LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Friday, July 22, 2011

The State authority has decided to establish a toll road as it was not having sufficient funds. In case the claim of the private appellant is allowed and as the State is not in a position to grant further facility to collect the toll fee at such a belated stage, the purpose of establishing the toll road itself stands frustrated. More so, the toll fee cannot be collected to recover the amount never spent by the contractor. It is evident from the discourse in pre-bid meetings of the parties that it had been decided that compensation would be worked out on the basis of investment made by concerned contractor. More so, the statutory notification dated 10.2.1997 provided to recover the cost of construction and maintenance including interest thereon. Therefore, the question of non-execution of work of second phase of the contract becomes very material and relevant to determine the real controversy. The State authorities for the reasons best known to them, did not make reference to the arbitration proceedings for non- execution of the work of the second phase of the contract. However,


                                                                                         REPORTABLE





                          IN THE SUPREME COURT OF INDIA


                          CIVIL APPELLATE JURISDICTION


                           CIVIL APPEAL NO. 5416 OF 2011

                     


        M/s. MSK Projects (I) (JV) Ltd.                                        ... Appellant


                                                      Versus


        State of Rajasthan & Anr.                                                         ...Respondents


                                                       with


                           CIVIL APPEAL NO. 5417  OF  2011

                   





                                             J U D G M E N T





        Dr. B.S. CHAUHAN, J.




        1.        Both   these   appeals   have   been   preferred   by   the   rival   parties


        against the judgment and order dated 24.4.2007 passed by the High


        Court of Rajasthan (Jaipur Bench) in Civil Misc. Appeal No.1581 of


        2006 under Section 37(1)(A) of the Arbitration and Conciliation Act,


        1996   (hereinafter   called   "Act   1996")   against   the   order   dated


17.1.2006   passed   by   the   District   Judge,   Jaipur   City,   Jaipur   in


Arbitration   Case   No.89/2004   whereby   the   application   filed   by   the


State of Rajasthan under Section 34 of the Act 1996 for setting aside


the arbitral award dated 1.12.2003 had been allowed.




2.     Facts and circumstances giving rise to these appeals are:


A.     The   Public   Works   Department   of   the   State   of   Rajasthan


(hereinafter called "PWD") decided in September 1997 to construct


the   Bharatpur   bye-pass   for   the   road   from   Bharatpur   to   Mathura,


which passed through a busy market of the city of Bharatpur. For the


aforesaid work, tenders were invited with a stipulation that the work


would   be   executed   on   the   basis   of   Build   Operate   and   Transfer


(BOT).    The  total  extent of the  road  had  been  10.850 k.ms.  out of


which   9.6   k.ms.   was   new   construction   and   1.25   k.ms.   was


improvement, i.e. widening and strengthening of the existing portion


of Bharatpur-Deeg Road.




B.     After   having   pre-bid   conference/meeting   and   completing   the


required   formalities   it   was  agreed   between   the   tenderers  and   PWD


that compensation  would be worked out on the basis of investment


made   by   the   concerned   entrepreneur.     The   tender   submitted   by


MSK-appellant   for   Rs.1,325   lacs   was   accepted   vide   letter   dated





                                                                            2


5.2.1998 and the MSK-appellant was called upon to furnish security


deposit which was done on 25.7.1998. Concession agreement dated


19.8.1998 was entered into between the parties authorising collection


of toll fee by MSK-appellant.  According to this agreement, period of


concession   had   been   111   months   including   the   period   of


construction.     The   said   period   would   end   on   6.4.2008.   It   also


contained the provisions for making  repayment/collection of toll  fee


and   in   case   of   any   difference/dispute   to   refer   the   matter   to   the


Arbitrator.




C.     MSK-appellant   completed   the   Bharatpur   bye-pass   Project   on


10.4.2000 and also started collection of toll fee as provided under the


agreement   with   effect   from   28.4.2000.     There   had   been   some


problem   in   collecting   the   toll   fee   because   of   agitation   by   local


people.     The   State   issued   Notification     dated     1.9.2000   under   the


provisions   of   the   Indian   Tolls   Act,   1851   and   Rajasthan   Motor


Vehicles   Taxation   (Amendment)   Act,   1994   (hereinafter   called   the


`Notification   dated   1.9.2000')   preventing   the   entry   of  vehicles   into


Bharatpur   city   stipulating   its   operation   with   effect   from   1.10.2000.


MSK-appellant   invoked   arbitration   clause   raising   the   dispute   with


respect to:





                                                                                  3


  (a) Delay   in   issuance   of   Notification   prohibiting   entry   of


          commercial   vehicles   into   Bharatpur   town   and   diverting


          traffic through the bye-pass; and


  (b) Collection of toll from vehicles using Bharatpur-Deeg patch of


          the road.




