pooling Station formed an approved part of the Southern Region transmission strengthening plan and BPTA, were placed in "Regular Service" on 04.01.2015 and 08.01.2015 upon RLDC trial-operation certification and CEA compliance, and actually routed evacuated power through the pooling station to the distribution licensee (TANGEDCO), the assets were used and operational; lack of "beneficial use" cannot be invented to deny tariff, and the generating company delaying its statutory duty under Section 10 to construct its DTL until 27.10.2016 is liable for transmission charges during the intervening period on a non-PoC basis (PGCIL v. M.P. Power Transmission Co. Ltd., (2025) 8 SCC 705; PTC India Ltd. v. CERC, (2010) 4 SCC 603; Energy Watchdog v. CERC, (2017) 14 SCC 80). (Paras 15–20, 22, 34–37, 42–49)

CERC (Terms and Conditions of Tariff) Regulations (2014), Regn. 4(3)(ii) — Determination of COD by CERC — No re-determination required where regular service is established.

Regulation 4(3)(ii) applies where a transmission element is prevented from regular service due to delay in commissioning of a generating station or upstream/downstream transmission systems. Where generation and evacuation occurred and the LILOs were in regular service upon RLDC certification and approved by the CERC on record, APTEL erred in questioning the COD and ordering re-determination under Regulation 4(3)(ii). (Paras 38–41, 46, 49)

Ratio Decidendi

Commissioned LILO transmission assets forming an approved part of a regional evacuation scheme and placed in regular service upon RLDC trial certification—which actually route generated power through a pooling station to the distribution licensee—are includable in transmission tariff on a non-PoC basis from their approved CODs (04.01.2015 and 08.01.2015) until the generating company commissions its Dedicated Transmission Line (27.10.2016), regardless of later upstream line commissioning or a non-statutory "beneficial use" test, and APTEL erred in disturbing CERC's COD determination under Regulation 4(3)(ii) of the 2014 Tariff Regulations. (Paras 16–20, 35–41, 46–50)