LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Friday, December 20, 2019

condonation of delay and lache - what should be considered = In the matter of condonation of delay and laches, the well accepted position is also that the accrued right of the opposite party cannot be lightly dealt with. In that regard, rather than taking note of the hardship that would be caused to the respondent No.13 as contended by the learned Senior Counsel, what is necessary to be taken note is the manner in which the respondent No.11– DMRC has proceeded in the matter. The respondent No.11­ DMRC is engaged in providing the public transport and for the said purpose the Government through policy decision has granted approval to generate resources through property development and in that regard the development as earlier indicated, is taken up. Pursuant thereto the respondent No.11 has received a sum of Rs.218.20 crores from respondent No.13 as far back as in the year 2008. The said amount as indicated is used for its projects providing metro rail service to the commuting public. In such circumstance, if at this stage the inordinate delay is condoned unmindful of the lackadaisical manner in which the appellant has proceeded in the matter, it would also be contrary to public interest.

                REPORTABLE
             
   IN THE SUPREME COURT OF INDIA
   CIVIL APPELLATE JURISDICTION
   CIVIL APPEAL NOS.    9488­9489      OF 2019
   (Arising out of SLP (Civil) Nos.5581­5582 of 2019)
University of Delhi                 .…Appellant(s)
Versus
Union of India & Ors.              ….  Respondent(s)
J U D G M E N T
A.S. Bopanna,J.       
Leave granted.
2. These   appeals   have   been   preferred   by   the
appellant­University   of   Delhi   through   its   Registrar   to
challenge   the   common   judgment   and   order   dated
29.10.2018 whereby, the High Court of Delhi declined to
condone   the   delay   of   916   days   in   filing   the   appeal   to
challenge the judgment dated 27.04.2015 whereunder, the
learned   Single   Judge   had   dismissed   the   W.P   (C)
No.2743/2012 filed by the University of Delhi.
3. The challenge in the writ petition was, inter alia, to
the decision dated 12.5.2011 of the Delhi Development
Page 1 of 34
Authority (hereinafter referred to as the, “DDA” for short)
who had allowed respondent no.13­M/s Young Builders
(P) Ltd.  to construct a high­rise multistory group housing
society in the control zone of Zone­C in the University
campus, without any height restriction. The construction
permission was allowed on the plot leased out to the Delhi
Metro   Rail   Corporation   (hereinafter   referred   to   as   the,
“DMRC” for short) by permitting segregation of 2 hectares
as a separate entity from the total 3 hectares of land,
acquired for the metro station. 
4. The   principal   contentions   of   the   appellantUniversity on the merits of the challenge were as follows: 
a)  the permission sought by Respondent No. 13
(namely, M/s Young Builders Private Limited)
for   the   proposed   construction   of   a   group
housing society on the land originally owned by
the   Ministry   of   Defence   in   the   University
enclave   is   violative  of   the   MPD­2021  and   is
against the larger public interest, given the fact
that the project site in question and its vicinity
are within the North Campus of the University
and   that   it   contains   various   historical   and
archaeological   buildings,   apart   from   it   being
Page 2 of 34
the centre of higher education and advanced
learning; and
b)   the change in the character of the subject land
is impermissible in law, since the land having
been   acquired   for   public   purpose   for
construction   of   the   metro   rail   project,   has
suddenly been diverted to private commercial
use   and   auctioned   to   private   builder   for
building a group housing society in a manner
contrary   to   the   purpose   and   charter   of
incorporation   of   the   Delhi   Metro   Rail
Corporation (DMRC)
c)     The restriction on certain developments for
Metro Station prescribed under Master Plan of
Delhi   –   2021   (‘MPD’   for   short)   was   also   a
contention raised by the writ petitioner which
imposed   ban   on   construction   of   high­rise
buildings   in   the   control   zone   of   the   Delhi
University.     The   location   of   various   ladies’
hostels of the University in close vicinity of the
proposed construction site was highlighted as
an important privacy concern. The impediment
to access of thousands of students, teachers at
the entrance of the University was the other
main contention raised in the writ petition. 
5.  On the other hand, the DMRC had projected that
after   construction   of   the   University   Metro   Station,   2
Page 3 of 34
hectares of land remained surplus and the housing project
was intended to generate revenue for the DMRC as per the
policy of the Government.  The formal application made to
the   authorities   for   change   of   land   use   and   approval
secured for conversion of the land for residential use, was
also highlighted by the DMRC.
