LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Tuesday, October 22, 2019

The award passed by the Arbitral Tribunal can be interfered with in the proceedings under Sections 34 and 37 of Arbitration Act only in a case where the finding is perverse and/or contrary to the evidence and/or the same is against the public policy. Once it is held that the termination was illegal and thereafter when the learned Arbitral Tribunal has considered the claims on merits, which basically were with respect to the unpaid amount in respect of the work executed under the contract and loss of profit. Cogent reasons have been given by the learned Arbitral Tribunal while allowing/partly allowing the respective claims. It is required to be noted that the learned Arbitral Tribunal has partly allowed some of the claims and even disallowed also some of the claims. There is a proper application of mind by the learned Arbitral Tribunal on the respective claims. Therefore, the same is not required to be interfered with, under Sections 34 and 37 of the Arbitration Act.

The award passed by the   Arbitral  Tribunal   can  be  interfered   with   in   the  proceedings
under Sections 34 and 37 of Arbitration Act only in a case where the finding is perverse and/or contrary to the evidence and/or the same is against the public policy.

Once it is held that the termination was illegal and thereafter when the learned Arbitral Tribunal has considered the claims on merits, which basically were with respect to the unpaid amount in respect of the work executed under the contract and loss of profit. Cogent reasons have been given by the learned Arbitral Tribunal while allowing/partly allowing the respective claims.  
It is required to be noted that the learned Arbitral Tribunal has partly allowed some of the claims and even disallowed also some of the claims.
There   is   a   proper   application   of   mind   by   the   learned   Arbitral Tribunal   on   the   respective  claims.     
Therefore,   the   same   is   not required   to   be   interfered   with,  under Sections 34 and 37 of the Arbitration Act.

1
NON­REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE TO APPEAL (C) No. 13117 of 2019
The State of Jharkhand & Ors. .. Petitioners
Versus
M/s HSS Integrated SDN & Anr. .. Respondents
J U D G M E N T
M. R. Shah, J.
1. Aggrieved   by   the   impugned   judgment   and   order   dated
30.01.2019 passed by the High Court of Jharkhand at Ranchi in
Commercial Appeal No. 01 of 2018, by which the High Court has
dismissed the said appeal preferred by the petitioners herein under
Section 37 of the Arbitration and Conciliation Act, 1996 (for short
‘the Arbitration Act’) and has confirmed the award declared by the
learned Arbitral Tribunal, confirmed by the First Appellate Court,
2
the   original   appellants   have   preferred   the   present   special   leave
petition.   
2. This special leave petition arises out of the contractual dispute
between the petitioners­State and the respondents in relation to a
consultancy   agreement   over   construction   of   six­lane   Divided
Carriage Way of certain parts of Ranchi Ring Road.   Respondent
Nos. 1 and 2 acted as a consortium for providing such consultancy
and supervisory services.  An agreement was entered into between
the parties on 28.08.2007.   The original work period under the said
agreement was for 36 months, i.e. from 01.10.2007 to 30.09.2010.
There   was   a   dispute   with   respect   to   the   non­performance   and
unsatisfactory   work   done   by   the   respondents.       However,   the
respondents were granted extension of contract twice.   Thereafter,
a letter dated 25.11.2011 was issued by the Executive Engineer to
the respondents and other contractors entrusted with the task of
construction, granting a second extension of time of contract for
construction work.     The respondents were called upon to make
compliances with the issues pointed out, at the earliest.  In the said
communication   dated   25.11.2011,   it   was   stated   that   if   the
deficiencies are not removed and/or complied with, in that case,
3
there  shall   be   suspension   of  payment   under  Clause  2.8  of   the
General   Conditions   of   Contract   (for   short   ‘the   GCC’).         On
05.12.2011,   a   review   meeting   was   held   between   the   parties,
followed by a letter dated 07.12.2011 issued by the respondentsoriginal claimants in reply/compliance of the aforesaid letter dated
25.11.2011.  It was the case on behalf of the respondents­original
claimants that without properly considering the said letter of the
respondents­original   claimants   dated   07.12.2011,   petitioners
herein issued letter dated 12.12.2011 invoking Clause 2.8 of the
GCC for suspension of payment, alleging certain deficiencies.     It
was the case on behalf of the respondents­original claimants that
by letter dated 27.12.2011, they replied to the suspension notice
and   complied   with   the   deficiencies.       In   reply   to   the   aforesaid
letters,   the   petitioners   issued   letters   dated   23.12.2011   and
28.12.2011   asking   the   claimants   to   ensure   compliance   of   the
pending issues.   That by letter/communication dated 09.02.2012,
the petitioners served a notice upon the respondents terminating
the contract with effect from 12.03.2012.   The said termination
notice was issued under Clause 2.9.1(a) and (d) of the GCC. The
respondents­original   claimants   replied   to   the   said   termination
notice by letters dated 16.02.2012 and 24.02.2012 and requested
4
the petitioners to re­consider the matter.   However, the dispute
between the parties was not resolved.   The respondents­original
claimants served a legal notice dated 10.03.2012 and invoked the
arbitration clause 2.9.1(a).   Pursuant to the order passed by the
High Court, the Arbitral Tribunal was constituted. 
