LawforAll
advocatemmmohan
- advocatemmmohan
- since 1985 practicing as advocate in both civil & criminal laws
WELCOME TO LEGAL WORLD
WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE
Tuesday, January 10, 2012
arbitration act ,= referring the disputes to the named arbitrator shall be the rule. The Chief Justice or his designate will have to merely reiterate the arbitration agreement by referring the parties to the named arbitrator or named Arbitral Tribunal. Ignoring the named arbitrator/Arbitral Tribunal and nominating an independent arbitrator shall be the exception to the rule, to be resorted for valid reasons."
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION NO.11 OF 2011
Denel (Proprietary Limited) ...Petitioner
VERSUS
Govt. of India, Ministry of Defence ...
Respondent
O R D E R
SURINDER SINGH NIJJAR, J.
1. The petitioner has filed the present application under Sections
11(4) and (6) of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as the `Act') read with paragraph 2 of the
appointment of the Arbitrators by the Chief Justice of India
Scheme, 1996. It is stated that a contract was entered into between
- 1 -
the parties for the supply of Base Bleed Units. Initially the quantity
to be supplied was 42,000 units. Later on, the quantity was
increased to 52,000 units as per Clause 20 of the agreement. By
5th January, 2005, the petitioner had supplied substantial quantity
of the goods. However, some of the goods supplied by the petitioner
were rejected by the respondent. The petitioner, thereafter, informed
the respondent that two more lots were ready for discharge on 17th
March, 2005. However, Union of India never responded to the letter,
hence, loss and damage has been caused to the petitioner. In April,
2005, after various discussions, the petitioner came to know that
improper fuzes were used by the Union of India which led to the
problem that occurred in the lots which were rejected. Thereafter,
on 21st April, 2005, Union of India put on hold all contracts.
Further, on 14th May, 2008, Union of India sent a notice seeking
refund of amount of US $ 23,20,240, failing which legal action was
to issue.
- 2 -
2. The disputes having arisen between the parties, efforts were
made to resolve the same. The details of the efforts made are
narrated in the petition. Since the disputes could not be resolved
through mutual discussions, the DGOF appointed one Mr. A.K.
Jain, Additional General Manager, Ordnance Factory, Ambajhari,
Nagpur as an arbitrator in terms of Clause 19(F) of the contract,
which reads as under:-
"All the disputes and difference arising out of or in any
way touching or concerning the agreement (matters for
which the decision of a specific authority as specified in
the contract shall be final under this agreement, shall
not be subject to arbitration) shall be referred to the sole
arbitration of the Director General, Ordnance Fys. Govt.
of India for the time being or a Government servant
appointed by him. The appointee shall not be a Govt.
Servant who had dealt with the matters to which this
agreement relates and that in the course of his duties as
Govt. Servant has had not expressed views on all or any
of the matter is in dispute or difference. In case the
appointed Govt. Servant in place of the incumbents."
3. The petitioner objected to the appointment of the Arbitrator.
The petitioner apprehended that the arbitrator would be favorably
inclined towards the employer. Therefore, on 23rd January, 2009,
the petitioner issued a notification under Section 14 of the
- 3 -
Arbitration Act stating that the mandate of the arbitrator had been
terminated. Since inspite of the aforesaid notification, the
arbitrator continued with the arbitration proceedings, the petitioner
moved the Principal District Court, Chandrapur and filed Civil Misc.
Application No. 45 of 2009 under Section 14(2) of the Act. On 21st
December, 2010, the Principal District Court, Chandrapur
terminated the mandate of the Sole Arbitrator with the observation
that the arbitrator has been biased in favour of respondent No.1. A
direction was also issued in the following terms:-
"Director General, Ordnance Factory, Government of
India, is appointed as an Arbitrator or he may appoint
Government servant as an Arbitrator , as per Clause
19(F) of February 2004 contract and 19(E) of November
2004 contract, after following due procedure."
