for effective management of the water resources in the country by nationalization and inter-linking of rivers from Ganga - Cauveri, Vaigai-Tambaravarmi up to Cape Kumari. According to him, as early as in 1834, Sir Arthur Cotton, who had constructed the Godavari and Krishna dams, suggested a plan called the `Arthur Cotton 2
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
WRIT PETITION (CIVIL) NO. 512 OF 2002
"IN RE : NETWORKING OF RIVERS"
WITH
WRIT PETITION (CIVIL) NO. 668 OF 2002
J U D G M E N T
Swatanter Kumar, J.
1. Nearly ten years back, the petitioner in Writ Petition
(Civil) No. 668 of 2002, a practicing advocate, instituted the
petition based on some study that there was a need to
conserve water and properly utilize the available resources.
Thus, the present petition has been instituted with the
following prayers:-
"a. Issue an appropriate writ order or
direction, more particularly a writ in
the nature of Mandamus directing the
respondent no. 1 to take appropriate
1
steps/action to nationalize all the
rivers in the country.
b. Issue an appropriate writ order or
direction, more particularly a writ in
the nature of Mandamus, directing
the respondent No. 1 to take
appropriate steps/action to inter link
the rivers in the southern peninsula
namely, Ganga, Kaveri, Vaigai and
Tambaravani.
c. Issue an appropriate writ order or
direction in the nature of mandamus
directing the respondents to
formulate a scheme whereby the
water from the west flowing rivers
could be channelized and equitably
distributed."
2. The above directions were sought by the petitioner
against the Central Government as well as against various
State Governments, for effective management of the water
resources in the country by nationalization and inter-linking
of rivers from Ganga - Cauveri, Vaigai-Tambaravarmi up to
Cape Kumari. According to him, as early as in 1834, Sir
Arthur Cotton, who had constructed the Godavari and
Krishna dams, suggested a plan called the `Arthur Cotton
2
Scheme' to link the Ganga and Cauveri rivers. In 1930, Sir
C.P. Ramaswamy Aiyar also suggested and supported such
-
a scheme. Thereafter, various political leaders of the
country have supported the cause; but no such schemes
have actually been implemented. It is the case of the
petitioner that the Inter-State Water Disputes Act, 1956 (for
short `the Act') and the River Boards Act, 1956 were enacted
by the Parliament under Article 262 read with Entry 56 of
List-I of the Seventh Schedule to the Constitution of India,
1950 (hereafter, `the Constitution'). Due to reluctance of
water-rich States, the National Water Development Agency
(hereafter, `NWDA') has not been allowed to undertake
detailed survey and it is argued that only by nationalization
of the rivers, by the Government of India, this problem can
be resolved to some extent. The petitioner had filed a writ
before the High Court of Judicature at Madras, being Writ
Petition No. 6207 of 1983, praying for various reliefs. This
Writ Petition was disposed of without any effective orders by
the High Court. Persisting with his effort, the petitioner
3
earlier filed writ petitions before this Court, being Writ
Petition (C) No. 75 of 1998 and Writ Petition (C) No. 15 of -
1999, praying inter alia for nationalized navigation and
inter-linking of all the rivers in the country.
3. We must notice, to put the records straight, that on
29th September, 1994, a Bench of this Court took suo motu
notice of a write-up that had appeared in the Hindustan
Times newspaper, dated 18th July, 1994, titled "And quiet
flows the maili Yamuna". Notice was issued to the Central
Pollution Control Board, Municipal Corporation of Delhi,
Irrigation and Flood Department of the Government of India,
National Capital Territory of Delhi and the Delhi
Administration. Since then, the writ petition is being
continuously monitored by this Court, till date. During the
pendency of this writ petition, I.A. No. 27 came to be filed,
wherein the learned Amicus Curiae in that case referred to
the address of Dr. A.P.J. Abdul Kalam, the then President of
India, on the eve of the Independence Day. This, inter alia,
related to creating a network between various rivers in the
4
country, with a view to deal with the paradoxical situation
of floods in one part of the country and droughts in other
parts. In other words, it related to the inter-linking of rivers
-
and taking of other water management measures. On 16th
September, 2002, this Court, while considering the said I.A.,
directed that the application be treated as an independent
writ petition and issued notice to the various State
Governments as well as the Attorney General for India and
passed the following order:-
"Based on the speech of the President on
the Independence Day Eve relating to the
need of networking of the rivers because
of the paradoxical phenomenon of flood
in one part of the country while some
other parts face drought at the same
time, the present application is filed. It
will be more appropriate to treat to treat
it as independent Public Interest
Litigation with the cause title "IN RE :
NETWORKING OF RIVERS -- v. ---"
Amended cause title be filed within a
week.
Issue notice returnable on 30th
September, 2002 to the respondents as
well as to the Attorney General.
5
Serve notice on the standing counsel of
the respective States.
Dasti service, in addition, is permitted."
4. This is how I.A. No. 27 in Writ Petition (Civil) No.
725 of 1994 was converted into Writ Petition (Civil) No. 512
of -
2002. The Writ Petition (Civil) No. 512 of 2002 was taken up
for hearing and notice was issued to all the States, inviting
affidavits regarding their stance on the issue of networking
of rivers.
5. In view of the above order, the petitioner in Writ
Petition (Civil) No. 668 of 2002 withdrew Writ Petition (C)
No. 75 of 1998 as well as Writ Petition (C) 15 of 1999, which
leave was granted by this Court.
6. As already discussed above, the petitioner had filed
Writ Petition (Civil) No. 668 of 2002 with somewhat similar
prayers as contained in I.A. No. 27. In that writ petition,
the petitioner has averred that no prayer with regard to
inter linking of rivers covering the southern part of the
6
Peninsular Region had been claimed and it was also his
contention that the southern part was most drought prone
and had been witnessing more inter-state water disputes.
Thus, he had filed Writ Petition (Civil) No. 668 of
2002 and prayers made therein were liable to be allowed.
-
7. In the present case, we are concerned with Writ
Petition (C) No.668 of 2002, Writ Petition (C) No. 512 of
2002 as well as the I.A.s and the contempt petitions filed in
these two petitions. Accordingly, this order shall dispose of
all these matters but we make it clear that presently, we are
not dealing with Writ Petition (C) No. 725 of 1994.