2.1 The   Arbitral   Tribunal   comprised   of   nominees   of   the   rival
parties and a retired Judge of the Jharkhand High Court as the
Presiding Arbitrator.  The respondents­original claimants claimed a
total sum of Rs.5,17,88,418/­ under 13 different heads, excluding
interest.     The   petitioners   also   filed   a   counter­claim   for
Rs.6,00,78,736/­   under   five   heads.       The   claim   of   the   original
claimants primarily involved the unpaid amount in respect of the
work  executed under  the  contract,  loss of   profit  and  over­head
charges,   apart   from   other   consequential   claims   arising   out   of
termination.     It was the specific case on behalf of the original
claimants that the termination was absolutely illegal and not being
in according with the terms of the contract.  The counter­claim filed
by   the   petitioners­State   was   for   reimbursement   on   account   of
unsatisfactory performance by the respondents.   
2.2 That,   on   appreciation   of   evidence,   the   learned   Arbitral
Tribunal gave a specific finding that the termination of the contract
5
was illegal and without following the procedure as required under
the contract (paras 17 to 36).    That, thereafter the learned Arbitral
Tribunal proceeded to consider the claims on merits and ultimately
allowed the claims to the extent of Rs.2,10,87,304/­ under different
heads as under:
Claims Amount Allowed Comments
Claim   1A   –   Claim
Unpaid   Bills   from
1/11/2011   to
28/2/2012
53,37,294 50,59,957 Partly allowed
Claim   1B   –   Claim
Due/Unpaid   against
Bills   from   Oct   2007
to Oct 2011
79,04,819 67,07,032 Partly allowed
Claim   1C   –   Claim
against   Design   of
Bridges
8,30,000 8,30,000 Allowed
Total Claim 1 1,40,72,11
3
1,25,96,98
9
Claim 2 – Invoice for
the month of March,
2012 (month of
termination)
11,05,954 11,05,954 Allowed
Claim 3 – Claim
towards Shifting of
Office from Ranchi to
site
1,57,000 ­ Disallowed
Claim 4 – Claim
towards Laboratory
set up at site
4,41,000 ­ Disallowed
Claim 5 –
Demobilisation of
staff
5,00,000 ­ Disallowed
Claim 6 – Bank
Guarantee charge for
extended period
33,730 ­ Disallowed
6
Claim 7 – Claim
towards cost incurred
to submit record to
EE in person
1,28,500 ­ Disallowed
Claim 8 – Loss of
profit (for 24 months
extension period)
1,18,54,639 19,75,733 Partly allowed
Claim 9 – Claim
against Encashment
of BG
14,08,765 13,90,000 Partly allowed
Claim 10 – Claim
towards solicitor and
advocates payments
3,06,200
Claim 11 – Claim
towards arbitration
cost
10,00,000 10,00,000 Partly allowed
Claim 12 – Staff
maintenance fee (3
months notice pay
only)
17,97,084 ­ Disallowed
Claim 13 – Claim
towards inability to
bid for projects bad
reputation
50,00,000 ­ Disallowed
Interest claimed as
per contract beyond
60 days of Invoice
submission
1,39,89,633 30,18,588 Interest   @   12%
from   the   date
when   Tribunal
got constituted.
TOTAL OF CLAIMS
& ALLOWED (Indian
Rupees)
5,17,94,61
8
2,10,94,30
4
% amount allowed 40.71
2.3 In   view   of   the   finding   arrived   at   by   the   learned   Arbitral
Tribunal   that   the   termination   of   the   contract   was   illegal   and
without following due procedure as required under the contract and
7
in view of allowing the claims of the claimants partly, the Arbitral
Tribunal dismissed the counter claims submitted by the petitioners.
2.4 The award declared by the learned Arbitral Tribunal has been
confirmed   by   the   First   Appellate   Court   in   a   proceeding   under
Section 34 of the Arbitration Act.     The same has been further
confirmed by the High Court by the impugned judgment and order
in an appeal under Section 37 of the Arbitration Act.