4. It is an admitted fact that pursuant to the aforesaid directions,
within 30 days, DGOF did not himself commence the arbitration
proceedings; nor did he appoint any Government servant as an
arbitrator. The petitioner has, therefore, moved the present petition
under Section 11(6) of the Act on 2nd of March, 2011 seeking
appointment of an independent arbitrator. The petitioner claims
- 4 -
that the directions issued by the District Court are without any
authority or jurisdiction and as such void ab initio. According to the
petitioner, the direction of the learned District Judge is based upon
an incorrect interpretation of Section 15 of the Act, whereby the
learned Judge assumed the authority to appoint an arbitrator,
which is beyond her jurisdiction. The Act does not make provision
for the appointment of an arbitrator other than in accordance with
the arbitration agreement and in the limited circumstances
provided for in Section 11. The petitioner also claims that the DGOF
would be disqualified to act as an arbitrator as the dispute is
against the Government of India and particularly against the
Ordnance Factory, Ministry of Defence. If the Director General,
Ordnance Factory, Government of India (DGOF) or a Government
servant is appointed as an arbitrator, he shall always be bound by
the directions/instructions issued by his superior authorities and,
therefore, such an arbitrator would not be in a position to
independently decide the dispute between the parties. According to
the petitioner, such an appointment would be contrary to the
- 5 -
provisions of Section 12 of the Act. The petitioner further claims
that the DGOF has already through his actions in the dispute
between the parties demonstrated his lack of independence and
impartiality. The learned District Judge in her judgment alluded to
the fact that the DGOF without receiving any request for referral of
the dispute between the petitioner and the respondent colluded
with the previous arbitrator to appoint him as an arbitrator without
any notice to the petitioner. The petitioner further claims that the
DGOF has been directly involved in the dispute as would be evident
from the correspondence between the petitioner and the
respondent. The petitioner thereafter makes a reference to the letter
dated 30th June, 2008 wherein the DGOF took the view that the
petitioner is liable to replace the rejected Base Bleed units, as
alleged by the respondent, making specific reference to the
correspondence in which respondent stated its claim against the
petitioner and cancelled the contract with the petitioner. The
petitioner further claims that the DGOF has failed to appoint the
arbitrator either as directed by the learned District Judge or in
- 6 -
accordance with Section 15 of the Act within 30 days of the order
dated 21st December, 2010. Therefore, the respondent
has forfeited the right to make an appointment from the date of the
filing of the petition.
5. The respondent has controverted the plea put forward by the
petitioner by way of a detailed counter affidavit. It is claimed by the
respondent that the petition under Section 11(6) of the Act is not
maintainable, as Mr.Satyanarayana has been appointed as a
substitute arbitrator on 16th March, 2011. The petitioner was duly
notified about the appointment of the arbitrator in its letter dated
26th March, 2011. The petitioner was requested to forward its claim
within 10 days. The petitioner was informed that if such a claim
does not reach by 8th April, 2011, the arbitrator will presume that
the petitioner did not have any further claim. Upon receipt of that
letter, the petitioner objected to the appointment of a new arbitrator
by its letter dated 15th April, 2011, as being contrary to clause
19(F). The petitioner has wrongly claimed that since the
- 7 -
appointment of the arbitrator was not made prior to the filing of the
petition under Section 11(6), the respondent has forfeited the right
to make the appointment.
6. I have heard the learned counsel for the parties.
7. On the basis of facts narrated above, Mr. Naphade submits
that the petitioner has forfeited its right to appoint the arbitrator.
In support of the submission, he relied on the judgments of this
Court in the case of Datar Switchgears Ltd. Vs. Tata Finance Ltd.
&
Anr.1
, Punj Lloyd Ltd. Vs. Petrone
t MHB Ltd.2
and Yashwith
Constructions (P) Ltd. Vs. Simplex Concrete Piles India Ltd. &
Anr.
3
8. On the other hand, Mr. Raval, appearing for the Union of India
has submitted that the petitioner has failed to make out a case for
not appearing before the arbitrator appointed pursuant to the order
1 2000 (8) SCC 151
2 2006 (2) SCC 638
3 2006 (6) SCC 204
- 8 -
of the Principal District Court, Chandrapur on 21st December, 2010.
He submits that the respondents have willingly accepted the
appointment of the earlier arbitrator in accordance with the
arbitration clause. Therefore, they can have no justification to
challenge the appointment of the present arbitrator, who has only
been appointed as the mandate of the earlier arbitrator had been
terminated by the orders of the Court. The petitioner was duly
informed about the appointment of the arbitrator on 16th March,
2011. The arbitrator had intimated both the parties about the
appointment and had requested them to submit their respective
claims within a period of 10 days. It was only at that stage that the
petitioner wrote a letter dated 15th April, 2011 stating that the
appointment of the arbitrator was in violation of arbitration clause.
