LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Sunday, October 14, 2018

whether Section 14(3)(c) of the Act is a bar to a suit by a developer for specific performance of a development agreement between himself and the owner of the property. In dealing with this issue, the court needs to assess whether the word “defendant” in Section 14(3)(c)(iii) has the effect of confining the scope of the suit for specific performance only to a particular class (consisting of owners) or whether a purposive interpretation to the legislation would be required, so as to provide a broader set of remedies to both owners and developers. = “Although we find no merit in this appeal, we wanted to give liberty to the plaintiff for amendment of the plaint for the purpose of getting alternative relief by way of return of security of money and damages, if at all suffered, in terms of Section 22 of the Specific Relief Act; but Mr. Das, the learned Advocate appearing on behalf of the appellant after taking instruction from his client submitted before us that his client did not want to avail of such remedy and wanted to challenge our decision by preferring an appeal if we decided to refuse the prayer for specific performance of the contract. ” The same statement has been made before this Court, as was made before the High Court. In the absence of any plea for damages or monetary relief by the respondents, there is no reason to remit the appeal back to the High Court.

1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1129 OF 2012
SUSHIL KUMAR AGARWAL .....Appellant
Versus
MEENAKSHI SADHU & ORS. .....Respondents

J U D G M E N T
Dr Dhananjaya Y Chandrachud, J
1. The present appeal1
is from the judgment of a Division Bench of the High
Court of Calcutta2
. The appellant, who is a builder, instituted a suit for specific
performance of a development agreement, against the respondents, who are
owners of the premises. The suit was dismissed by the City Civil Court. The
High Court dismissed the first appeal.

1 Leave was granted on 12 January 2012.
2 The High Court delivered judgment on 18 February 2009.
2
2. The subject matter of the suit for specific performance is a development
agreement dated 14 April 1992, entered into by the appellant with the
predecessor-in-interest of the respondents (Late Kalidas Sadhu)3
in respect of
premises situated at 243N, Acharya Prafulla Chandra Road, P.S. Burtolla,
Kolkata – 700 006. The agreement recites that the owners had approached the
appellant for construction of a building on the land and that the following terms,
inter alia, were agreed upon by and between the parties:
a) The appellant agreed to apply at his own costs and expenses for sanction
of the plan of a proposed building complex on 14 cottahs 5 chittacks and
40 square feet, to the Calcutta Municipal Corporation (Clause-1 of the
agreement);
b) The plan of the building complex would be prepared and submitted by the
appellant to the Calcutta Municipal Corporation, after the approval of the
respondent (Clause -2 of the agreement);
c) The appellant shall deposit with the respondent an amount of ₹ 4,00,000/-
without interest which shall be refundable upon the completion of the
building (Clause-3 of the agreement);
d) If for any reason after the plan is sanctioned or for any act or omission on
the part of the appellant, the construction cannot take place, the appellant
shall refund the deposit in addition to all costs, charges and expenses
incurred by the respondent (Clause-22 of the agreement);

3 Late Kalidas Sadhu was the original respondent. Upon his death, by an order dated 12 May 2018, the legal
heirs of the original respondent were substituted as existing respondents.
3
e) The respondent shall retain 42% of the total constructed area as ‘sole
owned’ and the balance 58% of the total constructed area shall remain
secured for due payment of the construction costs. The total construction
cost shall not exceed the value of 58% of the constructed area. The
respondent agreed to pay the appellant the costs and expenses along with
agreed remuneration upon completion of the construction and if the
respondent failed to pay, the appellant was entitled to realise its money by
selling 58% of the total constructed area (Clauses – 6, 10 and 11 of the
agreement); and
f) The respondent was entitled to demand any loss and/or damage suffered
by him for any illegal activities of the appellant and the appellant was also
entitled to recover damages from the respondent for lapse and negligence,
in addition to the right of the parties to claim specific performance (Clause
-24 of the agreement).
3. The appellant alleged that upon the execution of the agreement, he found
that the premises were encumbered and that there were arrears of municipal
tax and electricity dues, besides which there were labour and industrial disputes
and ‘factory closure problems’. The respondent is alleged to have requested
the appellant to make payments and assured that he will reimburse him before
the sanction of the building plan was obtained. Accordingly, the appellant claims
to have made a payment of ₹ 7,03,000/-.
4
4. On 18 March 2002, the respondent addressed a letter to the appellant
and denied the execution of the agreement. The appellant, by a letter dated 4
April 2002 protested the denial and requested the respondent to give him the
authority to obtain sanction of the building plans. Parties thereafter met and
agreed to modify the terms of the agreement with revised terms under which (i)
allocation of the owner would be 47% instead of 42%; and (ii) allocation of the
developer would be 53% instead of 58%.
5. On 26 May 2003, the appellant issued to the respondent a notice for
payment of his share of the sanctioned fees. On 3 June 2003 the owner wrote
a letter to the appellant through his advocate, denying the contents of the notice
on the ground that he had by a notice dated 19 May 2003 cancelled the
agreement and requested the appellant to return all documents and collect the
deposit.
6. On 6 August 2003, the appellant instituted a suit4
in the City Civil Court
seeking a declaration that the cancellation of the agreement by the respondent
was invalid and a permanent injunction restraining the respondent from entering
into any agreement with a third party for sale of the premises. On 28 September
2005 the City Civil Court allowed an amendment of the plaint, by which a prayer
for specific performance was included.