6. The learned Single Judge having noticed the entire
sequence   refused   to   entertain   the   writ   petition   of   the
University including on the ground of delay and laches.  In
the   judgment   dated   27.04.2015   the   Court   however
observed that DDA is the master of the formulation and
implementation   of   the   Master   Plan   and,   necessary
approvals   have   been   taken   from   various   statutory
authorities for the housing project.  It was also observed
that   the   change   in   the   land   use   from   “public”   to
“residential” is permissible by adverting to the Delhi High
Court’s   Division   Bench   Judgment   in  Adil   Singh   vs.
Union  of   India  (2010) 171 DLT 748.   According to the
Writ court, since it was a policy decision taken by the
Government body and since the appellant­University has
Page 4 of 34
failed to demonstrate any illegality, impropriety, mala fide
in the decision making by the authority, interference of the
Court with the policy decision, would not be justified. 
7. It is the case of the appellant that following the
dismissal of the writ petition and being concerned about
the   future   use   of   the   subject   land,   the   University
Authorities constituted  a Committee  to recommend  the
appropriate course of action to be taken by the University.
The Committee’s report furnished on 11.11.2016 is stated
to   have   been   laid   before   the   Executive   Council   of   the
University and after due consideration of the report and
the judgment of the learned Single Judge, the Executive
Council of the University through their resolution dated
28.02.2017/07.03.2017 decided to prefer an intra­Court
Appeal in the High Court.
8. While the above deliberations were on, accessibility
concern to the University’s Metro Station area was raised
under the Rights of Persons with Disabilities Act, 2016 by
persons with disabilities.   The University also received a
report on preventive measures to be taken in the accidentprone area of the Metro Station. With these and other
Page 5 of 34
projection, the appeal in LPA No.89/2018 came to be filed
on 01.03.2018 after a delay of 916 days, together with the
C.M.No.8654/2018 for condonation of delay in filing the
appeal.
9.  The  delay of  916 days  caused  in preferring  the
Appeal   was   explained   in   the   application   seeking   delay
condonation   and   the   rejoinder   to   the   reply   to   said
application to the following effect;
(i) Non­convening of Executive Council and delay
occasioned   due   to   non­availability   of   ViceChancellor.   The   case   in   the   present   LPA   is
different from other routine litigation preferred or
contested by the appellant.   It is the only case
where, the approval from the Executive Council of
the University of Delhi was required to be taken
and before such approval, various deliberations
preceded so as to appraise the Executive Council
of   the   different   shades   of   the   subject   matter.
Being a statutory body, an adherence to the just
method of decision making requires consultations
with affected departments of the University itself
Page 6 of 34
and therefore, the final say in the matter rests
with the Executive Council which is constituted
under   Section   21   of   the   Delhi   University   Act,
1922.     The   Council   includes   the   senior   most
Deans,   democratically   elected   representatives   of
teachers, the Visitor’s nominee, the Registrar, and
the Vice­Chancellor. 
(ii)      The judgment of learned Single Judge was
sent by the Counsel representing the University
quite late and it was, then, place before the Legal
Cell of the University for examining the matter.
After going through the voluminous paper book, it
was opined that the matter be referred to the ViceChancellor   for   consideration   and   pursuant
thereto,   a   meeting   was   held,   wherein   it   was
decided that the matter needs to be dealt with
holistically, having regard to all the issues decided
and connotations thereof.   The issue could not be
taken up for consideration as the post of ViceChancellor   had   fallen   vacant   w.e.f.   28.10.2015
and could be considered only after the new VicePage 7 of 34
Chancellor had assumed office and taken stock of
things.   On 10.03.2016, the new Vice­Chancellor
joined the office and in order to ensure democratic
functioning   of   the   University,   he   decided   to
constitute   a   Committee   comprising   of   senior
faculty persons representing different sections of
the University. The terms of reference of the Fivemember   Committee   were,   to   recommend   the
course of action to the University in the light of
the   dismissal   of   the   Writ   Petition   filed   by   the
University in the DMRC matter. 
(iii)     On   11.11.2016,   the   above   constituted
Committee gave its Report. Based on the Report
of the five­member Committee, it was decided by
the Competent Authority that the subject matter
of the present case be referred to the Executive
Council of the University for its final decision. In
the   Executive   Council   meeting   held   on
28.02.2017, the matter was discussed. The item
was   again   discussed   in   the   Executive   Council
meeting   held   on   7.3.2017   (continued   meeting),
Page 8 of 34
where the members of the Council referred to the
earlier   discussions   and   decisions   of   both   the
Academic Council and the Executive Council with
respect to the same matter and it was decided
unanimously   to   prefer   an   Appeal   against   the
Order   of   the   learned   Single   Judge   dated
27.04.2015 after adequate preparation.