8. It has also been averred by the petitioners and the
intervenors in these petitions that the need to conserve
water resources and assuring their optimum consumption
can be seen from the steps taken in this regard, not only by
the developed countries but also by developing and under-
developed countries. The Government of India has always
shown considerable concern regarding the management of
7
water resources in the country and had framed, for this
purpose, the National Water Policy which is being updated
on a yearly basis. The National Water Policy seeks to make
available water supply to those areas which face shortages.
This aspect of the matter could be effectively dealt with, only
if the various rivers in the country are linked and are
nationalized. This has been a matter of public debate and -
discussion for a considerable time and still continues to be
so, without showing any reflection of ground reality.
9. The Ministry of Irrigation, along with the Central
Water Commission, had formulated in the year 1980 a
National Perspective Plan (NPP) for optimum utilization of
water resources in the country which envisaged inter-basin
transfer of water from water-surplus to water-deficit areas.
Apart from diverting water from rivers which are surplus, to
deficit areas, the river linking plan in its ultimate stage of
development will also enable flood moderation. It was
comprised of two components: Peninsular Rivers
Development and Himalayan Rivers Development. The first
8
involved major inter-linking of the river systems and the
latter envisaged the construction of storage reservoirs on
the principal tributaries of rivers Ganga and Brahmaputra
in India, Bhutan and Nepal. This was to help transfer
surplus flows of the eastern tributaries of the Ganga to the
West, apart from linking the main Brahmaputra and its
tributaries with the Ganga and Mahanadi rivers. The
scheme is divided into four major parts:
i) -
ii) Interlinking of Mahanadi-Godavari-Krishna-
Cauvery rivers and building storages at
potential sites in these basins.
iii) Interlinking of West flowing rivers north of
Bombay and south of Tapi.
iv) Interlinking of rivers Ken & Chambal.
v) Diversion of other west flowing rivers from
Kerala.
9
10. The petitioners have also made several suggestions
which have been appreciated by the competent authorities
on consideration. It is emphasized that the cost is negligible
when compared to the potential benefits which may be
bestowed on the nation. The petitioners rely upon Article
262 of the Constitution, read along with Entry 17, List II
and Entry 56 of List I of the Seventh Schedule to the
Constitution to substantiate their submissions. Finally, the
petitioners submit that the preservation of water resources
is a part of the right to life and livelihood, enshrined in
Article 21 of the Constitution and that the Central
Government should take immediate and urgent steps to
nationalize the rivers, so that equitable and proper -
distribution of water can be ensured for the betterment of
the population. According to them, the Central Government
should also adopt all necessary measures, both scientifically
and naturally, to increase the usable water resources and to
preserve whatever resources the Union of India has already
been naturally gifted with.
10
11. As a result and because of the inaction on the part
of the Central Government and the State Governments, it is
submitted that grant of the reliefs as prayed for in the writ
petition would be in consonance with the constitutional
spirit and in the larger public interest.
12. The learned Amicus Curiae, who had been pursuing
this public cause for a number of years, in furtherance to
the request of this Court, has also submitted a detailed note
with regard to the background and summary of the
proceedings in these petitions.
13. As per the learned Amicus Curiae, on 14th August,
2002, the then President of India, Dr. APJ Abdul Kalam, in
his address to the nation on the eve of Independence Day, -
had observed that the need of the hour was the creation of a
Water Mission which, inter alia, would look into the
question of networking of rivers with a view to deal with the
paradoxical situation of floods in one part of the country
and drought in the other. Based on this and as afore-
recorded, a notice was issued, on 16th September, 2002, to
11
the States and the Attorney General for India as
respondents. In response to the said notice, none of the
States or Union Territories, except the State of Tamil Nadu,
had filed affidavits supporting/opposing the prayers made
in the writ petition. The time for filing of affidavits was again
extended up to 30th September, 2002, but no further
affidavits were received by that time.
14. The learned then Attorney General for India, on
behalf of the Union of India, stated that the Government
had accepted the concept of interlinking of rivers and a High
Powered Task Force would be formed. Therefore, this
Court, vide Order dated 31st October, 2002, recorded that
there is in-principle consensus amongst all States to go
ahead with the project of interlinking of rivers.
-
15. Vide Order dated 30th August, 2004, it was noticed
by this Court that, though there had been a change in the
Government, the then Solicitor General, appearing for the
12
Government, informed this Court that a decision had been
taken, in principle, to continue with interlinking of rivers.
16. A high level Task Force was set up. However, vide
order dated 5th May, 2003, this Court observed that inputs
from other experts, in many fields, were necessary and that
the Task Force was to give due consideration to such
inputs. Feasibility Reports (hereafter, `FR') were prepared
for the intended links. Subsequently, vide its order dated
8th April, 2005, this Court made it absolutely clear that the
orders of the Court in these respects have to be complied
with in letter and spirit. The FR of all links were to be put
on the website after their completion. This Court had also
made observations that the prior consent of any State
Government was not necessary for placing the FRs on the
website and directed them to be so placed. With great
persuasion and efforts, the FRs of 16 links had been placed
on the website. At the request of the Amicus, the website -
was ordered to be made interactive so that people could
submit their response thereto.
13
17. The status report filed on behalf of the Government
of India also showed that a committee of environmentalists,
social activists and other experts would be constituted to be
involved in the consultative process of formulation and
execution of the entire project.
18. The status reports filed, from time to time, have
been considered by this Court.
19. Now, we may deal with the response of various
States, as they appear from the record before us. The
response affidavits have been filed on behalf of ten States.
However, the remaining States have not responded, despite
the grant of repeated opportunities to do so. While the
States of Rajasthan, Gujarat and Tamil Nadu have
supported the concept of inter-linking of rivers, the State of
Madhya Pradesh had stated that networking of rivers is a
subject falling under the jurisdiction of the Central
Government and the Central Government should consider
the matter. The -
14
States of Karnataka, Bihar, Punjab, Assam and Sikkim have
given their approval to the concept in-principle, but with
definite reservations, i.e., a kind of qualified approval,
arguing that the matters with regard to the environmental
and financial implications, socio-economic and international
aspects, such as inter-basin water transfer, need to be
properly examined at the appropriate levels of the
Government. For example, all the rivers in Bihar originate
from Nepal and it may be necessary or desirable to take
consent of neighbouring countries, is a matter which would
require consideration of the appropriate authority in the
Central Government. According to the State of Punjab,
inter-linking of rivers should be started only from water-
surplus States to States facing water deficit. The States of
Assam, Sikkim and Kerala had raised their protests on the
grounds that they should have exclusive right to use their
water resources and that such transfer should not affect
any rights of these States. The State of Sikkim was
concerned with particular reference to tapping of the hydro
-
15
power potential in the State and the State of Kerala entirely
objected to long distance, inter-basin, water transfer.