4 TS No.1150/03
5
7. On 28 February 2007, the City Civil Court dismissed the Suit with the
following observation:
“No tangible evidence is forthcoming in the instant suit by
which it can be said that the plaintiff (developer) obtained
possession of the suit property i.e. the possession of the suit
property is/has handed over to him after the execution of the
agreement in question.”
The City Civil Court relied on a judgment of a Division Bench of the High Court
of Calcutta in Vipin Bhimani v Smt Sunanda Das5
, that a suit for specific
performance of a development agreement at the instance of a developer is
barred by the provisions of Section 14(3)(c) of the Specific Relief Act 1963 (“the
Act”). Upon examining various clauses of the agreement, the City Civil Court
concluded that the appellant had agreed to apply at his own cost and expense
to the Calcutta Municipal Corporation for getting the plans of the proposed
building approved. The City Civil Court noted that it was an admitted fact that
sanction was not obtained by the appellant and therefore, it could not be said
that he had obtained possession. As a result, the suit at the instance of the
appellant was held to be barred by Section14(3)(c).
8. Aggrieved by the judgment and order of the City Civil Court, the appellant
preferred an appeal6 before the High Court of Calcutta. On 18 February 2009
the Division Bench of the High Court dismissed the appeal, on the ground that
the suit was not maintainable under Section 14(3)(c) of the Act.

5
(2006) 2 CHN 396
6 F.A. No. 175 of 2007
6
The High Court rejected the appellant’s argument that even if Section 14(3)(c)
stood in the way of getting a decree for specific performance, the Specific Relief
Act not being exhaustive, there was no bar in granting a decree. The High Court
held:
“….if in the Act there is a clear prohibition in granting a decree
for specific performance in a given situation, such provision is
exhaustive and cannot be made nugatory by contending that
the Act is not exhaustive and thus, the Court can ignore such
provision.”
9. The High Court also rejected the argument of the appellant that the
agreement in question was not a contract for construction of building on the
land in a real sense, as the respondent was not getting any consideration for
building. The High Court held that the agreement was in substance a contract
of construction within the meaning of sub-section (3)(c) of Section 14 and the
consideration was payable only upon the completion of the work.
10. The issue which has been raised before this Court is whether Section
14(3)(c) of the Act is a bar to a suit by a developer for specific performance of
a development agreement between himself and the owner of the property. In
dealing with this issue, the court needs to assess whether the word “defendant”
in Section 14(3)(c)(iii) has the effect of confining the scope of the suit for specific
performance only to a particular class (consisting of owners) or whether a
purposive interpretation to the legislation would be required, so as to provide a
broader set of remedies to both owners and developers. In deciding this issue
the court will need to scrutinise the nature of a development agreement.
7
11. Section 14 provides thus:
“14. Contracts not specifically enforceable-
(1) The following contracts cannot be specifically enforced,
namely -
(a) a contract for the non-performance of which compensation
in money is an adequate relief;
(b) a contract which runs into such minute or numerous details
or which is so dependent on the personal qualifications or
volition of the parties, or otherwise from its nature is such, that
the court cannot enforce specific performance of its material
terms;
(c) a contract which is in its nature determinable;
(d) a contract the performance of which involves the
performance of a continuous duty which the court cannot
supervise.
(2) Save as provided by the Arbitration Act, 1940 (10 of 1940),
no contract to refer present or future differences to arbitration
shall be specifically enforced; but if any person who has made
such a contract (other than an arbitration agreement to which
the provisions of the said Act apply) and has refused to perform
it, sues in respect of any subject which he has contracted to
refer, the existence of such contract shall bar the suit.
(3) Notwithstanding anything contained in clause (a) or clause
(c) or clause (d) of sub-section (1), the court may enforce
specific performance in the following cases--
(a) where the suit is for the enforcement of a contract,-
(i) to execute a mortgage or furnish any other security for
securing the repayment of any loan which the borrower is not
willing to repay at once:
Provided that where only a part of the loan has been advanced
the lender is willing to advance the remaining part of the loan
in terms of the contract; or
(ii) to take up and pay for any debentures of a company;
(b) where the suit is for-
(i) the execution of a formal deed of partnership, the parties
having commenced to carry on the business of the partnership;
or
(ii) the purchase of a share of a partner in a firm;
8
(c) where the suit is for the enforcement of contract for the
construction of any building or the execution of any other work
on land:
Provided that the following conditions are fulfilled, namely: -
(i) the building or other work is described in the contract in
terms sufficiently precise to enable the court to determine the
exact nature of the building or work;
(ii) the plaintiff has a substantial interest in the performance of
the contract and the interest is of such a nature that
compensation in money for non-performance of the contract is
not an adequate relief; and
(iii) the defendant has, in pursuance of the contract, obtained
possession of the whole or any part of the land on which the
building is to be constructed or other work is to be executed.”
Section 14(1) provides categories of contracts which are not specifically
enforceable. Sub-section (3) of Section 14 is an exception to clauses (a), (c)
and (d) of sub-section (1). Though the species of contract stipulated in clauses
(a), (c) and (d) of sub-section (1) cannot be specifically enforced, a suit for
specific performance of contracts of that description will be maintainable if the
conditions set out in sub-clauses (i), (ii) and (iii) of clause (c) of Section 14(3)
are satisfied.
12. The consistent position of the common law is that courts do not normally
order specific performance of a contract to build or repair. But this rule is subject
to important exceptions, and a decree for specific performance of a contract to
build will be made only upon meeting the requisite requirements under law.
According to Halsbury’s Laws of England7
, the discretion to grant specific