Mr. Raval further submitted that in the present circumstances, the
matter is squarely covered against the petitioner by the judgment in
the case of Indian Oil Corporation Limited & Ors. Vs. Raja
Transport
Private Limited4
. On the basis of the aforesaid
judgment, the learned counsel submitted that the present petition
4 (2009) 8 SCC 520
- 9 -
under Section 11(6) is misconceived, as the Sole Arbitrator has been
appointed in terms of the agreed procedure contained in Clause 19
(F) and (E).
9. I have considered the submissions made by the learned
counsel. In my opinion, Mr. Naphade is correct in his submission
that the matter is squarely covered by the judgment in Datar
Switchgears Ltd. (supra), wherein this Court has observed as
follows:-
19." So far as cases falling under Section 11(6) are
concerned -- such as the one before us -- no time limit
has been prescribed under the Act, whereas a period of
30 days has been prescribed under Section 11(4) and
Section 11(5) of the Act. In our view, therefore, so far as
Section 11(6) is concerned, if one party demands the
opposite party to appoint an arbitrator and the opposite
party does not make an appointment within 30 days of
the demand, the right to appointment does not get
automatically forfeited after expiry of 30 days. If the
opposite party makes an appointment even after 30 days
of the demand, but before the first party has moved the
court under Section 11, that would be sufficient. In other
words, in cases arising under Section 11(6), if the
opposite party has not made an appointment within 30
days of demand, the right to make appointment is not
forfeited but continues, but an appointment has to be
made before the former files application under Section 11
- 10 -
seeking appointment of an arbitrator. Only then the right
of the opposite party ceases. We do not, therefore, agree
with the observation in the above judgments that if the
appointment is not made within 30 days of demand, the
right to appoint an arbitrator under Section 11(6) is
forfeited."
The aforesaid ratio has been reiterated in Punj Lloyd Ltd.
(supra).
10. In the facts and circumstances of this case, it would not be
possible to accept the submission of Mr. Raval that the present
petition filed by the petitioner under Section 11(6) of the Act is not
maintainable. On the admitted facts, it is evident that the mandate
of the earlier arbitrator Mr. Arun Kumar Jain was terminated by the
orders passed by the Principal District Court, Chandrapur in Civil
Misc. Application No. 45 of 2009 by order dated 21st December,
2010. A perusal of the aforesaid order would show that the
petitioner had challenged the validity of Clause 19(F). The aforesaid
submission was rejected by the Court with the observation that the
same cannot be the subject matter which could be resolved in a
- 11 -
petition under Section 14(2) of the Act. The petitioner was given an
opportunity to challenge the clauses in an appropriate forum. The
District Judge, however, accepted the submission of the petitioner
that there are justifiable reasons to indicate that the arbitrator has
not acted fairly. Hence the mandate of Mr. A.K. Jain as the Sole
Arbitrator was terminated. In accordance with Section 15(2) of the
Act, DGOF was appointed as an arbitrator. He was also given an
option to appoint Government servant as an arbitrator as per the
arbitration clause. It is a matter of record that DGOF did not act
himself as an arbitrator, pursuant to the aforesaid order of the
Principal District Judge, Chandrapur dated 21st December, 2010.
Mr. Satyanarayana, the subsequent arbitrator, had not been
appointed till 16th March, 2011. The present petition was moved on
2nd March, 2011. Therefore, the respondents had clearly forfeited
their right to make the appointment of an arbitrator. Consequently,
the appointment of Mr. Satyanarayana, as an
arbitrator, by letter dated 16th March, 2011 cannot be sustained.
- 12 -
11. Mr. Naphade then submits that in the peculiar facts and
circumstances of this case, the respondent cannot now be
permitted to insist that the Court should appoint an arbitrator only
in terms of the agreed procedure. In support of this submission, he
emphasised that DGOF can not act as an arbitrator as the same
will be against the principles of natural justice, as no one can be a
judge in his own cause. He further submitted that even if any
government employee is appointed as an arbitrator, he will not be in
a position to act against the Union of India as he will be obliged to
follow the instructions of the superiors. He placed reliance on
Bharat Sanchar Nigam Limited & Anr. Vs. Motorola India
Priva
te Limited5
. It is not possible to accept the submissions of
Mr. Naphade. This Court in the case of Indian Oil Corporation
Limited (supra) has considered such a submission and observed
that :-
"Arbitration is a binding voluntary alternative dispute
resolution process by a private forum chosen by the
parties. If a party, with open eyes and full knowledge
and comprehension of the relevant provision enters into a
contract with a Government/statutory
5 2009 (2) SCC 337
- 13 -
corporation/public sector undertaking containing an
arbitration agreement providing that one of its
Secretaries/Directors shall be the arbitrator, he cannot
subsequently turn around and contend that he is
agreeable for settlement of the disputes by arbitration,
but not by the named arbitrator who is an employee of
the other party.
