LawforAll
advocatemmmohan
- advocatemmmohan
- since 1985 practicing as advocate in both civil & criminal laws
WELCOME TO LEGAL WORLD
WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE
Wednesday, February 29, 2012
the buildings in question were constructed in violation of the sanctioned plans and that the flat buyers do not have the locus to complain against the action taken by the Corporation under Section 351 of 1888 Act. Both, the trial Court and the High Court have assigned detailed reasons for declining the petitioners' prayer for temporary injunction and we do not find any valid ground or justification to take a different view in the matter. 17. The submission of Dr. Abhishek Manu Singhvi that the constructed area should be measured with reference to the total area of the plot cannot be accepted for the simple reason that the State Government had sanctioned change of land use only in respect of 13049.45 sq. meters. 18. In view of the above, we may have dismissed the special leave petitions and allowed the Corporation to take action in furtherance of notices dated 19.11.2005 and orders dated 3/8.12.2005, but keeping in view the fact that the flat buyers and their families are residing in the buildings in question for the last
1
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE PETITION (CIVIL) NO. 33471 OF 2011
Esha Ekta Appartments CHS Ltd. and others ... Petitioners
Versus
The Municipal Corporation of Mumbai and another ... Respondents
With
SLP(C) No.33601 of 2011
SLP(C) No.33940 of 2011
SLP(C) No.35324 of 2011
SLP(C) No.35402 of 2011
O R D E R
1. Having failed to convince the trial Court and the High Court to entertain
their prayer for restraining respondent no. 1 - Municipal Corporation of
Mumbai (for short, `the Corporation') from demolishing the buildings
constructed on Plot No. 9, Scheme 58, Worli, Mumbai, the petitioners have
filed these petitions under Article 136 of the Constitution.
2
2. The petitioners are the Cooperative House Building Societies (for short,
`the societies') and their members, who are said to have purchased flats in the
buildings constructed by the developers on the plot in question. Their grievance
is that even though the flats were purchased under a bona fide belief that the
buildings have been constructed in accordance with law, the trial Court and the
High Court did not injunct the Corporation from demolishing the same on the
ground that the latter had taken action in furtherance of the orders passed in
Writ Petition Nos. 2040/1999, 2402/1999, 2403/1999, 2904/1999, 2949/1999
and 1808/2000.
3. The Corporation leased out the plot in question, of which the total area is
17907.60 sq. meters to M/s. Pure Drinks Pvt. Ltd. on 17.1.1962 for general
industrial use. After 18 years and about 11 months, the State Government
issued order dated 1.12.1980 under Section 37(2) of the Maharashtra Regional
and Town Planning Act, 1966 and sanctioned the change of use in respect of
13049.45 sq. meters land from industrial to residential. Between 1980 and
1982, M/s. Pure Drinks transferred that portion of land to the developers for
construction of residential buildings. The building plans submitted by the
developers for construction of 6 buildings comprising of basement, ground and
5 upper floors were sanctioned by the competent authority on 8.6.1981. The
amended building plans submitted by the developers for construction of 9
3
buildings with ground and 5 upper floors were also sanctioned by the competent
authority.
4. In 1984, the developers submitted new building plans proposing
construction of two buildings on stilts with 24 and 16 upper floors respectively,
additional 6th and 7th floors in building no. 2 and additional 6th floor on a portion
of building no. 3. The new plans were rejected by the competent authority on
6.9.1984. Notwithstanding this, the developers continued the construction and
did not stop their activity despite the stop work notice dated 12.11.1984 issued
by the Corporation.
5. After the purchasers of flats formed societies, they along with the
societies filed writ petitions for issue of a direction to the Corporation to
provide water connections. During the pendency of those petitions, the Division
Bench of the High Court took cognizance of the fact that the buildings had been
constructed in violation of the sanctioned plans and passed order dated
11.10.2005 and directed the Additional Commissioner of the Corporation to
appear in person to explain the reason for not taking action against the illegal
construction. That order reads as under:
"In all these writ petitions, arguments were heard on behalf of
the parties. None appeared for respondent no.4 in Writ Petition
No.2904-99, for respondent No.4 in Writ Petition No.2403-99,
for respondent Nos.4 and 5 in Writ Petition No.2402-99, for
respondent nos.4 and 5 in Writ Petition No.1808-2000. Shri
4
N.V. Patil, Sub-Engineer Building and Proposal (City) was
present in Court to assist the Advocate for the Corporation.