20. The Union of India filed three different affidavits
dated 25th October, 2002, 5th May, 2003 and 24th December,
2003. From these affidavits, the stand of the Union of India
appears to be that networking of rivers had been considered
with great seriousness even after the 1972 Rao Committee
Report. Surveys and studies were underway. The 1980
National Perspective Plan of the erstwhile Ministry of
Irrigation, presently the Ministry for Water Resources,
envisaged inter-basin transfer from water-surplus to deficit
areas. It would have direct benefits, like the irrigation of 35
million hectares (Mha), full exploitation of existing irrigation
projects of 140 Mha, power generation of 34 million Kilowatt
(KW); besides the indirect benefits like flood control,
navigation, water supply, fisheries, pollution control,
recreation facilities, employment generation, infrastructure
and socio-economic development etc. With regard to the
approvals required, it is submitted that the Ministry of
Environment and Forests, Union of India had given some -
16
clearances, while refusing the same in other cases. The
consent of some of the States had not been received. The
expected financial implication as far back as in 2002 was
Rs.5,60,000 crores.
21. However, the Union of India has submitted that
there is no necessity for formation of a high-powered
committee as prayed for in the petitions. The high-level
task force is to be set up for considering the modalities of
state-wise consensus. The NWDA was set up as
autonomous registered society under the aegis of Ministry of
Water Resources, in New Delhi in 1992, for the purposes of
preparation of FRs, conduct of water-balance and other
scientific studies, etc. for Peninsular Region rivers (and for
Himalayan Region rivers also, since 1990) and is headed by
the Union Minister of Water Resources. The Chief Ministers
and/or the Ministers and the Secretaries as their nominees
for Water Resources/Irrigation of the State governments are
its members. The pre-feasibility reports of all 30 identified
links had been completed by the NWDA.
17
-
22. The Union of India and some states have shown
their concerns and their apprehensions about these
projects, including questioning the reliability of water
supply from distant sources, distribution of water given the
existing tribunal awards and the continued availability of
existing water surpluses.
23. In another affidavit, the Union of India referred to
the Terms of Reference to the Task Force and the
appointment of its Members. Action Plan I was prepared,
which was expected to be implemented by 2016. Out of the
independent links to be pursued for discussion, the first
were the links in the States of Gujarat, Maharashtra,
Chattisgarh; secondly, the States of Karnataka, Madhya
Pradesh, Uttar Pradesh and Rajasthan were to be included
in discussions and thirdly, the States of Andhra Pradesh,
Tamil Nadu and Orissa were to be invited for discussion.
The Detailed Project Reports (hereafter, `DPR') were expected
to be completed by December, 2006. However, from the
18
record, it appears that these DPRs have not been completed
even till today. The scheme of inter-linking of -
rivers/preparation of DPRs is stated to be under review by
different groups and authorities.
24. The Union of India also intended that these project
reports should encompass water sector schemes, rainwater
harvesting schemes etc., as these cannot be implemented
independent of the inter-linking scheme. The last of the
affidavits filed on behalf of the Union of India was in
December, 2003. This affidavit gives details of the States,
with which a dialogue was to be held as also the details of
constitution of sub-committees. The Terms of Reference of
the Task Force included the approval of all links. With the
intention to arrive at a general consensus, before entering
into agreements, the Union of India has discussed details
with Maharashtra and Gujarat and preliminary discussion
has taken place with the States of Andhra Pradesh,
Chattisgarh, Karnataka, Orissa, Tamil Nadu and
Pondicherry. According to the Union of India, invoking the
19
matter internationally, at this stage, was not advisable as
the matter was premature. The NWDA was to begin the DPR
for the first link, i.e., the Ken-Betwa project, which itself -
was expected to take 30 months time. In this, the DPR has
now been prepared; however, the implementation is yet to
begin. We must notice that in all other links even the DPRs
are not ready, as of now. The draft Memorandum of
Understanding (hereafter, `MoU') had been circulated for
conduct of DPR of three more Peninsular links. The
Standing Committee of the Parliament on Water Resources,
(hereafter, `the Standing Committee'), in its report for the
year 2004-05 has commented that for the purpose of
preparation of DPRs for the Ken-Betwa link and the Parbati-
Kalisindh-Chambal link projects, a sum of Rs.14 crores had
been earmarked, out of the total Rs.35 crores allocated for
NWDA. However, the Standing Committee had been
constrained to observe that, though the FR of the Ken-
Betwa link was completed in November, 1996, the project
was still at a nascent stage. At the time of the report in
2004-05, the basic MoU between the Governments of Uttar
20
Pradesh and Madhya Pradesh, for preparation of DPR, still
remained to be signed, on the ground that the State of Uttar
Pradesh required more water to be allocated to it. They -
further observed that, if the Ministry of Water Resources,
Government of India had set a time frame for finalization of
issues like this, the precious time of eight years would not
have been lost. The matter still rests at that stage. Today,
though DPR has been prepared for this link alone, no link
project has reached the implementation stage.
25. The report of the Standing Committee which, inter
alia, had examined the river inter-linking proposal was
presented to the Parliament of India on 23rd August, 2004. It
was strongly recommended that the Government should
take firm steps and fix a definite time frame to lay down the
guidelines for completion of FRs, preparation of DPRs and
completion of projects so that they may be completed and
the benefits accrued within reasonable time and costs. It
was the opinion of the Standing Committee that the inter-
linking of Himalayan and Southern region rivers, if done
21
within a definite schedule, would save the nation from the
devastating ravages of chronic droughts and floods. The
recommendations of the Standing Committee deal primarily
with two kinds of States; the States having water shortage -
and the States having surplus water. Still, there would be a
third category of States, which would be comprised of those
States which have just sufficient water and therefore, do not
fall in either the flood-affected or the drought-affected
categories of States. The role of such States may not be
very project-related; but, their consent/concurrence is
needed for complete implementation of the programme.
Their role is relevant as some canal projects, linking
different rivers, may pass through such States. But as
already noticed, except one, no other DPR has so far been
finalized and in fact, none put into implementation. Thus,
this question would remain open and has to be examined at
the appropriate stage by the competent forum.