2.5 Feeling   aggrieved   and   dissatisfied   with   the   impugned
judgment   and   order   passed   by   the   High   Court   dismissing   the
appeal under Section 37 of the Arbitration Act and consequently
confirming the award passed by the learned Arbitral Tribunal, the
original respondents­State and others have preferred the present
special leave petition. 
3. Learned counsel appearing on behalf of the petitioners has
vehemently submitted that the High Court has materially erred in
dismissing the appeal under Section 37 of the Arbitration Act and
has materially erred in not properly appreciating the fact that the
arbitral award was passed contrary to the materials on record. 
3.1 It is vehemently submitted by the learned counsel appearing
on behalf of the petitioners that the High Court has materially erred
8
in   not   properly   considering   that   the   suspension   under   the
agreement   was   not   the   suspension   of   work  per   se,   rather   was
suspension of all payments to the consultants and therefore there
was no question of dilution/go­bye of the suspension letter.    It is
further submitted by the learned counsel appearing on behalf of the
petitioners   that   the   High   Court   has   not   properly
appreciated/considered the scheme of the contract.  It is submitted
that in case of non­performance of the contract satisfactorily, the
first   step   was   suspension   of   payment   and   if   the   failure   in
performance is not remedied, then the consequence which follows is
the next step that being notice of termination by issuing 30 days’
notice.     It   is   submitted   that   suspension   is   either   operative   or
revoked by resuming the payments, for, suspension is suspension
of payment and not suspension of work/contract.  It is submitted
that therefore the High Court has materially erred in confirming the
findings   recorded   by   the   learned   Arbitral   Tribunal   that   the
termination of the contract was illegal and without following due
procedure as required under the contract.
4. While   opposing   the   present   special   leave   petition,   learned
counsel appearing on behalf of the respondents­original claimants
9
has   vehemently   submitted   that,   as   such,   there   are   concurrent
findings of fact recorded by all the Courts below on the illegal
termination of the contract.   It is submitted that, on appreciation of
evidence, the learned Arbitral Tribunal (in paragraphs 17 to 36)
gave   the   specific   findings   by   giving   cogent   reasons   that   the
termination of the contract was illegal and without following due
procedure as required under the contract.  It is submitted that once
the   findings   recorded   by   the   learned   Arbitral   Tribunal   are   on
appreciation of evidence and considering the materials on record,
the same is rightly not interfered with by the Courts below in the
proceedings under Sections 34 and 37 of the Arbitration Act. 
4.1 Making the above submissions and relying upon the decisions
of this Court in the cases of Associate Builders v. DDA  (2015) 3
SCC   49,  NHAI   v.   Progressive­MVR  (2018)   14   SCC   688   and
Maharashtra  State  Electricity  Distribution  Co.  Ltd.   v.  Datar
Switchgear  Ltd.  (2018) 3 SCC 133, it is prayed to dismiss the
present special leave petition.
5. Heard learned counsel appearing on behalf of the respective
parties at length.   
10
6. The main controversy is with respect to the termination of the
contract   vide   letter/communication   dated   09.2.2012   terminating
the contract with effect from 12.03.2012 invoking Clause 2.9.1(1)
and   (d)   of   the   GCC.     That,   on   appreciation   of   evidence   and
considering the various clauses of the contract, the learned Arbitral
Tribunal has observed and held by giving cogent reasons that the
termination of the contract was illegal and contrary to the terms of
the contract and without following due procedure as required under
the   relevant   clauses   of   the   contract.   The   said   finding   of   fact
recorded   by   the   learned   Arbitral   Tribunal   is   on   appreciation   of
evidence.     The said finding of fact has been confirmed in the
proceedings   under   Sections   34   and   37   of   the   Arbitration   Act.
Thus, there are concurrent findings of fact recorded by the learned
Arbitral Tribunal, First Appellate Court and the High Court that the
termination of the contract was illegal and without following due
procedure as required under the relevant provisions of the contract.
6.1 In the case of Progressive­MVR (supra), after considering the
catena of decisions of this Court on the scope and ambit of the
proceedings under Section 34 of the Arbitration Act, this Court has
observed and held that even when the view taken by the arbitrator
is   a   plausible   view,   and/or   when   two   views   are   possible,   a
11
particular   view   taken   by   the   Arbitral   Tribunal   which   is   also
reasonable should not be interfered with in a proceeding under
Section 34 of the Arbitration Act.
