whether an “award” delivered by an Emergency Arbitrator under the Arbitration Rules of the Singapore International Arbitration Centre [“SIAC Rules”] can be said to be an order under Section 17(1) of the Arbitration and Conciliation Act, 1996 [“Arbitration Act”]; and
second, as to whether an order passed under Section 17(2) of the Arbitration Act in enforcement of 1 the award of an Emergency Arbitrator by a learned Single Judge of the High Court is appealable.
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs. 4492-4493 OF 2021
AMAZON.COM NV INVESTMENT
HOLDINGS LLC … APPELLANT
VERSUS
FUTURE RETAIL LIMITED & ORS. … RESPONDENTS
WITH
CIVIL APPEAL NOs. 4494-4495 OF 2021
CIVIL APPEAL NOs. 4496-4497 OF 2021
JUDGMENT
R.F. NARIMAN, J.
1. Two important questions arise in these appeals – first, as to whether
an “award” delivered by an Emergency Arbitrator under the Arbitration
Rules of the Singapore International Arbitration Centre [“SIAC Rules”] can
be said to be an order under Section 17(1) of the Arbitration and
Conciliation Act, 1996 [“Arbitration Act”]; and second, as to whether an
order passed under Section 17(2) of the Arbitration Act in enforcement of
1
the award of an Emergency Arbitrator by a learned Single Judge of the
High Court is appealable.
2. The brief facts necessary to appreciate the context in which these two
questions arise are as follows:
2.1. Proceedings were initiated by the Appellant, Amazon.com NV
Investment Holdings LLC [“Amazon”] before the High Court of Delhi under
Section 17(2) of the Arbitration Act to enforce the award/order dated 25th
October, 2020 of an Emergency Arbitrator, Mr. V.K. Rajah, SC. This order
was passed in arbitration proceedings being SIAC Arbitration No. 960 of
2020 commenced by Amazon against Respondents No. 1 to 13, who are
described as under:
(i) Respondent No.1 – Future Retail Limited, India’s second-largest
offline retailer [“FRL”]
(ii) Respondent No.2 – Future Coupons Pvt. Ltd., a company that holds
9.82% shareholding in FRL and is controlled and majority-owned by
Respondents No. 3 to 11 [“FCPL”]
(iii) Respondent No.3 – Mr. Kishore Biyani, Executive Chairman and
Group CEO of FRL
(iv) Respondent No.8 – Mr. Rakesh Biyani, Managing Director of FRL
(v) Respondents No. 4 to 7 and 9 to 11 – other members of the Biyani
family, namely, Ms. Ashni Kishore Biyani, Mr. Anil Biyani, Mr.
Gopikishan Biyani, Mr. Laxminarayan Biyani, Mr. Sunil Biyani, Mr.
Vijay Biyani, and Mr. Vivek Biyani, who are promoters and
shareholders of FRL
(vi) Respondents No. 12 and 13 – Future Corporate Resources Pvt. Ltd.
and Akar Estate and Finance Pvt. Ltd., group companies of FRL
2
Respondents No. 1 to 13 are hereinafter collectively referred to as the
“Biyani Group”.
2.2. The seat of the arbitral proceedings is New Delhi, and as per the
arbitration clause agreed upon by the parties, SIAC Rules apply.
2.3. Three agreements were entered into between the parties. A
Shareholders’ Agreement dated 12th August, 2019, was entered into
amongst the Biyani Group, i.e., Respondents No. 1 to 13 [“FRL
Shareholders’ Agreement”]. Under this Shareholders’ Agreement, FCPL
was accorded negative, protective, special, and material rights with regard
to FRL including, in particular, FRL’s retail stores [“retail assets”]. The
rights granted to FCPL under this Shareholders’ Agreement were to be
exercised for Amazon’s benefit and thus were mirrored in a Shareholders’
Agreement dated 22nd August, 2019 entered into between Amazon, FCPL,
and Respondents No. 3 to 13 [“FCPL Shareholders’ Agreement”].
Amazon agreed to invest a sum of Rs.1431 crore in FCPL based on the
rights granted to FCPL under the FRL Shareholders’ Agreement and the
FCPL Shareholders’ Agreement. This investment was recorded in the
Share Subscription Agreement dated 22nd August, 2019 entered into
between Amazon, FCPL, and Respondents No. 3 to 13 [“Share
3
Subscription Agreement”]. It was expressly stipulated that this investment
in FCPL would “flow down” to FRL. It appears that the basic understanding
between the parties was that Amazon’s investment in the retail assets of
FRL would continue to vest in FRL, as a result of which FRL could not
transfer its retail assets without FCPL’s consent which, in turn, could not be
granted unless Amazon had provided its consent. Also, FRL was prohibited
from encumbering/transferring/selling/divesting/disposing of its retail assets
to “restricted persons”, being prohibited entities, with whom FRL, FCPL,
and the Biyanis could not deal. A list of such restricted persons was then
set out in Schedule III of the FCPL Shareholders’ Agreement and also
under the FRL Shareholders’ Agreement vide letter dated 19th December,
2019. There is no doubt that the Mukesh Dhirubhai Ambani group
(Reliance Industries group) is a “restricted person” under both these
Shareholders’ Agreements.
2.4. On 26th December, 2019, Amazon invested the aforesaid sum of
Rs.1431 crore in FCPL which “flowed down” to FRL on the very same day.
The bone of contention between the parties is that within a few months
from the date of this investment, i.e., on 29th August, 2020, Respondents
No. 1 to 13 entered into a transaction with the Mukesh Dhirubhai Ambani
group which envisages the amalgamation of FRL with the Mukesh
4
Dhirubhai Ambani group, the consequential cessation of FRL as an entity,
and the complete disposal of its retail assets in favour of the said group.
2.5. Amazon initiated arbitration proceedings and filed an application on
5
th October, 2020 seeking emergency interim relief under the SIAC Rules,
asking for injunctions against the aforesaid transaction. Mr. V.K. Rajah, SC
was appointed as the Emergency Arbitrator and heard detailed oral
submissions from all parties and then passed an “interim award” dated 25th
October, 2020, in which the learned Arbitrator issued the following
injunctions/directions:
“B. Dispositive Orders/Directions
285. In the result, I award, direct, and order as follows:
(a) the Respondents are injuncted from taking any steps in
furtherance or in aid of the Board Resolution made by the
Board of Directors of FRL on 29 August 2020 in relation to the
Disputed Transaction, including but not limited to filing or
pursuing any application before any person, including
regulatory bodies or agencies in India, or requesting for
approval at any company meeting;
(b) the Respondents are injuncted from taking any steps to
complete the Disputed Transaction with entities that are part of
the MDA Group;
(c) without prejudice to the rights of any current Promoter
Lenders, the Respondents are injuncted from directly or
indirectly taking any steps to transfer/ dispose/ alienate/
encumber FRL’s Retail Assets or the shares held in FRL by the
Promoters in any manner without the prior written consent of
the Claimant;
(d) the Respondents are injuncted from issuing securities of
FRL or obtaining/securing any financing, directly or indirectly,
5
from any Restricted Person that will be in any manner contrary
to Section 13.3.1 of the FCPL SHA;
(e) the orders in (a) to (d) above are to take effect immediately
and will remain in place until further order from the Tribunal,
when constituted; and
(f) the Claimant is to provide within 7 days from the date hereof
a cross-undertaking in damages to the Respondents. If the
Parties are unable to agree on its terms, they are to refer their
differences to me qua EA for resolution; and
(g) the costs of this Application be part of the costs of this
Arbitration.”
2.6. The Biyani Group thereafter went ahead with the impugned
transaction, describing the award as a nullity and the Emergency Arbitrator
as coram non judice in order to press forward for permissions before
statutory authorities/regulatory bodies. FRL, consistent with this stand, did
not challenge the Emergency Arbitrator’s award under Section 37 of the
Arbitration Act, but instead chose to file a civil suit before the Delhi High
Court being C.S. No. 493 of 2020, in which it sought to interdict the
arbitration proceedings and asked for interim relief to restrain Amazon from
writing to statutory authorities by relying on the Emergency Arbitrator’s
order, calling it a “tortious interference” with its civil rights. A learned Single
Judge of the Delhi High Court, after finding a prima facie case of tortious
interference, then refused to grant any interim injunction as follows:
“12.3 Thus the trinity of the principles for grant of interim
injunction i.e., prima facie case, irreparable loss and balance of
6
convenience are required to be tested in terms of principles as
noted above. Since this Court has held that prima facie the
representation of Amazon based on the plea that the resolution
dated 29th August, 2020 of FRL is void and that on conflation of
the FCPL SHA and FRL SHA, the ‘control’ that is sought to be
asserted by Amazon on FRL is not permitted under the FEMA
FDI Rules, without the governmental approvals, this Court finds
that FRL has made out a prima facie case in its favour for grant
of interim injunction. However, the main tests in the present
case are in respect of “balance of convenience” and
“irreparable loss”. Even if a prima facie case is made out by
FRL, the balance of convenience lies both in favour of FRL and
Amazon. If the case of FRL is that the representation by
Amazon to the statutory authorities /regulators is based on
illegal premise, Amazon has also based its representation on
the alleged breach of FCPL SHA and FRL SHA, as also the
directions in the EA order. Hence it cannot be said that the
balance of convenience lies in favour of FRL and not in favour
of Amazon. It would be a matter of trial after parties have led
their evidence or if decided by any other competent forum to
determine whether the representation of Amazon that the
transaction between FRL and Reliance being in breach of the
FCPL SHA and FRL SHA would outweigh the plea of FRL in the
present suit. Further in case Amazon is not permitted to
represent its case before the statutory authorities/Regulators, it
will suffer an irreparable loss as Amazon also claims to have
created pre-emptive rights in its favour in case the Indian law
permitted in future. Further there may not be irreparable loss to
FRL for the reason even if Amazon makes a representation
based on incorrect facts thereby using unlawful means, it will be
for the statutory authorities/Regulators to apply their mind to the
facts and legal issues therein and come to the right conclusion.
There is yet another aspect as to why no interim injunction can
be granted in the present application for the reason both FRL
and Amazon have already made their representations and
counter representations to the statutory authorities/regulators
and now it is for the Statutory Authorities/Regulators to take a
decision thereon.
7
Therefore, this Court finds that no case for grant of interim
injunction is made out in favour of the FRL and against
Amazon.
Conclusion
13. Consequently, the present application is disposed of,
declining the grant of interim injunction as prayed for by FRL,
however, the Statutory Authorities/Regulators are directed to
take the decision on the applications/objections in accordance
with the law.”
No appeal against this order has been filed by the Biyani Group. On the
other hand, Amazon has filed an appeal against certain observations made
in the order. This appeal is pending.
2.7. Meanwhile, Amazon went ahead with an application filed under
Section 17(2) of the Arbitration Act which was heard and disposed of by a
learned Single Judge of the Delhi High Court. On 2nd February, 2021, the
learned Single Judge passed a status-quo order in which he restrained the
Biyani Group from going ahead with the impugned transaction, stating that
reasons and a detailed order will follow. An appeal against this was filed by
FRL, in which a Division Bench, vide order dated 8th February, 2021, after
setting out the facts of this case and after reaching certain prima facie
findings, stayed the operation, implementation, and execution of the Single
Judge order dated 2nd February, 2021 till the next date of hearing, and listed
the appeal for further hearing on 26th February, 2021. Meanwhile, on 22nd
8
February, 2021, the Supreme Court allowed the amalgamation proceedings
pending before the National Company Law Tribunal to continue, but not to
culminate in any final order of sanction of scheme of amalgamation.
2.8. On 18th March, 2020, the learned Single Judge passed a detailed
judgment giving reasons for an order made under Section 17(2) read with
Order XXXIX, Rule 2-A of the Code of Civil Procedure, 1908 [“Code of
Civil Procedure”] in which it was held that an Emergency Arbitrator’s
award is an order under Section 17(1) of the Arbitration Act. Since
breaches of the Agreements aforementioned were admitted, the only plea
being raised being that the Emergency Arbitrator’s award was a nullity, the
learned Single Judge held that such award was enforceable as an order
under the Arbitration Act, and further held that the injunctions/directions
granted by the said award were deliberately flouted by the Biyani Group.
He also found that any so-called violations of Foreign Exchange
Management Act, 1999 [“FEMA”] did not render the Emergency Arbitrator’s
award a nullity, and therefore, issued a show-cause notice under Order
XXXIX, Rule 2-A of the Code of Civil Procedure, after imposing Rs.20 lakh
as costs to be deposited with the Prime Minister Relief Fund for being used
for providing COVID vaccinations to the Below Poverty Line category of
senior citizens of Delhi. The learned Single Judge then directed as follows:
9
“Conclusion
188. The Emergency Arbitrator is an Arbitrator for all intents and
purposes; order of the Emergency Arbitrator is an order under
Section 17(1) and enforceable as an order of this Court under
Section 17(2) of the Arbitration and Conciliation Act.
189. Respondent No.2 is a proper party to the arbitration
proceedings and the Emergency Arbitrator has rightly invoked
the Group of Companies doctrine by applying the well settled
principles laid down by the Supreme Court in Chloro Controls
(supra), Cheran Properties (supra) and MTNL (supra). The
respondents have raised a plea contrary to the well settled law
relating to Group of Companies doctrine laid down by the
Supreme Court.
190. The respondents have raised a vague plea of Nullity
without substantiating the same. The interim order of the
Emergency Arbitrator is not a Nullity as alleged by respondent
No.2.
191. Combining/treating all the agreements as a single
integrated transaction does not amount to control of the
petitioner over FRL and therefore, the petitioner’s investment
does not violate any law.
192. All the objections raised by the respondents are hereby
rejected with cost of Rs.20,00,000/- to be deposited by the
respondents with the Prime Minister Relief Fund for being used
for providing COVID vaccination to the Below Poverty Line
(BPL) category - senior citizens of Delhi. The cost be deposited
within a period of two weeks and the receipt be placed on
record within one week of the deposit.
193. The respondents have deliberately and wilfully violated the
interim order dated 25th October, 2020 and are liable for the
consequences enumerated in Order XXXIX Rule 2-A of the
Code of Civil Procedure.
194. In exercise of power under Order XXXIX Rule 2-A(1) of the
Code of Civil Procedure, the assets of respondents No.1 to 13
are hereby attached. Respondents No.1 to 13 are directed to
file an affidavit of their assets as on today in Form 16A,
Appendix E under Order XXI Rule 41(2) of the Code of Civil
Procedure within 30 days. Respondent No.1, 2, 12 and 13 are
10
directed to file an additional affidavit in the format of Annexure
B-1 and respondents No.3 to 11 are directed to file an
additional affidavit in the format of Annexure A-1 to the
judgment of M/s Bhandari Engineers & Builders Pvt. Ltd. v. M/s
Maharia Raj Joint Venture, (supra) along with the documents
mentioned therein within 30 days.
195. Show cause notice is hereby issued to respondents No.3
to 13 to show cause why they be not detained in civil prison for
a term not exceeding three months under Order XXXIX Rule 2-
A(1) of the Code of Civil Procedure for violation of the order
dated 25th October, 2020. Reply to the show cause notice be
filed within two weeks. Rejoinder within two weeks thereafter.
196. The respondents are directed not to take any further action
in violation of the interim order dated 25th October, 2020. The
respondents are further directed to approach all the competent
authorities for recall of the orders passed on their applications
in violation of the interim order dated 25th October, 2020 within
two weeks. The respondents are directed to file an affidavit to
place on record the actions taken by them after 25th October,
2020 and the present status of all those actions at least three
days before the next date of hearing.
197. Respondents No.3 to 11 shall remain present before this
Court on the next date of hearing.”
He listed the matter for further directions on 28th April, 2021.
2.9. Against this detailed judgment, FAO No. 51 of 2021 was filed by FRL.
By the second impugned judgment in this case dated 22nd March, 2021, a
Division Bench of the Delhi High Court referred to its earlier order dated 8th
February, 2021 and stayed the learned Single Judge’s detailed judgment
and order for the same reasons given by the earlier order till the next date
of hearing, which was 30th April, 2021. Against the said order, Special
11
Leave Petitions were filed before this Court, and this Court by its order
dated 19th April, 2021 stayed further proceedings before the learned Single
Judge as well as the Division Bench of the Delhi High Court, and set the
matter down for final disposal before this Court.
3. Mr. Gopal Subramanium, learned Senior Advocate appearing on
behalf of Amazon, took us through the record with painstaking detail. He
castigated the impugned orders of the Division Bench as suffering from a
complete non-application of mind in that the order dated 8th February, 2021
referred to three agreements, the third being between FRL and Reliance
Retail Ltd., which is an error apparent on the face of the record. Secondly, it
went on to observe that in the aforesaid agreement, Amazon is not a party.
It then went on to hold that an appeal against an order under Section 17(2)
of the Arbitration Act would be maintainable under the provisions of the
Code of Civil Procedure on the basis of the reasoning contained in a Delhi
High Court judgment in South Delhi Municipal Corporation v. Tech
Mahindra, (2019) SCC Online Delhi 11863, relying upon paragraphs 8 to
11 thereof. Mr. Subramanium argued that had the learned Division Bench
bothered to refer to paragraphs 12 and 13 of the aforesaid judgment, it
would be clear that this authority would be an authority for exactly the
opposite proposition, thereby rendering an appeal under Order XLIII, Rule
12
1(r) of the Code of Civil Procedure non-maintainable when it is read with
Section 37 of the Arbitration Act. Further observations that prima facie, the
agreements are between different parties, and therefore, the group-ofcompanies doctrine cannot be invoked, without any reasoning, again
betrays a complete non-application of mind. Since the second impugned
order of the Division Bench relies upon this very order to stay even the
detailed judgment of the Single Judge, the learned senior counsel argued
that the second order, being a reiteration of the first, suffers from the same
malady.
3.1. Mr. Subramanium then referred us to Sections 2(1)(a), 2(1)(c), 2(1)
(d), 2(6), 2(8) and 19(2) to argue that the Arbitration Act reflects the
grundnorm of arbitration as being party autonomy, which is respected by
these provisions and delineated in several judgments of this Court. He then
referred to Section 37, pointing out that an appeal under Section 37(2)(b) is
restricted to granting or refusing to grant an interim measure under Section
17, which would refer to Section 17(1) and not Section 17(2). He went on to
argue that the Arbitration Act is a complete code in itself and if an appeal
does not fall within the four corners of Section 37, then it is incompetent, as
has been held by several judgments of this Court.