Projection of Status Reports : -
22
26. Different Status Reports have been filed in this
case. The last of the Status Reports have been filed by the
Union of India on 18th March, 2011. It has been pointed out
that the NWDA, which was to complete the task relating to
preparation of FRs and DPRs of link projects, has completed
-
208 preliminary water-balance study of basins, sub-basins
and diversion points, 74 toposheets and storage capacity
studies of reservoirs, 37 toposheet studies of link
alignments and 32 pre-feasibility reports of links, towards
the implementation of inter-linking of rivers in the country.
Based on these studies, this agency identified 30 links (16
under the peninsular river development component and 14
under the Himalayan river development component) for
preparation of FRs. The process of consensus building is
on-going, in regard to the feasibility of implementing other
interlinking projects. These reports have shown that a
significant effort and attempts have been made and the
unquestionable benefits that would accrue on the
23
implementation of the interlinking projects will be to benefit
the country at large. One aspect that needs to be noticed is
that, till today, no minor or major project has been actually
implemented at the ground level despite the fact that this
case has been pending before this Court for more than ten
years. Only the DPR of the Ken-Betwa link has been
prepared and its implementation is awaiting the approval of
-
the State Governments as well as the allocation of funds,
even to begin the work. This does not speak well of the
desire on the part of any of the concerned Governments to
implement these projects, despite the fact that there is
unanimity of views among all that this project is in the
national interest.
27. The Committee of Environmentalists, Social
Scientists and other Experts on inter-linking of rivers, had
met after the submission of the Status Report dated 5th
March, 2010. They discussed various aspects of different
projects. In the Himalayan region, FRs of two remaining
24
links were completed, i.e., the Sarda-Yamuna link and
Ghagra-Yamuna Link. The field survey and investigation for
Sone Dam on the southern tributaries of the Ganga link,
was still in progress. The Ministry of Environment and
Forests had refused permission for survey and investigation
of the Manas-Sankosh-Tista-Ganga link, but the toposheet
study for the alternative Jogigopa-Tista-Farakka link has
been completed. In the Peninsular region, the projects
relating to Bedti-Varada and Netravati-Hemavati-Tapi are
awaiting -
Karnataka Government's consent. In Netravati-Hemvati-
Tapi link, the Karnataka Government has refused to
consent even to the preparation of FR until decision of
related cases, pending in the Courts.
28. In the Dhadun dam, relating to the Ken-Betwa link,
two power houses and a link canal will be taken up in Phase
I and the Betwa basin will be completed in Phase-II. Upper
Betwa Sub-Basin will receive priority completion and minor
projects are proposed to be completed first. Phase-II will be
25
commenced after survey and investigation. However, this
project is still at the survey and planning stage and even
comprehensive clearances, from the Uttar Pradesh
Government, have not been received. The State of Rajasthan
refuses to consider the MoU for another priority link,
Parbati-Kalisindh-Chambal, until the updation of its
hydrology project.
29. Similarly, there are other projects where public
hindrances are caused against carrying out of survey and
investigation. In the Par-Tapi-Narmada and Damanganga--
Pinjal links, residents have shown concern about the extent
of land to be submerged on the construction of the proposed
dam. In response, the State Governments of Gujarat and
Maharashtra have set up Committees to take up the
matters with the panchayats and to commence the projects.
30. The NWDA had also, in the course of framing of its
policies, proposed intra-state links. Except for six States
and four Union Territories, all other States and Union
Territories have interest in these intra-State links. There
26
are eight inter-linking projects which are under review by
different State authorities. However, the details of the
divergence between the State Governments are not clearly
spelt out, even as of now.
31. An additional study was undertaken by the National
Council for Applied Economic Research (hereafter, `NCAER')
and the revised final report, published in April 2008,
assessed the economic impact of the rivers interlinking
program and suggested an investment roll out plan, i.e., a
practical implementation schedule, for the same. A copy of
-
this report was submitted in the year 2011, before this
Court.
32. As already noticed, the Task Force was constituted
by the Central Government for interlinking of river projects
in December 2002. It submitted its Action Plans I and II for
implementation of the project and also finalized the terms of
reference for the purposes of the DPRs. Action Plan I,
27
submitted in April 2003, envisages completion of 30 FRs by
the authorities by December 2005.
33. Action Plan II, submitted in April 2004, mainly
envisaged the appraisal of individual projects, in respect of
their economic viability, socio-economic and environmental
impacts, preparation of resettlement plans and reaching
speedy consensus among States. The reports have been
submitted to the Central Government and are under
consideration. With this completion of work, the Task Force
had completed its object and stood dissolved. After winding
up of the Task Force, a Special Cell on interlinking of rivers
was created under the Ministry of Water Resources. -
However, what happened to the two Action Plan reports
submitted by the Task Force is a matter left to the
imagination of anyone.
34. From the above, it is not difficult to visualize the
difficulties in preparation, execution, financing and
consensus building, still, it is the need of the hour to carry
28
out these projects more effectively and with greater
sensitivity.
Economic Aspect :
35. As per the report of the Standing Committee for the
year 2004-05, which was presented to the Parliament of
India, the planned budgetary allocation was made under
NWDA as follows :
36. Actual allocation for 2002-03 was Rs.15.30 crores,
the budget estimate for 2003-04 was 20 crores, the revised
estimate for the same year was Rs.21.95 crores and for
2004-05, the budget estimate was Rs.35 crores.
-
37. The Amicus Curiae, in his report, has noted that the
new aggregated cost of the entire program varies between
Rs. 4,44,331.20 crores, at 2003-04 prices, and
Rs.4,34,657.13 crores, at 2003-04 prices, depending on the
implementation of the proposed Manas-Sankosh-Tista-
Ganga link or the Jogigopa-Tista-Farakka link respectively.
29
38. As already noticed, the NCAER had been assigned
the work of assessing the economic impact of river
interlinking programmes, which in turn, suggested an
investment roll-out plan for the same. The report of the
NCAER was prepared in April, 2008. This report considers
various financial aspects and the impact of various river
interlinking projects in India. They point out that after
independence, irrigation was viewed as infrastructure for
agricultural development rather than as a commercial
enterprise. In 1983, the Nitin Desai Committee forwarded
the idea of Internal Rate of Return (hereinafter referred to as
`IRR'), suggesting that projects should normally earn a
minimum IRR of 9 per cent. However, for drought-prone
and hilly areas and in areas with only 75 per cent of
dependable flows -
in the basin, a lower IRR of 7 per cent was recommended.