7 Halsbury’s Laws of England, Fourth Edition, Volume 44(1), para 801
9
performance is not arbitrary or capricious; it is governed by principles developed
in precedents. The judge must exercise the discretion in a judicious manner.
Circumstances bearing on the conduct of the plaintiff, such as delay,
acquiescence and breach or some other circumstances outside the contract,
may render it inequitable to enforce it. The position as elucidated in Halsbury’s
Laws of England8
is thus:
“… the court does not normally order specific performance of
a contract to build or repair. However, this rule is subject to
important exceptions, and a decree for specific performance of
a contract to build will be made if the following conditions are
fulfilled: (1) that the building work is defined by the contract
between the parties; (2) that the plaintiff has a substantial
interest in the performance of the contract of such a nature that
he cannot be adequately be compensated in damages; (3) that
the defendant is in possession of the land on which the work is
contracted to be done.”
13. This principle was followed by the Court of Appeal in Wolverhampton
Corporation v Emmons9
, where the plaintiff, the urban sanitary authority, in
pursuance of a scheme of street improvement, sold and conveyed to the
defendant a plot of land abutting a street, the defendant covenanting with them
that he would erect buildings within a certain time. Upon the defendant failing
to perform the agreement, the plaintiffs brought a suit against him claiming
specific performance. Romer L.J, held that a plaintiff can bring himself within
the exception, if three things are shown to exist: (i) the building work, the
performance of which the plaintiff seeks to enforce, is defined by the contract
allowing the court to know the exact nature and extent of work; (ii) the plaintiff

8 Halsbury’s Laws of England, Fourth Edition, Volume 44(1), para 806
9
[1901] 1 K. B. 515
10
must have a substantial interest in having the contract performed and the
interest must be of such a nature that damages will not be an adequate
compensation for the non-performance of the contract; and (iii) the defendant
has obtained from the plaintiff by means of the contract the possession of the
land on which the work is to be done. The case was held to come within the
class of cases which had been recognised as forming an exception to the
general rule that specific performance of a building contract will not be ordered.
14. In a decision of the Chancery Division in Carpenters Estate v Davies10
,
an owner of land sold a certain portion of it to the purchaser for development,
retaining land adjoining it, and agreed to lay roads and provide mains, sewers
and drains on the land retained. The purchaser brought a suit for specific
performance against the owner for not performing his obligations under the
agreement. Farwell J., observed that the plaintiff is required to establish that the
defendant is in possession of the land on which the work is contracted to be
done. The facts of the case, indicated that the defendant was already in
possession of the land, and there was no difficulty for her to carry out her
obligations. Finding that the plaintiff proved all three conditions as laid out in
Wolverhampton Corporation (supra), the court granted specific performance
to the plaintiff.