13
3.2. He also referred to various judgments of this Court, arguing that an
Emergency Arbitrator’s award can never be characterised as a nullity and
ignored, and cited a number of judgments to show that until the said award
is set aside, it must be obeyed. He also referred to the important fact that
the award must be taken as it stands as no appeal was made therefrom by
the Biyani Group and that, therefore, it was not permissible to go behind
the award.
3.3. He also cited judgments to show that non-signatories to arbitration
agreements would nevertheless be bound thereby and on facts, it was
admitted that the “Ultimate Controlling Person” behind the entire
transaction was Mr. Kishore Biyani, who was defined as such under the
three Agreements.
3.4. He also argued that, as has been held in the judgments of this Court,
the FEMA is wholly unlike the Foreign Exchange Regulation Act, 1973
[“FERA”] and does not contain any provision nullifying an agreement, even
assuming that there was a breach thereof.
4. Mr. Aspi Chinoy, learned Senior Advocate also appearing on behalf of
Amazon, took us through various parts of the Emergency Arbitrator’s award
and argued that no equity can possibly be found in favour of the Biyani
14
Group as the breach of the Emergency Arbitrator’s award had been
admitted by them. Thus, they have come to the Court with a dishonest and
immoral case and if this is appreciated, it will be clear that on facts, after
openly flouting the Emergency Arbitrator’s award, they would have no case
on merits to resist the directions issued by the learned Single Judge under
Section 17(2) of the Arbitration Act. Even otherwise, he referred to Section
17(2) and argued that enforcement orders were made under the Arbitration
Act and not under the Code of Civil Procedure, as a result of which the
appeal filed under Order XLIII, Rule 1(r) would not be maintainable. Mr.
Chinoy also referred to a Division Bench judgment of the Bombay High
Court in Kakade Construction Co. Ltd. v. Vistra ITCL, 2019 SCC OnLine
Bom 1521 : (2019) 6 Bom CR 805 [“Kakade Construction”] to buttress his
submission.
5. Mr. Ranjit Kumar, learned Senior Advocate appearing on behalf of
Amazon, referred to Sections 9 and 17 of the Arbitration Act and the
Arbitration and Conciliation (Amendment) Act, 2015 [“2015 Amendment
Act”] which brought Section 17 into line with Section 9. He then referred to
Section 9(3) to argue that the legislative intent is to obtain interim orders
from an arbitral tribunal then constituted so as to decongest courts and free
them from the burdens of Section 9 petitions being filed before them. If this
15
is appreciated, then it would be clear that an Emergency Arbitrator’s award
would be a step in the right direction under institutional rules, furthering this
very objective. He also pointed out that by the very same amendment, a
non-obstante clause was added to Section 37(1), thereby making it
abundantly clear that unless an appeal falls within the four corners of
Section 37, the moment an order is passed under the Arbitration Act, no
other appeal could possibly be filed if it was outside the four corners of
Section 37.
6. Mr. Harish Salve, learned Senior Advocate appearing on behalf of
FRL, stated that he would not go to the extent of arguing that an
Emergency Arbitrator’s award would be outside the ken of the Arbitration
Act, but that it was sufficient for his purpose to argue that an Emergency
Arbitrator’s award cannot be said to fall under Section 17(1) of the Act. He
placed before us an extract of the 246th Law Commission Report, in which
the Law Commission advocated the amendment of Section 2 of the
Arbitration Act, to include within sub-section (1)(d) a provision for the
appointment of an Emergency Arbitrator. He said that despite this
suggestion being made, Parliament did not adopt the same when it
amended the Arbitration Act by the 2015 Amendment Act, thereby
indicating that such orders would not fall within Section 17(1) of the
16
Arbitration Act. He then took us through the definition sections in the
Arbitration Act and read out Sections 10 to 13, 16, 17, 21, 23, 27, 29A, and
30, in particular, to argue that an arbitral tribunal as defined by Section 2(1)
(d) of the Act can only mean a tribunal that is constituted between the
parties, which then decides the disputes between the parties finally and
cannot, given the scheme of the Act, include an Emergency Arbitrator who
is not an “arbitral tribunal” but a person who only decides, at best, an
interim dispute between the parties which never culminates in a final
award. He argued that Mr. Subramanium was trying to fit a square peg in a
round hole as the Arbitration Act only speaks of arbitral tribunals that are
constituted between the parties and that can finally decide the disputes
between the parties. As an example, if the tribunal rules on its own
jurisdiction and rejects a plea stating it has no jurisdiction, it must only
continue with the arbitral proceedings and make a final arbitral award,
which can never be done by an Emergency Arbitrator. The scheme,
therefore, of the entirety of Part I of the Act, would show that an Emergency
Arbitrator is a foreigner to the Indian Arbitration Act and cannot fit within its
scheme unless an amendment is made by Parliament.
6.1. He further argued, pointing to section 25.2 of the arbitral agreement
contained in the FCPL Shareholders’ Agreement (which is mirrored in the
17
FRL Shareholders’ Agreement as section 15.2), that in any case, the
provisions of the SIAC Rules relating to an Emergency Arbitrator’s award,
which were agreed to between the parties, were subject to the provisions of
the Arbitration Act; and since the Arbitration Act did not provide for
Emergency Arbitrators, this part of the SIAC Rules would not apply, making
it clear that an Emergency Arbitrator’s award cannot fall within Section
17(1) of the Act. He also argued that the scheme of Section 17(1) made it
clear that a party may, during arbitral proceedings, apply to the arbitral
tribunal. Even under the SIAC Rules, an Emergency Arbitrator is appointed
before the arbitral tribunal is constituted, as is clear from Rule 30 read with
Schedule 1. This being the case, an Emergency Arbitrator, not being
appointed during arbitral proceedings, falls outside Section 17(1).
6.2. He also contrasted the Arbitration Act with provisions contained in the
Singapore, New Zealand, Hong Kong, and English statutes which made it
clear that under those statutes, an Emergency Arbitrator’s awards were
expressly included and could thus be enforced under their provisions.
6.3. Mr. Salve made it clear that the appeal that was filed in the present
case was not under Section 37 of the Arbitration Act but was under Order
XLIII, Rule 1(r) of the Code of Civil Procedure. He then read Section 9
18
together with Section 37 of the Arbitration Act to stress that orders may be
made under Section 9 until enforcement of an award in accordance with
Section 36, and then read Section 36 to make it clear that the contours of
Section 37 did not go beyond orders and awards made under the
Arbitration Act. Since orders made in enforcement proceedings are not
under the Arbitration Act but only under the Code of Civil Procedure,
therefore, in enforcement proceedings – both under Section 17(2) and
under Section 36(1) – appeals can be filed from such orders under the
Code of Civil Procedure. He stressed upon the language of Section 36(1),
which made it clear that when a final award is made, it shall be enforced in
accordance with the provisions of the Code of Civil Procedure in the same
manner as if it were a decree of the court, thereby arguing that by a legal
fiction, an award is deemed to be a decree for the purposes of
enforcement, which would include all purposes, including appeals from
orders passed in enforcement proceedings. He also stressed upon the
language of Section 17(2) to indicate that an order passed under Section
17(1) is deemed to be an order of the court for all purposes and shall be
enforceable under the Code of Civil Procedure in the same manner as if it
were an order of the court, making it clear that enforcement is not under the
Arbitration Act but only under the Code of Civil Procedure. He stressed the
19
fact that the order of the learned Single Judge also made it abundantly
clear that he was exercising powers only under Order XXXIX, Rule 2-A of
the Code of Civil Procedure and not under the Arbitration Act. He then
pointed out that there would be various anomalies which cannot be
addressed if we were to accept the construction suggested by Mr.
Subramanium. As is well known, third-party objectors may object to an
order under Section 17(2) or an award. If their rights are affected, it cannot
be that they would have no right of appeal, as a perverse order against
their interests would certainly be appealable. He also pointed out that, as of
today, the application for modification/setting aside of the Emergency
Arbitrator’s award had been argued before a regularly constituted arbitral
tribunal, which would issue its order either agreeing with or rejecting the
Emergency Arbitrator’s award, from which either his clients or Mr.
Subramanium’s clients would file appeals, depending upon the orders so
passed. He referred to a number of judgments to buttress his submissions.
7. Mr. K.V. Viswanathan, learned Senior Advocate also appearing on
behalf of FRL, argued that four rules of interpretation of statutes in this
case would necessarily require us to allow these appeals in favour of the
Respondents. First, he argued that the words “as if” contained in Section
17(2) of the Act contain a legal fiction which, when taken to its logical
20
conclusion, would necessarily mean that enforcement proceedings would
be outside the pale of the Arbitration Act and within the confines of the
Code of Civil Procedure. Further, he argued that the use of the expression
“under the Code of Civil Procedure” in Section 17(2) is legislation by
reference and not by incorporation, leading to the conclusion that it is the
Code of Civil Procedure alone under which enforcement takes place. He
then reiterated that the expression “due regard” contained in Section 36(3)
is fundamentally different from the expression “under the Code of Civil
Procedure”, and that Section 36(1) and Section 17(2) are pari materia
provisions, distinct from Section 36(3), under which a stay of an award may
be granted under the Arbitration Act with “due regard to the Code of Civil
Procedure”. He then added that when different words are used in different
provisions, they are meant to be differentiated. He also cited judgments to
buttress each one of these submissions. He then went on to discuss
various High Court judgments which show that, in practice, appeals that are
filed against orders and awards sought to be enforced are filed under the
Code of Civil Procedure and not under the Arbitration Act.
7.1. He then referred to Section 17(1) and, in particular, to the expression
“and the arbitral tribunal shall have the same power for making orders, as
the court has for the purpose of, and in relation to, any proceedings before
21
it” and argued that the expression “in relation to” refers only to incidental
powers given to the tribunal and not to powers of enforcement. He also
argued that the expression “arbitral tribunal” in Section 17(1) is to be read
as defined by Section 2(1)(d), there being nothing in the context of Section
17(1) to the contrary which would obviate the application of Section 2(1)(d)
in the context of Section 17(1). He then referred to the arbitration clause
between the parties to argue that the parties contemplated, by virtue of
section 25.2 of the FCPL Shareholders’ Agreement, that only civil courts
could pass interim orders until the arbitral tribunal is properly constituted by
the parties. He then referred to a recent judgment of this Court, namely
National Highways Authority of India v. M. Hakeem, 2021 SCC OnLine
SC 473 [“NHAI”], arguing that Section 17 was like Section 34(1) of the
Arbitration Act in that nothing could be read into Section 17 so as to
incorporate awards made by an Emergency Arbitrator.
7.2. He then argued that on a reading of Schedule 1 of the SIAC Rules,
an Emergency Arbitrator cannot be said to be like an arbitral tribunal in that,
under Rule 3, the President of the SIAC must first accept as to whether or
not an Emergency Arbitrator be appointed at all. Also, under Rule 9, an
administrative authority alone is given the power to extend time in the
circumstances mentioned in the Rule, and under Rule 10, an Emergency
22
Arbitrator has no power to act after the arbitral tribunal is constituted, the
tribunal not being bound by any reasons given by the Emergency Arbitrator.
From this, he argued that an Emergency Arbitrator does not fit within the
Arbitration Act as such arbitrator is not an independent quasi-judicial body
under the Rules.
7.3. He then referred to certain judgments and authorities for the
proposition that a proper reading of Exception 1 to Section 28 of the Indian
Contract Act, 1872 would show that the civil court’s jurisdiction is ousted
and that only what is expressly provided for by the ouster provisions can be
given effect to as nothing can be implied therein. He then argued that the
learned Single Judge was in a great hurry to decide the case and did not
even give sufficient time to the Respondents to file objections to the
enforcement application, though he did concede that notes of written
arguments, including the objection as to an award by an Emergency
Arbitrator being a nullity, were raised before the learned Single Judge. He
also cited various judgments to show that this was a case in which the
Emergency Arbitrator lacked inherent jurisdiction, as a result of which his
clients were justified in ignoring the award passed by the Emergency
Arbitrator.
23
8. Mr. Vikram Nankani, learned Senior Advocate appearing on behalf of
Respondents No. 1 to 12 in Civil Appeal Nos. 4496-4497 of 2021 and
Respondents No. 2 to 13 in Civil Appeal Nos. 4494-4495 of 2021, was at
pains to point out that in the enforcement application, on the facts of this
case, it was specifically pleaded that the High Court was being approached
as a civil court, and that the application was filed only under Order XXXIX,
Rule 2-A. He also cited judgments to show that the provisions of Order
XXXIX, Rule 2-A, being punitive in nature and requiring a heightened
standard of wilful disobedience to be applied cannot be applied routinely or
in the cavalier manner in which the learned Single Judge has applied the
said provision. He also referred to the fact that only the SIAC Rules
pertaining to “arbitration” stricto sensu were agreed to between the parties,
which would exclude rules relating to awards by an Emergency Arbitrator.
He then distinguished the judgment in Kakade Construction (supra) relied
upon by Mr. Chinoy and the judgment in Jet Airways (India) Ltd. v.
Subrata Roy Sahara, 2011 SCC OnLine Bom 1379 : 2012 (2) AIR Bom
855 [“Jet Airways”], stating that they applied only to Section 36 of the Act
and are not authorities qua Section 17, which is the subject matter of
argument in the facts of the present case.
24
9. Having heard learned counsel for the parties, the first question to be
determined by this Court is whether an Emergency Arbitrator’s award can
be said to be within the contemplation of the Arbitration Act, and whether it
can further be said to be an order under Section 17(1) of the Act.
10. The relevant provisions of the Arbitration Act, so far as this contention
is concerned, are as follows:
“2. Definitions.—(1) In this Part, unless the context otherwise
requires,—
(a) “arbitration” means any arbitration whether or not
administered by permanent arbitral institution;
* * *
(c) “arbitral award” includes an interim award;
(d) “arbitral tribunal” means a sole arbitrator or a
panel of arbitrators;”
* * *
(6) Construction of references.—Where this Part, except
Section 28, leaves the parties free to determine a certain issue,
that freedom shall include the right of the parties to authorise
any person including an institution, to determine that issue.”
* * *
(8) Where this Part—
(a) refers to the fact that the parties have agreed or
that they may agree, or
(b) in any other way refers to an agreement of the
parties, that agreement shall include any
arbitration rules referred to in that agreement.”
“19. Determination of rules of procedure.—
* * *
25
(2) Subject to this Part, the parties are free to agree on the
procedure to be followed by the arbitral tribunal in conducting
its proceedings.”
“21. Commencement of arbitral proceedings.—Unless
otherwise agreed by the parties, the arbitral proceedings in
respect of a particular dispute commence on the date on which
a request for that dispute to be referred to arbitration is received
by the respondent.”
11. A reading of these provisions would show that an arbitration
proceeding can be administered by a permanent arbitral institution.
Importantly, Section 2(6) makes it clear that parties are free to authorise
any person including an institution to determine issues that arise between
the parties. Also, under Section 2(8), party autonomy goes to the extent of
an agreement which includes being governed by arbitration rules referred
to in the aforesaid agreements. Likewise, under Section 19(2), parties are
free to agree on the procedure to be followed by an arbitral tribunal in
conducting its proceedings.
12. Section 21 provides that arbitral proceedings in respect of a particular
dispute commence on the date on which a request for that dispute to be
referred to arbitration is received by the respondent. This Section is
expressly subject to agreement by the parties. Rule 3.3 of the SIAC Rules
reads as follows:
26
“Rule 3: Notice of Arbitration
* * *
3.3 The date of receipt of the complete Notice of Arbitration
by the Registrar shall be deemed to be the date of
commencement of the arbitration. For the avoidance of doubt,
the Notice of Arbitration is deemed to be complete when all the
requirements of Rule 3.1 and Rule 6.1(b) (if applicable) are
fulfilled or when the Registrar determines that there has been
substantial compliance with such requirements. SIAC shall
notify the parties of the commencement of the arbitration.”
By agreeing to the application of the SIAC Rules, the arbitral proceedings
in the present case can be said to have commenced from the date of
receipt of a complete notice of arbitration by the Registrar of the SIAC,
which would indicate that arbitral proceedings under the SIAC Rules
commence much before the constitution of an arbitral tribunal under the
said Rules. This being the case, when Section 17(1) uses the expression
“during the arbitral proceedings”, the said expression would be elastic
enough, when read with the provisions of Section 21 of the Act, to include
emergency arbitration proceedings, which only commence after receipt of
notice of arbitration by the Registrar under Rule 3.3 of the SIAC Rules as
aforesaid.
13. A conjoint reading of these provisions coupled with there being no
interdict, either express or by necessary implication, against an Emergency
27
Arbitrator would show that an Emergency Arbitrator’s orders, if provided for
under institutional rules, would be covered by the Arbitration Act.
14. As a matter of fact, a number of judgments of this Court have referred
to the importance of party autonomy as being one of the pillars of
arbitration in the Arbitration Act. Thus, in Antrix Corporation Ltd. v. Devas
Multimedia Pvt. Ltd., (2014) 11 SCC 560, this Court held as follows:
“35. In view of the language of Article 20 of the arbitration
agreement which provided that the arbitration proceedings
would be held in accordance with the rules and procedures of
the International Chamber of Commerce or UNCITRAL, Devas
was entitled to invoke the Rules of Arbitration of ICC for the
conduct of the arbitration proceedings. Article 19 of the
agreement provided that the rights and responsibilities of the
parties thereunder would be subject to and construed in
accordance with the laws of India. There is, therefore, a clear
distinction between the law which was to operate as the
governing law of the agreement and the law which was to
govern the arbitration proceedings. Once the provisions of the
ICC Rules of Arbitration had been invoked by Devas, the
proceedings initiated thereunder could not be interfered with in
a proceeding under Section 11 of the 1996 Act. The invocation
of the ICC Rules would, of course, be subject to challenge in
appropriate proceedings but not by way of an application under
Section 11(6) of the 1996 Act. Where the parties had agreed
that the procedure for the arbitration would be governed by the
ICC Rules, the same would necessarily include the
appointment of an Arbitral Tribunal in terms of the arbitration
agreement and the said Rules. Arbitration Petition No. 20 of
2011 under Section 11(6) of the 1996 Act for the appointment of
an arbitrator must, therefore, fail and is rejected, but this will not
prevent the petitioner from taking recourse to other provisions
of the aforesaid Act for appropriate relief.”
28
Similarly, in Bharat Aluminium Co. v. Kaiser Aluminium Technical
Services Inc., (2016) 4 SCC 126 [“Balco”], this Court stated thus:
“5. Party autonomy being the brooding and guiding spirit in
arbitration, the parties are free to agree on application of three
different laws governing their entire contract — (1) proper law of
contract, (2) proper law of arbitration agreement, and (3) proper
law of the conduct of arbitration, which is popularly and in legal
parlance known as “curial law”. The interplay and application of
these different laws to an arbitration has been succinctly
explained by this Court in Sumitomo Heavy Industries Ltd. v.