Successive Finance Commissions also stressed on recovery
of a certain percentage of the capital investment apart from
working expenses. The Eleventh Finance Commission has
recognized that this would have to be done in a gradual
30
manner. Receipts should cover not only maintenance
expenditure but also leave some surplus as return on the
capital invested.
39. This NCAER report, with some significance, noticed
that until 2003-04, it was only in four years that the
economy grew at more than 8 per cent per annum. Each of
these years coincided with very high rate of growth in the
agricultural sector. In contrast, industry and services
sectors have, at best, pulled up the Gross Domestic Product
(GDP) growth to 7.3 per cent per annum when there was no
significant contribution from the agricultural sector. The
report clearly opines that interlinking of river projects will
prove fruitful for the nation as a whole and would serve a
greater purpose by allowing higher returns from the
agricultural sector for the benefit of the entire economy. -
This would also result in providing of varied benefits like
control of floods, providing water to drought-prone States,
providing water to a larger part of agricultural land and
even power generation. Besides annuring to the benefit of
31
the country, it will also help the countries like Nepal etc.,
thus uplifting India's international role. Importantly, they
also point out to a very important facet of interlinking of
rivers, i.e., it may result in reduction of some diseases due
to the supply of safe drinking water and thus serve a greater
purpose for humanity.
40. The Bhakra dam has also been cited as an example
in this report as having enabled the States of Punjab and
Haryana to register faster growth as compared to the rest of
the country. This project provided an additional irrigated
area to the extent of 6.8 million hectares over 35 years.
Increased irrigation intensity led to increased usage of High
Yielding Variety (HYV) seeds which at present constitute
more than 90 per cent of the area under wheat and 80 per
cent of area under paddy cultivation. The region uses some
of the most advanced agricultural technologies in India. -
NCAER, while depicting the poverty ratio vis-`-vis these
States and the other States all over India, has provided the
following tables:
32
States Rural Urban Al
l
Ar
ea
s
1973-74 1999-00 1973-74 1999-00 1973-74 1999-
00
Punjab 28.21 6.35 27.96 5.75 28.15 6.16
Haryana 34.23 8.27 40.18 10.00 35.36 8.74
All India 56.44 27.09 49.01 23.62 54.88 26.10
41. Thus, they conclude that the Bhakra Dam was
instrumental in helping India achieve food security, in
reducing volatility of food grain prices and declining the
incidence of poverty in those regions.
42. Besides pointing out the benefits of Bhakra Dam,
the NCAER Report also states that the link canals have both
short and long term impacts on the economy. Short term
impact of link canals is in the form of increased employment
-
33
opportunities and the growth of the services sector. In the
medium to long term, the major impact of link canals is
through increased and assured irrigation. Although the
major and direct gainers from the interlinking of rivers (ILR)
programme will be agriculture and agriculture-dependant
households, the entire economy will benefit because of
increased agricultural production and other benefits.
43. The Report of the NCAER has pointed out various
benefits of rivers interlinking programme at the State and
National levels. However, when coming to the financial
aspect of the programme, two concepts are of great
relevance: firstly, the investment strain and secondly, the
scope of financial investment and its recoupment.
Primarily, it is clear from the records before us that this is a
programme/project on which the nation and the States
should have a rational but liberal approach for financial
investment. Referring to the financial strain, the NCAER
Report projects two sets of investment rollout plan. At the
start of the programme, investment would be small, but
34
would increase gradually peaking in the year 2011-2012. It
-
will then start falling. Investment rollout from the year
2008-2009 to 2014-2015 will have considerable strain on
the Central Government finances, especially after the
passage of Fiscal Responsibility and Budget Management
Rules (FRBMR). The Government is now committed to
reducing fiscal deficit by 0.3 percentage points of GDP every
year and was to reduce the fiscal deficit down to 3 per cent
of GDP by the fiscal year 2007-2008. The FRBMR also put
a restriction on Government borrowings. In each
subsequent financial year, the limit on borrowings of 9 per
cent of GDP was to progressively reduced by at least 1
percentage point of GDP, a commitment which is to be
adhered to by all Governments. The investment plan
prepared by the NCAER was intended to help in clearing
doubts in the minds of the people and opponents of the
programme that investment is not going to take place in a
single or couple of years, but over a period of at least ten
years. Since the impact analysis undertaken by the
35
NCAER assumes that the Interlinking of Rivers (ILR)
programme is entirely financed by the Central Government,
-
a longer rollout plan would also help in reducing the impact
on public finances.
44. The NCAER has also suggested changes which are
necessary for the effective implementation of the river
networking programme. Inter alia, it includes the pricing of
irrigation benefits and improvement in the quality of service.
It will be useful to notice at this stage, these suggested
changes termed as `Changes necessary' which are as under:
"A revision of water rates is necessary in
the interest of efficiency. However, it
should go hand in hand with
improvement in the quality of service
(Government of India 1992). Specific
recommendations were made by the
Committee on Pricing of Irrigation Water
(Government of India, 1992) with regards
to pricing:
1. Water rates are a form
of user charges, and
not a tax. Users of
public irrigation must
36
meet the cost of the
irrigation service.
2. As irrigation is one of
the key inputs similar
to seeds and fertilizer,
its pricing should be
addressed in the first
step.
3. Under-pricing of
irrigation is mainly
responsible for the -
4. deteriorating quality of
irrigation services. A
revision of water rates
is necessary in the
interest of efficiency.
However, it should go
hand in hand with
improvement in the
quality of service.
5. Rates for non-
agricultural users
(domestic and
industrial) should also
be revised so that full
cost is recovered.
6. Rates should be based
on O&M norms and
capital charges
(interest and
depreciation).
37
7. Averaging of rates by
region and/or
categories of projects
is desirable.
Categorisation could
be:
major and medium storage
system,
major and medium projects
based exclusively on
barrages/diversion works,
minor surface irrigation
works,
lift irrigation canals, and
lift irrigation from
groundwater.
8. Distinction of rates in
terms of tail and head
reaches of a system,
soil quality, and other
criteria for rate
determination should
be approached with
caution due to
complexities involved
with it.
9. -
10.Water rates should be
applied on two-part
tariff. All lands in
38
command area should
pay a flat annual fee
on a per hectare basis
for membership of the
system and a variable
fee linked to the actual
extent of service
(volume or area) used
by each member.
11.The move to full-
fledged volumetric
pricing cannot be
introduced
immediately. The
proposed
rationalization of water
pricing will have to be
accomplished in three
phases.