2. In the course of the argument, it was revealed by the
Advocate for the Corporation on taking instructions that
original licence for construction was granted in favour of four
persons viz. Shri Manjit Singh Madanjit Singh, Power of
Attorney Holder of S. Karanjit Singh, Chief Executive Officer
of Pure Drink Pvt. Ltd., Shri Ishwarsingh Chawla of PSD
Construction Pvt. Ltd., Shri D.K.Gupta of D.Y. Builders Pvt.
Ltd. and Abdula Yusuf Patel. Pursuant to the illegality in
construction having been found, notices were issued under
Section 53-1 of the M.R.T.P. Act on 20th February, 2002 to all
the four persons mentioned above. Thereafter, sanction was
granted for prosecution of all the four persons and decision in
that regard was taken on 19th May, 2003 by the Executive
Engineer (Building Proposal), CT/1 of the Corporation.
Meanwhile, the panchanama of the illegal construction was
carried out on 13th November, 2002. Besides, the prosecution
was launched against builder, developer and all the occupants
of the building and they were convicted on admission of guilt
and sentenced by way of imposition of fine from Rs.600/- to
Rs.2000/- imposed by the Magistrate. Apart from the above
actions, no other action has been taken by the Corporation in
relation to the illegal construction. The affidavit-in-reply filed
on behalf of the Corporation before issuance of rule in the
petition by Shri Kurmi Deonath Sitaram, Executive Engineer,
DP(City)(I) discloses that initial approval was granted for six
wings consisting of ground plus five upper floors and it was
issued on 9th June, 1981 and Commencement Certificate was
granted on 10th June, 1981. The amendment plans were
approved for nine wings of ground plus five upper floors on
2nd February, 1983. Thereafter, amendment plans proposing
stilt plus twenty-four floors and stilt plus sixteen floors with
additional sixth and seventh floor to building nos.2 and 4 and
additional sixth floor for the part of building no.3 were
submitted but they were refused on 6th September, 1984. In spite
of that, the constructive activities continued and the work
beyond the approved plans was carried out, and therefore Stop
Work notice was issued under Section 353-A of the MMC Act
on 12th November, 1984. However, the work continued. Again
5
new architect submitted further plan with a fresh notice under
Section 337. The same was rejected by the Corporation.
3. The affidavit also discloses the various illegalities committed
in the course of construction of the buildings which include
construction of additional floors without approval, increase in
the height of the building and carrying of construction beyond
the permissible limits of FSI, apart from other illegalities. The
affidavit, however, does not disclose as to what action, if any,
for prohibiting the developer and the owner from proceeding
with the construction, was taken as wall as what action was
taken after illegal construction having been carried out, apart
from launching prosecution and issuance of notices. Even in the
course of the argument, learned Advocate appearing for the
Corporation could not satisfy us about any concrete action
having been taken by the Corporation for stoppage of illegal
construction or demolition of illegal construction. In fact, the
arguments in the matter were heard partly on 27th September
and again yesterday and as well as today. On the very first day
of the argument, it was orally informed by the learned Advocate
for the Corporation that he would ensure the presence of the
officer of the Corporation to assist him in order to enable him to
give correct detail information in the matter. In spite the officer
being present, we are not able to get the detail information
regarding the action taken by the Corporation as also the detail
description of the illegalities committed by the builder and any
other persons on his behalf in the matter. It is to be noted that
undisputedly the records disclose some illegalities in the matter
of construction carried out since the year 1984 onwards. In spite
of affidavit having been filed in the year 2000, the Corporation
has not explained the reason for failure on its part to take
appropriate action against the illegal construction and even
today. Apart from being assisted by the officer of the
Corporation, the Advocate appearing for the Corporation is
unable to disclose the reason for the same. We find it necessary
to issue notice to the Additional Commissioner to appear in
person before us on Friday i.e. 14th October, 2005 at 11.00 a.m.
to explain the same along with all records in the matter, as it is
informed by the Advocate for the Corporation that
Commissioner is out of India.
6
4. The Registrar General is required to fax the copy of this
order to the Corporation apart from the fact that of the same is
being noted by the Advocate for the Corporation. At the request
of the learned Advocate for the Corporation, Registrar need not
send copy of this order by fax as learned Advocate for the
Corporation undertakes to the Court that he through the officer
present in Court will assure intimation of this order to the
Additional Commissioner and consequently, his presence
before the Court on 14th October, 2005 at 11.00 a.m."