10 (1940) Ch. D 160
11
15. The requirements to be satisfied by the plaintiff bringing forth a suit for
specific performance have been analysed in Hudson’s Building and
Engineering Contracts11 and in Price v Strange12
, where the rule has been
settled that the court will order specific performance of an agreement to build if:
(i) the building work is sufficiently defined by the contract, for example by
reference to detailed plans;
(ii) the plaintiff has a substantial interest in the performance of the contract of
such a nature that damages would not compensate him for the defendant’s
failure to build; and
(iii) the defendant is in possession of the land so that the plaintiff cannot
employ another person to build without committing a trespass.
16. The expression “development agreement” has not been defined
statutorily. In a sense, it is a catch-all nomenclature which is used to be
describe a wide range of agreements which an owner of a property may enter
into for development of immovable property. As real estate transactions have
grown in complexity, the nature of these agreements has become increasingly
intricate. Broadly speaking, (without intending to be exhaustive), development
agreements may be of various kinds:
(i) An agreement may envisage that the owner of the immovable property
engages someone to carry out the work of construction on the

11 Hudson’s Building and Engineering Contracts, Eleventh Edition, Volume 1, page 677
12 [1978] 1 Ch. 337 at page 359
12
property for monetary consideration. This is a pure construction
contract;
(ii) An agreement by which the owner or a person holding other rights in
an immovable property grants rights to a third party to carry on
development for a monetary consideration payable by the developer
to the other. In such a situation, the owner or right holder may in effect
create an interest in the property in favour of the developer for a
monetary consideration;
(iii) An agreement where the owner or a person holding any other rights
in an immovable property grants rights to another person to carry out
development. In consideration, the developer has to hand over a part
of the constructed area to the owner. The developer is entitled to deal
with the balance of the constructed area. In some situations, a society
or similar other association is formed and the land is conveyed or
leased to the society or association;
(iv) A development agreement may be entered into in a situation where
the immovable property is occupied by tenants or other right holders.
In some cases, the property may be encroached upon. The developer
may take on the entire responsibility to settle with the occupants and
to thereafter carry out construction; and
(v) An owner may negotiate with a developer to develop a plot of land
which is occupied by slum dwellers and which has been declared as
a slum. Alternately, there may be old and dilapidated buildings which
13
are occupied by a number of occupants or tenants. The developer
may undertake to rehabilitate the occupants or, as the case may be,
the slum dwellers and thereafter share the saleable constructed area
with the owner.
When a pure construction contact is entered into, the contractor has no interest
in either the land or the construction which is carried out. But in various other
categories of development agreements, the developer may have acquired a
valuable right either in the property or in the constructed area. The terms of the
agreement are crucial in determining whether any interest has been created in
the land or in respect of rights in the land in favour of the developer and if so,
the nature and extent of the rights.
17. In a construction contract, the contractor has no interest in either the land
or the construction carried out on the land. But, in other species of development
agreements, the developer may have acquired a valuable right either in the
property or the constructed area. There are various incidents of ownership of in
respect of an immovable property. Primarily, ownership imports the right of
exclusive possession and the enjoyment of the thing owned. The owner in
possession of the thing has the right to exclude all others from its possession
and enjoyment. The right to ownership of a property carries with it the right to
its enjoyment, right to its access and to other beneficial enjoyments incidental
to it. (B Gangadhar v BG Rajalingam13). Ownership denotes the relationship

13 (1995) 5 SCC 239 at para 6
14
between a person and an object forming the subject matter of the ownership. It
consists of a complex of rights, all of which are rights in rem, being good against
the world and not merely against specific persons. There are various rights or
incidents of ownership all of which need not necessarily be present in every
case. They may include a right to possess, use and enjoy the thing owned; and
a right to consume, destroy or alienate it. (Swadesh Ranjan Sinha v Haradeb
Banerjee14). An essential incident of ownership of land is the right to exploit the
development, potential to construct and to deal with the constructed area. In
some situations, under a development agreement, an owner may part with such
rights to a developer. This in is essence is a parting of some of the incidents of
ownership of the immovable property. There could be situations where pursuant
to the grant of such rights, the developer has incurred a substantial investment,
altered the state of the property and even created third party rights in the
property or the construction carried out to be carried out. There could be
situations where it is the developer who by his efforts has rendered a property
developable by taking steps in law. In development agreements of this nature,
where an interest is created in the land or in the development in favour of the
developer, it may be difficult to hold that the agreement is not capable of being
specifically performed. For example, the developer may have evicted or settled
with occupants, got land which was agricultural converted into non-agricultural
use, carried out a partial development of the property and pursuant to the rights
conferred under the agreement, created third party rights in favour of flat