ONGC Ltd. [Sumitomo Heavy Industries Ltd. v. ONGC Ltd.,
(1998) 1 SCC 305], which is one of the earliest decisions in that
direction and which has been consistently followed in all the
subsequent decisions including the recent Reliance Industries
Ltd. v. Union of India [Reliance Industries Ltd. v. Union of India,
(2014) 7 SCC 603 : (2014) 3 SCC (Civ) 737].”
* * *
“10. In the matter of interpretation, the court has to make
different approaches depending upon the instrument falling for
interpretation. Legislative drafting is made by experts and is
subjected to scrutiny at different stages before it takes final
shape of an Act, Rule or Regulation. There is another category
of drafting by lawmen or document writers who are
professionally qualified and experienced in the field like drafting
deeds, treaties, settlements in court, etc. And then there is the
third category of documents made by laymen who have no
knowledge of law or expertise in the field. The legal quality or
perfection of the document is comparatively low in the third
category, high in second and higher in first. No doubt, in the
process of interpretation in the first category, the courts do
make an attempt to gather the purpose of the legislation, its
context and text. In the second category also, the text as well
as the purpose is certainly important, and in the third category
of documents like wills, it is simply intention alone of the
executor that is relevant. In the case before us, being a contract
executed between the two parties, the court cannot adopt an
approach for interpreting a statute. The terms of the contract
will have to be understood in the way the parties wanted and
29
intended them to be. In that context, particularly in agreements
of arbitration, where party autonomy is the grund norm, how the
parties worked out the agreement, is one of the indicators to
decipher the intention, apart from the plain or grammatical
meaning of the expressions and the use of the expressions at
the proper places in the agreement.”
The importance of party autonomy in arbitration and commercial contracts
was further delineated in the judgment of Centrotrade Minerals & Metal
Inc. v. Hindustan Copper Ltd., (2017) 2 SCC 228 [“Centrotrade”] as
follows:
“38. Party autonomy is virtually the backbone of arbitrations.
This Court has expressed this view in quite a few decisions. In
two significant passages in Balco [Bharat Aluminium Co. v.
Kaiser Aluminium Technical Services Inc., (2016) 4 SCC 126]
this Court dealt with party autonomy from the point of view of
the contracting parties and its importance in commercial
contracts. In para 5 of the Report, it was observed: (SCC p.
130)
“5. Party autonomy being the brooding and guiding
spirit in arbitration, the parties are free to agree on
application of three different laws governing their entire
contract— (1) proper law of contract, (2) proper law of
arbitration agreement, and (3) proper law of the conduct
of arbitration, which is popularly and in legal parlance
known as “curial law”. The interplay and application of
these different laws to an arbitration has been succinctly
explained by this Court in Sumitomo [Sumitomo Heavy
Industries Ltd. v. ONGC Ltd., (1998) 1 SCC 305] which is
one of the earliest decisions in that direction and which
has been consistently followed in all the subsequent
decisions including the recent Reliance Industries Ltd. v.
Union of India [Reliance Industries Ltd. v. Union of India,
(2014) 7 SCC 603 : (2014) 3 SCC (Civ) 737].”
(emphasis in original)
30
Later in para 10 of the Report, it was held: (SCC pp. 131-32)
“10. In the matter of interpretation, the court has to
make different approaches depending upon the
instrument falling for interpretation. Legislative drafting is
made by experts and is subjected to scrutiny at different
stages before it takes final shape of an Act, Rule or
Regulation. There is another category of drafting by
lawmen or document writers who are professionally
qualified and experienced in the field like drafting deeds,
treaties, settlements in court, etc. And then there is the
third category of documents made by laymen who have
no knowledge of law or expertise in the field. The legal
quality or perfection of the document is comparatively low
in the third category, high in second and higher in first. No
doubt, in the process of interpretation in the first category,
the courts do make an attempt to gather the purpose of
the legislation, its context and text. In the second category
also, the text as well as the purpose is certainly important,
and in the third category of documents like wills, it is
simply intention alone of the executor that is relevant. In
the case before us, being a contract executed between
the two parties, the court cannot adopt an approach for
interpreting a statute. The terms of the contract will have
to be understood in the way the parties wanted and
intended them to be. In that context, particularly in
agreements of arbitration, where party autonomy is the
grund norm, how the parties worked out the agreement, is
one of the indicators to decipher the intention, apart from
the plain or grammatical meaning of the expressions and
the use of the expressions at the proper places in the
agreement.”
(emphasis in original)
* * *
“42. Be that as it may, the legal position as we understand it is
that the parties to an arbitration agreement have the autonomy
to decide not only on the procedural law to be followed but also
the substantive law. The choice of jurisdiction is left to the
contracting parties. In the present case, the parties have
agreed on a two-tier arbitration system through Clause 14 of
31
the agreement and Clause 16 of the agreement provides for the
construction of the contract as a contract made in accordance
with the laws of India. We see nothing wrong in either of the two
clauses mutually agreed upon by the parties.”
* * *
“46. For the present we are concerned only with the
fundamental or public policy of India. Even assuming the broad
delineation of the fundamental policy of India as stated in
Associate Builders [Associate Builders v. DDA, (2015) 3 SCC
49 : (2015) 2 SCC (Civ) 204] we do not find anything
fundamentally objectionable in the parties preferring and
accepting the two-tier arbitration system. The parties to the
contract have not by-passed any mandatory provision of the
A&C Act and were aware, or at least ought to have been aware
that they could have agreed upon the finality of an award given
by the arbitration panel of the Indian Council of Arbitration in
accordance with the Rules of Arbitration of the Indian Council of
Arbitration. Yet they voluntarily and deliberately chose to agree
upon a second or appellate arbitration in London, UK in
accordance with the Rules of Conciliation and Arbitration of the
International Chamber of Commerce. There is nothing in the
A&C Act that prohibits the contracting parties from agreeing
upon a second instance or appellate arbitration — either
explicitly or implicitly. No such prohibition or mandate can be
read into the A&C Act except by an unreasonable and awkward
misconstruction and by straining its language to a vanishing
point. We are not concerned with the reason why the parties
(including HCL) agreed to a second instance arbitration — the
fact is that they did and are bound by the agreement entered
into by them. HCL cannot wriggle out of a solemn commitment
made by it voluntarily, deliberately and with eyes wide open.”
(emphasis supplied)
The principle of party autonomy, as delineated in Balco (supra) and
Centrotrade (supra), has recently been quoted with approval by this Court
32
in PASL Wind Solutions Pvt. Ltd. v. GE Power Conversion India Pvt.
Ltd., 2021 SCC OnLine SC 331 (see paragraphs 101 and 102).
15. A recent judgment in NHAI v. M. Hakeem (supra) dealt with certain
provisions of the National Highways Act, 1956, which laid down a scheme
of acquisition different from that contained in the Land Acquisition Act,
1984. As part of the said scheme, arbitral awards passed under the
National Highways Act were challengeable only under Section 34 of the
Arbitration Act. The question squarely raised before this Court was as to
whether, when a court was empowered to “set aside” awards under Section
34 of the Act, would this power include the power to modify an award.
16. In answering this question, this Court referred to Article 34 of the
UNCITRAL Model Law on International Commercial Arbitration, 1985
[“Model Law”], and came to the conclusion that given the fact that Section
34 is a verbatim reproduction of Article 34 of the Model Law, it would not
contain any power to modify an arbitral award. In this case, since the
parliamentary intention was crystal clear, and there was no play in the joints
to apply purposive or creative interpretation, this Court came to the
conclusion that only an amendment of the Arbitration Act could set right the
position as otherwise, the Court would be guilty of altering the material of
33
which the Act was woven and not merely ironing out creases which were
found in the statute.
17. By way of contrast, the present is a case akin to Centrotrade (supra).
As has been pointed out in Centrotrade (supra), the parties to the contract,
in the present case, by agreeing to the SIAC Rules and the award of the
Emergency Arbitrator, have not bypassed any mandatory provision of the
Arbitration Act. There is nothing in the Arbitration Act that prohibits
contracting parties from agreeing to a provision providing for an award
being made by an Emergency Arbitrator. On the contrary, when properly
read, various Sections of the Act which speak of party autonomy in
choosing to be governed by institutional rules would make it clear that the
said rules would apply to govern the rights between the parties, a position
which, far from being prohibited by the Arbitration Act, is specifically
endorsed by it. This judgment is, therefore, entirely distinguishable from the
fact situation in the present case.
18. However, Mr. Salve argued, relying strongly upon the provisions of
Sections 10 to 13, 16, 17, 21, 23, 27, 29A, and 30 of the Arbitration Act, in
particular, that the “arbitral tribunal” spoken of in these provisions, and
referable to Section 2(1)(d) of the Act, is exhaustively defined, which means
34
a sole arbitrator or a panel of arbitrators, which, when read with these
provisions, would only include an arbitral tribunal which can not only pass
interim orders, but which is constituted between the parties so that interim
and/or final awards can be passed by this very tribunal. He also argued,
contrasting the language of Section 9(1) with the language of Section
17(1), that Section 17(1) would only apply where a party, during arbitral
proceedings, applies to an arbitral tribunal (as defined) for interim relief,
which cannot possibly apply to an Emergency Arbitrator who is admittedly
appointed only before an arbitral tribunal is properly constituted. By way of
contrast, he argued that under Section 9(1), an interim measure by the
courts may be availed by a party even before arbitral proceedings
commence, up to the stage of enforcement in accordance with Section 36.
19. There can be no doubt that the “arbitral tribunal” as defined in Section
2(1)(d) speaks only of an arbitral tribunal that is constituted between the
parties and which can give interim and final relief, “given the scheme of the
Act”, as Mr. Salve puts it, as contained in the aforementioned Sections.
However, like every other definition section, the definition contained in
Section 2(1)(d) only applies “unless the context otherwise requires”. Given
that the definition of “arbitration” in Section 2(1)(a) means any arbitration,
whether or not administered by a permanent arbitral institution, when read
35
with Sections 2(6) and 2(8), would make it clear that even interim orders
that are passed by Emergency Arbitrators under the rules of a permanent
arbitral institution would, on a proper reading of Section 17(1), be included
within its ambit. It is significant to note that the words “arbitral proceedings”
are not limited by any definition and thus encompass proceedings before
an Emergency Arbitrator, as has been held hereinabove with reference to
Section 21 of the Act read with the SIAC Rules. The short point is as to
whether the definition of “arbitral tribunal” contained in Section 2(1)(d)
should so constrict Section 17(1), making it apply only to an arbitral tribunal
that can give final reliefs by way of an interim or final award.
20. The heart of Section 17(1) is the application by a party for interim
reliefs. There is nothing in Section 17(1), when read with the other
provisions of the Act, to interdict the application of rules of arbitral
institutions that the parties may have agreed to. This being the position, at
least insofar as Section 17(1) is concerned, the “arbitral tribunal” would,
when institutional rules apply, include an Emergency Arbitrator, the context
of Section 17 “otherwise requiring” – the context being interim measures
that are ordered by arbitrators. The same object and context would apply
even to Section 9(3) which makes it clear that the court shall not entertain
an application for interim relief once an arbitral tribunal is constituted unless
36
the court finds that circumstances exist which may not render the remedy
provided under Section 17 efficacious. Since Section 9(3) and Section 17
form part of one scheme, it is clear that an “arbitral tribunal” as defined
under Section 2(1)(d) would not apply and the arbitral tribunal spoken of in
Section 9(3) would be like the “arbitral tribunal” spoken of in Section 17(1)
which, as has been held above, would include an Emergency Arbitrator
appointed under institutional rules.
21. However, Mr. Salve relied upon Firm Ashok Traders v. Gurumukh
Das Saluja, (2004) 3 SCC 155 and, in particular, the following passage:
“18. Under the A&C Act, 1996, unlike the predecessor Act of
1940, the Arbitral Tribunal is empowered by Section 17 of the
Act to make orders amounting to interim measures. The need
for Section 9, in spite of Section 17 having been enacted, is that
Section 17 would operate only during the existence of the
Arbitral Tribunal and its being functional. During that period, the
power conferred on the Arbitral Tribunal under Section 17 and
the power conferred on the court under Section 9 may overlap
to some extent but so far as the period pre- and post- the
arbitral proceedings is concerned, the party requiring an interim
measure of protection shall have to approach only the court. …”
This judgment also does not carry the Respondents’ case any further as
the question for decision in this case is whether the Emergency Arbitrator’s
award can be said to be by an “arbitral tribunal” as defined, and does not
have any reference to when a party may approach a court under Section 9.
37
22. Mr. Salve then argued that in any case, the arbitration agreement
between the parties, contained in section 25.2 of the FCPL Shareholders’
Agreement (pari materia with section 15.2 of the FRL Shareholders’
Agreement), makes it clear that the SIAC Rules would be subject to the
Indian Arbitration Act, and being so subject, the provisions governing an
award made by an Emergency Arbitrator under the SIAC Rules would not
be applicable between the parties. Sections 25.1 and 25.2 of the FCPL
Shareholders’ Agreement (pari materia with sections 15.1 and 15.2 of the
FRL Shareholders’ Agreement) read as follows:
“25.1. Governing Law
This Agreement shall be governed by and construed in
accordance with the Laws of India. Subject to the provisions of
Section 25.2 (Dispute Resolution), the courts at New Delhi,
India shall have exclusive jurisdiction over any matters or
Dispute (hereinafter defined) relating or arising out of this
Agreement.
“25.2. Dispute Resolution
25.2.1. Arbitration
Any dispute, controversy, claim or disagreement of any kind
whatsoever between or among the Parties in connection with or
arising out of this Agreement or the breach, termination or
invalidity thereof (hereinafter referred to as a “Dispute”), failing
amicable resolution through negotiations, shall be referred to
and finally resolved by arbitration irrespective of the amount in
Dispute or whether such Dispute would otherwise be
considered justifiable or ripe for resolution by any court. The
parties agree that they shall attempt to resolve through good
faith consultation, any such Dispute between any of the Parties
and such consultation shall begin promptly after a Party has
delivered to another Party a written request for such
38
consultation. In the event the Dispute is not resolved by means
of negotiation within a period of 30 (thirty) days or such different
period mutually agreed between the Parties, such Dispute shall
be referred to and finally resolved by Arbitration in accordance
with the arbitration rules of the Singapore International
Arbitration Centre (“SIAC”), and such rules (the “Rules”) as may
be modified by the provisions of this Section 25 (Governing Law
and Dispute Resolution). This Agreement and the rights and
obligations of the Parties shall remain in full force and effect
pending the award in such arbitration providing, which award, if
appropriate, shall determine whether and when any termination
shall become effective.”
As has been held by us above, it is wholly incorrect to say that Section
17(1) of the Act would exclude an Emergency Arbitrator’s orders. This
being the case, even if section 25.2 of the FCPL Shareholders’ Agreement
(pari materia with section 15.2 of the FRL Shareholders’ Agreement) makes
the SIAC Rules subject to the Arbitration Act, the said Act, properly
construed, would include an Emergency Arbitrator’s awards/orders, there
being nothing inconsistent in the SIAC Rules when read with the Act.
23. Also, Mr. Nankani’s argument that the arbitration agreement
contained in section 25.2 of the FCPL Shareholders’ Agreement referred to
hereinabove would indicate that the SIAC Rules were only agreed upon
insofar as arbitration alone is concerned is wholly incorrect. Rule 1.3 of the
SIAC Rules indicates that an award of an Emergency Arbitrator is included
within the ambit of these Rules, and that an Emergency Arbitrator, as
39
defined, means an arbitrator appointed in accordance with paragraph 3 of
Schedule 1. This makes it clear beyond doubt that “arbitration” mentioned
in section 25.2 of the FCPL Shareholders’ Agreement would include an
arbitrator appointed in accordance with the SIAC Rules which, in turn,
would include an Emergency Arbitrator.
24. The SIAC Rules, with which we are immediately concerned, deal with
the concept of an Emergency Arbitrator as follows:
“Rule 1: Scope of Application and Interpretation
* * *
1.3 In these Rules:
“Award” includes a partial, interim or final award and an award
of an Emergency Arbitrator;
* * *
“Emergency Arbitrator” means an arbitrator appointed in
accordance with paragraph 3 of Schedule 1;”
“Rule 30: Interim and Emergency Relief
30.1 The Tribunal may, at the request of a party, issue an order
or an Award granting an injunction or any other interim relief it
deems appropriate. The Tribunal may order the party
requesting interim relief to provide appropriate security in
connection with the relief sought.
30.2 A party that wishes to seek emergency interim relief prior
to the constitution of the Tribunal may apply for such relief
pursuant to the procedures set forth in Schedule 1.
30.3 A request for interim relief made by a party to a judicial
authority prior to the constitution of the Tribunal, or in
exceptional circumstances thereafter, is not incompatible with
these Rules.”
40
“SCHEDULE 1
EMERGENCY ARBITRATOR
1. A party that wishes to seek emergency interim relief may,
concurrent with or following the filing of a Notice of Arbitration
but prior to the constitution of the Tribunal, file an application for
emergency interim relief with the Registrar. The party shall, at
the same time as it files the application for emergency interim
relief, send a copy of the application to all other parties. The
application for emergency interim relief shall include:
a. the nature of the relief sought;
b. the reasons why the party is entitled to such relief; and
c. a statement certifying that all other parties have been
provided with a copy of the application or, if not, an
explanation of the steps taken in good faith to provide
a copy or notification to all other parties.
* * *
3. The President shall, if he determines that SIAC should
accept the application for emergency interim relief, seek to
appoint an Emergency Arbitrator within one day of receipt by
the Registrar of such application and payment of the
administration fee and deposits.
4. If the parties have agreed on the seat of the arbitration,
such seat shall be the seat of the proceedings for emergency
interim relief. Failing such an agreement, the seat of the
proceedings for emergency interim relief shall be Singapore,
without prejudice to the Tribunal’s determination of the seat of
the arbitration under Rule 21.1.
5. Prior to accepting appointment, a prospective Emergency
Arbitrator shall disclose to the Registrar any circumstances that
may give rise to justifiable doubts as to his impartiality or
independence. Any challenge to the appointment of the
Emergency Arbitrator must be made within two days of the
communication by the Registrar to the parties of the
appointment of the Emergency Arbitrator and the circumstances
disclosed.
6. An Emergency Arbitrator may not act as an arbitrator in
any future arbitration relating to the dispute, unless otherwise
agreed by the parties.