6. The Commissioner of the Corporation appeared before the High Court on
14.10.2005 and gave an assurance that necessary steps would be taken in
accordance with law within a period of two months in relation to the illegal
constructions. Thereafter, the Corporation issued notices dated 19.11.2005 to
respondent no. 2, the societies and their members under Section 351 of the
Mumbai Municipal Corporation Act, 1888 (for short, `the 1888 Act') requiring
them to show cause as to why the unauthorized constructions may not be pulled
down and the buildings be brought in tune with the sanctioned plans. In the
notices it was also stipulated that if the noticees fail to show sufficient cause,
then the Corporation will pull down the illegal construction and also take action
under Section 475A of the 1888 Act. The societies and their members sent reply
dated 28.11.2005 through their advocate and pleaded that they were in no way
responsible for the unauthorized constructions. Deputy Chief Engineer,
Building Proposals (City) did not accept the reply sent by the advocate of the
societies and their members and passed orders dated 3.12.2005 and 8.12.2005
7
and directed the petitioners to remove the illegal constructions. Thereupon, the
petitioners filed Long Cause Suits for declaring notices dated 19.11.2005 and
orders dated 3/8.12.2005 to be illegal. They further prayed for grant of
permanent injunction restraining the Corporation, its servants, agents and
representatives from taking any action demolishing the buildings. The
petitioners also filed notices of motion for grant of temporary injunction. On
17.12.2005, the trial Court passed ad-interim orders and directed the parties to
maintain status quo in respect of the suit structures.
7. In the detailed written statement filed on behalf of the Corporation,
several objections were taken to the maintainability of the suits. On merits, it
was pleaded that the buildings were constructed in violation of the sanctioned
plans and the developers did not stop the construction activity despite stop work
notice. It was further pleaded that action taken under Section 351 of the 1888
Act was legal and justified because the buildings had been constructed in gross
violation of the sanctioned plans. It was then averred that those who purchased
the flats knowing fully well that the buildings were being/had been constructed
in violation of the sanctioned plans are not entitled to complain against the
action taken by the Corporation for removal of the illegal/unauthorized
constructions.
8
8. After hearing the counsel for the parties, the trial Court passed orders
dated 23.3.2010 and rejected the petitioners' prayer for temporary injunction.
For the sake of reference paragraphs 36 to 39 of the order passed in the case of
the petitioners, who have filed SLP(C) No. 33471 of 2011 are extracted below:
"36. In so far as claim of the plaintiffs that they are bona fide
purchasers of their respective flats and they were not aware
about illegal construction raised by the building/Developer is
concerned, it is submitted by both the counsels of the defendant
no. 2 that the fact of illegal construction itself mentioned in the
agreement in between the plaintiffs and developers. In this
respect while perusing the agreement produced by the plaintiffs
on record revising plans for putting up multi-storied building
submitted to the Corporation and for sanction. It means on that
day it was made known to the purchaser the revised plan has
been submitted. In short on that date the upper floor
construction was not sanctioned by the Corporation.
37. Not only this it is appeared from the letter of Jayant Chitnis,
Architect who specifically mentioned in his letter that he
already addressed a letter dated 5.1.1990 and informed to the
concerned developer about the show cause notice issued by the
Corporation about the construction of upper floors which were
not sanctioned. This letter also addressed to the said society by
the said Architect. It means the Architect made aware to the
societies as well as the Developer when show cause notice has
been issued by the Corporation when Corporation noticed the
construction of illegal upper floors. From this fact it is clear that
even on the date of purchase the respective flat owners were
aware that the construction of upper floors which is mentioned
in the 351 notice were illegal and unauthorized. Till then by
adopting the risk of demolition they have purchased the same.
38. From the documentary evidence as well as direction given
by the Hon'ble High Court in the abovesaid writ petitions it is
clear that on the buildings of the plaintiffs there are certain
illegal constructions of upper floors as mentioned in the notice
9
under Section 351. Therefore, at this prima-facie stage plaintiffs
have not made out any case to protect their illegal construction.
39. Not only this as per the direction of the Hon'ble High Court
the MMC has issued notices and after receiving the reply from
the respective societies, the AMC passed order of demolition of
such illegal upper floors. Prima facie in the order I found no
illegalities carried out by the AMC in passing the same.
Considering all the documents and submissions I found no any
three cardinal principles available with the plaintiffs for
granting ad-interim injunction. Therefore, I answer above
points in the negative. Hence, I proceed to pass the following
order.
ORDER
1) Notices of Motion No. 4807/2005 is hereby dismissed.
2) Cost in cause.
3) Notices of Motion No. 4807/2005 is disposed of
accordingly."
9. The appeals filed by the petitioners were dismissed by the learned Single
Judge of the High Court who, after examining the documents filed by the
parties, agreed with the trial Court that the constructions made in violation of
the sanctioned building plans were illegal and the Corporation did not commit
any error by ordering demolition of the unauthorized portions of the buildings.
