LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Monday, August 24, 2020

National Green Tribunal has set aside the Environmental Clearance (‘EC’ for short) issued by the State Environment Impact Assessment Authority (‘SEIAA’ for short), Karnataka, in favour of the appellants through its order dated 10.01.2018. = remanded - It is thus evident that as on the date the impugned order was passed i.e. 03.02.2020 the final round of inspection had not been completed and as such the NGT did not have the benefit of the final report by the Joint Committee for making a factual determination, to arrive at a conclusion keeping in view the legal position. Though the report of the Joint Committee is presently placed before this Court, it would not be appropriate for this Court to advert to the details of the report and in that background take note of the rival contentions on merits since first appellate authority, based on the same has not made a factual determination so as to consider the correctness or otherwise of the same in an appeal of the present nature.

1
NON­REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1713 OF 2020
Wonder Projects Development Pvt. Ltd.
& Anr.             ..Appellant(s)
                                              Versus
Union of India & Ors.                            ..Respondent(s)
J U D G M E N T
1. The appellants are before this Court claiming to be
aggrieved   by   the   order   dated   03.02.2020   passed   by   the
National Green Tribunal, Principal Bench, New Delhi (‘NGT’
for short) in Appeal No. 54/2018.   The appellants herein
were arrayed as respondent Nos. 11 and 12 in the appeal
before the NGT.   By the order impugned herein, the NGT
has set aside the Environmental Clearance (‘EC’ for short)
issued   by   the   State   Environment   Impact   Assessment
CA No.1713 of 2020
2
Authority (‘SEIAA’ for short), Karnataka, in favour of the
appellants through its order dated 10.01.2018. 
2. The   brief   facts   are   that   the   appellants   herein   are
undertaking the construction of New High Rise Residential
Building.     The   project   is   being   undertaken   in   Survey
Nos.61/2, 62 and 63/2 of Kasavanahalli Village, Varthur
Hobli,   Bengaluru   East   Taluk,   Bengaluru   District.     The
construction is proposed on a plot area of 50,382.91 sq. m.
with total built up area of 1,28,193.9 sq.m.  In respect of the
said project the appellants had sought for issue of EC from
the SEIAA, Karnataka which is the Competent Authority in
that regard.  The SEIAA having considered the project report
of the appellants has granted the EC through its order dated
10.01.2018.   The respondent No.2 herein being aggrieved
that the construction being undertaken by the appellants
herein is in the buffer zone of the Kaikondarahalli Lake,
apart from being on the primary and secondary Rajkaluve
and, therefore, the area being eco­fragile had assailed the
EC granted in favour of the appellants by filing the appeal
before the NGT.   The appellants herein had appeared and
CA No.1713 of 2020
3
filed   their   objection   statements   denying   the   allegations
made in the appeal.   In addition to the appellants being
respondents   in   the   said   appeal,   the   Bruhat   Bengaluru
Mahangara   Palike   (‘BBMP’   for   short)   within   whose
jurisdiction the proposed project is being undertaken was
also one of the respondents in the appeal.  The BBMP had
filed   a   detailed   reply   dated   05.09.2019   and   had   in   fact
contended   that   the   project   is   illegal   and   they   have   also
issued the ‘stop work’ notice to the project proponent on
13.07.2018   since   there   is   violation   of   these   Zoning
Regulation of the Revised Master Plan – 2015.
3. Based on the pleadings since a factual determination
was   required   to   be   made   by   the   NGT,   the   NGT   also
constituted a Joint Committee comprising of the Central
Pollution   Control   Board   (‘CPCB’   for   short),   SEIAA,
Karnataka, State Pollution Control Board (‘KSPCB’ for short)
and   the   Ministry   of   Environment,   Forest   and   Climate
Change (‘MOEF&CC’ for short).  The said Joint Committee
was required to make a spot inspection and submit a report.
CA No.1713 of 2020
4
4. When   this   was   the   position   the   Joint   Committee
submitted one of its reports dated 23.09.2019 indicating the
details   of   the   property   situate   in   the   various   Survey
Numbers, the activity carried out therein and the remarks
relating to the violation if any in the buffer zone.  The NGT
on   taking   note   of   the   pleadings   of   the   parties,   more
particularly   the   reply   filed   by   the   BBMP   and   the   Joint
Committee Report dated 23.09.2019 has in that background
taken note of the decision rendered by this Court in the case
of Mantri Techzone Pvt. Ltd. Vs. Forward Foundation &
Ors.  2019 SCC Online SC 322 wherein it was ordered to
restore the buffer zones in terms of the zonal plan.  The NGT
in that regard has also taken note that the original buffer
zone as per zonal plan is 30 mtrs. around the lake and 50
mtrs. from middle of the Rajkaluves in the case of primary
Rajkaluves   and   25   mtrs.   in   the   case   of   secondary
Rajkaluves and 15 mtrs. in the case of tertiary Rajkaluves.