D.      The State/PWD failed to make appointment of the Arbitrator.


MSK-appellant preferred SB Civil Arbitration Application  No.31 of


2002 before the High Court and the High Court vide order 12.4.2002


appointed   the   Arbitrator.   The   Arbitrators   so   appointed   in   their


meeting on 8.5.2002 appointed the third Arbitrator.   Claim Petition


was filed before the Tribunal by MSK-appellant on 23.9.2002. The


State submitted its reply to the claim petition on 7.12.2002.




E.       The Arbitral Award was made in favour of  MSK-appellant on


1.12.2003 according to which there had been delay on the part of the


State of Rajasthan in issuing the Notification and the State failed to


implement the same and the contractor was entitled to collect toll fee


even from the vehicles using Bharatpur-Deeg part of the road .   The


State   of  Rajasthan   was  directed   to   pay   a   sum   of   Rs.990.52   lacs   to


MSK-appellant as loss  due upto 31.12.2003 with 18% interest from


31.12.2003   onwards.   The   Tribunal   further   gave   various   other





                                                                                    4


directions to the State in this regard.




F.     Being aggrieved, the State of Rajasthan filed objections under


Section 34 of the Act 1996 and while deciding the same, the District


Judge vide order dated 17.1.2006 set aside the Arbitral Award on the


grounds   that   there   was   no   clause   in   the   agreement   to   issue


notification barring the entry of vehicles in the city of Bharatpur; and


the Tribunal erred in taking 1997 survey as basis for calculating the


loss suffered by MSK-appellant.  It held that MSK-appellant was not


entitled   to   any   monetary   compensation   under   clause   10   of   the


concession   agreement,   but   only   entitled   to   extension   of   concession


period, and the rate of interest was reduced from 18% to 10%.




G.     Being   aggrieved,   MSK-appellant   preferred   an   appeal   before


the High Court wherein the High Court vide impugned judgment and


order dated 24.4.2007 held that Bharatpur-Deeg section was part of


the project and the contractor could collect the toll fee from the users


of this part of the road also. Clause 10 of the concession agreement


was not attracted in the facts of the case.   There was no agreement


for issuance of Notification by the State barring the use of old route


and directing the vehicles to use the new route alone. Therefore, the


question of grant of compensation on that account for the traffic loss





                                                                              5


 could not arise.  The District Judge was justified in reducing the rate


 of   interest   from   18%   to   10%   in   view   of   the   provisions   of   Section


 31(7)(b) of the Act,1996 and economic realities, whereby the rate of


 interest had been reduced by the Banks in India.


         Hence, these two appeals.




3.       Mr. K.K. Venugopal, learned senior counsel appearing for the


private appellant, has submitted that it was implied in the agreement


and   there   has   been   an   understanding   between   the   parties   that   State


Government   would   issue   notification   barring   the   vehicles   driven


through   the   markets   of   Bharatpur   City.   This   was   not   even   an   issue


before the Tribunal and thus, could not be agitated by the State at all.


Thus,   the   courts   below   erred   in   setting   aside   the   award   of   arbitral


tribunal   to   that   extent,   and   secondly,   that   the   rate   of   interest   as


reduced from 18 per cent to 10 per cent by the District Court as well


as the High Court is in contravention of the terms of contract between


the   parties   which   fixed   the   rate   of   interest   at   20   per   cent.     Further


opposing   the   appeal   by   the   State   of   Rajasthan,   Shri   Venugopal   has


submitted   that   Bharatpur-Deeg   patch   was   an   integral   part   of   the


project   as   there   was   only   one   composite   contract   of   the   entire   bye-


pass and, therefore, the private appellant was entitled to collect the toll


fee from the users of that part of the road also.




                                                                                          6


4.       Per contra, Dr. Manish Singhvi, learned Additional Advocate


General   for   the   State   of   Rajasthan,   has   submitted   that   arbitration


proceedings could not be proceeded in contravention to the terms of


agreement and statutory provisions.   There was no obligation on the


part   of   the   State   authorities   to   issue   the   notification   restraining   the


entry of vehicles to the market side of the city.  The rate of interest has


rightly   been   reduced   considering   the   prevailing   rate   of   interest   in


banking transactions during the relevant period of contract. In support


of the appeal of the State, it has been submitted that there was a clear


understanding between the parties that the private appellant shall not


collect any toll fee on the Bharatpur-Deeg patch and to that extent the


Tribunal and  the courts below committed an error.  It has further been


submitted that the total contract had been for a sum of Rs.13.25 crores


including interest.  The project was to be executed in two phases. The


second phase for a sum  of Rs.3.24 crores had never been executed by


the  private   appellant.  The   contractor  could  collect  the  compensation


only on the basis of investment made by it.  The concept of toll fee is


of   compensatory   in   nature   wherein   the   State   which   has   spent   huge


amount on construction of roads/bridges etc. has a right to get the said


amount  reimbursed,  and therefore,  in such  a contract  the concept of


profit which prevails in other forms of contract cannot be the relevant




                                                                                       7


component.