The reasons assigned by the High Court for negating the petitioners challenge
to the order of the trial Court are contained in paragraphs 12 to 15 of the
impugned which are extracted below:
10
"12. It may be mentioned that for immovable properties
authorized construction can be shown only by documentary
evidence. No party can contend orally that the construction is
authorized without showing documentary evidence. In a case
such as this, where flats have been constructed in the building
and have been sold under agreements to flat purchasers in a
proposed co-operative society under the provisions of MOFA,
the documentary evidence must be present to the mind of the
flat purchasers upon taking inspection of the plans and
specifications statutorily required to be shown and inspected.
Consequently in such a case the only documentary evidence
would be expected to be with the flat purchasers who, under the
specific statutory mandate, would require to inspect the title
contained in the sanctioned plan and the specifications. If that is
shown in reply to the notice, of course, the notice would not
proceed. That essential document which would be only to the
knowledge of the party receiving the notice and the party
purchasing the flat would have to be shown by that party alone
and not by the MMC just because the party orders or directs the
MMC to produce the plans which never were.
13. The fact that the flat purchasers purchased flats which are
shown not to have been specifically under sanctioned plans
shows that they are not bonafide purchasers. The fact that the
regularization application has been made itself shows that the
admitted position that the structure was illegal which required
regularization. No party can apply for regularization of a
regular structure. Consequently it is self-contradictory to state
that the structure is authorized and yet apply for regularization.
14. In fact a preposterous argument is that the lease of the
lessees is not terminated by the MMC who is the lessor and the
lessees have malafide sought to complain and get the impugned
notice enforced.
15. It is gratifying to note that the learned Judge has passed a
legal order upon seeing a blatant defiance of law and the legal
procedure throwing to the winds all legal requirements and
mandates of construction under the supervision of the planning
authority obviously upon the conviction and expectation that
such extensive construction, however illegal, would not be
demolished."
11
10. Before proceeding further, we deem it appropriate to mention that in
January 2002, Corporation had decided to demolish the buildings constructed in
violation of the sanctioned plans. On coming to know of this, the flat buyers
made applications through their architect for regularization of the buildings and
gave out that they were prepared to pay concessional penalty. Their
applications were rejected by the Corporation. The appeals filed against the
orders of the Corporation were dismissed by the State Government and the
petitioners have challenged both the orders by filing separate writ petitions.
11. Dr. Abhishek Manu Singhvi, Shri Mukul Rohatgi, Shri Shyam Divan,
Senior Advocates and Shri Santosh Paul and Shri Abhimanyu Bhandari, learned
counsel for the petitioners argued that the impugned order is liable to be set
aside because if the disputed constructions are demolished, the suits will
become infructuous and the members of the societies and their families will
suffer irreparable loss inasmuch as they will become roofless. Dr. Singhvi,
placed before the Court satellite map of the site and argued that if the total
constructed area is measured with reference to the area of the plot which was
leased out by the Corporation to M/s. Pure Drinks Pvt. Ltd., the construction
made by the developers cannot be said to be excessive and the trial Court and
the High Court committed serious error in recording a finding that the
construction of buildings with 24 and 16 floors is illegal. Learned counsel then
12
referred to the agreements entered into between the flat buyers and the
developers to show that the former had purchased the flats under a bona fide
belief that the developers will be able to persuade the Corporation to sanction
the revised building plans and they should not be made to suffer on account of
the wrong, if any, committed by the developers. Learned counsel also pointed
out that the writ petitions filed by the petitioners for issue of a mandamus to the
Corporation to regularize the illegal/unauthorized construction are pending
before the High Court and submitted that till the disposal of those petitions the
Corporation should not be allowed to demolish the buildings or the
constructions which are said to have been made in violation of the sanctioned
plans. In support of this submission, Shri Mukul Rohatgi placed before this
Court xerox copies of the order sheets of Writ Petition No. 6550 of 2010.
Learned counsel for the petitioners lastly submitted that the Court may consider
the desirability of transferring the writ petitions filed by the petitioners for
regularization of the construction to this Court so that the issue of regularization
may be finally decided and 200 families which are residing in the flats allegedly
constructed in violation of the sanctioned plan may not be rendered homeless.
12. Shri Pallav Shishodia, learned senior counsel appearing for the
Corporation argued that the action taken under Section 351 of the 1888 Act is
perfectly legal because the buildings in question were constructed despite
13
rejection of the revised building plans and the issue of stop work notice.
Learned senior counsel emphasized that the Corporation had taken belated
action for removing the illegal construction in the light of the observations
made by the Division Bench of the High Court on 11.10.2005 and, therefore,
notices dated 19.11.2005 and orders dated 3/8.12.2005 cannot be faulted.