14 (1991) 4 SCC 572
15
purchasers in the proposed building. In such a situation, if for no fault of the
developer, the owner seeks to resile from the agreement and terminates the
development agreement, it may be difficult to hold that the developer is not
entitled to enforce his rights. This of course is dependent on the terms of the
agreement in each case. There cannot be a uniform formula for determining
whether an agreement granting development rights can be specifically enforced
and it would depend on the nature of the agreement in each case and the rights
created under it.
18 In Chheda Housing Development Corporation v Bibijan Shaikh
Farid15
, a Division Bench of the Bombay High Court while dealing with the
question of whether specific performance should be granted of a development
agreement held as follows:
“In our opinion from a conspectus of these judgments, what is
relevant would be the facts of each case and the agreement
under consideration. Agreements considering what is
discussed, amongst others, could be:
(a) An Agreement only entrusting construction work to a party
for consideration.
(b) An Agreement for entrusting the work of development to a
party with added rights to sell the constructed portion to flat
purchasers, who would be forming a Co-operative Housing
Society to which society, the owner of the land, is obliged to
convey the constructed portion as also the land beneath
construction on account of statutory requirements.
(c) A normal agreement for sale of an immovable property.
An Agreement of the first type normally is not enforceable as
compensation in money is an adequate remedy. An Agreement
of the third type would normally be specifically enforceable

15 (2007) 3 Mah LJ 402
16
unless the contrary is proved. A mere agreement for
development, which creates no interest in the land would not
be specifically enforced.”
19. The judgement of the Bombay High Court in Della Developers Private
Limited v Noble Organics Private Limited16, deals with a case where a
development agreement was executed between the petitioners and the
respondents. A dispute arose between the parties and arbitration proceedings
were initiated. An order was passed by the Arbitrator under Section 17 of the
Arbitration and Conciliation Act 1996 against which an appeal was filed under
Section 37. Before the High Court, the findings of the sole arbitrator under
Section 17 were challenged. Upon examining the agreement, the High Court
held that the agreement created a right or interest in immovable property. On
the issue of the maintainability of a proceeding initiated by the developer against
the owner under Section 14(3)(c), the court reiterated the requirement of
fulfilling the three conditions under Section 14(3)(c). Hon’ble Mr. Justice A M
Khanwilkar (as my learned Brother then was) held as follows:
“Insofar as present case is concerned, out of the three
conditions specified in Section 14(3)(c), prima facie, from the
terms of the Agreement as executed between the parties, there
is nothing to indicate that the Petitioner in pursuance of the
contract, was put in possession of the whole or any part of the
land on which the building is to be constructed or other work is
to be executed.”
20. In Ashok Kumar Jaiswal v Ashim Kumar Kar17
, a Full Bench of the
Calcutta High Court held that a development agreement with a clause for