5.         We have considered the rival submissions made on behalf of


the parties and perused the record.




           In   the   appeal   filed   by   the   private   contractor,   MSK   Projects,


two issues are involved; namely,  whether it was mandatory/necessary


in   view   of   the   agreement/contract   or   on   the   basis   of   pre-bid   under-


standing   that   the   State   had   to   issue   the   notification   barring   the


vehicles through the markets of Bharatpur city; and secondly  whether


the rate of interest could be reduced from 18% to 10% by the courts


below.




           In the State appeal, the only issue required to be considered is


whether the private appellant had a right to collect the toll fee on the


patch between Bharatpur - Deeg.




6.         The issue regarding the jurisdiction of the Arbitral Tribunal to


decide an issue not referred to is no more  res integra. It is a settled


legal proposition that special Tribunals like Arbitral Tribunals and La-


bour   Courts  get   jurisdiction   to   proceed   with   the   case   only   from   the


reference   made   to   them.     Thus,   it   is   not   permissible   for   such


Tribunals/authorities to travel beyond the terms of reference.   Powers





                                                                                     8


cannot   be   exercised   by   the   Tribunal   so   as   to   enlarge   materially   the


scope of reference itself.




         If the dispute is within the scope of the arbitration clause, it is


no part of the province of the court to enter into the merits of the dis-


pute on the issue not referred to it. If the award goes beyond the refer-


ence or there is an error apparent on the face of the award it would


certainly be open to the court to interfere with such an award. (Vide:


Grid   Corporation   of   Orissa   Ltd.   &   Anr. v. Balasore   Technical


School,   AIR   1999   SC   2262;   and  Delhi   Development   Authority


v. R.S. Sharma and Company, New Delhi, (2008) 13 SCC 80).




7.       In  Associated   Engg.   Co. v. Govt.   of   Andhra   Pradesh   &


Anr., AIR 1992 SC 232, this Court held that an umpire or arbitrator


cannot   widen   his   jurisdiction   by   deciding   a   question   not   referred   to


him by  the parties.    If he exceeded  his jurisdiction by so  doing, his


award would be liable to be set aside. Thus, an arbitrator cannot be al-


lowed to assume jurisdiction over a question which has not been re-


ferred to him, and similarly, he cannot widen his jurisdiction by hold-


ing   contrary   to   the   fact   that   the   matter   which   he   wants   to   decide   is


within the submission of the parties.





                                                                                          9


8.       If   the   arbitrator   commits   an   error   in   the   construction   of   the


contract, that is an error within his jurisdiction. But if he wanders out -


side the contract and deals with matters not allotted to him, he com-


mits   a   jurisdictional   error.   Extrinsic   evidence   is   admissible   in   such


cases because the dispute is not something which arises under or in re-


lation to the contract or dependent on the construction of the contract


or to be determined within the award. The ambiguity of the award can,


in   such   cases,   be   resolved   by   admitting   extrinsic   evidence.   The   ra-


tionale of this rule is that the nature of the dispute is something which


has to be determined outside and independent of what appears in the


award. Such a jurisdictional error needs to be proved by evidence ex-


trinsic to the award. (See: Gobardhan Das v. Lachhmi Ram & Ors.,


AIR 1954 SC 689; Seth Thawardas Pherumal v. The Union of In-


dia, AIR 1955 SC 468; Union of India v. Kishorilal Gupta & Bros.,


AIR 1959 SC 1362; Alopi Parshad & Sons. Ltd. v.  Union of India,


AIR   1960   SC   588;  Jivarajbhai   Ujamshi   Sheth   &   Ors.   v.


Chintamanrao   Balaji   &   Ors.,  AIR   1965   SC   214;   and  Renusagar


Power   Co.   Ltd.   v. General   Electric   Company   &  Anr.,  AIR   1985


SC 1156).




9.       In  Kishore   Kumar   Khaitan   &   Anr.   v.   Praveen   Kumar


Singh, (2006) 3 SCC 312, this Court held that when a court asks itself




                                                                                      10


a wrong question or approaches the question in an improper manner,


even if it comes to a finding of fact, the said finding of fact cannot be


said   to   be   one   rendered   with   jurisdiction.   The   failure   to   render   the


necessary findings to support its order would also be a jurisdictional


error liable to correction.




(See also: Williams v. Lourdusamy & Anr., (2008) 5 SCC 647)





10.      In Cellular Operators Association of India & Ors. v. Union


of India & Ors., (2003) 3 SCC 186, this Court held as under:




         "As regards the issue of jurisdiction, it posed a wrong

         question   and   gave   a   wrong   answer................The

         learned   TDSAT,   therefore,   has   posed   absolutely   a

         wrong question and thus its impugned decision suffers

         from a misdirection in law."