41
* * *
8. The Emergency Arbitrator shall have the power to order
or award any interim relief that he deems necessary, including
preliminary orders that may be made pending any hearing,
telephone or video conference or written submissions by the
parties. The Emergency Arbitrator shall give summary reasons
for his decision in writing. The Emergency Arbitrator may modify
or vacate the preliminary order, the interim order or Award for
good cause.
9. The Emergency Arbitrator shall make his interim order or
Award within 14 days from the date of his appointment unless,
in exceptional circumstances, the Registrar extends the time.
No interim order or Award shall be made by the Emergency
Arbitrator until it has been approved by the Registrar as to its
form.
10. The Emergency Arbitrator shall have no power to act after
the Tribunal is constituted. The Tribunal may reconsider, modify
or vacate any interim order or Award issued by the Emergency
Arbitrator, including a ruling on his own jurisdiction. The Tribunal
is not bound by the reasons given by the Emergency Arbitrator.
Any interim order or Award issued by the Emergency Arbitrator
shall, in any event, cease to be binding if the Tribunal is not
constituted within 90 days of such order or Award or when the
Tribunal makes a final Award or if the claim is withdrawn.
* * *
12. The parties agree that an order or Award by an
Emergency Arbitrator pursuant to this Schedule 1 shall be
binding on the parties from the date it is made, and undertake
to carry out the interim order or Award immediately and without
delay. The parties also irrevocably waive their rights to any form
of appeal, review or recourse to any State court or other judicial
authority with respect to such Award insofar as such waiver
may be validly made.”
25. A reading of the aforesaid Rules indicates that even before an arbitral
Tribunal is constituted under the Rules, urgent interim reliefs can be
42
granted by what is termed as an “Emergency Arbitrator”. An “Emergency
Arbitrator” is defined by Rule 1.3 of these Rules as meaning an arbitrator
appointed in accordance with paragraph 3 of Schedule 1. Under paragraph
7 of Schedule 1, the Emergency Arbitrator has all the powers vested in the
arbitral tribunal pursuant to SIAC Rules, including the authority to rule on
his own jurisdiction. Importantly, under paragraph 8 of Schedule 1 to the
SIAC Rules, the Emergency Arbitrator shall have the power to order such
interim relief that he deems necessary, and is to give summary reasons for
his decision in writing. Under paragraph 9, the interim order is to be made
within 14 days of his appointment, unless time is extended. Importantly,
once the arbitral tribunal is constituted under paragraph 10, the tribunal
may reconsider, modify, or vacate any such interim order. Such interim
order or award issued by the Emergency Arbitrator will continue to bind the
parties unless it is modified or vacated by the arbitral tribunal, once it is
constituted, until the tribunal makes a final award or until the claim is
withdrawn. Paragraph 10 of Schedule 1 also provides that any interim order
or award made by the Emergency Arbitrator shall cease to be binding only
if the tribunal is not constituted within 90 days of such order or award.
Under paragraph 12, the parties agree that such orders shall be binding on
43
the parties from the date it is made and undertake to carry out the interim
order immediately and without delay.
26. No doubt, as has been submitted, the 246th Law Commission Report
did provide for the insertion of an Emergency Arbitrator’s orders into
Section 2(1)(d) of the Arbitration Act as follows:
“Amendment of Section 2
1. In section 2 of the Arbitration and Conciliation Act, 1996,–
(i) In sub-section (1), clause (d), after the words “…panel of
arbitrators” add “and, in the case of an arbitration conducted
under the rules of an institution providing for appointment of an
emergency arbitrator, includes such emergency arbitrator;”
[NOTE: This amendment is to ensure that institutional rules
such as the SIAC Arbitration Rules which provide for an
emergency arbitrator are given statutory recognition in India.]”
27. As has been held in Avitel Post Studioz Ltd. & Ors. v. HSBC PI
Holdings (Mauritius) Ltd., (2021) 4 SCC 713, the mere fact that a
recommendation of a Law Commission Report is not followed by
Parliament, would not necessarily lead to the conclusion that what has
been suggested by the Law Commission cannot form part of the statute as
properly interpreted. This Court held:
“27. Mr Saurabh Kirpal took exception to Sikri, J.'s judgment in
that Sikri, J. did not refer to Para 52 of the 246th Law
Commission Report and its aftermath. Para 52 of the 246th Law
Commission Report reads as follows:
44
“52. The Commission believes that it is important to set
this entire controversy to a rest and make issues of fraud
expressly arbitrable and to this end has proposed
amendments to Section 16.”
The Law Commission then added, by way of amendment, a
proposed Section 16(7) as follows:
“Amendment of Section 16
10. In Section 16,
After sub-section (6), insert sub-section “(7) The Arbitral
Tribunal shall have the power to make an award or give a
ruling notwithstanding that the dispute before it involves a
serious question of law, complicated questions of fact or
allegations of fraud, corruption, etc.”
[Note: This amendment is proposed in the light of the
Supreme Court decisions (e.g. N. Radhakrishnan v.
Maestro Engineers [N. Radhakrishnan v. Maestro
Engineers, (2010) 1 SCC 72 : (2010) 1 SCC (Civ) 12])
which appear to denude an Arbitral Tribunal of the power
to decide on issues of fraud, etc.]”
28. Mr Saurabh Kirpal then referred to the fact that the
aforesaid sub-section was not inserted by Parliament by the
2015 Amendment Act, which largely incorporated other
amendments proposed by the Law Commission. His argument
therefore was that N. Radhakrishnan [N. Radhakrishnan v.
Maestro Engineers, (2010) 1 SCC 72] not having been
legislatively overruled, cannot now be said to be in any way
deprived of its precedential value, as Parliament has taken note
of the proposed Section 16(7) in the 246th Law Commission
Report, and has expressly chosen not to enact it. For this
proposition, he referred to La Pintada [President of India v. La
Pintada Compania Navigacion SA, 1985 AC 104 : (1984) 3
WLR 10 (HL)]. This judgment related to a challenge to an award
granting compound interest, inter alia, in a case where a debt is
paid late, but before any proceedings for its recovery had
begun.
28. He then referred to the fact that the aforesaid sub-section
was not inserted by Parliament by the 2015 Amendment Act,
which largely incorporated other amendments proposed by the
45
Law Commission. His argument therefore was that N.
Radhakrishnan [N. Radhakrishnan v. Maestro Engineers,
(2010) 1 SCC 72] not having been legislatively overruled,
cannot now be said to be in any way deprived of its
precedential value, as Parliament has taken note of the
proposed section 16(7) in the 246th Law Commission Report,
and has expressly chosen not to enact it. For this proposition,
he referred to La Pintada (supra). This judgment related to a
challenge to an award granting compound interest, inter alia, in
a case where a debt is paid late, but before any proceedings for
its recovery had begun.
29. Lord Brandon of Oakbrook, who wrote the main judgment in
this case, stated: (La Pintada case [President of India v. La
Pintada Compania Navigacion SA, 1985 AC 104 : (1984) 3
WLR 10 (HL)] , AC p. 122)
“There are three cases in which the absence of any
common law remedy for damage or loss caused by the
late payment of a debt may arise, cases which I shall in
what follows describe for convenience as Case 1, Case 2
and Case 3. Case 1 is where a debt is paid late, before
any proceedings for its recovery have been begun. Case
2 is where a debt is paid late, after proceedings for its
recovery have been begun, but before they have been
concluded. Case 3 is where a debt remains unpaid until
as a result of proceedings for its recovery being brought
and prosecuted to a conclusion, a money judgment is
given in which the original debt becomes merged.”
* * *
“32. It is a little difficult to apply this case to resurrect the ratio
of N. Radhakrishnan [N. Radhakrishnan v. Maestro Engineers,
(2010) 1 SCC 72] as a binding precedent given the advance
made in the law by this Court since N. Radhakrishnan was
decided. Quite apart from what has been stated by us in paras
17 to 21 above, as to how N. Radhakrishnan cannot be
considered to be a binding precedent for the reasons given in
the said paragraph, we are of the view that the development of
the law by this Court cannot be thwarted merely because a
certain provision recommended in a Law Commission Report is
not enacted by Parliament. Parliament may have felt, as was
46
mentioned by Lord Reid in British Railways Board v.
Herrington [British Railways Board v. Herrington, 1972 AC 877 :
1972 2 WLR 537 (HL)] , that it was unable to make up its mind
and instead, leave it to the courts to continue, case by case,
deciding upon what should constitute the fraud exception. [This
case is referred to in Lord Brandon’s judgment in La Pintada,
1985 AC 104 : (1984) 3 WLR 10 (HL) and distinguished at AC
p. 130 of his judgment.] Parliament may also have thought that
Section 16(7), proposed by the Law Commission, is clumsily
worded as it speaks of “a serious question of law, complicated
questions of fact, or allegations of fraud, corruption, etc.” N.
Radhakrishnan did not lay down that serious questions of law
or complicated questions of fact are non-arbitrable. Further,
“allegations of fraud, corruption, etc.” is vague. For this reason
also, Parliament may have left it to the courts to work out the
fraud exception. In any case, we have pointed out that dehors
any such provision, the ratio in N. Radhakrishnan, being based
upon a judgment under the 1940 Act, and without considering
Sections 5, 8 and 16 of the 1996 Act in their proper perspective,
would all show that the law laid down in this case cannot now
be applied as a precedent for application of the fraud mantra to
negate arbitral proceedings. For the reasons given in this
judgment, the House of Lords’ decision would have no
application inasmuch as N. Radhakrishnan has been tackled on
the judicial side and has been found to be wanting.”
28. It is pertinent to note that the High-Level Committee constituted by
the Government of India under the chairmanship of Justice B.N. Srikrishna
(Retd.) to review the institutionalisation of arbitration mechanism in India
and look into the provisions of the Arbitration Act after the 2015 Amendment
Act, submitted a report on 30th July, 2017 [“Srikrishna Committee
Report”], in which it is stated as follows:
“16. Enforcement of emergency awards
47
There is significant uncertainty in the law regarding the
enforceability of emergency awards in arbitrations seated in
India. The LCI in its 246th Report had recommended
recognising the concept of emergency arbitrator by widening
the definition of arbitral tribunal under section 2(d) of the ACA to
include emergency arbitrator. However, this recommendation
was not incorporated in the 2015 Amendment Act.
While one could possibly rely on section 17(2) of the ACA to
enforce emergency awards for arbitrations seated in India, the
Delhi High Court decision in Raffles Design International India
Pvt. Ltd.& Anr. v. Educomp Professional Education Ltd. & Ors.,
(2016) 234 DLT 349 held that an emergency award in an
arbitration seated outside India is not enforceable in India.
India’s approach differs from that of developed arbitration
jurisdictions such as Singapore and Hong Kong which have
recognised the enforceability of orders given by an emergency
arbitrator. Singapore amended the IAA in 2012 to broaden the
definition of ‘arbitral tribunal’ in section 2(1) to include
emergency arbitrator(s). Hong Kong amended the AO in 2013
to include Part 3A which deals with the enforcement of
emergency relief. Section 22B provides that emergency relief
granted by an emergency arbitrator shall with the leave of the
Court of First Instance of the High Court be enforceable in the
same manner as an order or direction of the Court.
Given that international practice is in favour of enforcing
emergency awards (Singapore, Hong Kong and the United
Kingdom all permit enforcement of emergency awards), it is
time that India permitted the enforcement of emergency awards
in all arbitral proceedings. This would also provide legislative
support to rules of arbitral institutions that presently provide for
emergency arbitrators (See Dennis Nolan and Roger Abrams,
‘Arbitral Immunity’, Berkeley Journal of Employment and Labour
Law, Vol. 11 Issue 2 (1989), pp.228–266). For this purpose, the
recommendation made by the LCI in its 246th Report may be
adopted.”
48
29. The Delhi High Court judgment in Raffles Design International
India Pvt. Ltd. v. Educomp Professional Education Ltd., 2016 SCC
OnLine Del 5521 : (2016) 234 DLT 349 dealt with an award by an
Emergency Arbitrator in an arbitration seated outside India (as was
mentioned in Srikrishna Committee Report). What is of significance is that
the said Report laid down that it is possible to interpret Section 17(2) of the
Act to enforce emergency awards for arbitrations seated in India, and
recommended that the Act be amended only so that it comes in line with
international practice in favour of recognising and enforcing an emergency
award.
30. It is relevant to note that the 246th Law Commission Report also
recommended the insertion of Section 9(2) and 9(3) as follows:
“Amendment of Section 9
6. In section 9,
(i) before the words “A party may, before” add sub-section “(1)”
(ii) after the words “any proceedings before it” add sub-section
“(2) Where, before the arbitral proceedings, a Court grants any
interim measure of protection under sub-section (1), the arbitral
proceedings shall be commenced within 60 days from the date
of such grant or within such shorter or further time as indicated
by the Court, failing which the interim measure of protection
shall cease to operate.
[NOTE: This amendment is to ensure the timely initiation of
arbitration proceedings by a party who is granted an interim
measure of protection.]
49
(iii) Add sub-section “(3) Once the Arbitral Tribunal has been
constituted, the Court shall, ordinarily, not entertain an
Application under this provision unless circumstances exist
owing to which the remedy under section 17 is not efficacious.”
[NOTE: This amendment seeks to reduce the role of the Court
in relation to grant of interim measures once the Arbitral
Tribunal has been constituted. After all, once the Tribunal is
seized of the matter it is most appropriate for the Tribunal to
hear all interim applications. This also appears to be the spirit of
the UNCITRAL Model Law as amended in 2006.
Accordingly, section 17 has been amended to provide the
Arbitral Tribunal the same powers as a Court would have under
section 9]”
31. The 2015 Amendment Act, therefore, introduced sub-sections (2) and
(3) to Section 9, which read as follows:
“9. Interim measures, etc. by Court.—
* * *
(2) Where, before the commencement of the arbitral
proceedings, a court passes an order for any interim measure
of protection under sub-section (1), the arbitral proceedings
shall be commenced within a period of ninety days from the
date of such order or within such further time as the court may
determine.
(3) Once the arbitral tribunal has been constituted, the court
shall not entertain an application under sub-section (1), unless
the court finds that circumstances exist which may not render
the remedy provided under Section 17 efficacious.”
32. In essence, what is provided by the SIAC Rules and the other
institutional rules, is reflected in Sections 9(2) and 9(3) so far as interim
orders passed by courts are concerned. The introduction of Sections 9(2)
50
and 9(3) would show that the objective was to avoid courts being flooded
with Section 9 petitions when an arbitral tribunal is constituted for two good
reasons – (i) that the clogged court system ought to be decongested, and
(ii) that an arbitral tribunal, once constituted, would be able to grant interim
relief in a timely and efficacious manner.
33. Similarly, the 246th Law Commission Report recommended the
amendment of Section 17 as follows:
“Amendment of Section 17
11. In section 17
* * *
(vi) In sub-section (1), after sub-clause “(d)”, insert sub-clause
“(e) such other interim measure of protection as may appear to
the Arbitral Tribunal to be just and convenient, and the arbitral
tribunal shall have the same power for making orders as the
Court has for the purpose of, and in relation to, any
proceedings before it.”
[NOTE: This is to provide the arbitral tribunal the same powers
as a civil court in relation to grant of interim measures. When
this provision is read in conjunction with section 9(2), parties will
by default be forced to approach the Arbitral Tribunal for interim
relief once the Tribunal has been constituted. The Arbitral
Tribunal would continue to have powers to grant interim relief
post-award. This regime would decrease the burden on Courts.
Further, this would also be in tune with the spirit of the
UNCITRAL Model Law as amended in 2006.]
(vii) delete words in sub-section (2) and add the words “(2)
Subject to any orders passed in appeal under section 37, any
order issued by the arbitral tribunal under this section shall be
deemed to be an Order of the Court for all purposes and shall
be enforceable under the Code of Civil Procedure, 1908 in the
same manner as if it were an Order of the Court.”
51
[NOTE: This is to ensure the effective enforcement of interim
measures that may be ordered by an arbitral tribunal.]”
34. Section 17 was then amended by the very same 2015 Amendment
Act (which brought in sub-sections (2) and (3) to Section 9) to substitute
Section 17 so that Section 17(1) would be a mirror image of Section 9(1),
making it clear that an arbitral tribunal is fully clothed with the same power
as a court to provide for interim relief. Also, Section 17(2) was added so as
to provide for enforceability of such orders, again, as if they were orders
passed by a court, thereby bringing Section 17 on par with Section 9.
35. An Emergency Arbitrator’s “award”, i.e., order, would undoubtedly be
an order which furthers these very objectives, i.e., to decongest the court
system and to give the parties urgent interim relief in cases which deserve
such relief. Given the fact that party autonomy is respected by the Act and
that there is otherwise no interdict against an Emergency Arbitrator being
appointed, as has been held by us hereinabove, it is clear that an
Emergency Arbitrator’s order, which is exactly like an order of an arbitral
tribunal once properly constituted, in that parties have to be heard and
reasons are to be given, would fall within the institutional rules to which the
parties have agreed, and would consequently be covered by Section 17(1),
when read with the other provisions of the Act, as delineated above.
52
36. A party cannot be heard to say, after it participates in an Emergency
Award proceeding, having agreed to institutional rules made in that regard,
that thereafter it will not be bound by an Emergency Arbitrator’s ruling. As
we have seen hereinabove, having agreed to paragraph 12 of Schedule 1
to the SIAC Rules, it cannot lie in the mouth of a party to ignore an
Emergency Arbitrator’s award by stating that it is a nullity when such party
expressly agrees to the binding nature of such award from the date it is
made and further undertakes to carry out the said interim order immediately
and without delay.
37. However, Mr. Viswanathan argued that an Emergency Arbitrator
under the SIAC Rules is not an independent judicial body like an arbitral
tribunal constituted under the very Rules, and referred to and relied upon
Rules 3, 9, and 10 to buttress this proposition. Rule 3 merely states that the
President may appoint an Emergency Arbitrator if he determines that the
SIAC should accept the application for emergency interim relief. Once the
Emergency Arbitrator enters upon the reference, he is given all the powers
of an arbitral tribunal under Rule 7 and is to decide completely
independently of any other administrative authority under the SIAC Rules.
Equally, Rule 9 does not, in any manner, impinge upon the independence
of the Emergency Arbitrator as it only lays down the timeframe within which
53
an interim order or award is to be made, which time is extendable by the
Registrar. The interim order or award that is finally made by the Emergency
Arbitrator has only to be approved by the Registrar as to its “form” and not
on merits. Further, Rule 10 also does not, in any manner, interfere with the
independence of the decision of the Emergency Arbitrator. This argument
is, therefore, rejected.