16 (2010) 2 Bom CR 13
17 AIR 2014 Cal 92
17
conditional sale of the premises in question will also be an agreement for sale
subject to certain conditions. While deciding whether a suit at the instance of a
developer is maintainable in view of Section 14(3)(c), the Court, inter alia, held
that in the absence of a definition of "developer" or "development agreement"
the nature of the agreement which is the subject-matter of a suit must be
considered in order to determine whether it is an agreement to merely provide
construction of a building or whether the developer has obtained a share of, and
interest in, the developed property which is the outcome of the agreement,
creating a contract for transfer of immovable property. The Full Bench observed
thus:
“An owner without any funds or the independent resources to
construct a new building on such owner’s land may engage for
such purpose with the consideration for the construction being
paid by allocation of a part of the constructed area. There could
be several variants of the same basic structure of a
development agreement…..Such agreements are not merely
for the construction of any building or for the mere execution of
any other work on the land. The developer is not merely a
contractor engaged to undertake the construction; the
developer is, under the agreement with the owner, promised a
part of the constructed premises as owner thereof together with
the proportionate area of the land.”
The Full Bench held that a right to seek specific performance of a development
agreement is not barred either expressly or by necessary implication by the
1963 Act and a broad interpretation should be given to allow an adequate
remedy:
“….it would be preposterous to say that only the owner can
maintain a suit against the developer for enforcing his rights
and not vice-versa. If the developer has a right under the
18
contract he must be having a remedy in the form of
approaching a forum for appropriate redressal. A question of
maintainability of a suit is completely different from the
question of whether the suit will succeed or not on the facts of
the case and in the light of the applicable law. Section 14 (3)(c)
of the Act can in no manner be interpreted as debarring a
developer from approaching the legal forum for redressal of his
grievance.”
21. In the present case, the respondent agreed to pay the appellant the
costs and expenses along with the agreed remuneration upon completion of
the construction. If the respondent failed to pay, the appellant was entitled to
realise its money by selling 58% of the total constructed area. Clauses 6, 10
and 11 of the agreement indicate that the respondent would retain 42% of the
total constructed area and the balance 58% would remain secured for due
payment of the construction costs. It was further agreed, that the total
construction costs shall not exceed 58% of the constructed area. The intention
of the parties is clear from the agreement. This was an agreement to carry out
the construction of the building for which payment of the construction costs and
agreed remuneration had to be made. The agreement did not create an interest
in the land for the developer. If the payment due to the developer was made,
there would arise no security interest. Moreover, the security interest in respect
of 42% of the constructed area would arise only if the construction came up and
the payment due to the builder was not made. In present case, admittedly there
is no construction at all.
19
22. Various High Courts have interpreted the requirements under Section
14(3)(c) of the Act and opined on the maintainability of a suit by the developer
for specific performance against the owner of the property for a breach in the
conditions of the development agreement. A common thread that runs through
the analysis in decided cases is the following:
(i) The courts do not normally order specific performance of a contract to build
or repair. But this rule is subject to important exceptions, and a decree for
specific performance of a contract to build will be made only upon meeting
the requirements under law;
(ii) The discretion to grant specific performance is not arbitrary or capricious
but judicious; it is to be exercised on settled principles; the conduct of the
plaintiff, such as delay, acquiescence, breach or some other circumstances
outside the contract, may render it inequitable to enforce it;
(iii) In order to determine the exact nature of the agreement signed between
the parties, the intent of the parties has to be construed by reading the
agreement as a whole in order to determine whether it is an agreement
simpliciter for construction or an agreement that also creates an interest
for the builder in the property. Where under a development agreement, the
developer has an interest in land, it would be difficult to hold that such an
agreement is not capable of being specifically enforced; and
(iv) A decree for specific performance of a contract to build will be made if the
following conditions are fulfilled:
20
a) the work of construction should be described in the contract in a
sufficiently precise manner in order for the court to determine the exact
nature of the building or work;
b) the plaintiff must have a substantial interest in the performance of the
contract and the interest should be of such a nature that compensation
in money for non-performance of the contract is not an adequate relief;
and
c) the defendant should have, by virtue of the agreement, obtained
possession of the whole or any part of the land on which the building is
to be constructed or other work is to be executed.
23. The issue before this Court is whether Section 14(3)(c)(iii) is a bar to a
suit by a developer for specific performance of a development agreement
between himself and the owner of the property. The condition under Section
14(3)(c)(iii) is that the defendant has, by virtue of the agreement, obtained
possession of the whole or any part of the land on which the building is to be
constructed or other work is to be executed. If the rule of literal interpretation is
adopted to interpret Section 14(3)(c)(iii), it would lead to a situation where a suit
for specific performance can only be instituted at the behest of the owner
against a developer, denying the benefit of the provision to the developer
despite an interest in the property having been created. This anomaly is created
by the use of the words “the defendant has, by virtue of the agreement, obtained
possession of the whole or any part of the land” in Section 14(3)(c)(iii). Under a
21
development agreement, an interest in the property may have been created in
favour of the developer. If the developer is the plaintiff and the suit is against
the owner, strictly applied, clause (iii) would require that the defendant should
have obtained possession under the agreement. In such a case if the developer
files a suit for specific performance against the owner, and the owner is in
possession of the land by virtue of a lawful title, the defendant (i.e. the owner)
cannot be said to have obtained possession of the land by way of the
agreement. This would lead to an anomalous situation where the condition in
Section 14(3)(c)(iii) would not be fulfilled in the case of a suit by a developer.
Application of the literal rule of interpretation to Section 14(3)(c)(iii), would lead
to an absurdity and would be inconsistent with the intent of the Act.
24. The conditions that should be present to justify a departure from the plain
words of any statute, have been elucidated in Justice GP Singh’s treatise on
Principles of Statutory Interpretation18 (while discussing the decision of the
House of Lords in Stock v Frank Jones (Tipton) Ltd.19):
“...a court would only be justified in departing from the plain
words of the statute when it is satisfied that (1) there is clear
and gross balance of anomaly; (2) Parliament, the legislative
promoters and the draftsman could not have envisaged such
anomaly and could not have been prepared to accept it in the
interest of a supervening legislative objective; (3) the anomaly
can be obviated without detriment to such a legislative
objective; and (4) the language of the statute is susceptible of
the modification required to obviate the anomaly.”