11.      This Court, in Oil & Natural Gas Corporation Ltd. v.  SAW


Pipes Ltd., AIR 2003 SC 2629; and Hindustan Zinc Ltd. v. Friends


Coal   Carbonisation,  (2006)   4   SCC   445),   held   that   an   arbitration


award contrary to substantive provisions of law, or provisions of the


Act, 1996 or against terms of the contract, or public policy, would be


patently illegal, and if it affects the rights of the parties, it would be


open for the court to interfere under Section 34(2) of the Act 1996.




12.      Thus,   in   view   of   the   above,   the   settled   legal   proposition




                                                                                      11


emerges   to   the   effect   that   the   arbitral   tribunal   cannot   travel   beyond


terms   of   reference;   however,   in   exceptional   circumstances   where   a


party pleads that the demand of another party is beyond the terms of


contract   and   statutory   provisions,   the   tribunal   may   examine   by   he


terms of contract as well as the statutory provisions. In the absence of


proper   pleadings   and   objections,   such   a   course   may   not   be


permissible.




13.      Be   that   as   it   may,   in   the   instant   case,   a   reference   to   the


Tribunal had been made on the basis of statement of facts, claims by


the   private   appellant,   defence   taken   by   the   respondent-State   and   re-


joinder by the claimant. After completing the formalities of admission


and   denial   by   each   party   in   respect   of   each   other's   documents   and


submission of draft proposed issues and respective oral evidence, the


Tribunal on 4.1.2003 framed the following issues:




1.       Whether claimant as per agreement is entitled to recover

its amount of claim of Rs.453.69 lacs upto 31.12.2002 and on-

wards or not?


2.       Whether there was delay on part of State in issuing noti-

fication   for   restriction   of   traffic   through   the   Bharatpur   Town,

which has effected the toll tax or not? If so, how much delay and

delay in full rate of safe implementation as on date, or not? By

virtue   of   it,   is   the   claimant   entitled   to   recover   its   claim   of

Rs.292.17 lacs upto 31.12.2002 and thereafter onward or not; or

merely by extension of concession period as averred by respond-

ent?





                                                                                         12


3. As  a   consequence   of   issue   1   &2,   which   party   breached   the

       contract?


4.         Whether  the  claimant  is entitled  to  claim interest   on  its

any due claim amount as per decision of issue 1 & 2? If so, from

what date and at what rate of simple/compound interest?


5. Whether claimant or respondent is entitled for cost of arbitra-

       tion incurred and claimed by, each party? If so, what amount

       and to which party?


6.         Any other if any demanded by any party during proceed-

ings.





14.        The Tribunal considered the relevant agreement provisions as


well as land lease deed, total package documents, minutes of pre-bid


meetings   and   deed   authorising   collection   of   toll   fee   etc.,   and   pro-


ceeded with the arbitration proceedings.  The State of Rajasthan  had


not taken the defence that it was not agreed between the parties to is-


sue the notification barring the traffic through the markets of Bharat-


pur city. The only issue remained as to whether there was delay in is-


suance of notification and implementation thereof.  In such a fact-situ-


ation   and   considering   the   settled   legal   propositions,   we   are   of   the


view that the District Judge as well as the High Court fell in error con-


sidering   the   issue   which   was   not   taken   by   the   State   before   the


Tribunal during the arbitration proceedings.





                                                                                   13


15.      Furthermore, it is a settled legal proposition that the arbitrator


is   competent   to   award   interest   for   the   period   commencing   with   the


date of award to the date of decree or date of realisation, whichever is


earlier. This is also quite logical for, while award of interest for the


period prior to an arbitrator entering upon the reference is a matter of


substantive   law,   the   grant   of   interest   for   the   post-award   period   is   a


matter of procedure.




(Vide: Seth Thawardas Pherumal (Supra); Union of India v. Bungo


Steel Furniture Pvt. Ltd., AIR 1967 SC 1032; Executive Engineer,


Irrigation, Galimala & Ors. v. Abnaduta Jena, AIR 1988 SC 1520;


Gujarat   Water   Supply   &   Sewerage   Board v. Unique   Erectors


(Gujarat) (P) Ltd. & Anr., AIR 1989 SC 973; Secretary, Irrigation


Department,   Govt.   of   Orissa &   Ors.  v. G.C.   Roy,  AIR   1992   SC


732; Hindustan Construction Co. Ltd. v.  State of Jammu & Kash-


mir, AIR 1992 SC 2192; Executive Engineer, Dhenkanal Minor Ir-


rigation   Division,   Orissa v. N.C.   Budharaj  (Dead)  by   Lrs., AIR


2001   SC   626;  Bhagawati   Oxygen   Ltd.   v. Hindustan   Copper


Ltd., AIR 2005 SC 2071; and   Indian Hume Pipe Co. Ltd. v. State


of Rajasthan, (2009) 10 SCC 187).