Resultantly the NGT has arrived at the conclusion that the
EC   could   not   have   been   granted   so   as   to   permit
construction in the buffer zone of the lake and drain by
CA No.1713 of 2020
5
imposing   conditions.     The   appellants   are   therefore
aggrieved.
5. Heard   Dr.   Abhishek   Manu   Singhvi,   learned   Senior
Counsel for the appellants, Mr. N. Venkatraman, learned
Additional   Solicitor   General,   Mr.   Darpan   for   respective
respondents and perused the appeal papers.
6. While reiterating the grounds urged in the appeal the
learned   Senior   Counsel   for   the   appellants  inter   alia
contended   that   the   very   manner   in   which   the   NGT   has
proceeded to decide the appeal is not justified.  Apart from
referring to the nature of the construction being put up by
the   appellants   it   was   contended   that   though   a   Joint
Committee had been appointed by the NGT and a report was
sought, the appeal was considered and disposed of despite
the report relating to the construction in the property in
question   not   being     available   with   the   NGT.     It   was
contended that as such the consideration made based on
the   report   dated   23.09.2019   is   not   justified   since   the
Committee   had   indicated   that   a   separate   report   will   be
submitted in respect of the instant project.   Though the
CA No.1713 of 2020
6
respective learned counsel for the respondents sought to
justify the order of NGT on merits by seeking to contend
that   there   is   violation   of   the   zoning   regulation   and   the
construction being put up by the appellants in the buffer
zone cannot be permitted and the learned Senior Counsel
for   the   appellants   while   seeking   to   controvert   the   said
position sought to refer to the project details, we are of the
opinion that the merits of the rival contentions relating to
the   permissibility   or   otherwise   of   the   project   need   not
engage our attention at this juncture.   We are of the said
opinion   for   the   reason   that   the   point   which   requires
consideration at the outset at this juncture is as to whether
the   entire   material   including   the   report   of   the   Joint
Committee which was relevant to consider the case of the
parties   herein   was   available   before   the   NGT   and   as   to
whether the NGT was justified in proceeding with the matter
in the manner as it has presently done.
7. In order to consider this aspect, a careful perusal of
the order dated 03.02.2020 impugned herein would disclose
that the reply filed by the BBMP is extensively extracted.  It
CA No.1713 of 2020
7
is no doubt true that contention has been urged by BBMP
with regard to the project not being permissible.  In the light
of the rival pleadings since the tribunal was to render a
factual   finding   the   report   by   the   Joint   Committee   after
making a spot inspection was necessary so as to assist the
NGT in arriving at a conclusion.   As indicated above, the
NGT   has   no   doubt   taken   note   of   one   of   the   reports
submitted by the Joint Committee dated 23.09.2019.  The
said   report   has   been   extracted   in   the   course   of   the
impugned order which refers to the existing properties in
Kaikondarahalli Lake buffer area and in the tabulated form
the survey number, activity and violation of buffer if any is
indicated   as   a   remark.     In   respect   of   certain   other
properties, the remarks have been made either with regard
to   there   being   no   violation   or   the   activity   not   being   a
permitted activity.   Insofar as the property bearing Survey
No.62 of Kasavanahalli Village which is one of the survey
numbers   wherein   the   project   of   the   appellants   is   being
developed, a reference is made and in the remark; it is
recorded as hereunder:
CA No.1713 of 2020
8
S.No
.
Activity Violation of Buffer
62 Godrej   by   name   “Wonder
Projects   Development   Pvt.
Ltd”   have   obtained
Environmental   Clearance
from SEIAA and consent for
establishment   from   KSPCB
and   for   establishment   of
residential apartment in Sy
Nos.61/2,   62   and   63/2.
There   is   Nala   within   the
project area which connects
Kasavanahalli   tank   to
Kaikondrahalli   Tank.
Project under construction.
Sy   No.62   and   63   falls
under Lake buffer area.