18 Principles of Statutory Interpretation, 12th Edition - 2010, Lexis Nexis - page 144
19 (1978) 1 WLR 231
22
The principle has been also adverted to in Maxwell on Interpretation of
Statutes20 :
“Where the language of a statute, in its ordinary meaning and
grammatical construction, leads to a manifest contradiction of
the apparent purpose of the enactment, or to some
inconvenience or absurdity, hardship or injustice, presumably
not intended, a construction may be put upon it which modifies
the meaning of the words, and even the structure of the
sentence.”
By giving a purposive interpretation to Section 14(3)(c)(iii), the anomaly and
absurdity created by the third condition will have no applicability in a situation
where the developer who has an interest in the property, brings a suit for
specific performance against the owner. The developer will have to satisfy the
two conditions laid out in sub clause (i) and (ii) of Section 14(3)(c), for the suit
for specific performance to be maintainable against the owner. This will ensure
that both owners and developers can avail of the remedy of specific
performance under the Act. A suit for specific performance filed by the
developer would then be maintainable. Whether specific performance should in
the facts of a case be granted is a separate matter, bearing on the discretion of
the court.
25. Having dealt with the first aspect of the matter, it is now necessary to
determine whether, in the facts of the present case, the agreement between the
appellant and the respondent is capable of specific performance. For this

20 Maxwell, Interpretation of Statutes, 11th Edition, page 221
23
purpose, it would be necessary to consider the terms and conditions of the
agreement between the parties.
26. The condition under Section 14(3)(c)(i) is that the building or other work
described in the contract is sufficiently precise to enable the court to determine
the exact nature of the building or work. To examine the question as to whether
the scope of the building or work described in the agreement is sufficiently
defined, the Court needs to determine the exact nature of the work by referring
to the relevant clauses of the agreement. Clause 8 of the agreement provides
that the building shall be constructed in accordance with approved plans and
built with “first class materials” with wooden doors, mosaic floor, basin and
lavatories, tap water arrangement, masonry work, electric points, finished
distemper and bath room fittings of glazed tiles up to 6” height and lift, “etc.”
Further, at clause 13 of the agreement, the parties have agreed that the
contractor would construct a building at the premises consisting of “residential
apartments of various sizes and denomination” in the said building complex in
accordance with plans sanctioned by the Calcutta Municipal Corporation and
the owner shall convey the proportionate share in the land to the respective
buyers. Clause 22 of the agreement states that if for any reason after the plan
is sanctioned or “for any act or omission on the part of the owner” the building
cannot be constructed; the owner shall refund to the contractor ₹4,00,000/- in
addition to all costs, charges and expenses incurred by the contractor. At clause
20 of the agreement, the parties have agreed that the apartments of the owner
24
shall be constructed and be made in “similar condition” as that of the contractor
with water connection, sewerage, electric wiring except “special fittings”. Use
of such vague terms in the agreement such as “first class materials”, “residential
apartment of various sizes and denomination”, “etc.”, “similar condition”, and
“special fittings”, while discussing the scope of work clearly shows that the exact
extent of work to be carried out by the developer and the obligations of the
parties, have not been clearly brought out. Parties have not clearly defined, inter
alia, the nature of material to be used, the requirements of quality, structure of
the building, sizes of the flats and obligations of the owner after the plan is
sanctioned. Further, clause 9 of the agreement states that the owner shall pay
the contractor costs, expenses along with agreed remuneration only after
completion of the building on receiving the possession. However, the exact
amount of remuneration payable by the owner to the contractor is not to be
found in the agreement. The agreement between the parties is vague. The court
cannot determine the exact nature of the building or work. The first condition in
Section 14(3)(c)(i) is not fulfilled.
27. Another condition under Section 14(3)(c)(ii) is that the plaintiff has a
substantial interest in the performance of the contract and the interest is of such
a nature that compensation in money for non-performance of the contract is not
an adequate relief. The intent of the section is to make a distinction between
cases where a breach of an agreement can be remedied by means of
compensation in terms of money and those cases where no other remedy other
25
than specific performance will afford adequate relief. Therefore, before granting
the remedy of specific performance, we need to analyse the extent of the
alleged harm or injury suffered by the developer and whether compensation in
money will suffice in order to make good the losses incurred due to the alleged
breach of the agreement by the owner. From the facts of the case, it is clear
that the case of the developer is that he incurred an expenditure of ₹ 18,41,000/-
towards clearing outstanding dues, security deposit and development,
incidental and miscellaneous expenses. The alleged losses/damages incurred
by the Plaintiff can be quantified. The plaintiff can be provided recompense for
the losses allegedly incurred by payment of adequate compensation in the form
of money. The developer has failed to satisfy the conditions under sub-clause
(i) and (ii) of Section 14(3)(c) of the Act. In such a case, specific performance
cannot be granted.
28. By the Specific Relief (Amendment) Act 201821
, Section 14 has been
amended to read as follows:
“14. The following contracts cannot be specifically enforced,
namely:—
(a) where a party to the contract has obtained substituted
performance of contract in accordance with the provisions of
section 20;
(b) a contract, the performance of which involves the
performance of a continuous duty which the court cannot
supervise;
(c) a contract which is so dependent on the personal
qualifications of the parties that the court cannot enforce
specific performance of its material terms; and
(d) a contract which is in its nature determinable.”