                                                                                       14


16.     So far as the rate of interest is concerned, it may be necessary


to refer to the provisions of Section 3 of the Interest Act 1978, relev-


ant part of which reads as under:




        "(1)  In  any proceedings  for the  recovery   of any  debt  or

        damages or in any proceedings in which a claim for in-

        terest in respect of' any debt or damages already paid is

        made, the court may, if it thinks fit, allow interest to the

        person entitled to the debt or damages or to the person

        making such claim, as the case may be, at a rate not ex-

        ceeding the current rate of interest...."    (Emphasis ad-

        ded)


               Thus, it is evident that the aforesaid  provisions empower the


Court to award interest at the rate prevailing in the banking   transac-


tions. Thus, impliedly, the court   has a power to vary the rate of in-


terest agreed by the parties.




17.     This Court in  Krishna Bhagya Jala Nigam Ltd. v. G.   Har-


ischandra Reddy & Anr., AIR 2007 SC 817, while dealing with the


similar issue held as under:




        "...after economic reforms in our country the interest re-

        gime    has  changed   and  the   rates  have   substantially   re-

        duced and, therefore, we are of the view that the interest

        awarded by the arbitrator at 18% for the pre-arbitration

        period, for the pendente lite period and future interest be

        reduced to 9%."





18.     In  H.U.D.A   v.   Raj   Singh   Rana,  AIR   2008   SC   3035,   this





                                                                               15


Court   considered   various   earlier   judgments   of   this   Court   including


Ghaziabad Development Authority v. Balbir Singh,  AIR 2004 SC


2141;  Bihar State Housing Board v. Arun Dakshy,  (2005) 7 SCC


103;  Haryana Urban Development Authority v. Manoj Kumar &


Anr.,  (2005)   9   SCC   541;  H.U.D.A   v.   Prem   Kumar   Agarwal   &


Anr., JT 2008 (1) SC 590 and came to the conclusion:


        ".......the   rate   of   interest   is   to   be   fixed   in   the

        circumstances   of   each   case   and   it   should   not   be

        imposed  at a  uniform  rate  without  looking  into the

        circumstances   leading   to   a   situation   where

        compensation was required to be paid."





19.     Be that as it may, the High Court while dealing with the rate of


interest   has   relied   upon   the   judgment   of   this   Court   in  Krishna


Bhagya Jala Nigam Ltd.  (supra) and thus, there is no scope for us to


interfere with the rate of interest fixed by the courts below.




20.     The issue raised by the State before this Court in its appeal as


to   whether   the   Bharatpur-Deeg   patch   was   an   integral   or   composite


part of the project and the private appellant could collect the toll fee


on that part also stands concluded by the High Court after considering


the entire evidence on record.




21.     It is evident from the record as well as the judgments of the


courts below that bid documents contained data collected on the flow



                                                                              16


of traffic on 14th  and 15th  April, 1994 to find out the viability and re-


quirement of the establishment of Bharatput bye-pass and it included


the   traffic   flow   on   the   Bharatpur-Deeg   section   also   which   indicates


that this particular patch had also been an integral part of the project.




22.      In pre-bid conference the interveners wanted a clarification as


to   whether   the   persons   using   this   particular   patch   of   road   between


Bharatpur-Deeg  could be liable to pay toll fee. It was clarified by the


respondent-State authorities that the users of this patch would be re-


quired to pay the toll fee.




23.      Clause 5 of the Concession agreement also provided that Gov-


ernment would levy and charge the fee from all persons using the pro-


ject facilities. The project was not in parts rather it was a composite


and   integrated   project   which   included   the   Bharatpur-Deeg   section


also.   Hence, it was not permissible for the respondent-State to take


the plea that persons using such section of the road were not liable to


pay the toll fee. We do not find any force in the submission made by


Dr.   Manish   Singhvi,   learned   counsel   for   the   State   that   it   was   not   a


newly constructed road. However, he is not in a position to deny that


the   said   portion   of   road   had   been   widened   and   strengthened   by   the


private appellant and could not be termed as service road which could





                                                                                       17


be used free of charge in view of clause 7 of the concession agreement


as service road has been defined as any road constructed temporarily


for   use   of      traffic   for   short   period   during   construction   of   the   main


road. Such a facility had to be provided in order to maintain the free


flow of traffic during the construction of the road.




24.      Thus, in view of the above, the issue raised by the State that


Bharatpur-Deeg   section   of   the   road   was   out   of   the   project   and   the


private appellant was not entitled to collect the toll fee on that part of


the road, stands settled in favour of the private appellant.




25.      Determination of the aforesaid three issues brings us to the en-


titlement of the private appellant.




        The Court is not oblivious to the fact that the State authorities


cannot be permitted to use the collection of toll fee as augmenting the


State revenues.   In  State of U.P. & Ors. v. Devi Dayal Singh,  AIR


2000 SC 961, this Court defined 'toll' as a sum of money taken in re-


spect of a benefit arising out of the temporary use of land. It implies


some   consideration   moving   to   the   public   either   in   the   form   of   a


liberty, privilege or service. In other words, for the valid imposition of


a toll, there must be a corresponding benefit. The Court further held:




         "Although   the   section   has   empowered   the   State



                                                                                         18


          Government   to   levy   rates   of   tolls   "as   it   thinks   fit",

          having regard to the compensatory nature of the levy,

          the rate of toll must bear a reasonable relationship to

          the providing of benefit. No doubt, by virtue of Section

          8 of the Act, the tolls collected are part of the public

          revenue and may be absorbed in the general revenue

          of the State, nevertheless by definition a toll cannot be

          used for otherwise augmenting the State's revenue."