12.In the first phase,
rationalization and
simplification of the
existing system of
assessment (based on
crop-wise irrigated
area on an individual
basis) to a system of
season-specific areas
rates should be taken
up. The level of cost
recovery to be aimed
during the first phase
39
should at least cover
O&M costs and 1 per
cent interest on capital
employed. The
irrigated area under a
crop which spreads
over to more than one
season should be
charged at the rates
applicable to different
seasons. However, in
each season,
distinction should be
made -
13.between paddy,
sugarcane, and
perennial crops.
14.In the second phase,
the aim should be on
volumetric measure for
irrigation water
charging.
15.In third phase, the
focus should be on
people participation
for improving water
use and, thus,
productivity.
The recommendations of the Committee
on Pricing of Irrigation (also known as the
Vaidynathan Committee Report) were
further studied by the Group of Officers
formed by the Planning Commission in
40
October, 1992. It recommended that the
irrigation water rates should cover the full
annual O & M cost in phases in the next
five years. These recommendations and
the Vaidyanathan Committee Report
were, in February 1995, sent to all the
States/union territories that had started
taking action with several states revising
water rates upwards."
To sum up the short comings and their analysis,
the report states as under :
"One shortcoming of the above analysis is
that it has not considered the issue of
cost of resettlement of displaced people
due to ILR Project. A draft National
Rehabilitation Policy was prepared with
the objective of minimizing development
induced displacement of people by -
promoting non-displacing or least
displacing alternatives for meeting
development objectives. The draft policy
is yet to be finalized by the National
Advisory Council (NAC). The NAC intends
to finalise a rehabilitation package that
includes, inter alia, providing land for all
agricultural families, implementing
special employment guarantee
programmes, providing homesteads and
dwelling houses, bearing transportation
cost, providing training and other support
services, instituting a rehabilitation grant
in order to compensate loss of
income/livelihood. The ILR project has to
consider displacement costs on the basis
of norms stipulated in the national
41
Rehabilitation Policy as and when it gets
finalized."
45. Besides making the above observations and
recommendations, the NCAER also suggests that after
completion of the linking of rivers programme, the different
river links should be maintained by separate river basin
organizations, which would all be functioning under the
direct control of the Central Water Commission or such
other appropriate central body.
46. In the summing up of its Report, the NCAER has
stated that water is essential for production of food, -
economic growth, health and support to environment. Its
main contribution to economic well-being is through its use
of agriculture to improve food security. Water is essential to
increase agricultural productivity under modern technology.
Nearly 64 per cent of the population in rural area and 4 per
cent in urban area depends on agriculture as their principal
source of income. The analysis carried out in the State
shows that the ILR programme has the potential to increase
the growth rate of agriculture, which declined from 4.4 per
42
cent in 1980s to 3.0 per cent in 1990s and which is still
susceptible to the vagaries of rainfall. In order to put our
economy on the high growth path and improve the quality
for life of people in the rural areas, a mixed policy of both
increased availability of irrigation and increasing non-farm
activity is required.
Principles Applied:
47. From the above narrated facts, stated
recommendations and principles, it is clear that primarily
there is unanimity between all concerned authorities -
including the Centre and a majority of the State
Governments, with the exception of one or two, that
implementation of river linking will be very beneficial. In
fact, the expert opinions convincingly dispel all other
impressions. There shall be greater growth in agricultural
and allied sectors, prosperity and stimulus to the economy
potentially causing increase in per capita income, in
addition to the short and long term benefits likely to accrue
by such implementation. These would accrue if the expert
43
recommendations are implemented properly and within a
timeframe. Then there shall be hardly any financial strain
on the economy. On the contrary, such implementation
would help advancement of India's GDP and bring greater
wealth and prosperity to the nation as a whole. Besides
actual benefits accruing to the common man, the
Governments also benefit from the definite possibility of
saving the States from drought on the one hand and floods
on the other. This project, when it becomes a reality, will
provide immeasurable benefits. We see no reason as to why
the Governments should not take appropriate and timely -
interest in the execution of this project, particularly when,
in the various affidavits filed by the Central and the State
Governments, it has been affirmed that the governments are
very keen to implement this project with great sincerity and
effectiveness.
48. The States of Rajasthan, Gujarat, Tamil Nadu have
fully supported the concept. Madhya Pradesh has also
supported the Scheme, but believes that it must be
44
implemented by the Central Government. The States of
Karnataka, Bihar, Punjab and Sikkim have given some
qualified approvals. Their main concern is, with regard to
inter basin transfer, which must involve quid pro quo, as
with any other resources inter-linking must be from water
surplus to water deficit States and in regard to
environmental and financial implications. Some of the
other States are not connected with these projects as they
have no participation in inter-linking of rivers. The State of
Kerala has protested to some extent, to the long distance
inter basin water transfer on the basis that the State needs
-
water to supply their intricate network of natural and man-
made channels.
49. It is also the case of the State of Kerala that their
rivers are monsoon-fed and not perennial in nature,
therefore, Kerala experiences severe water scarcity during
summer or off-monsoon months.
45
50. The stand taken by the respective States, as noticed
above, shows that, by and large, there is unanimity in
accepting interlinking of rivers but the reservations of these
States can also not be ignored, being relatable to their
particular economic, geographical and socio-economic
needs. These are matters which squarely fall within the
domain of general consensus and thus, require a framework
to be formulated by the competent Government or the
Legislature, as the case may be, prior to its execution.
51. The National Commission for Review of the Working
of the Constitution (NCRWC) 2002 in its Report also dealt
with another important facet of river interlinking i.e. sharing
of river waters. Explaining the doctrines of river sharing, it
-
described Doctrine of Riparian Rights, Doctrine of Prior
Appropriation, Territorial Integrity Theory, Doctrine of
Territorial Sovereignty, English Common Law Principle of
Riparian Right, Doctrine of Community Interest, Doctrine of
Equitable Apportionment. It also explained that when
46
determining what a reasonable and equitable share is, the
factors which should be taken into consideration. In that
behalf, it specifically referred to agreements, judicial
decisions, awards and customs that already are in place.
Furthermore, relative economic and social needs of
interested states, volume of stream and its uses, land not
watered were other relevant considerations. Thus, it will be
for the expert bodies alone to examine on such issues and
their impact on the project.
52. Be that as it may, we have no hesitation in
observing that the national interest must take precedence
over the interest of the individual States. The State
Governments are expected to view national problems with a
greater objectivity, rationality and spirit of service to the
nation and -
ill-founded objections may result in greater harm, not only
to the neighbouring States but also to the nation at large.