It is now well settled by a series of decisions that
arbitration agreements in government contracts providing
that an employee of the Department (usually a high
official unconnected with the work of the contract) will be
the arbitrator, are neither void nor unenforceable. All the
decisions proceed on the basis that when senior officers
of Government/statutory corporations/public sector
undertakings are appointed as arbitrators, they will
function independently and impartially, even though they
are employees of such institutions/organizations."
In my opinion, the aforesaid observations are a complete answer to
the submission made by Mr. Naphade.
12. Learned senior counsel then submitted that even if the
arbitration clause is held to be valid, Mr. Satyanarayana still can
not be permitted to continue with arbitration as the petitioner has a
strong apprehension that he is biased in favour of the respondents.
In support of the submission, the learned senior counsel has relied
on the various notices issued by the arbitrator which were
- 14 -
invariably received after the expiry of the time fixed by the
arbitrator. In support of his submission, he relied on a judgment of
this Court in the case of Denel (Proprietary) Limited Vs. Bharat
Electronics
Limited & Anr.6
.
13. Replying to the apprehension of bias pleaded by Mr.
Naphade, it is submitted by Mr. Raval that non-receipt of the letters
in time can not possibly give rise to an apprehension that Mr.
Satyanarayana is in any manner biased against the petitioner. He
submits that the reliance of the petitioner on the judgment in Denel
(Proprietary) Limited (supra) is also misconceived as the aforesaid
judgment was confined to the facts of that particular matter. He,
therefore, submits that the Court ought to follow the agreed
procedure and not to interfere with the appointment of Mr.
Satyanarayana as the arbitrator. In the alternative, he submits that
even if the appointment of Mr. Satyanarayana is held to be invalid,
the matter has to be left to the DGOF to either act as an arbitrator
himself or to appoint an officer appointed by him.
6 2010 (6) SCC 394
- 15 -
14. It is true that in normal circumstances while exercising
jurisdiction under Section 11(6), the Court would adhere to the
terms of the agreement as closely as possible. But if the
circumstances warrant, the Chief Justice or the nominee of the
Chief Justice is not debarred from appointing an independent
arbitrator other then the named arbitrator.
15. A Three Judge Bench of this Court in the case of Northern
Railway Administration, Ministry of Railway, New Delhi Vs.
Patel
Engineering Company Limited7
, considered the scope and
ambit of Section 11(6) of the Act, as divergent views were taken in
two decisions of this Court in Ace Pipeline Contracts (P) Ltd. Vs.
Bharat
Petroleum Corpn. Ltd.8
and Union of India Vs. Bharat
Battery Manufacturing Co. (P) Ltd. (supra). Upon consideration of
the relevant provisions it was inter-alia observed as follows:-
"A bare reading of the scheme of Section 11 shows that
the emphasis is on the terms of the agreement being
7 2008 (10) SCC 240
8 2007 (5) SCC 304
- 16 -
adhered to and/or given effect as closely as possible. In
other words, the Court may ask to do what has not been
done. The Court must first ensure that the remedies
provided for are exhausted. It is true as contended by Mr.
Desai, that it is not mandatory for the Chief Justice or
any person or institution designated by him to appoint
the named arbitrator or arbitrators. But at the same
time, due regard has to be given to the qualifications
required by the agreement and other considerations."
16. Keeping in view the observations made above, I have examined
the facts pleaded in this case. I am of the opinion that in the
peculiar facts and circumstances of this case, it would be necessary
and advisable to appoint an independent arbitrator. In this case,
the contract is with Ministry of Defence. The arbitrator Mr.
Satyanarayana has been nominated by DGOF, who is bound to
accept the directions issued by the Union of India. Mr.