                                                                      (Emphasis added)



26.       In   fact,   the   toll   fee   under   the   Tolls   Act,   1851   is   of


compensatory in nature wherein the Government can reimburse itself


the amount which it had spent on construction of road/bridge etc.


          Clause   IV(a)   of   the   statutory   notification   dated   10.2.1997


which   entitled   the   government   to   give   present   road   on   toll   is


reproduced below:


          "IV(a).          The   toll   of   any   of   the   aforesaid

          facilities/constructions shall be levied only for so long

          as the total cost of its construction and maintenance

          including   interest   thereupon,   and   the   total

          expenditure   in   realisation   of   toll   has   not   been

          realised in full or for a period of 30 years."

                                                                      (Emphasis added)


            It is evident that Clause  IV(a)   of   the   Notification   dated


10.02.1997 envisages that toll can only be collected as long as total


cost of construction and maintenance  including interest thereupon is


recovered.     A   person   is   debarred   by   law   and   statutory   inhibition   as


contained   in   Clause   IV(a)   of   the   notification   from   collection   of   toll


beyond the recovery of cost of construction.





                                                                                          19


27.      Thus,  from the above referred provisions, it is evident that toll


fee   is   compensatory   in   nature   and   can   be   collected   by   the   State   to


reimburse   itself   the   amount   it   has   spent   on   construction   of   the


road/bridge etc. The State is competent to levy/collect the toll fee only


for the period stipulated under the Statute or till the actual cost of the


project with interest etc. is recovered. However, it cannot be a source


of revenue for the State.




28.               In common  parlance, "reimbursement"  means and implies


restoration   of   an   equivalent   for   something   paid   or   expanded.


Similarly,   "Compensation"   means   anything   given   to   make   the


equivalent. (See:  State of Gujarat v.  Shantilal Mangaldas & Ors.,


AIR 1969 SC 634; Tata Iron & Steel Co. Ltd. v. Union of India &


Ors.,  AIR   2000   SC   3706;  Ghaziabad   Development   Authority


(Supra); and H.U.D.A v. Raj Singh Rana, (Supra).




29.      However, in  Dwaraka  Das v. State of Madhya Pradesh &


Anr., AIR 1999 SC 1031, it was held that a claim by a contractor for


recovery   of   amount   as   damages   as   expected   profit   out   of   contract


cannot   be   disallowed   on   ground   that   there   was   no   proof   that   he


suffered   actual   loss   to   the   extent   of   amount   claimed  on   account   of





                                                                                      20


breach of contract.




30.      In  M/s.  A.T.   Brij   Paul   Singh   &   Ors.   v.   State   of   Gujarat,


AIR 1984 SC 1703, while interpreting the provisions of Section 73 of


the   Indian   Contract   Act,   1972,   this  Court   held   that   damages   can   be


claimed   by   a   contractor   where   the   government   is  proved   to   have


committed breach by improperly rescinding the contract  and for


estimating   the   amount   of   damages,   court   should   make   a   broad


evaluation  instead of going into minute  details. It was specifically


held that where in the works contract, the party entrusting the work


committed  breach   of   contract,   the   contractor   is   entitled   to   claim


the   damages   for   loss   of   profit   which   he   expected   to   earn   by


undertaking the works contract. Claim of expected profits is legally


admissible on proof of the breach of contract by the erring party. It


was further observed that what would be the measure of profit would


depend upon facts and circumstances of each case. But that there shall


be  a   reasonable   expectation   of  profit   is  implicit   in  a   works  contract


and   its   loss   has  to   be   compensated   by   way   of  damages   if   the   other


party   to   the   contract  is   guilty   of   breach   of   contract  cannot   be


gainsaid.





                                                                                     21


31.     In  B.S.N.L   v.   Reliance   Communication   Ltd.,  (2011)   1   SCC


394, this court held as under:



           "53.  Lastly,   it   may   be   noted   that   liquidated

       damages   serve   the   useful   purpose   of   avoiding

       litigation   and   promoting   commercial   certainty   and,

       therefore,   the   court   should   not   be   astute   to

       categorise   as   penalties   the   clauses   described   as

       liquidated damages."