47
53. Now, we may refer to certain constitutional
provisions which have bearing on the matters in issue
before us. Under the constitutional scheme, there is a
clear demarcation of fields of operation and jurisdiction
between the Legislature, Judiciary and the Executive. The
Legislature may save unto itself the power to make certain
specific legislations not only governing a field of its
legislative competence as provided in the Seventh Schedule
of the Constitution, but also regarding a particular dispute
referable to one of the Articles itself. Article 262 of the
Constitution is one of such powers. Under this Article, the
Parliament, by law, can provide for the adjudication of any
dispute or complaint with respect to the use, distribution
and control of water of any inter-state river or river valley.
54. Article 262(2) of the Constitution opens with a non-
obstante expression, that `notwithstanding anything
contained in the Constitution, Parliament may by law -
provide that neither the Supreme Court nor any other Court
shall exercise jurisdiction in respect of any dispute or
complaint as referred to in Article 262(1)'. In other words,
48
the Parliament can reserve to itself, the power to oust the
jurisdiction of the courts, including the highest Court of the
land, in relation to a water dispute as stated under this
Article. The jurisdiction of the Court will be ousted only
with regard to the adjudication of the dispute and not all
matters incidental thereto. For example, the Supreme
Court can certainly direct the Central Government to fulfill
its statutory obligation under Section 4 of the Act, which is
mandatory, without deciding any water dispute between the
States. [See : Tamil Nadu Cauvery Neerppasana
Vilaiporulgal Vivasayigal Nala Urimai Padhugappu Sangam
v. Union of India & Ors., AIR 1990 SC 1316].
55. One of the possible views taken with regard to
Article 262 is that the use of expression `may' in the
Constitution does not indicate a clear legislative intent,
thus, it may be possible that Section 11 of the Act could
refer only to such disputes as are already referred to a
-
49
Tribunal and which are outside the purview of the courts.
Once a specific adjudicatory mechanism is created, that
machinery comes into operation with the creation of the
Tribunal and probably, then alone will the Court's
jurisdiction be ousted.
56. The Seventh Schedule to the Constitution spells out
different fields of legislation under the Union List (List I),
State List (List II) and Concurrent List (List III). Entry 56 of
List I empowers the Union Parliament to enact laws in
relation to the regulation and development of inter-state
rivers and river valleys, to the extent that such regulation
and development is declared by the Parliament, by law, to
be expedient in the public interest. Entry 57 deals with
fishing and fisheries beyond territorial waters. Entry 97 is
a residual entry, which confers those legislative fields upon
the Union Parliament which are not specifically provided for
under List II and/or List III. Entry 17 relates to water,
that is to say, water supplies, irrigation and canals,
drainage and embankments, water storage and water
power, subject to the provisions of Entry 56 of List I. -
50
Agriculture is again a State subject. The Concurrent List
(List III) does not contain any entry in regard to water and
agriculture, as such.
57. Entry 42 of List III is the law relating to acquisition
and requisition of property by the Union and the State
Parliaments. The result is that, in relation to acquisition,
the Centre and the State, both, have power to legislate.
Entry 20 of List III deals with economic and social planning.
Thus, with the aid of the residual powers under Entry 97,
List I, the Union Parliament gets a very wide field of
legislation, relatable to various subjects.
58. The River Boards Act, 1956 was enacted by the
Parliament under Entry 56 of List I. The Inter-State Water
Disputes Act was also enacted with reference to the same
Entry. Whereas the mandate of the latter is to provide a
machinery for the settlement of disputes, the former is an
Act to establish Boards for the regulation and development
of inter-State river basins, through advice and coordination,
-
51
and thereby to reduce the friction amongst the concerned
States.
59. It is this kind of coordination which is required to
be generated at all levels to implement the inter-linking of
rivers program, as proposed. Huge amounts of public
money have been spent, at the planning stage itself and it
will be travesty of good governance and the epitome of harm
to public interest, if these projects are not carried forward
with a sense of sincerity and a desire for its completion.
60. In a more recent judgment of this Court in the case
of State of Karnataka v. State of Andhra Pradesh & Ors.
[(2000) 9 SCC 572], a Constitution Bench of this Court took
the view that in Section 11 of the Act, the expression `use,
distribution and control of water in any river' are the key
words in determination of the scope of power conferred on a
Tribunal constituted under Section 3 of the Act. If a matter
fell outside the scope of these three crucial words, the power
of Section 11 in ousting the jurisdiction of the courts in
respect of any water dispute, which is otherwise to be -
52
referred to Tribunal, would not have any manner of
application. The test of maintainability of a legal action
initiated by a State in a Court would thus be, whether the
issues raised therein are referable to a Tribunal for
adjudication of the manner of use, distribution and control
of water.
61. Further, this Court while declining to issue a
mandamus directing the States of Karnataka, Andhra
Pradesh and Maharashtra to constitute a common Tribunal,
held:
"168. ......It is settled law that such a
direction cannot possibly be granted so
as to compel an authority to exercise a
power which has a substantial element of
discretion. In any event the mandamus to
exercise a power which is legislative in
character cannot be issued and I am in
full agreement with the submission of Mr.
Solicitor General on this score as well. At
best it would only be an issue of good
governance but that by itself would not
mean and imply that the Union
Government has executive power even to
force a settlement upon the State."
-
53
62. The above stated principles clearly show that a
greater element of mutuality and consensus needs to be
built between the States and the Centre on the one hand,
and the States inter se on the other. It will be very difficult
for the Courts to undertake such an exercise within the
limited scope of its power of judicial review and even on the
basis of expanded principles of Public Interest Litigation. A
Public Interest Litigation before this Court has to fall within
the contours of constitutional law, as no jurisdiction is
wider than this Court's constitutional jurisdiction under
Article 32 of the Constitution. The Court can hardly take
unto itself tasks of making of a policy decision or planning
for the country or determining economic factors or other
crucial aspects like need for acquisition and construction of
river linking channels under that program. The Court is not
equipped to take such expert decisions and they essentially
should be left for the Central Government and the
concerned State. Such an attempt by the Court may
amount to the Court sitting in judgment over the opinions of
the experts in the respective fields, without any tools and -
54
expertise at its disposal. The requirements in the present
case have different dimensions. The planning, acquisition,
financing, pricing, civil construction, environmental issues
involved are policy decisions affecting the legislative
competence and would squarely fall in the domain of the
Government of States and Centre. We certainly should not
be understood to even imply that the proposed projects of
inter-linking of rivers should not be completed.