38. Mr. Viswanathan also went on to argue, relying upon Section 28 of
the Contract Act, Justice R.S. Bachawat’s Law of Arbitration and
Conciliation (Sixth Ed., LexisNexis), and the Chancery Division judgment of
In Re Franklin and Swathling’s Arbitration, [1929] 1 Ch. 238, for the
proposition that arbitration, conceptually, is an ouster of the civil court’s
jurisdiction and that, therefore, only what is expressly provided in the ouster
provisions can be followed – there is no room for any implication here. This
argument may have found favour with a court if it were dealing with
Arbitration Act, 1940. As has been held in several decisions of this Court,
the Arbitration and Conciliation Act, 1996 is a complete break with the past
and is no longer to be viewed as an ouster statute but as a statute which
favours the remedy of arbitration so as to de-clog civil courts which are, in
today’s milieu, extremely burdened. As a matter of fact, Section 5 of the
Arbitration Act puts paid to the submission when it overrides all other laws
54
for the time being in force and goes on to state that in matters governed by
Part I of the Act, no judicial authority shall intervene except where so
provided in that Part. The Arbitration Act, therefore, turns the principle of
ouster on its head when it comes to arbitration as a favoured means of
resolving civil disputes. This argument also, therefore, stands rejected.
39. Even otherwise, as has been correctly pointed out by Mr.
Subramanium, no order bears the stamp of invalidity on its forehead and
has to be set aside in regular court proceedings as being illegal. This is
felicitously stated in several judgments – See Krishnadevi Malchand
Kamathia v. Bombay Environmental Action Group, (2011) 3 SCC 363
(at paragraphs 16 to 19), and Anita International v. Tungabadra Sugar
Works Mazdoor Sangh, (2016) 9 SCC 44 (at paragraphs 54 and 55). As a
matter of fact, in Tayabbhai M. Bagasarwalla v. Hind Rubber Industries
(P) Ltd., (1997) 3 SCC 443, this Court has unequivocally held that even if
an order is later set aside as having been passed without jurisdiction, for
the period of its subsistence, it is an order that must be obeyed. This Court
held:
“15. The next thing to be noticed is that certain interim orders
were asked for and were granted by the Civil Court during this
period. Would it be right to say that violation of and
disobedience to the said orders of injunction is not punishable
because it has been found later that the Civil Court had no
55
jurisdiction to entertain the suit. Mr Sorabjee suggests that
saying so would be subversive of the Rule of Law and would
seriously erode the majesty and dignity of the courts. It would
mean, suggests the learned counsel, that it would be open to
the defendants-respondents to decide for themselves whether
the order was with or without jurisdiction and act upon that
belief. This can never be, says the learned counsel. He further
suggests that if any party thinks that an order made by the Civil
Court is without jurisdiction or is contrary to law, the appropriate
course open to him is to approach that court with that plea and
ask for vacating the order. But it is not open to him to flout the
said order assuming that the order is without jurisdiction. It is
this principle which has been recognised and incorporated in
Section 9-A of Civil Procedure Code (inserted by Maharashtra
Amendment Act No. 65 of 1977), says Mr Sorabjee. Section 9-A
reads as follows:
“9-A. Where at the hearing of an application relating to
interim relief in suit, objection to jurisdiction is taken, such
issue to be decided by the Court as a preliminary issue.—
(1) Notwithstanding anything contained in this Code or
any other law for the time being in force, if, at the hearing
of any application for granting or setting aside an order
granting any interim relief, whether by way of stay
injunction, appointment of a receiver or otherwise, made
in any suit, an objection to the jurisdiction of the Court to
entertain such suit is taken by any of the parties to the
suit, the Court shall proceed to determine at the hearing
of such application the issue as to the jurisdiction as a
preliminary issue before granting or setting aside the
order granting the interim relief. Any such application shall
be heard and disposed of by the Court as expeditiously
as possible and shall not in any case be adjourned to the
hearing of suit.
(2) Notwithstanding anything contained in sub-section
(1), at the hearing of any such application, the Court may
grant such interim relief as it may consider necessary,
pending determination by it of the preliminary issue as to
the jurisdiction.”
56
16. According to this section, if an objection is raised to the
jurisdiction of the court at the hearing of an application for grant
of, or for vacating, interim relief, the court should determine that
issue in the first instance as a preliminary issue before granting
or setting aside the relief already granted. An application raising
objection to the jurisdiction to the court is directed to be heard
with all expedition. Sub-rule (2), however, says that the
command in sub-rule (1) does not preclude the court from
granting such interim relief as it may consider necessary
pending the decision on the question of jurisdiction. In our
opinion, the provision merely states the obvious. It makes
explicit what is implicit in law. Just because an objection to the
jurisdiction is raised, the court does not become helpless
forthwith — nor does it become incompetent to grant the interim
relief. It can. At the same time, it should also decide the
objection to jurisdiction at the earliest possible moment. This is
the general principle and this is what Section 9-A reiterates.
Take this very case. The plaintiff asked for temporary injunction.
An ad interim injunction was granted. Then the defendants
came forward objecting to the grant of injunction and also
raising an objection to the jurisdiction of the court. The court
overruled the objection as to jurisdiction and made the interim
injunction absolute. The defendants filed an appeal against the
decision on the question of jurisdiction. While that appeal was
pending, several other interim orders were passed both by the
Civil Court as well as by the High Court. Ultimately, no doubt,
the High Court has found that the Civil Court had no jurisdiction
to entertain the suit but all this took about six years. Can it be
said that orders passed by the Civil Court and the High Court
during this period of six years were all non est and that it is
open to the defendants to flout them merrily, without fear of any
consequence. Admittedly, this could not be done until the High
Court's decision on the question of jurisdiction. The question is
whether the said decision of the High Court means that no
person can be punished for flouting or disobeying the
interim/interlocutory orders while they were in force, i.e., for
violations and disobedience committed prior to the decision of
the High Court on the question of jurisdiction. Holding that by
virtue of the said decision of the High Court (on the question of
jurisdiction), no one can be punished thereafter for
57
disobedience or violation of the interim orders committed prior
to the said decision of the High Court, would indeed be
subversive of the Rule of Law and would seriously erode the
dignity and the authority of the courts. We must repeat that this
is not even a case where a suit was filed in the wrong court
knowingly or only with a view to snatch an interim order. As
pointed out hereinabove, the suit was filed in the Civil Court
bona fide. We are of the opinion that in such a case the
defendants cannot escape the consequences of their
disobedience and violation of the interim injunction committed
by them prior to the High Court's decision on the question of
jurisdiction.
* * *
“27. The learned counsel for Defendants 1 and 2 submitted that
this is not a proceeding for contempt but a proceeding under
Rule 2-A of Order 39 of the Civil Procedure Code. The learned
counsel submitted that proceedings under Order 39 Rule 2-A
are a part of the coercive process to secure obedience to its
injunction and that once it is found that the Court has no
jurisdiction, question of securing obedience to its orders any
further does not arise. The learned counsel also submitted that
enforcing the interim order after it is found that the Court had no
jurisdiction to try the said suit would not only be unjust and
illegal but would also reflect adversely upon the dignity and
authority of the Court. It is also suggested that the plaintiff had
instituted the present suit in the Civil Court knowing fully well
that it had no jurisdiction to try it. It is not possible to agree with
any of these submissions not only on principle but also in the
light of the specific provision contained in Section 9-A of the
Code of Civil Procedure (Maharashtra Amendment). In the light
of the said provision, it would not be right to say that the Civil
Court had no jurisdiction to pass interim orders or interim
injunction, as the case may be, pending decision on the
question of jurisdiction. The orders made were within the
jurisdiction of the Court and once this is so, they have to be
obeyed and implemented. It is not as if the defendants are
being sought to be punished for violations committed after the
decision of the High Court on the question of jurisdiction of the
Civil Court. Here the defendants are sought to be punished for
the disobedience and violation of the order of injunction
58
committed before the decision of the High Court in Vishanji Virji
Mepani [AIR 1996 Bom 366]. According to Section 9-A, the Civil
Court and the High Court did have the power to pass interim
orders until that decision. If they had that power, they must also
have the power to enforce them. In the light of the said
provision, it cannot also be held that those orders could be
enforced only till the said decision but not thereafter. The said
decision does not render them (the interim orders passed
meanwhile) either non est or without jurisdiction. Punishing the
defendants for violation of the said orders committed before the
said decision (Vishanji Virji Mepani [AIR 1996 Bom 366]) does
not amount, in any event, to enforcing them after the said
decision. Only the orders are being passed now. The violations
are those committed before the said decision.”
40. However, learned counsel for the Respondents referred to and relied
upon the classic passage in Kiran Singh v. Chaman Paswan, (1955) 1
SCR 117 (at page 122) and various other judgments following it to contend
that in cases of inherent lack of jurisdiction, it would be open to a party to
ignore an award by an Emergency Arbitrator. They also referred to the
judgment in CIT v. Pearl Mechanical Engineering & Foundry Works (P)
Ltd., (2004) 4 SCC 597, where this Court spoke of the jurisdiction of a
court or tribunal by stating that such jurisdiction only subsists when a court
or tribunal exercises such jurisdiction from the law. It is a power which
nobody on whom the law is not conferred can exercise. None of these
judgments are applicable in the fact situation of the present case. On the
contrary, we have pointed out that no party, after agreeing to be governed
59
by institutional rules, can participate in a proceeding before an Emergency
Arbitrator and, after losing, turn around and say that the award is a nullity or
coram non judice when there is nothing in the Arbitration Act which
interdicts an Emergency Arbitrator’s order from being made. As has been
pointed out, Section 17, as construed in the light of the other provisions of
the Act, clearly leads to the position that such emergency award is made
under the provisions of Section 17(1) and can be enforced under the
provisions of Section 17(2).
41. We, therefore, answer the first question by declaring that full party
autonomy is given by the Arbitration Act to have a dispute decided in
accordance with institutional rules which can include Emergency Arbitrators
delivering interim orders, described as “awards”. Such orders are an
important step in aid of decongesting the civil courts and affording
expeditious interim relief to the parties. Such orders are referable to and
are made under Section 17(1) of the Arbitration Act.
42. We now come to the question as to the maintainability of the appeal
that has been filed under Order XLIII, Rule 1(r). Order XLIII, Rule 1(r) reads
as under:
“ORDER XLIII – Appeals from Orders
60
1. Appeals from orders.—An appeal shall lie from the
following orders under the provisions of Section 104, namely:—
* * *
(r) an order under Rule 1, Rule 2, Rule 2-A, Rule 4 or Rule 10
of Order XXXIX;”
43. In order to answer this question, it is important to advert to Sections
9, 17, and 37 of the Arbitration Act. Section 9(1) reads as follows:
“9. Interim measures, etc. by Court.—(1) A party may, before
or during arbitral proceedings or at any time after the making of
the arbitral award but before it is enforced in accordance with
Section 36, apply to a Court:—
(i) for the appointment of a guardian for a minor or a person of
unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of the
following matters, namely:—
(a) the preservation, interim custody or sale of any
goods which are the subject-matter of the arbitration
agreement;
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any
property or thing which is the subject-matter of the
dispute in arbitration, or as to which any question
may arise therein and authorising for any of the
aforesaid purposes any person to enter upon any
land or building in the possession of any party, or
authorising any samples to be taken or any
observation to be made, or experiment to be tried,
which may be necessary or expedient for the
purpose of obtaining full information or evidence;
(d) interim injunction or the appointment of a receiver;
(e) such other interim measure of protection as may
appear to the Court to be just and convenient,
61
and the Court shall have the same power for making orders as
it has for the purpose of, and in relation to, any proceedings
before it.”
After the 2015 Amendment Act, Section 17(1), which, as has been stated
hereinabove, is now a mirror image of Section 9(1), reads as follows:
“17. Interim measures ordered by arbitral tribunal.—(1) A
party may, during the arbitral proceedings, apply to the arbitral
tribunal—
(i) for the appointment of a guardian for a minor or person of
unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of the
following matters, namely—
(a) the preservation, interim custody or sale of any goods
which are the subject matter of the arbitration
agreement;
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any
property or thing which is the subject matter of the
dispute in arbitration, or as to which any question may
arise therein and authorising for any of the aforesaid
purposes any person to enter upon any land or
building in the possession of any party, or authorising
any samples to be taken, or any observation to be
made, or experiment to be tried, which may be
necessary or expedient for the purpose of obtaining full
information or evidence;
(d) interim injunction or the appointment of a receiver;
(e) such other interim measure of protection as may
appear to the arbitral tribunal to be just and
convenient,
and the arbitral tribunal shall have the same power for making
orders, as the court has for the purpose of, and in relation to,
any proceedings before it.”
62
Section 17(2), which was also introduced by the same Amendment Act,
reads:
“17. Interim measures ordered by arbitral tribunal.—
* * *
(2) Subject to any orders passed in an appeal under section 37,
any order issued by the arbitral tribunal under this section shall
be deemed to be an order of the court for all purposes and shall
be enforceable under the Code of Civil Procedure, 1908 (5 of
1908), in the same manner as if it were an order of the court.”
Section 37, within the four corners of which appeals against orders are to
be made under the Arbitration Act, reads as follows:
“37. Appealable orders.—(1) Notwithstanding anything
contained in any other law for the time being in force, an appeal
shall lie from the following orders (and from no others) to the
court authorised by law to hear appeals from original decrees of
the Court passing the order, namely:—
(a) refusing to refer the parties to arbitration under
Section 8;
(b) granting or refusing to grant any measure under
Section 9;
(c) setting aside or refusing to set aside an arbitral award
under Section 34.
(2) An appeal shall also lie to a court from an order of the
arbitral tribunal—
(a) accepting the plea referred to in sub-section (2) or
sub-section (3) of Section 16; or
(b) granting or refusing to grant an interim measure
under Section 17.
(3) No second appeal shall lie from an order passed in appeal
under this section, but nothing in this section shall affect or take
away any right to appeal to the Supreme Court.”
63
44. As has been pointed out hereinabove, the Law Commission
recommended an amendment to Section 17 to provide the arbitral tribunal
the same powers as a court would have under Section 9.
45. Section 9(1), after setting out in clauses (i) and (ii) what interim
measures or protection could be granted, then goes on to add, “and the
court shall have the same power for making orders as it has for the
purpose of, and in relation to, any proceedings before it”.
46. The italicised words arose for interpretation in Adhunik Steels Ltd. v.
Orissa Manganese and Minerals (P) Ltd., (2007) 7 SCC 125. In
paragraph 11 of the judgment, this Court held:
“11. It is true that Section 9 of the Act speaks of the court by
way of an interim measure passing an order for protection, for
the preservation, interim custody or sale of any goods, which
are the subject-matter of the arbitration agreement and such
interim measure of protection as may appear to the court to be
just and convenient. The grant of an interim prohibitory
injunction or an interim mandatory injunction are governed by
well-known rules and it is difficult to imagine that the legislature
while enacting Section 9 of the Act intended to make a
provision which was dehors the accepted principles that
governed the grant of an interim injunction. Same is the position
regarding the appointment of a receiver since the section itself
brings in the concept of “just and convenient” while speaking of
passing any interim measure of protection. The concluding
words of the section, “and the court shall have the same power
for making orders as it has for the purpose and in relation to
any proceedings before it” also suggest that the normal rules
that govern the court in the grant of interim orders is not sought
64
to be jettisoned by the provision. Moreover, when a party is
given a right to approach an ordinary court of the country
without providing a special procedure or a special set of rules in
that behalf, the ordinary rules followed by that court would
govern the exercise of power conferred by the Act. On that
basis also, it is not possible to keep out the concept of balance
of convenience, prima facie case, irreparable injury and the
concept of just and convenient while passing interim measures
under Section 9 of the Act.”
47. Quite apart from the above, the language of the last part of Section
9(1) clearly refers to Section 94 of the Code of Civil Procedure read with
Order XXXIX thereof. Section 94 of the Code of Civil Procedure reads as
follows:
“94. Supplemental proceedings.—In order to prevent the
ends of justice from being defeated the Court may, if it is so
prescribed,—
(a) issue a warrant to arrest the defendant and bring him
before the Court to show cause why he should not give
security for his appearance, and if he fails to comply with
any order for security commit him to the civil prison;
(b) direct the defendant to furnish security to produce any
property belonging to him and to place the same at the
disposal of the Court or order the attachment of any
property;
(c) grant a temporary injunction and in case of disobedience
commit the person guilty thereof to the civil prison and
order that his property be attached and sold;
(d) appoint a receiver of any property and enforce the
performance of his duties by attaching and selling his
property;
(e) make such other interlocutory orders as may appear to the
Court to be just and convenient.”
65
Order XXXIX, Rules 1, 2, and 2-A read as follows:
“ORDER XXXIX
Temporary injunctions
1. Cases in which temporary injunction may be granted.—
Where in any suit it is proved by affidavit or otherwise—
(a) that any property in dispute in a suit is in danger of being
wasted, damaged or alienated by any party to the suit, or
wrongfully sold in execution of a decree, or
(b) that the defendant threatens, or intends, to remove or
dispose of his property with a view to defrauding his
creditors,
(c) that the defendant threatens to dispossess the plaintiff or
otherwise cause injury to the plaintiff in relation to any
property in dispute in the suit,
the Court may by order grant a temporary injunction to restrain
such act, or make such other order for the purpose of staying
and preventing the wasting, damaging, alienation, sale, removal
or disposition of the property or dispossession of the plaintiff, or
otherwise causing injury to the plaintiff in relation to any
property in dispute in the suit] as the Court thinks fit, until the
disposal of the suit or until further orders.
2. Injunction to restrain repetition or continuance of
breach.—(1) In any suit for restraining the defendant from
committing a breach of contract or other injury of any kind,
whether compensation is claimed in the suit or not, the plaintiff
may, at any time after the commencement of the suit, and either
before or after judgment, apply to the Court for a temporary
injunction to restrain the defendant from committing the breach
of contract or injury complained of, or any breach of contract or
injury of a like kind arising out of the same contract or relating
to the same property or right.
(2) The Court may by order grant such injunction, on such
terms as to the duration of the injunction, keeping an account,
giving security, or otherwise, as the Court thinks fit.
66
2-A. Consequence of disobedience or breach of injunction.
—(1) In the case of disobedience of any injunction granted or
other order made under Rule 1 or Rule 2 or breach of any of
the terms on which the injunction was granted or the order
made, of the Court granting the injunction or making the order,
or any Court to which the suit or proceeding is transferred, may
order the property of the person guilty of such disobedience or
breach to be attached, and may also order such person to be
detained in the civil prison for a term not exceeding three
months, unless in the meantime the Court directs his release.