32.      This Court further stated in  Oil & Natural Gas Corporation


Ltd. v. SAW Pipes Ltd. (Supra):



           "64....This section is to be read with Section 74,

       which deals with penalty stipulated in the contract,

       inter   alia  (relevant   for   the   present   case)   provides

       that   when   a   contract   has   been   broken,   if   a   sum   is

       named   in   the   contract   as  the   amount   to   be   paid   in

       case of such breach, the party complaining of breach

       is   entitled,   whether   or   not   actual   loss   is   proved   to

       have been caused, thereby to receive from the party

       who   has   broken   the   contract   reasonable

       compensation   not   exceeding   the   amount   so   named.

       Section   74   emphasizes   that   in   case   of   breach   of

       contract,   the   party   complaining   of   the   breach   is

       entitled to receive reasonable compensation whether

       or not actual loss is proved to have been caused by

       such breach...."




33.    Thus, the case requires consideration in the light of the aforesaid


settled legal principles.



          Undoubtedly, the total construction was for Rs. 13.25 crores.  It



is evident from the Bid-documents filed by the private appellant that


the   work   was   to   be   executed   in   two   phases   and   the   relevant   part




                                                                                   22


          thereof reads as under:


                                            PHASE - I



Year           Const.       Supervision      Total         Interest @      Total           Upto   date

                            Charges   @                    20%             investment      investment
               Cost
                            10%                                            of Strs
                                             (in lacs)                                     (in lacs)
               (in lacs)


1998-99


6/98           75           7.5              82.50         4.12            86.62           86.62


9/98           80           8.0              88.00         8.52            92.52           183.14


12/98          80           8.0              88.00         12.92           100.92          284.06


3/99           80           8.0              88.00         17.32           105.32          389.32


Total          315          31.5             346.50        42.88           389.38          389.88





1999-2000


6/99           110          11.0            121           23.37           144.37          533.75


9/99           120          12.0            132.0         29.97           161.97          695.72


12/99          120          12.0            132.0         36.57           168.57          864.29


3/2000         125          12.50           137.50        43.44           180.94          1045.23


Total          475          47.50           522.50        133.35          655.85          1045.23


Grand          790          79.0            869.0         176.23          1045.23         1045.23

Total





                                       PHASE - II



2005-06


6/2005         150          15.0            165           8.25            173.25          173.25


9/2005         150          15.0            165           16.50           181.50          354.75


Total          300          30.0            330           24.75           354.75          354.75





                                                                                                        23


          The documents further reveal that phase II work was of worth


Rs.354.75   lacs   and   it   included   repairing,   maintenance   and   second


layer   of   bitumen   on   the   entire   road.     Admittedly,   this   part   of   the


contract had never been executed by the private appellant. More so,


the chart filed by the State of Rajasthan shows that the estimated cost


of   the   work   had   been   recovered   by   the   private   appellant   as   the


schedule   prepared  for   repayment   tally   with  the   amount   collected   by


the private appellant as toll fee within the stipulated period.



34.         In the first phase, the private appellant spent about Rs.10.45


crores and recovered the said amount with certain profit, though the


actual figure i.e. the toll fee recovered has not been disclosed. So far


as the second phase is concerned, admittedly, the amount of Rs.354.75


lacs has not been spent by the private appellant.   This issue has been


agitated   by   the   State   of   Rajasthan   before   this   Court   in   its   Counter


Affidavit wherein it is stated as under:


            "It is respectfully submitted that as per the terms of

            the Agreement, petitioner was required to complete

            the   project   in   two   phases.   In   the   first   phase

            investment of Rs.1045 lacs and after 5 years in the

            second phase Rs. 354.75 lacs was to be made by the

            petitioner.   However, the petitioner has not abided

            by the terms of the agreement and has not made any

            investment   for   the   second   phase   and,   therefore,   it

            has   breached   the   terms   of   the   contract   and,

            therefore,   it   is   respectfully   submitted   that   the

            contention   of   the   petitioner   that   he   is   entitled   to

            recover its investment, is erroneous and petitioner



                                                                                     24


           is   trying   to   give   wrong   picture   about   investment

           made and has not come to this Hon'ble Court with

           clean   hands   and,   therefore,   the   present   Special

           Leave   Petition   is   liable   to   be   dismissed   by   the

           Hon'ble Court. The concession period has come to

           an end."




35.      The aforesaid allegations have not been denied by the private


appellant   while   submitting   its   rejoinder.     Relevant   part   of   the


rejoinder affidavit reads:


             ".....the present contention as raised was not part

           of   the   arbitration   proceeding,   before   the   arbitral

           Tribunal.     It   is   further   submitted   that   this

           contention   was   never   raised   before   the   District

           Court  and  as  well  as  before  the Hon'ble  Court  of

           Rajasthan.     The   point   as   raised   is   subsequent   to

           completion of the project and work to be done after

           the period of 5 years...."




         Thus,  there  is no specific  denial  of the allegations/averments


taken by the State as required by the principle enshrined in Order VIII


Rule 5 of the Code of Civil Procedure, 1908.