6.2 In the case of Datar Switchgear Ltd. (supra), this Court has
observed   and   held   that   the   Arbitral   Tribunal   is   the   master   of
evidence   and   the   findings   of   fact   which   are   arrived   at   by   the
arbitrators on the basis of the evidence on record are not to be
scrutinized as if the Court was sitting in appeal.   In para 51 of the
judgment, it is observed and held as under:
51  Categorical   findings   are   arrived   at   by   the
Arbitral   Tribunal   to   the   effect   that   insofar   as
Respondent 2 is concerned, it was always ready and
willing to perform its contractual obligations, but was
prevented by the appellant from such performance.
Another   specific   finding   which   is   returned   by   the
Arbitral Tribunal is that the appellant had not given
the list of locations and, therefore, its submission
that Respondent 2 had adequate lists of locations
available but still failed to install the contract objects
was   not   acceptable.   In   fact,   on   this   count,   the
Arbitral Tribunal has commented upon the working
of the appellant itself and expressed its dismay about
lack of control by the Head Office of the appellant
over the field offices which led to the failure of the
contract. These are findings of facts which are arrived
at   by   the   Arbitral   Tribunal   after   appreciating   the
evidence   and   documents   on   record.   From   these
findings   it   stands   established   that   there   is   a
fundamental breach on the part of the appellant in
carrying   out   its   obligations,   with   no   fault   of
Respondent 2 which had invested whopping amount
of Rs 163 crores  in the  project. A perusal of  the
12
award   reveals   that   the   Tribunal   investigated   the
conduct of the entire transaction between the parties
pertaining to the work order, including withholding of
DTC locations, allegations and counter­allegations by
the   parties   concerning   installed   objects.   The
arbitrators did not focus on a particular breach qua
particular   number   of   objects/class   of   objects.
Respondent   2   is   right   in   its   submission   that   the
fundamental breach, by its very nature, pervades the
entire contract and once committed, the contract as a
whole stands abrogated. It is on the aforesaid basis
that the Arbitral Tribunal has come to the conclusion
that the termination of contract by Respondent 2 was
in order and valid. The proposition of law that the
Arbitral Tribunal is the master of evidence and the
findings of fact which are arrived at by the arbitrators
on  the  basis  of evidence on  record  are  not  to  be
scrutinised as if the Court was sitting in appeal now
stands settled by a catena of judgments pronounced
by this Court without any exception thereto [ See
— Associate   Builders v. DDA,   (2015)   3   SCC   49   :
(2015) 2 SCC (Civ) 204 and S. Munishamappa v. B.
Venkatarayappa, (1981) 3 SCC 260] .
As held by this Court in catena of decisions, the award passed by
the   Arbitral  Tribunal   can  be  interfered   with   in   the  proceedings
under Sections 34 and 37 of Arbitration Act only in a case where
the finding is perverse and/or contrary to the evidence and/or the
same is against the public policy.  (see Associate Builders v. DDA
(2015) 3 SCC 49 etc.)
13
6.3 In the present case, the categorical findings arrived at by the
Arbitral   Tribunal   are   to   the   effect   that   the   termination   of   the
contract was illegal and without following due procedure of the
provisions of the contract.   The findings are on appreciation of
evidence considering the relevant provisions and material on record
as   well   as   on   interpretation   of   the   relevant   provisions   of   the
contract, which are neither perverse nor contrary to the evidence in
record.   Therefore, as such, the First Appellate Court and the High
Court have rightly not interfered with such findings of fact recorded
by the learned Arbitral Tribunal.
6.4 Once it is held that the termination was illegal and thereafter
when the learned Arbitral Tribunal has considered the claims on
merits, which basically were with respect to the unpaid amount in
respect of the work executed under the contract and loss of profit.
Cogent reasons have been given by the learned Arbitral Tribunal
while allowing/partly allowing the respective claims.  It is required
to be noted that the learned Arbitral Tribunal has partly allowed
some of the claims and even disallowed also some of the claims.
There   is   a   proper   application   of   mind   by   the   learned   Arbitral
Tribunal   on   the   respective   claims.     Therefore,   the   same   is   not
required   to   be   interfered   with,   more   particularly,   when   in   the
14
proceedings under Sections 34 and 37 of the Arbitration Act, the
petitioners have failed.
7. Once the finding recorded by the learned Arbitral Tribunal
that the termination of the contract was illegal is upheld and the
claims made by the claimants have been allowed or allowed partly,
in that case, the counter­claim submitted by the petitioners was
liable   to   be   rejected   and   the   same   is   rightly   rejected.     No
interference of this Court is called for.
8. In view of the above and for the reasons stated above, the
present   special   leave   petition   deserves   to   be   dismissed   and   is
accordingly dismissed.  However, in the facts and circumstances of
the case, there will be no order as to costs.
..................................J.
(ARUN MISHRA)
...................................J.
(M. R. SHAH)
New Delhi,
October 18, 2019.