21Act 18 of 2018
26
However, the amended section has been notified on 19 September 2018 and
the central government has appointed 1 October 2018 as the date on which the
provision of Act 18 of 2018 will come into force22
. However, in the present case,
we are not called upon to examine the effect of this amended provision. In any
case, we have indicated the reasons why Section 14(3)(c) was not attracted.
29. The appellants have relied on the decision of this Court in Her Highness
Maharani Shantidevi P Gaikwad v Savjibai Haribai Patel23
, where an
agreement was entered into between the landowner and the developer for the
purpose of construction of houses for the weaker sections on excess vacant
land under a scheme sanctioned under Section 21 of the Urban Land (Ceiling
and Regulation) Act 1976. This Court reversed the decision of the High Court
that granted the decree of specific performance to the developer on the grounds
that it was inequitable to enforce specific performance in view of a change in
the Master Plan. The court noted that a contract which involved continuous
supervision of the court, was not specifically enforceable. Further, in the opinion
of the court, at best the plaintiff - builder could claim damages and the
expenditure incurred by him for the implementation of the terms of the
agreement. The above case has no applicability to the facts of the present case
and is of no relevance as the issue in relation to the maintainability of a suit for
specific performance by the builder against the owner has not been discussed.

22 S.O.4888(E) dated 19.09.2018
23 AIR 2001 SC 1462
27
30. The appellant has also placed reliance on the decision in Faqir Chand
Gulati v Uppal Agencies Private Limited24, where the issue before this Court
was whether a landowner, who enters into an agreement with the builder, for
construction of an apartment building is a “consumer” entitled to maintain a
complaint against the builder as a service provider under the Consumer
Protection Act, 1986. The Court held:
“We may notice here that if there is a breach by the landowner
of his obligations, the builder will have to approach a civil court
as the landowner is not providing any service to the builder but
merely undertakes certain obligations towards the builder,
breach of which would furnish a cause of action for specific
performance and/or damages. On the other hand, where the
builder commits breach of his obligations, the owner has two
options. He has the right to enforce specific performance
and/or claim damages by approaching the civil court. Or he can
approach the Forum under Consumer Protection Act, 1986 for
relief as consumer, against the builder as a service- provider.”
The issue involved before this Court was in relation to the interpretation of the
Consumer Protection Act, 1986 and not on the maintainability of a suit filed by
the developer against the owner for specific performance in view of Section
14(3)(c) of the Act. Therefore, the decision cannot be relied upon in relation to
the issue before us.
31. Ordinarily, if there was an alternative plea for damages or monetary relief,
we would have remanded the case to the High Court for consideration of the
prayer. However, in the impugned judgment, the Division Bench has observed
thus:

24 (2008) 10 SCC 345
28
“Although we find no merit in this appeal, we wanted to give
liberty to the plaintiff for amendment of the plaint for the
purpose of getting alternative relief by way of return of security
of money and damages, if at all suffered, in terms of Section
22 of the Specific Relief Act; but Mr. Das, the learned Advocate
appearing on behalf of the appellant after taking instruction
from his client submitted before us that his client did not want
to avail of such remedy and wanted to challenge our decision
by preferring an appeal if we decided to refuse the prayer for
specific performance of the contract. ”
The same statement has been made before this Court, as was made before the
High Court. In the absence of any plea for damages or monetary relief by the
respondents, there is no reason to remit the appeal back to the High Court.
32. For the above reasons we find no merit in this appeal. The appeal stands
dismissed. There shall be no order as to costs.
.……..….....................................................J
 [A M KHANWILKAR]
.…………....................................................J
 [Dr DHANANJAYA Y CHANDRACHUD]
New Delhi;
October 09, 2018.