(2) No attachment made under this rule shall remain in force for
more than one year, at the end of which time, if the
disobedience or breach continues, the property attached may
be sold and out of the proceeds, the Court may award such
compensation as it thinks fit to the injured party and shall pay
the balance, if any, to the party entitled thereto.”
Prior to the Code of Civil Procedure (Amendment) Act, 1976 [“1976
Amendment Act”], disobedience of an injunction or breach of any of its
terms was enforced under sub-rules (3) and (4) of Order XXXIX, Rule 2 as
follows:
“2. Injunction to restrain repetition or continuance of
breach.—
* * *
(3) In case of disobedience, or of breach of any such terms, the
Court granting an injunction may order the property of the
person guilty of such disobedience or breach to be attached,
and may also order such person to be detained in the civil
prison for a term not exceeding six months, unless in the
meantime the Court directs his release.”
(4) No attachment under this rule shall remain in force for more
than one year, at the end of which time, if the disobedience or
breach continues, the property attached may be sold, and out
of the proceeds the Court may award such compensation as it
67
thinks fit, and shall pay the balance, if any, to the party entitled
thereto.”
A controversy arose as to whether sub-rules (3) and (4) to Rule 2 applied to
breach of injunctions that were granted under Rule 1 of Order XXXIX. This
controversy was set at rest by omitting sub-rules (3) and (4) from Order
XXXIX, Rule 2 and introducing a new Rule 2-A to Order XXXIX. The
Statement of Objects and Reasons for this provision read as follows:
“Clause 89 – Sub-rule (iii) – New Rule 2-A is being inserted to
provide for the consequences of a breach of an injunction
issued under Rule 1 which is, at present, not covered. The
amendment is intended to seek the application of the provisions
for breach, which are, at present, available under an injunction
granted under Rule 2, to the said class of cases as well. There
is a controversy as to whether under the existing provision, a
court to which a suit is transferred can punish disobedience of
an injunction issued by the predecessor court. New Rule 2-A
provides that the transferee court can also exercise that power.”
(See Gazette of Ind., 8th April 1974, Pt. II, S. 2. Ext. p. 335)
48. A reading of Order XXXIX, Rule 2(3) and 2(4) as it originally stood,
and Order XXXIX, Rule 2-A as it stands after the 1976 Amendment Act is to
“prescribe” under Section 94 of the Code of Civil Procedure as to what is
the consequence when a temporary injunction order and/or an order
appointing a receiver of property is flouted. The consequences are
mentioned in Sections 94(c) and (d) itself and fleshed out by Order XXXIX
as aforesaid.
68
49. Mr. Nankani cited the judgment of Food Corporation of India v.
Sukh Deo Prasad, (2009) 5 SCC 665, in which he relied upon the
following observations of this Court:
“38. The power exercised by a court under Order 39 Rule 2-A of
the Code is punitive in nature, akin to the power to punish for
civil contempt under the Contempt of Courts Act, 1971. The
person who complains of disobedience or breach has to clearly
make out beyond any doubt that there was an injunction or
order directing the person against whom the application is
made, to do or desist from doing some specific thing or act and
that there was disobedience or breach of such order. While
considering an application under Order 39 Rule 2-A, the court
cannot construe the order in regard to which
disobedience/breach is alleged, as creating an obligation to do
something which is not mentioned in the “order”, on surmises,
suspicions and inferences. The power under Rule 2-A should
be exercised with great caution and responsibility.”
He also relied upon the judgment of U.C. Surendranath v. Mambally’s
Bakery, (2019) 20 SCC 666, and paragraph 7 in particular, which states:
“7. For finding a person guilty of wilful disobedience of the order
under Order 39 Rule 2-A CPC there has to be not mere
“disobedience” but it should be a “wilful disobedience”. The
allegation of wilful disobedience being in the nature of criminal
liability, the same has to be proved to the satisfaction of the
court that the disobedience was not mere “disobedience” but a
“wilful disobedience”. As pointed out earlier, during the second
visit of the Commissioner to the appellant's shop, tea cakes and
masala cakes were being sold without any wrappers/labels. The
only thing which the Commissioner has noted is that “nonremoval of the hoarding” displayed in front of the appellant’s
shop for which the appellant has offered an explanation which,
in our considered view, is acceptable one.”
69
50. It is one thing to say that the power exercised by a court under Order
XXXIX, Rule 2-A is punitive in nature and akin to the power to punish for
civil contempt under the Contempt of Courts Act, 1971. It is quite another
thing to say that Order XXXIX, Rule 2-A requires not “mere disobedience”
but “wilful disobedience”. We are prima facie of the view that the latter
judgment in adding the word “wilful” into Order XXXIX, Rule 2-A is not quite
correct and may require to be reviewed by a larger Bench. Suffice it to say
that there is a vast difference between enforcement of orders passed under
Order XXXIX, Rules 1 and 2 and orders made in contempt of court. Orders
which are in contempt of court are made primarily to punish the offender by
imposing a fine or a jail sentence or both. On the other hand, Order XXXIX,
Rule 2-A is primarily intended to enforce orders passed under Order
XXXIX, Rules 1 and 2, and for that purpose, civil courts are given vast
powers which include the power to attach property, apart from passing
orders of imprisonment, which are punitive in nature.1
Orders passed under
Section 17(2) of the Arbitration Act, using the power contained in Order
XXXIX, Rule 2-A are, therefore, properly referable only to the Arbitration
1 When an order for permanent injunction is to be enforced, Order XXI, Rule 32
provides for attachment and/or detention in a civil prison. Orders that are passed under
Order XXI, Rule 32 are primarily intended to enforce injunction decrees by methods
similar to those contained in Order XXXIX, Rule 2-A. This also shows the object of
Order XXXIX, Rule 2-A is primarily to enforce orders of interim injunction.
70
Act. Neither of the aforesaid judgments are an authority for any proposition
of law to the contrary.
51. It is well settled that the expression “in relation to”, which occurs in
both Section 9(1) and Section 17(1), is an expression which is
comprehensive in nature, having both a direct as well as an indirect
significance. Thus, in Bandekar Brothers Pvt. Ltd. v. Prasad Vassudev
Keni, 2020 SCC OnLine SC 707 this Court held:
“20. The words “in relation to” have been the subject matter of
judicial discussion in many judgments. Suffice it to say that for
the present, two such judgments need to be noticed. In State
Wakf Board, Madras v. Abdul Azeez Sahib, AIR 1968 Mad. 79,
the expression “relating to” contained in Section 57(1) of the
Wakf Act, 1954 fell for consideration before the Madras High
Court. The High Court held:
“8. We have no doubt whatever that the learned Judge,
(Kailasam, J.), was correct in his view that even the second
suit has to be interpreted as within the scope of the words
employed in S. 57(1) namely, “In every suit or proceeding
relating to title to Wakf property”. There is ample judicial
authority for the view that such words as “relating to” or “in
relation to” are words of comprehensiveness which might
both have a direct significance as well as an indirect
significance, depending on the context. They are not words
of restrictive content and ought not to be so construed. The
matter has come up for judicial determination in more than
one instance. The case in Compagnie Financiec Dae
Pacifique v. Peruvian Guano Co, is of great interest, on this
particular aspect and the judgment of Brett, L.J., expounds
the interpretation of O. 31, R. 12 of the Rules of the
Supreme Court, 1875, in the context of the phrase “material
to any matter in question in the action”. Brett, L.J.,
observed that this could both be direct as well as indirect in
71
consequences and according to the learned Judge the test
was this (at page 63):
“…a document can properly be said to contain
information which may enable the party requiring
the affidavit either to advance his own case or to
damage the case of his adversary if it is a document
which may fairly lead him to a train of inquiry, which
may have either of these consequences.””
21. Likewise, in Mansukhlal Dhanraj Jain v. Eknath Vithal
Ogale, (1995) 2 SCC 665, the expression “Suits and
proceedings between a licensor and licensee…relating to the
recovery of possession” under Section 41(1) of the Presidency
Small Cause Courts Act, 1882 came up for consideration before
this Court. The Court held:
“14. …The words ‘relating to’ are of wide import and
can take in their sweep any suit in which the grievance is
made that the defendant is threatening to illegally recover
possession from the plaintiff-licensee. Suits for protecting
such possession of immovable property against the
alleged illegal attempts on the part of the defendant to
forcibly recover such possession from the plaintiff, can
clearly get covered by the wide sweep of the words
“relating to recovery of possession” as employed by
Section 41(1).”
* * *
“16. It is, therefore, obvious that the phrase “relating to
recovery of possession” as found in Section 41(1) of the
Small Cause Courts Act is comprehensive in nature and
takes in its sweep all types of suits and proceedings
which are concerned with the recovery of possession of
suit property from the licensee and, therefore, suits for
permanent injunction restraining the defendant from
effecting forcible recovery of such possession from the
licensee-plaintiff would squarely be covered by the wide
sweep of the said phrase. Consequently, in the light of the
averments in the plaints under consideration and the
prayers sought for therein, on the clear language of
Section 41(1), the conclusion is inevitable that these suits
could lie within the exclusive jurisdiction of Small Cause
72
Court, Bombay and the City Civil Court would have no
jurisdiction to entertain such suits.”
52. As a matter of fact, the judgment of this Court in Thyssen
Stahlunion Gmbh v. Steel Authority of India Ltd., (1999) 9 SCC 334, set
out Section 85 of the Arbitration Act in paragraph 2 as follows:
“2. This Section 85 of the new Act we reproduce at the outset:
“85. Repeal and savings.—(1) The Arbitration (Protocol
and Convention) Act, 1937 (6 of 1937), the Arbitration Act,
1940 (10 of 1940) and the Foreign Awards (Recognition
and Enforcement) Act, 1961 (45 of 1961) are hereby
repealed.
(2) Notwithstanding such repeal,—
(a) the provisions of the said enactments shall apply
in relation to arbitral proceedings which
commenced before this Act came into force unless
otherwise agreed by the parties but this Act shall
apply in relation to arbitral proceedings which
commenced on or after this Act comes into force;
(b) all rules made and notifications published, under
the said enactments shall, to the extent to which
they are not repugnant to this Act, be deemed
respectively to have been made or issued under
this Act.”
The expression “in relation to” appears in Section 85(2)(a). The question
which arose before the Court, and which was answered by the Court, was
whether enforcement proceedings would be included within the ambit of
Section 85(2)(a). Holding that they did, this Court opined:
“32. …… We are, therefore, of the opinion that it would be the
provisions of the old Act that would apply to the enforcement of
73
the award in the case of Civil Appeal No. 6036 of 1998. Any
other construction on Section 85(2)(a) would only lead to
confusion and hardship. This construction put by us is
consistent with the wording of Section 85(2)(a) using the terms
“provision” and “in relation to arbitral proceedings” which would
mean that once the arbitral proceedings commenced under the
old Act it would be the old Act which would apply for enforcing
the award as well.”
This passage was referred to by this Court in BCCI v. Kochi Cricket (P)
Ltd., (2018) 6 SCC 287, in paragraph 69, as follows:
“69. However, Shri Viswanathan strongly relied upon the
observations made in para 32 in Thyssen [Thyssen Stahlunion
GmbH v. SAIL, (1999) 9 SCC 334] and the judgment in
Hameed Joharan v. Abdul Salam [Hameed Joharan v. Abdul
Salam, (2001) 7 SCC 573]. It is no doubt true that para 32
in Thyssen [Thyssen Stahlunion GmbH v. SAIL, (1999) 9 SCC
334] does, at first blush, support Shri Viswanathan’s stand.
However, this was stated in the context of the machinery for
enforcement under Section 17 of the 1940 Act which, as we
have seen, differs from Section 36 of the 1996 Act, because of
the expression “in relation to arbitral proceedings”, which took in
the entire gamut, starting from the arbitral proceedings before
the Arbitral Tribunal and ending up with enforcement of the
award. It was also in the context of the structure of the 1940 Act
being completely different from the structure of the 1996 Act,
which repealed the 1940 Act. ……”
Finally, however, this Court held that Section 36, as amended by the 2015
Amendment Act, should apply to Section 34 applications filed even before
the commencement of the 2015 Amendment Act.
74
53. Coupled with this, the expression “any proceedings”, occurring in
Section 9(1) and Section 17(1), would also be an expression
comprehensive enough to take in enforcement proceedings. The
expression “any” has been construed by some of the judgments of this
Court. Thus, in Shri Balaganesan Metals v. M.N. Shanmugham Chetty,
(1987) 2 SCC 707, in context of Section 10(3)(c) of the Tamil Nadu
Buildings (Lease and Rent Control) Act, 1960, this Court held as follows:
“18. In construing Section 10(3)(c) it is pertinent to note that the
words used are “any tenant” and not “a tenant” who can be
called upon to vacate the portion in his occupation. The word
“any” has the following meaning:
“some; one of many; an indefinite number. One
indiscriminately or whatever kind or quantity.
Word ‘any’ has a diversity of meaning and may be
employed to indicate ‘all’ or ‘every’ as well as ‘some’ or
‘one’ and its meaning in a given statute depends upon the
context and the subject-matter of the statute.
It is often synonymous with ‘either’, ‘every’ or ‘all’. Its
generality may be restricted by the context;” (Black’s Law
Dictionary, 5th Ed.)
19. Unless the legislature had intended that both classes of
tenants can be asked to vacate by the Rent Controller for
providing the landlord additional accommodation, be it for
residential or non-residential purposes, it would not have used
the word “any” instead of using the letter “a” to denote a
tenant.”
75
Similarly, in Lucknow Development Authority v. M.K. Gupta, (1994) 1
SCC 243, this Court, while construing the word “service” under the
Consumer Protection Act, 1986, held as follows:
“4. What is the meaning of the word ‘service’? Does it extend to
deficiency in the building of a house or flat? Can a complaint be
filed under the Act against the statutory authority or a builder or
contractor for any deficiency in respect of such property. The
answer to all this shall depend on understanding of the word
‘service’. The term has variety of meanings. It may mean any
benefit or any act resulting in promoting interest or happiness. It
may be contractual, professional, public, domestic, legal,
statutory etc. The concept of service thus is very wide. How it
should be understood and what it means depends on the
context in which it has been used in an enactment. Clause (o)
of the definition section defines it as under:
“‘service’ means service of any description
which is made available to potential users and
includes the provision of facilities in connection with
banking, financing, insurance, transport, processing,
supply of electrical or other energy, board or lodging
or both, housing construction, entertainment,
amusement or the purveying of news or other
information, but does not include the rendering of
any service free of charge or under a contract of
personal service;”
It is in three parts. The main part is followed by inclusive clause
and ends by exclusionary clause. The main clause itself is very
wide. It applies to any service made available to potential users.
The words ‘any’ and ‘potential’ are significant. Both are of wide
amplitude. The word ‘any’ dictionarily means ‘one or some or
all’. In Black's Law Dictionary it is explained thus, “word ‘any’
has a diversity of meaning and may be employed to indicate ‘all’
or ‘every’ as well as ‘some’ or ‘one’ and its meaning in a given
statute depends upon the context and the subject-matter of the
statute”. The use of the word ‘any’ in the context it has been
76
used in clause (o) indicates that it has been used in wider
sense extending from one to all. …”
In Union of India v. A.B. Shah, (1996) 8 SCC 540, this Court, while
examining the purport of the expression “at any time” contained in one of
the conditions set by the Director General of Coal Mines in exercise of his
powers under the Coal Mines Regulations, 1957 read with the Mines Act,
1952, held as follows:
“12. If we look into Conditions 3 and 6 with the object and
purpose of the Act in mind, it has to be held that these
conditions are not only relatable to what was required at the
commencement of depillaring process, but the unstowing for
the required length must exist always. The expression “at any
time” finding place in Condition 6 has to mean, in the context in
which it has been used, “at any point of time”, the effect of
which is that the required length must be maintained all the
time. The accomplishment of object of the Act, one of which is
safety in the mines, requires taking of such a view, especially in
the backdrop of repeated mine disasters which have been
taking, off and on, heavy toll of lives of the miners. It may be
pointed out that the word ‘any’ has a diversity of meaning and
in Black's Law Dictionary it has been stated that this word may
be employed to indicate ‘all’ or ‘every’, and its meaning will
depend “upon the context and subject-matter of the statute”. A
reference to what has been stated in Stroud's Judicial
Dictionary Vol. I, is revealing inasmuch as the import of the
word ‘any’ has been explained from pp. 145 to 153 of the 4th
Edn., a perusal of which shows it has different connotations
depending primarily on the subject-matter of the statute and the
context of its use. A Bench of this Court in Lucknow
Development Authority v. M.K. Gupta [(1994) 1 SCC 243], gave
a very wide meaning to this word finding place in Section 2(o)
of the Consumer Protection Act, 1986 defining ‘service’.
(See para 4)”
77
54. Properly so read, the expressions “in relation to” and “any
proceedings” would include the power to enforce orders that are made
under Section 9(1), and are not limited to incidental powers to make interim
orders, as was suggested by Mr. Viswanathan. Thus, if an order under
Section 9(1) is flouted by any party, proceedings for enforcement of the
same are available to the court making such orders under Section 9(1).
These powers are, therefore, traceable directly to Section 9(1) of the Act –
which then takes us to the Code of Civil Procedure. Thus, an order made
under Order XXXIX Rule 2-A, in enforcement of an order made under
Section 9, would also be referable to Section 9(1) of the Arbitration Act.
55. Given the fact that the 2015 Amendment Act has provided in Section
17(1) the same powers to an arbitral tribunal as are given to a court, it
would be anomalous to hold that if an interim order was passed by the
tribunal and then enforced by the court with reference to Order XXXIX Rule
2-A of the Code of Civil Procedure, such order would not be referable to
Section 17. Section 17(2) was necessitated because the earlier law on
enforcement of an arbitral tribunal’s interim orders was found to be too
cumbersome. Thus, in Alka Chandewar v. Shamshul Ishrar Khan, (2017)
16 SCC 119, this Court referred to the earlier position as follows:
78
“8. Coming to Shri Rana Mukherjee’s submission that subsection (2) of Section 17 introduced by the 2015 Amendment
Act now provides for the necessary remedy against infraction of
interim orders by the Tribunal, suffice it to state that the Law
Commission itself, in its 246th Report, found the need to go one
step further than what was provided in Section 27(5) as
construed by the Delhi High Court [Sri Krishan v. Anand, 2009
SCC OnLine Del 2472 : (2009) 112 DRJ 657 : (2009) 3 Arb LR
447]. The Commission, in its Report, had this to say:
“Powers of Tribunal to order interim measures
46. Under Section 17, the Arbitral Tribunal has the
power to order interim measures of protection, unless the
parties have excluded such power by agreement. Section
17 is an important provision, which is crucial to the
working of the arbitration system, since it ensures that
even for the purposes of interim measures, the parties
can approach the Arbitral Tribunal rather than await
orders from a court. The efficacy of Section 17 is
however, seriously compromised given the lack of any
suitable statutory mechanism for the enforcement of such
interim orders of the Arbitral Tribunal.