36.      It is strange that a person who has not complied with terms of


contract   and   has   acted   in   contravention   of   the   terms   of   agreement


claims that he was entitled to earn more profit.   The private appellant


cannot be permitted to claim damages/compensation in respect of the


amount   of   Rs.13.25   crores,   as   he   did   not   spend   the   said   amount


stipulated in the terms of agreement.   Private appellant cannot claim





                                                                                 25


the amount of Rs. 7.13 crores for a period of three years for a small


patch   of   1.25   kilometres   out   of   the   total   length   of   the   road   to   the


extent of 10.85 kilometres.




37.           In   fact,   the   tribunal   has   dealt   with   the   issue   in   correct


perspective   only   to   the   extent   the   period   of   delay   by   which   the


notification   barring   the   heavy   vehicles   through   market   of  Bharatpur


had been issued stating as under:


                "The   traffic   survey   conducted   by   the   claimant

            on   17th,   18th  &   19th  April,   2000   has   not   been

            accepted by the respondent. The arbitral tribunal

            also feels   that this survey, which has been done

            by the claimant alone, cannot be relied upon for

            this purpose, because respondent is not a party to

            this survey. The claim lodged by claimant on its

            own survey as per para 12.3(iii) from 12/4/2000

            to 30/9/2000 is for Rs.31.18 lacs. In this regard

            tribunal   is   of   the   opinion   that   traffic   survey   of

            1997   as   per   agreement   in   which   both   parties

            bears consent of each other therefore can safely

            be relied upon for purpose of assessment of such

            losses to the claimant, because the occurrence of

            loss as such to the claimant has not been denied

            by respondent, which otherwise is an established

            fact as per documentary evidence on record. The

            tribunal   has   assessed   this   part   of   loss   on   the

            traffic   survey   of   1997   for   commercial   vehicles

            only   as   Rs.26.34   lacs   from   12/4/2000   to

            30/9/2000."




                     As   the   notification   had   been   issued,   and   it   was   not   the


responsibility   of   the   State   to   establish   a   police   chowki   etc.   to





                                                                                             26


implement the notification, there was no occasion for the tribunal to


proceed   further.     Therefore,   any   award   in   favour   of   the   private


appellant   in   that  respect   for   non-issuance   of  notification   beyond  the


date of the notification, cannot be held to be justified and the same is


liable to be set aside.




38.      The   State   authority   has   decided   to   establish   a   toll   road   as   it


was   not   having   sufficient   funds.     In   case   the   claim   of   the   private


appellant   is   allowed   and   as   the   State   is   not   in   a   position   to   grant


further   facility   to   collect   the   toll   fee   at   such   a   belated   stage,   the


purpose of establishing the toll road itself stands frustrated.  More so,


the toll fee cannot be collected to recover the amount never spent by


the contractor.  It is evident from the discourse in pre-bid meetings of


the     parties   that   it   had   been   decided   that   compensation   would   be


worked out  on the basis of investment made by concerned contractor.


More   so,   the   statutory   notification   dated   10.2.1997   provided   to


recover   the   cost   of   construction   and   maintenance   including   interest


thereon. Therefore, the question of non-execution of work of second


phase of the contract becomes very material and relevant to determine


the real controversy. The State authorities for the reasons best known


to them, did not make reference to the arbitration proceedings for non-


execution of the work of the second phase of the contract. However,




                                                                                         27


the   relief   claimed   by   the   private   appellant   would   prove   to   be   a


"windfall   profit"   without   carrying   out   the   obligation   to   execute   the


work just  on technicalities.  We have held in this very case,  that the


arbitrator   cannot   proceed   beyond   the   terms   of   reference   and,


therefore,   the   question   of   considering   the   non-execution   of   work   of


second  phase of the work was neither permissible  nor possible  as it


had   arisen   subsequent   to   the   date   of   award   in   the   arbitration


proceedings.


            Be that as it may, in order to do complete justice between the


parties   and   protect   the   public   exchequer,   we   feel   that   the   matter


requires adjudication and reconsideration on the following points by


the arbitration tribunal:


     i)         What   amount   could   have   been   recovered   by   the   private


                appellant   for   Bharatpur-Deeg   part   of   the   road   from   the


                vehicles using the road?


     ii)        What   could   be   the   effect   on   the   contract   as   a   whole   for


                non-executing the work of the second phase?




             In view of the fact that a long time has elapsed, we request the


learned tribunal to decide the case as early as possible after giving due


opportunity   to   the   parties   concerned.   The   private   appellant   shall   be


entitled only for a sum of Rs.26.34 lacs awarded by the tribunal for


delay in issuing the notification with 10% interest, if not paid already




                                                                                         28


or   it   could   be   adjusted   in   the   final   accounts   bills.     With   these


observation, the appeals stand disposed of.  No costs.


       



                                                                .............................J.

                                                  (P. SATHASIVAM)




                                                       

                                                .............................J.

                                                (Dr. B.S. CHAUHAN)

 New Delhi,

 July 21,   2011





                                                                                   29