13. Shri Harish N. Salve, learned senior counsel appearing for respondent no.
2 argued that total area of Plot No. 9 cannot be taken into consideration for the
purpose of deciding whether the buildings have been constructed in violation of
the sanctioned plan because the State Government had allowed change on land
use only in respect of 13049.45 sq. meters. Learned senior counsel submitted
that the members of the societies who purchased the flats knowing fully well
that the buildings had been constructed in violation of the sanctioned plans
cannot claim any equity or complain against the action taken by the Corporation
for demolition of the illegal/unauthorized structures.
14. We have considered the respective submissions and carefully scrutinized
the record. The scope of the appellate Court's power to interfere with an interim
order passed by the Court of first instance has been considered by this Court in
several cases. In Wander Ltd. v. Antox India (P) Ltd 1990 Supp SCC 727, the
Court was called upon to consider the correctness of an order of injunction
passed by the Division Bench of the High Court which had reversed the order
14
of the learned Single Judge declining the respondent's prayer for interim relief.
This Court set aside the order of the Division Bench and made the following
observations:
"In such appeals, the appellate court will not interfere with the
exercise of discretion of the court of first instance and substitute
its own discretion except where the discretion has been shown
to have been exercised arbitrarily, or capriciously or perversely
or where the court had ignored the settled principles of law
regulating grant or refusal of interlocutory injunctions. An
appeal against exercise of discretion is said to be an appeal on
principle. Appellate court will not reassess the material and
seek to reach a conclusion different from the one reached by the
court below if the one reached by that court was reasonably
possible on the material. The appellate court would normally
not be justified in interfering with the exercise of discretion
under appeal solely on the ground that if it had considered the
matter at the trial stage it would have come to a contrary
conclusion. If the discretion has been exercised by the trial
court reasonably and in a judicial manner the fact that the
appellate court would have taken a different view may not
justify interference with the trial court's exercise of discretion."
15. In Skyline Education Institute (India) Pvt. Ltd. v. S.L. Vaswani (2010) 2
SCC 142, the 3-Judge Bench considered a somewhat similar question in the
context of the refusal of the trial Court and the High Court to pass an order of
temporary injunction, referred to the judgments in Wander Ltd. v. Antox India
(P) Ltd (supra), N.R. Dongre v. Whirlpool Corpn. (1996) 5 SCC 714 and
observed:
"The ratio of the abovenoted judgments is that once the court of
first instance exercises its discretion to grant or refuse to grant
15
relief of temporary injunction and the said exercise of discretion
is based upon objective consideration of the material placed
before the court and is supported by cogent reasons, the
appellate court will be loath to interfere simply because on a de
novo consideration of the matter it is possible for the appellate
court to form a different opinion on the issues of prima facie
case, balance of convenience, irreparable injury and equity."
16. In these cases, the trial Court and the High Court have, after threadbare
analysis of the pleadings of the parties and the documents filed by them
concurrently held that the buildings in question were constructed in violation of
the sanctioned plans and that the flat buyers do not have the locus to complain
against the action taken by the Corporation under Section 351 of 1888 Act.
Both, the trial Court and the High Court have assigned detailed reasons for
declining the petitioners' prayer for temporary injunction and we do not find
any valid ground or justification to take a different view in the matter.
17. The submission of Dr. Abhishek Manu Singhvi that the constructed area
should be measured with reference to the total area of the plot cannot be
accepted for the simple reason that the State Government had sanctioned
change of land use only in respect of 13049.45 sq. meters.
18. In view of the above, we may have dismissed the special leave petitions
and allowed the Corporation to take action in furtherance of notices dated
19.11.2005 and orders dated 3/8.12.2005, but keeping in view the fact that the
flat buyers and their families are residing in the buildings in question for the last
16
more than one decade, we feel that it will be in the interest of justice that the
issue relating to the petitioners' plea for regularization should be considered by
this Court at the earliest so that they may finally know their fate.
19. We, therefore, direct the petitioners to furnish the particulars of the writ
petitions filed for regularization of the construction which are pending before
the High Court. The needful be done within a period of two weeks from today.
Within this period of two weeks, the petitioners shall also furnish the particulars
and details of the developers from whom the members of the societies had
purchased the flats. List the cases on 16th March, 2012 (Friday).
20. If the petitioners fail to comply the aforesaid directions, the special leave
petitions shall stand automatically dismissed.
.......................................................J.
(G.S. SINGHVI)
.......................................................J.
New Delhi; (SUDHANSU JYOTI MUKHOPADHAYA)
February 29, 2012.