47. In Sundaram Finance Ltd. [Sundaram Finance Ltd.
v. NEPC India Ltd., (1999) 2 SCC 479], the Supreme
Court observed that though Section 17 gives the Arbitral
Tribunal the power to pass orders, the same cannot be
enforced as orders of a court and it is for this reason only
that Section 9 gives the court power to pass interim
orders during the arbitration proceedings. Subsequently,
in Army Welfare Housing Organisation v. Sumangal
Services (P) Ltd., (2004) 9 SCC 619, the Court had held
that under Section 17 of the Act no power is conferred on
the Arbitral Tribunal to enforce its order nor does it
provide for judicial enforcement thereof.
48. In the face of such categorical judicial opinion, the
Delhi High Court attempted to find a suitable legislative
basis for enforcing the orders of the Arbitral Tribunal
under Section 17 in Sri Krishan v. Anand, 2009 SCC
OnLine Del 2472 : (2009) 112 DRJ 657 : (2009) 3 Arb LR
447 [followed in Indiabulls Financial Services Ltd. v.
79
Jubilee Plots & Housing (P) Ltd., 2009 SCC OnLine Del
2458]. The Delhi High Court held that any person failing to
comply with the order of the Arbitral Tribunal under
Section 17 would be deemed to be “making any other
default” or “guilty of any contempt to the Arbitral Tribunal
during the conduct of the proceedings” under Section
27(5) of Act. The remedy of the aggrieved party would
then be to apply to the Arbitral Tribunal for making a
representation to the court to mete out appropriate
punishment. Once such a representation is received by
the court from the Arbitral Tribunal, the court would be
competent to deal with such party in default as if it is in
contempt of an order of the court i.e., either under the
provisions of the Contempt of Courts Act or under the
provisions of Order 39 Rule 2-A of the Code of Civil
Procedure, 1908.
49. The Commission believes that while it is important
to provide teeth to the interim orders of the Arbitral
Tribunal as well as to provide for their enforcement, the
judgment of the Delhi High Court in Sri Krishan v. Anand,
2009 SCC OnLine Del 2472 : (2009) 112 DRJ 657 :
(2009) 3 Arb LR 447 is not a complete solution. The
Commission has, therefore, recommended amendments
to Section 17 of the Act which would give teeth to the
orders of the Arbitral Tribunal and the same would be
statutorily enforceable in the same manner as the orders
of a court. In this respect, the views of the Commission
are consistent with (though do not go as far as) the 2006
amendments to Article 17 of the UNCITRAL Model Law.”
(emphasis in original)
9. Pursuant to this 246th Report, sub-section (2) to Section 17
was added by the 2015 Amendment Act, so that the
cumbersome procedure of an Arbitral Tribunal having to apply
every time to the High Court for contempt of its orders would no
longer be necessary. Such orders would now be deemed to be
orders of the court for all purposes and would be enforced
under the Civil Procedure Code, 1908 in the same manner as if
they were orders of the court. Thus, we do not find Shri Rana
Mukherjee's submission to be of any substance in view of the
80
fact that Section 17(2) was enacted for the purpose of providing
a “complete solution” to the problem.”
56. It was to remedy this situation that Section 17(2) was introduced.
There is no doubt that the arbitral tribunal cannot itself enforce its orders,
which can only be done by a court with reference to the Code of Civil
Procedure. But the court, when it acts under Section 17(2), acts in the
same manner as it acts to enforce a court order made under Section 9(1). If
this is so, then what is clear is that the arbitral tribunal’s order gets enforced
under Section 17(2) read with the Code of Civil Procedure.
57. There is no doubt that Section 17(2) creates a legal fiction. This
fiction is created only for the purpose of enforceability of interim orders
made by the arbitral tribunal. To extend it to appeals being filed under the
Code of Civil Procedure would be a big leap not envisaged by the
legislature at all in enacting the said fiction. As a matter of fact, this Court,
in Paramjeet Singh Patheja v. ICDS Ltd., (2006) 13 SCC 322, dealt with
Section 36 of the Arbitration Act as it stood immediately before the 2015
Amendment Act (Section 36 as it then stood is the mirror image of Section
36(1) post amendment). In answering the question raised before it – as to
whether an arbitration award can be said to be a decree for the purpose of
Section 9 of the Presidency Towns Insolvency Act, 1909, this Court held:
81
“39. Section 15 of the Arbitration Act, 1899 provides for
“enforcing” the award as if it were a decree. Thus, a final award,
without actually being followed by a decree (as was later
provided by Section 17 of the Arbitration Act of 1940), could be
enforced i.e., executed in the same manner as a decree. For
this limited purpose of enforcement, the provisions of CPC were
made available for realising the money awarded. However, the
award remained an award and did not become a decree either
as defined in CPC and much less so far the purposes of an
entirely different statute such as the Insolvency Act are
concerned.
40. Section 36 of the Arbitration and Conciliation Act of 1996
brings back the same situation as it existed from 1899 to 1940.
Only under the Arbitration Act, 1940, was the award required to
be made a rule of court i.e., required a judgment followed by a
decree of court.
41. Issuance of a notice under the Insolvency Act is fraught with
serious consequences: it is intended to bring about a drastic
change in the status of the person against whom a notice is
issued viz. to declare him an insolvent with all the attendant
disabilities. Therefore, firstly, such a notice was intended to be
issued only after a regularly constituted court, a component of
the judicial organ established for the dispensation of justice,
has passed a decree or order for the payment of money.
Secondly, a notice under the Insolvency Act is not a mode of
enforcing a debt; enforcement is done by taking steps for
execution available under CPC for realising monies.
42. The words “as if” demonstrate that award and decree or
order are two different things. The legal fiction created is for the
limited purpose of enforcement as a decree. The fiction is not
intended to make it a decree for all purposes under all statutes,
whether State or Central.”
(emphasis supplied)
58. Mr. Viswanathan cited the judgment Rajasthan State Industrial
Development & Investment Corporation v. Diamond & Gem
Development Corporation Ltd., (2013) 5 SCC 470. Far from supporting
82
his contention that the legal fiction contained in Section 17(2) extends to
the filing of an appeal under the Code of Civil Procedure as enforcement
proceedings are different from interim orders, paragraph 26 states as
follows:
“VI. “As if”—Meaning of
26. The expression “as if” is used to make one applicable in
respect of the other. The words “as if” create a legal fiction. By
it, when a person is “deemed to be” something, the only
meaning possible is that, while in reality he is not that
something, but for the purposes of the Act of legislature he is
required to be treated that something, and not otherwise. It is a
well-settled rule of interpretation that, in construing the scope of
a legal fiction, it would be proper and even necessary to
assume all those facts on the basis of which alone such fiction
can operate. The words “as if” in fact show the distinction
between two things and, such words must be used only for
a limited purpose . They further show that a legal fiction must be
limited to the purpose for which it was created. [Vide
Radhakissen Chamria v. Durga Prosad Chamria [(1939-40) 67
IA 360 : (1940) 52 LW 647 : AIR 1940 PC 167], CIT v. S. Teja
Singh [AIR 1959 SC 352], Ram Kishore Sen v. Union of
India [AIR 1966 SC 644], Sher Singh v. Union of India [(1984) 1
SCC 107 : AIR 1984 SC 200], State of Maharashtra v. Laljit
Rajshi Shah [(2000) 2 SCC 699 : 2000 SCC (Cri) 533 : AIR
2000 SC 937], Paramjeet Singh Patheja v. ICDS Ltd. [(2006) 13
SCC 322 at p. 341, para 28] and CIT v. Willamson Financial
Services [(2008) 2 SCC 202].]”
(emphasis supplied)
The celebrated judgment in East End Dwellings Co. Ltd. v. Finsbury
Borough Council, 1952 AC 109 : (1951) 2 All ER 587 (HL) then follows in
83
paragraph 27, followed by another judgment of this Court in paragraph 28,
as follows:
“27. In East End Dwellings Co. Ltd. v. Finsbury Borough
Council [1952 AC 109 : (1951) 2 All ER 587 (HL)] this Court
approved the approach which stood adopted and followed
persistently. It set out as under: (AC p. 133)
“… The statute says that you must imagine a certain
state of affairs; it does not say that having done so, you
must cause or permit your imagination to boggle when it
comes to the inevitable corollaries of that state of affairs.”
28. In Industrial Supplies (P) Ltd. v. Union of India [(1980) 4
SCC 341] this Court observed as follows: (SCC p.351, para 25)
“25. It is now axiomatic that when a legal fiction is
incorporated in a statute, the court has to ascertain for
what purpose the fiction is created. After ascertaining the
purpose, full effect must be given to the statutory fiction
and it should be carried to its logical conclusion. The court
has to assume all the facts and consequences which are
incidental or inevitable corollaries to giving effect to the
fiction. The legal effect of the words ‘as if he were’ in the
definition of ‘owner’ in Section 3(n) of the Nationalisation
Act read with Section 2(1) of the Mines Act is that
although the petitioners were not the owners, they being
the contractors for the working of the mine in question,
were to be treated as such though, in fact, they were not
so.”
(emphasis supplied)
59. There can be no doubt that the legal fiction created under Section
17(2) for enforcement of interim orders is created only for the limited
purpose of enforcement as a decree of the court. To extend this fiction to
encompass appeals from such orders is to go beyond the clear intention of
the legislature. Mr. Salve’s argument in stressing the words “under the
84
Code of Civil Procedure” in Section 17(2), thus holds no water as a limited
fiction for the purpose of enforcement cannot be elevated to the level of a
genie which has been released from a statutory provision and which would
encompass matters never in the contemplation of the legislature.
60. In a recent judgment of this Court in Union of India v. Vedanta Ltd.,
(2020) 10 SCC 1, this Court held that a petition to enforce a foreign award,
made under Section 49 of the Arbitration Act, is governed by Article 137 of
the Limitation Act, 1963 and not by Article 136 of the said Act. This
conclusion was arrived at as follows:
“69. Section 36 of the Arbitration Act, 1996 creates a statutory
fiction for the limited purpose of enforcement of a “domestic
award” as a decree of the court, even though it is otherwise an
award in an arbitral proceeding [Umesh Goel v. H.P. Coop.
Group Housing Society Ltd., (2016) 11 SCC 313 : (2016) 3
SCC (Civ) 795]. By this deeming fiction, a domestic award is
deemed to be a decree of the court [Sundaram Finance
Ltd. v. Abdul Samad, (2018) 3 SCC 622 : (2018) 2 SCC (Civ)
593], even though it is as such not a decree passed by a civil
court. The Arbitral Tribunal cannot be considered to be a
“court”, and the arbitral proceedings are not civil proceedings.
The deeming fiction is restricted to treat the award as a decree
of the court for the purposes of execution, even though it is, as
a matter of fact, only an award in an arbitral proceeding. In
Paramjeet Singh Patheja v. ICDS Ltd., (2006) 13 SCC 322, this
Court in the context of a domestic award, held that the fiction is
not intended to make an award a decree for all purposes, or
under all statutes, whether State or Central. It is a legal fiction
which must be limited to the purpose for which it was created.
Paras 39 and 42 of the judgment in Paramjeet Singh Patheja v.
ICDS Ltd., (2006) 13 SCC 322] read as: (SCC pp. 345-46)
85
“39. Section 15 of the Arbitration Act, 1899 provides for
“enforcing” the award as if it were a decree. Thus a final
award, without actually being followed by a decree (as
was later provided by Section 17 of the Arbitration Act of
1940), could be enforced i.e. executed in the same
manner as a decree. For this limited purpose of
enforcement, the provisions of CPC were made available
for realising the money awarded. However, the award
remained an award and did not become a decree either
as defined in CPC and much less so far the purposes of
an entirely different statute such as the Insolvency Act are
concerned.
* * *
42. The words “as if” demonstrate that award and
decree or order are two different things. The legal fiction
created is for the limited purpose of enforcement as a
decree. The fiction is not intended to make it a decree for
all purposes under all statutes, whether State or Central.”
(emphasis in original)
* * *
“72. Foreign awards are not decrees of an Indian civil court. By
a legal fiction, Section 49 provides that a foreign award, after it
is granted recognition and enforcement under Section 48,
would be deemed to be a decree of “that court” for the limited
purpose of enforcement. The phrase “that court” refers to the
court which has adjudicated upon the petition filed under
Sections 47 and 49 for enforcement of the foreign award. In our
view, Article 136 of the Limitation Act would not be applicable
for the enforcement/execution of a foreign award, since it is not
a decree of a civil court in India.
73. The enforcement of a foreign award as a deemed decree of
the High Court concerned [as per the amended Explanation to
Section 47 by Act 3 of 2016 confers exclusive jurisdiction on the
High Court for execution of foreign awards] would be covered
by the residuary provision i.e. Article 137 of the Limitation Act. A
three-Judge Bench of this Court in Kerala SEB v. T.P.
Kunhaliumma [Kerala SEB v. T.P. Kunhaliumma, (1976) 4 SCC
634] held that the phrase “any other application” in Article 137
cannot be interpreted on the principle of ejusdem generis to be
86
applications under the Civil Procedure Code. The phrase “any
other application” used in Article 137 would include petitions
within the word “applications”, filed under any special
enactment. This would be evident from the definition of
“application” under Section 2(b) of the Limitation Act, which
includes a petition. Article 137 stands in isolation from all other
Articles in Part I of the Third Division of the Limitation Act,
1963.”
* * *
“77. The application under Sections 47 and 49 for enforcement
of the foreign award, is a substantive petition filed under the
Arbitration Act, 1996. It is a well-settled position that the
Arbitration Act is a self-contained code. [Fuerst Day Lawson
Ltd. v. Jindal Exports Ltd., (2011) 8 SCC 333 : (2011) 4 SCC
(Civ) 178; Kandla Export Corpn. v. OCI Corpn., (2018) 14 SCC
715 : (2018) 4 SCC (Civ) 664; Shivnath Rai Harnarain (India)
Co. v. Glencore Grain Rotterdam, 2009 SCC OnLine Del 3564 :
(2009) 164 DLT 197; Usha Drager (P) Ltd. v. Dragerwerk AG,
2009 SCC OnLine Del 2975 : (2010) 170 DLT 628; Sumitomo
Corpn. v. CDC Financial Services (Mauritius) Ltd., (2008) 4
SCC 91; Conros Steels (P) Ltd. v. Lu Qin (Hong Kong) Co. Ltd.,
2014 SCC OnLine Bom 2305 : (2015) 1 Arb LR 463 : (2015) 2
Bom CR 1] The application under Section 47 is not an
application filed under any of the provisions of Order 21 CPC,
1908. The application is filed before the appropriate High Court
for enforcement, which would take recourse to the provisions of
Order 21 CPC only for the purposes of execution of the foreign
award as a deemed decree. The bar contained in Section 5,
which excludes an application filed under any of the provisions
of Order 21 CPC, would not be applicable to a substantive
petition filed under the Arbitration Act, 1996. Consequently, a
party may file an application under Section 5 for condonation of
delay, if required in the facts and circumstances of the case.”
This judgment is, therefore, authority for the proposition that the fiction
created by Section 49 of the Arbitration Act is limited to enforcement of a
foreign award, with the important corollary that an application to enforce an
87
award is an application under the Arbitration Act and not an application
under Order XXI of the Code of Civil Procedure (in which case, such
application would have been governed by Article 136 of the Limitation Act
as an execution application under Order XXI, and not an application under
the residuary Article 137 of the Limitation Act). Mr. Salve’s attempt to
distinguish this judgment on the ground that Section 49 lays down an
entirely different procedure from the procedure to be followed for a
domestic award qua enforceability does not, in any manner, distinguish the
ratio of this judgment which is that an application to enforce a foreign award
is not under Order XXI of the Code of Civil Procedure but under the
Arbitration Act. Also, the deeming provision in Section 49, having reference
to a decree of “that Court”, which refers to the court which is satisfied that
the foreign award is enforceable, again, makes no difference to the
aforesaid ratio of the judgment.
61. Mr. Salve then painted a lurid picture of third parties being affected in
enforcement proceedings. No such third party is before us. As to a third
party, i.e., a party who is not a party to the arbitration agreement and to the
subject matter covered by the award and who is affected by an order made
in enforcement, we say nothing, leaving the question open to be argued on
the facts of a future case.
88
62. Mr. Salve then read the provisions of the New Zealand Arbitration Act,
1996, the Hong Kong Arbitration Ordinance (Cap. 209), the Singapore
Arbitration Act, 2001 as well as the Singapore International Arbitration Act,
1994, and the English Arbitration Act, 1996 to argue that in all the aforesaid
legislations, awards passed by an Emergency Arbitrator were expressly
included with varying provisions as to their enforcement. A contrast of these
legislations with the provisions of the Indian Arbitration Act, again, does not
take us very far, given the fact that we have, on a proper interpretation of
the said Act, held that an award/order by an Emergency Arbitrator would be
covered by Section 17 of the Arbitration Act, when properly read with other
provisions of the Act.
63. Mr. Salve and Mr. Viswanathan then argued that Section 36(1), which
is a pari materia provision with Section 17(2), must be contrasted with the
provisions of Section 36(3). They argued that there is a basic difference
between having “due regard to the provisions for grant of stay of a money
decree under the provisions of the Code of Civil Procedure” and
enforcement of an award “in accordance with the provisions of the Code of
Civil Procedure”. According to them, it is clear that the court granting a stay
under sub-sections (2) and (3) of Section 36 does so under the Arbitration
Act only having due regard to the provisions regarding grant of stay of a
89
money decree under the Code of Civil Procedure. By way of contrast, an
award is enforced in accordance with the provisions of the Code of Civil
Procedure and not under the Arbitration Act. It was also argued that Section
17(2) and Section 36(1) are instances of legislation by reference and not
legislation by incorporation.
64. The interpretation of Section 36 is not before us – the interpretation
of Section 17 read with Section 9 is. As far as Section 17 is concerned, as
has been pointed out by us hereinabove, the scheme qua interim orders
passed by an arbitral tribunal mirrors the scheme qua interim orders
passed by civil courts under Section 9. This vital difference between the
provisions of Section 17 read with Section 9 and as contrasted with Section
36 puts paid to this argument.