As   there   is   separate
O.A.602/2019   on   this
project, the same will be
inspected   by   the
committee   as   per   the
order dated 19.07.2019
and separate report will
be   submitted   by   the
committee.
   
            (emphasis
supplied)
 8. A   perusal   of   the   remark   extracted   and   emphasised
herein would indicate that a separate O.A. No.602/2019 is
also filed in respect of the instant project and the Committee
has indicated that a separate report will be submitted by it.
The   NGT   in   the   course   of   the   impugned   order   dated
03.02.2020 at para 7 has recorded that O.A. No.281/2019
and O.A. No.602/2019 which are also raised on an identical
issue are being contemporaneously disposed of by separate
orders.  The same would disclose that as on the date when
the   appeal   wherein   the   impugned   order   is   passed   was
CA No.1713 of 2020
9
disposed of along with O.A. No.602/2019 the report relating
to the project of the appellant was not available on record
before the NGT if the remarks extracted above are kept in
view, since the Joint Committee was yet to complete the
inspection.
9. In this regard it is to be noted that while ordering
notice   in   this   appeal   on   02.03.2020   the   parties   were
permitted   to   file   the   report   in   O.A.   No.602/2019   in   the
Registry of this Court.   The respondent No.7 herein along
with the affidavit has filed the report of the Joint Committee,
which at the outset indicates that it is with regard to the
project   relating   to   the   appellants   herein.     Further   on
referring to certain aspects relating to the project the details
of   the   inspection   carried  out   by   the  Joint   Committee   is
referred at Clause 6.0.  It is indicated therein that in order
to finalize the report the Joint Committee comprising of the
members whose details are indicated made another round of
inspection and meeting on 05.02.2020.   It is thus evident
that as on the date the impugned order was passed i.e.
03.02.2020   the   final   round   of   inspection   had   not   been
CA No.1713 of 2020
10
completed and as such the NGT did not have the benefit of
the final report by the Joint Committee for making a factual
determination, to arrive at a conclusion keeping in view the
legal position.  Though the report of the Joint Committee is
presently   placed   before   this   Court,   it   would   not   be
appropriate for this Court to advert to the details of the
report   and   in   that   background   take   note   of   the   rival
contentions on merits since first appellate authority, based
on the same has not made a factual determination so as to
consider the correctness or otherwise of the same in an
appeal of the present nature.
10. Presently since the report of the Joint Committee is
available in O.A. No.602/2019 relating to the same project,
the said report is required to be taken as a part of the
consideration of the Appeal No.54/2018 which is disposed
of through the impugned order by the NGT and a factual
determination   in   accordance   with   law   is   required   to   be
made.   To enable the same we find it appropriate to set
aside   the   impugned   order   dated   03.02.2020   and   restore
Appeal No.54/2018 to the file of the NGT so as to enable it
CA No.1713 of 2020
11
to reconsider the appeal by taking into consideration the
report   of   the   Joint   Committee   prepared   in   O.A.
No.602/2019, which shall be made available to the NGT by
respondent   No.7   herein.     It   is   made   clear   that   in   the
circumstances under which the order dated 03.02.2020 is
set aside, the validity or otherwise of the EC will remain
subject to the fresh decision that would be taken by the
NGT and the EC shall not stand revived at this juncture.
This Court has not expressed any opinion on merits and all
contentions are left open.
11. Taking note of the urgency indicated by the learned
Senior Counsel for the appellants we request the NGT to
dispose of the appeal after reconsideration within a period of
six weeks from the first date on which the parties appear
before the NGT.   For the said purpose the NGT shall on
receipt of this order indicate a date for appearance which
shall   be   voluntarily   ascertained   by   the   parties   herein
without expecting fresh notice to be issued by the NGT.  The
NGT shall also provide opportunity to all the parties to put
forth any additional documents or objections if any to the
CA No.1713 of 2020
12
report and thereafter consider the matter in accordance with
law. 
12. In the result, the appeal is allowed in part.  The order
dated 03.02.2020 is set aside and the matter is remitted to
the NGT to restore Appeal No.54/2018 and reconsider the
same in the manner indicated above.  No construction shall
be put up in the meanwhile. There shall be no order as to
costs.
13. Pending applications, if any, shall stand disposed of.
……………………………CJI.
                                     [S.A. BOBDE]
……..………………………,J.
                                       [A.S. BOPANNA]
………….…………………,J.
                                                     [V. RAMASUBRAMANIAN]
New Delhi,
August 11, 2020
CA No.1713 of 2020