63. We would recommend, with all the judicial authority
at our command, that these projects are in the national
interest, as is the unanimous view of all experts, most State
Governments and particularly, the Central Government.
But this Court may not be a very appropriate forum for
planning and implementation of such a programme having
wide national dimensions and ramifications. It will not only
be desirable, but also inevitable that an appropriate body
should be created to plan, construct and implement this
inter linking of rivers program for the benefit of the nation
as a whole.
55
-
64. Realizing our limitations, we would finally dispose of
this Public Interest Litigation with the following directions:-
(I) We direct the Union of India and particularly the
Ministry of Water Resources, Government of India, to
forthwith constitute a Committee to be called a `Special
Committee for Inter-linking of Rivers' (hereinafter
referred as `the Committee') of which, the following
shall be the Members:-
(a) The Hon'ble Minister for Water Resources.
(b) Secretary, Ministry for Water Resources.
(c) Secretary, Ministry of Environment and Forests.
(d) Chairman, Central Water Commission.
(e) Member-Secretary, National Water Development
Authority.
(f) Four experts to be nominated, one each from the
following Ministries/bodies:
(i) One Expert from the Ministry of Water
Resources
(ii) One Expert from the Ministry of Finance
56
(iii) One Expert from the Planning Commission
-
(iv) One Expert from the Ministry of Environment
& Forests.
(g) Minister for Water and/or Irrigation from each of
the concurring States, with the Principal
Secretary of the concerned Department of the
same State.
(h) The Chief Secretary or his nominee not below the
rank of the Principal Secretary of the concerned
Department in case of any other State involved
directly or indirectly in the water linking river
project.
(i) Two social activists to be nominated by each of
the concerned Ministries.
(j) Mr. Ranjit Kumar (Amicus Curiae).
(II) The Committee shall meet, at least, once in two
months and shall maintain records of its discussion
and the Minutes.
57
(III) In the absence of any person from such meeting,
irrespective of his/her status, the meeting shall not be
adjourned. If the Hon'ble Minister for Water Resources
-
is not available, the Secretary, Ministry of Water Resources,
Government of India, shall preside over the Meeting.
(IV) The Committee would be entitled to constitute such
sub-committees, as it may deem necessary for the
purposes of carrying on the objects of the Inter-Linking
of River Program, on such terms and conditions as it
may deem proper.
(V) The Committee shall submit a bi-annual report to the
Cabinet of the Government of India placing before it
the status-cum-progress report as well as all the
decisions required to be taken in relation to all matters
communicated therewith. The Cabinet shall take all
final and appropriate decisions, in the interest of the
countries as expeditiously as possible and preferably
within thirty days from the date the matters are first
placed before it for consideration.
58
(VI) All the reports of the expert bodies as well as the status
reports filed before this Court during the pendency of
this petition, shall be placed before the Committee for
-
its consideration. Upon due analysis of the Reports and
expert opinions, the Committee shall prepare its plans
for implementation of the project.
(VII) The plans so prepared shall have different phases,
directly relatable to the planning, implementation,
construction, execution and completion of the project.
(VIII) We are informed that large sums have been spent on
preparation of initial and detailed project reports of the
project `Ken-Betwa Project'. The DPR is now ready.
The States of Madhya Pradesh and Uttar Pradesh and
also the Central Government had already given their
approval and consent. The clarifications sought will be
discussed by the Committee. We would direct the
Committee to take up this project for implementation
at the first instance itself.
59
(IX) Keeping in view the expert reports, we have no
hesitation in observing and directing that time is a
very material factor in the effective execution of the
Interlinking of Rivers project. As pointed out in the
Report by NCAER and by the Standing Committee, the
-
delay has adversely affected the financial benefits that could
have accrued to the concerned parties and the people
at large and is in fact now putting a financial strain on
all concerned.
(X) It is directed that the Committee shall take firm steps
and fix a definite timeframe to lay down the guidelines
for completion of feasibility reports or other reports
and shall ensure the completion of projects so that the
benefits accrue within reasonable time and cost.
(XI) At the initial stages, this program may not involve
those States which have sufficient water and are not
substantially involved in any inter-linking of river
programme and the projects can be completed without
their effective participation.
60
(XII) However, the Committee may involve any State for
effective completion of the programme at any
subsequent stage.
(XIII) There are projects where the paper work has been
going for the last ten years and at substantial cost to
the public exchequer. Therefore, we direct the Central
-
and the State Governments to participate in the program
and render all financial, administrative and executive
help to complete these projects more effectively.
(XIV) It is evident from the record that the Reports
submitted by the Task Force have not been acted
upon. Thus, the entire effort put in by the Task Force
has practically been of no use to the concerned
governments, much less the public. The Task Force
has now been wound up. Let the reports of the Task
Force also be placed before the Committee which shall,
without fail, take due note of the suggestions made
therein and take decisions as to how the same are to
be implemented for the benefit of the public at large.
61
(XV) The Committee constituted under this order shall be
responsible for carrying out the inter-linking program.
Its decisions shall take precedence over all
administrative bodies created under the orders of this
Court or otherwise.
-
(XVI) We grant liberty to the learned Amicus Curiae to file
contempt petition in this Court, in the event of default
or non-compliance of the directions contained in this
order.
65. We would fail in our duty if we do not place on
record the appreciation for the valuable and able assistance
rendered by the learned Amicus Curiae and all other senior
counsel and assisting counsel appearing in the present PIL.
66. We not only express a pious hope of speedy
implementation but also do hereby issue a mandamus to
the Central and the State Governments concerned to comply
with the directions contained in this judgment effectively
and expeditiously and without default. This is a matter of
national benefit and progress. We see no reason why any
62
State should lag behind in contributing its bit to bring the
Inter-linking River Program to a success, thus saving the
people living in drought-prone zones from hunger and
people living in flood-prone areas from the destruction
caused by floods.
-
67. With the observations and directions recorded
supra, Writ Petition (Civil) No.512 of 2002, Writ Petition
(Civil) No.668 of 2002 and all the applications filed in both
these writ petitions are hereby finally disposed of with no
order as to costs.
.............................CJI.
[S.H. Kapadia]
..................................,J.
[A.K. Patnaik]
..................................,J.
[Swatanter Kumar]
New Delhi;
February 27, 2012