65. We will now deal with some of the judgments of this Court cited by
the learned counsel for the Respondents. They strongly relied upon the
judgment of the Delhi High Court in Daelim Industrial Co. Ltd. v.
Numaligarh Refinery Ltd., 2009 SCC OnLine Del 511 : (2009) 159 DLT
579 [“Daelim Industrial Co.”] for the proposition that enforcement
applications under Section 36 of the Arbitration Act are independent of
arbitral proceedings which culminate in an award. The Delhi High Court
90
held that since execution applications would be governed by Sections 38
and 39 of the Code of Civil Procedure, Section 42 of the Arbitration Act
cannot be held to apply and as a result, the courts mentioned in Sections
38 and 39 of the Code of Civil Procedure would have jurisdiction to execute
arbitral awards.
66. In Sundaram Finance Ltd. v. Abdul Samad, (2018) 3 SCC 622, this
Court, in paragraph 18, referred to Daelim Industrial Co. (supra) with
approval. The question which arose before this Court was posed thus:
“The divergence of legal opinion of different High Courts on the
question as to whether an award under the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as “the said Act”)
is required to be first filed in the court having jurisdiction over
the arbitration proceedings for execution and then to obtain
transfer of the decree or whether the award can be
straightaway filed and executed in the Court where the assets
are located is required to be settled in the present appeal.”
A Division Bench of this Court, after setting out the relevant provisions of
the Code of Civil Procedure and the Arbitration Act, then held:
“14. …… The aforesaid provision would show that an award is
to be enforced in accordance with the provisions of the said
Code in the same manner as if it were a decree. It is, thus, the
enforcement mechanism, which is akin to the enforcement of a
decree but the award itself is not a decree of the civil court as
no decree whatsoever is passed by the civil court. It is the
Arbitral Tribunal, which renders an award and the tribunal does
not have the power of execution of a decree. For the purposes
91
of execution of a decree the award is to be enforced in the
same manner as if it was a decree under the said Code.”
The judgment ultimately turned on Section 32 of the Arbitration Act, which
made it clear that after arbitral proceedings had been terminated, Section
42 of the Act would not apply. This being so, the question posed before the
Court was answered thus:
“20. We are, thus, unhesitatingly of the view that the
enforcement of an award through its execution can be filed
anywhere in the country where such decree can be executed
and there is no requirement for obtaining a transfer of the
decree from the court, which would have jurisdiction over the
arbitral proceedings.”
This judgment does not, in any manner, take the matter any further as it
does not advert to Section 17 of the Act at all and is on a completely
different point as to whether execution of an award can only be in the first
court which is approached under Section 42 of the Act or can be a
proceeding which can be filed and pursued in any court.
67. The learned counsel for the Respondents then relied upon the Full
Bench judgment of the Bombay High Court in Gemini Bay Transcription
Pvt. Ltd. v. Integrated Sales Service Ltd., 2018 SCC OnLine Bom 216 :
AIR 2018 Bom 89 (FB) [“Gemini Bay”] which dealt with the same question
and decided that Section 42 of the Act would not apply to enforcement
92
applications under the Act, which have to follow the drill of Sections 38 and
39 of the Code of Civil Procedure. The learned counsel for Amazon,
however, strongly relied upon judgments of the Bombay High Court in Jet
Airways (supra), Kakade Construction (supra), and Global Asia Venture
Co. v. Arup Parimal Deb, 2018 SCC OnLine Bom 13061. Since these
judgments deal with enforcement proceedings filed under Section 36 of the
Arbitration Act, we do not express any opinion on their correctness.
68. Mr. Salve then relied upon Punjab State Civil Supplies Corporation
Ltd. v. Atwal Rice & General Mills, (2017) 8 SCC 116. This judgment
dealt with objections to the enforcement of an arbitral award in execution.
In the course of dealing with the aforesaid objections, the Court observed:
“18. In other words, the arbitral award has been given the
status of a decree of the civil court and, therefore, it is enforced
like a decree of the civil court by applying the provisions of
Order 21 of the Code and all other provisions, which deal with
the execution of the decree of the civil court.”
This judgment again does not take the matter very much further. It does not
deal with Section 17 of the Act at all but deals with Section 36 which, as
has been pointed out by us, contains a scheme different from that
contained for enforcement of interim orders under Section 17.
93
69. We now come to the appeal provision in the Arbitration Act. There
can be no doubt that Section 37 is a complete code so far as appeals from
orders and awards made under the Arbitration Act are concerned. This has
further been strengthened by the addition of the non-obstante clause by the
Arbitration and Conciliation (Amendment) Act, 2019.
70. This Court, in Kandla Export Corporation v. OCI Corporation,
(2018) 14 SCC 715 [“Kandla Export”], held in the context of a Section 50
appeal as follows:
“20. Given the judgment of this Court in Fuerst Day
Lawson [Fuerst Day Lawson Ltd. v. Jindal Exports Ltd., (2011)
8 SCC 333 : (2011) 4 SCC (Civ) 178] , which Parliament is
presumed to know when it enacted the Arbitration Amendment
Act, 2015, and given the fact that no change was made in
Section 50 of the Arbitration Act when the Commercial Courts
Act was brought into force, it is clear that Section 50 is a
provision contained in a self-contained code on matters
pertaining to arbitration, and which is exhaustive in nature. It
carries the negative import mentioned in para 89 of Fuerst Day
Lawson [Fuerst Day Lawson Ltd. v. Jindal Exports Ltd., (2011)
8 SCC 333 : (2011) 4 SCC (Civ) 178] that appeals which are
not mentioned therein, are not permissible. This being the case,
it is clear that Section 13(1) of the Commercial Courts Act,
being a general provision vis-à-vis arbitration relating to appeals
arising out of commercial disputes, would obviously not apply to
cases covered by Section 50 of the Arbitration Act.
21. However, the question still arises as to why Section 37 of
the Arbitration Act was expressly included in the proviso to
Section 13(1) of the Commercial Courts Act, which is equally a
special provision of appeal contained in a self-contained code,
which in any case would be outside Section 13(1) of the
Commercial Courts Act. One answer is that this was done ex
94
abundanti cautela. Another answer may be that as Section 37
itself was amended by the Arbitration Amendment Act, 2015,
which came into force on the same day as the Commercial
Courts Act, Parliament thought, in its wisdom, that it was
necessary to emphasise that the amended Section 37 would
have precedence over the general provision contained in
Section 13(1) of the Commercial Courts Act. Incidentally, the
amendment of 2015 introduced one more category into the
category of appealable orders in the Arbitration Act, namely, a
category where an order is made under Section 8 refusing to
refer parties to arbitration. Parliament may have found it
necessary to emphasise the fact that an order referring parties
to arbitration under Section 8 is not appealable under Section
37(1)(a) and would, therefore, not be appealable under Section
13(1) of the Commercial Courts Act. Whatever may be the
ultimate reason for including Section 37 of the Arbitration Act in
the proviso to Section 13(1), the ratio decidendi of the judgment
in Fuerst Day Lawson [Fuerst Day Lawson Ltd. v. Jindal
Exports Ltd., (2011) 8 SCC 333 : (2011) 4 SCC (Civ) 178]
would apply, and this being so, appeals filed under Section 50
of the Arbitration Act would have to follow the drill of Section 50
alone.
22. This, in fact, follows from the language of Section 50 itself.
In all arbitration cases of enforcement of foreign awards, it is
Section 50 alone that provides an appeal. Having provided for
an appeal, the forum of appeal is left “to the Court authorised
by law to hear appeals from such orders”. Section 50 properly
read would, therefore, mean that if an appeal lies under the
said provision, then alone would Section 13(1) of the
Commercial Courts Act be attracted as laying down the forum
which will hear and decide such an appeal.
23. In fact, in Sumitomo Corpn. v. CDC Financial Services
(Mauritius) Ltd. [Sumitomo Corpn. v. CDC Financial Services
(Mauritius) Ltd., (2008) 4 SCC 91], this Court adverted to
Section 50 of the Arbitration Act and to Sections 10(1)(a) and
10-F of the Companies Act, 1956, to hold that once an appeal is
provided for in Section 50, the Court authorised by law to hear
such appeals would then be found in Sections 10(1)(a) and 10-
F of the Companies Act. The present case is a parallel instance
95
of Section 50 of the Arbitration Act providing for an appeal, and
Section 13(1) of the Commercial Courts Act providing the forum
for such appeal. Only, in the present case, as no appeal lies
under Section 50 of the Arbitration Act, no forum can be
provided for.”
* * *
“25. What is important to note is that it is Section 50 that
provides for an appeal, and not the letters patent, given the
subject-matter of appeal. Also, the appeal has to be adjudicated
within the parameters of Section 50 alone. Concomitantly,
where Section 50 excludes an appeal, no such appeal will lie.”
This judgment is, therefore, an authority for the proposition that the
Arbitration Act is a self-contained code on matters pertaining to arbitration,
which is exhaustive in nature. The appeal provision in that case (Section
50) was held to carry a negative import that only such matters as are
mentioned in the Section are permissible, and matters not mentioned
therein cannot be brought in. It was further held that what follows from this
is that the substantive provision of appeal is contained in Section 50 of the
Act, which alone must be read, Section 13(1) of the Commercial Courts
Act, 2015 being a general provision, which must give way to the specific
provision contained in Section 50.
71. Likewise, in Deep Industries Ltd. v. ONGC, (2020) 15 SCC 706, this
Court opined:
“15. Given the aforesaid statutory provision and given the fact
that the 1996 Act repealed three previous enactments in order
96
that there be speedy disposal of all matters covered by it, it is
clear that the statutory policy of the Act is that not only are timelimits set down for disposal of the arbitral proceedings
themselves but time-limits have also been set down for Section
34 references to be decided. Equally, in Union of India v.
Varindera Constructions Ltd. (2020) 2 SCC 111 : (2020) 1 SCC
(Civ) 277, dated 17-9-2018, disposing of SLP (C) No. 23155 of
2013, this Court has imposed the selfsame limitation on first
appeals under Section 37 so that there be a timely resolution of
all matters which are covered by arbitration awards.
16. Most significant of all is the non obstante clause contained
in Section 5 which states that notwithstanding anything
contained in any other law, in matters that arise under Part I of
the Arbitration Act, no judicial authority shall intervene except
where so provided in this Part. Section 37 grants a constricted
right of first appeal against certain judgments and orders and
no others. Further, the statutory mandate also provides for one
bite at the cherry, and interdicts a second appeal being filed
[see Section 37(2) of the Act].”
72. In BGS SGS SOMA JV v. NHPC, (2020) 4 SCC 234, this time, the
Court dealt with the maintainability of an appeal under Section 37 of the Act
in a case in which an application under Section 34 of the Act was ordered
to be transferred from a court which had no jurisdiction to a court which had
jurisdiction. In deciding this question, this Court referred copiously to
Kandla Export (supra) in paragraph 12. It then went on to decide:
“13. Given the fact that there is no independent right of appeal
under Section 13(1) of the Commercial Courts Act, 2015, which
merely provides the forum of filing appeals, it is the parameters
of Section 37 of the Arbitration Act, 1996 alone which have to
be looked at in order to determine whether the present appeals
were maintainable. Section 37(1) makes it clear that appeals
shall only lie from the orders set out in sub-clauses (a), (b) and
97
(c) and from no others. The pigeonhole that the High Court in
the impugned judgment [NHPC Ltd. v. Jaiparkash Associates
Ltd., 2018 SCC OnLine P&H 1304 : (2019) 193 AIC 839] has
chosen to say that the appeals in the present cases were
maintainable is sub-clause (c). According to the High Court,
even where a Section 34 application is ordered to be returned
to the appropriate court, such order would amount to an order
“refusing to set aside an arbitral award under Section 34”.
14. Interestingly, under the proviso to Section 13(1-A) of the
Commercial Courts Act, 2015, Order 43 CPC is also mentioned.
Order 43 Rule 1(a) reads as follows:
“1. Appeals from orders.— An appeal shall lie from
the following orders under the provisions of Section 104,
namely—
(a) an order under Rule 10 of Order 7 returning a plaint
to be presented to the proper court except where the
procedure specified in Rule 10-A of Order 7 has been
followed;”
This provision is conspicuous by its absence in Section 37 of
the Arbitration Act, 1996, which alone can be looked at for the
purpose of filing appeals against orders setting aside, or
refusing to set aside awards under Section 34. Also, what is
missed by the impugned judgment [NHPC Ltd. v. Jaiparkash
Associates Ltd., 2018 SCC OnLine P&H 1304 : (2019) 193 AIC
839] is the words “under Section 34”. Thus, the refusal to set
aside an arbitral award must be under Section 34 i.e. after the
grounds set out in Section 34 have been applied to the arbitral
award in question, and after the Court has turned down such
grounds. Admittedly, on the facts of these cases, there was no
adjudication under Section 34 of the Arbitration Act, 1996 — all
that was done was that the Special Commercial Court at
Gurugram allowed an application filed under Section 151 read
with Order 7 Rule 10 CPC, determining that the Special
Commercial Court at Gurugram had no jurisdiction to proceed
further with the Section 34 application, and therefore, such
application would have to be returned to the competent court
situate at New Delhi.”
98
This judgment is determinative of the issue before us as it specifically ruled
out appeals under Order XLIII Rule 1 of the Code of Civil Procedure when it
comes to orders being made under the Arbitration Act.
73. At this juncture, it is important to notice that Section 37 did not remain
untouched by the 2015 Amendment Act. As a matter of fact, a new category
of appeals was infused into the said provision by adding a new sub-section
(1)(a), which reads as follows:
“37. Appealable orders.—(1) Notwithstanding anything
contained in any other law for the time being in force, an appeal
shall lie from the following orders (and from no others) to the
court authorised by law to hear appeals from original decrees of
the Court passing the order, namely:—
(a) refusing to refer the parties to arbitration under Section 8;”
* * *
74. Despite Section 17 being amended by the same Amendment Act, by
making Section 17(1) the mirror image of Section 9(1) as to the interim
measures that can be made, and by adding Section 17(2) as a
consequence thereof, significantly, no change was made in Section 37(2)
(b) to bring it in line with Order XLIII, Rule 1(r). The said Section continued
to provide appeals only from an order granting or refusing to grant any
interim measure under Section 17. There can be no doubt that granting or
refusing to grant any interim measure under Section 17 would only refer to
99
the grant or non-grant of interim measures under Section 17(1)(i) and 17(1)
(ii). In fact, the opening words of Section 17(2), namely, “subject to any
orders passed in appeal under Section 37…” also demonstrates the
legislature’s understanding that orders that are passed in an appeal under
Section 37 are relatable only to Section 17(1). For example, an appeal
against an order refusing an injunction may be allowed, in which case subsection (2) of Section 17 then kicks in to enforce the order passed in
appeal. Also, the legislature made no amendment to the granting or
refusing to grant any measure under Section 9 to bring it in line with Order
XLIII, Rule 1(r), under Section 37(1)(b). What is clear from this is that
enforcement proceedings are not covered by the appeal provision.
75. However, learned counsel appearing on behalf of the Respondents
pressed into service a recent judgment of this Court in Chintels (India)
Ltd. v. Bhayana Builders (P) Ltd., (2021) 4 SCC 602. The precise
question that arose before this Court was as to when an application
seeking condonation of delay in filing an appeal is dismissed, whether this
would amount to “refusal to set aside an arbitral award” under Section 34
and thus be appealable under Section 37(1)(c) of the Act. In answering this
question, this Court referred to Section 37(1) of the Act and stressed the
fact that an application for setting aside an award must be in accordance
100
with sub-sections (2) and (3) of Section 34 – See paragraph 9. The Court
then set out Section 34(3) and opined:
11. A reading of Section 34(1) would make it clear that an
application made to set aside an award has to be in accordance
with both sub-sections (2) and (3). This would mean that such
application would not only have to be within the limitation period
prescribed by sub-section (3), but would then have to set out
grounds under sub-sections (2) and/or (2-A) for setting aside
such award. What follows from this is that the application itself
must be within time, and if not within a period of three months,
must be accompanied with an application for condonation of
delay, provided it is within a further period of 30 days, this Court
having made it clear that Section 5 of the Limitation Act, 1963
does not apply and that any delay beyond 120 days cannot be
condoned — see State of H.P. v. Himachal Techno Engineers
[State of H.P. v. Himachal Techno Engineers, (2010) 12 SCC
210 : (2010) 4 SCC (Civ) 605] at para 5.”
Coming to Section 37(1)(c), the Court then held:
“12. We now come to Section 37(1)(c). It is important to note
that the expression “setting aside or refusing to set aside an
arbitral award” does not stand by itself. The expression has to
be read with the expression that follows— “under Section 34”.
Section 34 is not limited to grounds being made out under
Section 34(2). Obviously, therefore, a literal reading of the
provision would show that a refusal to set aside an arbitral
award as delay has not been condoned under sub-section (3)
of Section 34 would certainly fall within Section 37(1)(c). The
aforesaid reasoning is strengthened by the fact that under
Section 37(2)(a), an appeal lies when a plea referred to in subsection (2) or (3) of Section 16 is accepted. This would show
that the legislature, when it wished to refer to part of a section,
as opposed to the entire section, did so. Contrasted with the
101
language of Section 37(1)(c), where the expression “under
Section 34” refers to the entire section and not to Section 34(2)
only, the fact that an arbitral award can be refused to be set
aside for refusal to condone delay under Section 34(3) gets
further strengthened.”
Unlike the language of Section 34, a literal reading of Section 17 would
show that the grant or non-grant of interim measures under Section 37(2)
(b) refers only to Section 17(1) of the Act. Also, in the context of Section
37(2)(b), the entirety of Section 17 was referred to when Sections 17 and
37 were first enacted in 1996. It is only by the 2015 Amendment Act that
Section 17 was bifurcated into two sub-sections. What is significant in this
context is that no corresponding amendment was made to Section 37(2)(b)
to include within its scope the amended Section 17, as has been pointed
out hereinabove. This judgment is also distinguishable and, therefore, does
not carry the Respondents’ argument any further.
76. The second question posed is thus answered declaring that no
appeal lies under Section 37 of the Arbitration Act against an order of
enforcement of an Emergency Arbitrator’s order made under Section 17(2)
of the Act. As a result, all interim orders of this Court stand vacated. The
102
impugned judgments of the Division Bench, dated 8
th February, 2021 and
22nd March, 2021, are set aside. The appeals are disposed of accordingly.
………………………………..J.
(R.F. Nariman)
………………………………..J.
(B.R. Gavai)
New Delhi.
August 06, 2021
103