Satyanarayana is an employee within the same organization. The
attitude of the respondents towards the proceeding is not indicative
of an impartial approach. In fact, the mandate of the earlier
arbitrator was terminated on the material produced before the
Court, which indicated that the arbitrator was biased in favour of
the Union of India. In the present case also, Mr. Naphade has
- 17 -
made a reference to various notices issued by the arbitrator, none of
which were received by the petitioner within time. Therefore, the
petitioner was effectively denied the opportunity to present his case
before the Sole Arbitrator. Therefore, the apprehensions of the
petitioner can not be said to be without any basis.
17. It must also be remembered that even while exercising the
jurisdiction under Section 11(6), the Court is required to have due
regard to the provisions contained in Section 11(8) of the Act. The
aforesaid section provides that apart from ensuring that the
arbitrator possesses the necessary qualifications required of the
arbitrator by the agreement of the parties, the Court shall have due
regard to other considerations as are likely to ensure the
appointment of an independent and impartial arbitrator. Keeping
in view the aforesaid provision, this Court in the case of Indian Oil
Corporation Limited (supra), whilst emphasizing that normally the
Court shall make the appointment in terms of the agreed procedure
has observed that the Chief Justice or his designate may deviate
- 18 -
from the same after recording reasons for the same. In paragraph
45 of the aforesaid judgment, it is observed as follows:-
"45. If the arbitration agreement provides for arbitration
by a named arbitrator, the courts should normally give
effect to the provisions of the arbitration agreement. But
as clarified by Northern Railway Admn.10, where there is
material to create a reasonable apprehension that the
person mentioned in the arbitration agreement as the
arbitrator is not likely to act independently or impartially,
or if the named person is not available, then the Chief
Justice or his designate may, after recording reasons for
not following the agreed procedure of referring the
dispute to the named arbitrator, appoint an independent
arbitrator in accordance with Section 11(8) of the Act. In
other words, referring the disputes to the named
arbitrator shall be the rule. The Chief Justice or his
designate will have to merely reiterate the arbitration
agreement by referring the parties to the named
arbitrator or named Arbitral Tribunal. Ignoring the
named arbitrator/Arbitral Tribunal and nominating an
independent arbitrator shall be the exception to the rule,
to be resorted for valid reasons."
(emphasis
supplied)
18. The material placed before the Court by the petitioner would
indicate that it would not be unreasonable to entertain the belief
that the arbitrator appointed by the respondent would not be
- 19 -
independent. That being so, the appointment of Mr. Satyanarayana
can not pass the test under Section 11(8) of the Act.
19. Similarly, applying the test laid down in Indian Oil
Corporation Ltd. (supra), this Court in the case of Denel
(Proprietary) Limited (supra) also observed that the Managing
Director, Bharat Electronics Limited, which is a Government
company is bound by the directions/instructions issued by his
superior authority. The Court also observed that according to the
pleaded case of the respondents, though it was liable to pay the
amount due under the purchase order, it was not in a position to
supply the dues only because of the direction issued by the
Ministry of Defence, Government of India. Therefore, the Court
concluded that the Managing Director may not be in a position to
independently decide the dispute between the parties.
Consequently, the Court proceeded to appoint an independent
arbitrator.
- 20 -
20. In my opinion, the circumstances in the present case are
similar and a similar course needs to be adopted. In view of the
above, the petition is allowed.
21. In exercise of my powers under Section 11(4) and (6) of the
Arbitration and Conciliation Act, 1996 read with Paragraph 2 of the
Appointment of Arbitrator by the Chief Justice of India Scheme,
1996, I hereby appoint Hon. Mr. Justice Ashok C. Agarwal, Retd.
Chief Justice of the Madras High Court, R/o No. 20, Usha Kiran, 2nd
Pasta Lane, Colaba, Mumbai-400 005, as the Sole Arbitrator, to
adjudicate the disputes that have arisen between the parties, on
such terms and conditions as the learned Sole Arbitrator deems fit
and proper. Undoubtedly, the learned Sole Arbitrator shall decide
all the disputes arising between the parties without being
influenced by any prima facie opinion expressed in this order, with
regard to the respective claims of the parties.
- 21 -
22. The registry is directed to communicate this order to the Sole
Arbitrator forthwith to enable him to enter upon the reference and
decide the matter as expeditiously as possible.
...............................J.
[Surinder Singh Nijjar]
New Delhi;
January 09, 2012.
- 22 -