(iv)    In the meanwhile, reservation was strongly
put forth by the disabled students and faculty in
the light of the proposed project by the private
builder at the very main entrance of the University
of Delhi.  Such representations were received from
individuals as well as groups which the University
had to consider and were therefore forwarded to
the Equal Opportunity Cell for consideration. The
Equal Opportunity Cell, University of Delhi, which
looks after the welfare of disabled students and
others, in the light of the new enactment on the
Rights   of   Persons   with   Disabilities   Act,   2016,
analyzed   the   probable   outcome.   After   detailed
deliberations,   the   Equal   Opportunity   Cell
Page 9 of 34
submitted its Report on 28.04.2017 which was
brought to the notice of Competent Authorities for
their consideration. The Report was considered at
various   levels   of   the   University   including   the
Office   of   the   Dean,   Student   Welfare,   the
Department   of   legal   affairs,   the   Office   of   the
Proctor,   the   Engineering   Department,   and   the
Department   of   Environmental   Studies.   Holding
discussions and deliberations among these bodies
and considering their inputs involved further time
and it involved co­ordination and interaction with
various   authorities   and   stake   holders.   All   this
exercise involved a further period of five to six
months   before   a   considered   opinion   could   be
generated by the University of Delhi. Hence the
representations   and   the   Report   of   the   Equal
Opportunity Cell could be finally considered by
the University of Delhi around the end of year
2017.
(v)      In the interregnum, the accidents occurred
at Chhatra Marg in December 2017 led to the
Page 10 of 34
need for the preparation of a Report by the Office
of the Proctor of the University dated 05.02.2018
wherein the Proctor recommended the area to be
declared as accident prone.   Both the Reports ­
one by the Equal Opportunity Cell and the other
by the Office of Proctor ­­ were sent to the Counsel
concerned   who   was   holding   the   brief   for   the
preparation   of   the   Appeal   memorandum.   
Subsequently legal opinion was sought and the
draft appeal and petition was prepared which was
thereafter   got   vetted   and   settled   by   the   Senior
Counsel. The finalized Appeal was thereafter again
considered at the highest level at the University to
take the final decision, which entailed some time.
On 01.03.2018, the LPA was filed before the Delhi
High Court.
10. The above explanation for the delayed filing was
however not accepted and the Division Bench of the High
Court on 29.10.2018 dismissed the LPA on the ground of
delay without considering the merits of the appeal. Thus,
Page 11 of 34
aggrieved the appellant­University has filed this appeal.
11. Shri Mohan Parasaran, learned Senior Counsel for
the appellant submits that the implication of the rejection
of the writ petition and the LPA without considering the
substantial contention raised by the University on merits
would cause grave injury to the public institution.   The
learned   Senior   Counsel   submits   that   the   University
Authorities   have   been   pursuing   the   issue   with   due
diligence but decision had to be taken after consultation
with   all   the   stakeholders   and   therefore,   the   delay   in
preferring   the   LPA   should   not   be   attributed   to   any
inaction, much less a deliberate inaction.  The endeavor of
the Courts according to Shri Parasaran should be to do
substantial justice to the parties by deciding the matters
on merits but in the present case, neither the learned
Single Judge nor the Division Bench of the High Court had
considered   the   merit   of   the   contention   raised   by   the
appellant­University.     Shri   Parasaran   argues   that   the
expression “sufficient cause” is elastic enough to enable
the courts to apply the law of limitation in a meaningful
manner.  He also projects that since the builders are yet to
Page 12 of 34
start   their   construction,   the   delayed   filing   of   the   LPA
should   not   have   resulted   in   non­consideration   of   the
contention on merits, as major public interest issues have
been raised in the present matter.   The learned Senior
Counsel argues that important questions effecting public
interest   cannot   be   defeated   on   technical   objection,
inasmuch   as   the   proposed   site   for   construction   was
originally owned by the Defence Ministry and the land was
acquired for public purpose at public expense but is now
sought to be given over to a private builder, for a profit
oriented   motive.     The   said   contentions   are   also
supplemented by Shri R. Venkataramani and Shri Ramji
Srinivasan, learned Senior Advocates.
12. Ms.   Meenakshi   Arora,   learned   Senior   Counsel
representing the applicants/intervenors submits that six
girl hostels are located near to the project site and if high
rise apartments are allowed to be constructed, the privacy
of the hostel residents would be compromised.  Ms. Arora
also   refers  to   the   letter  dated   25.10.1943  of   the   Joint
Secretary, Government of India, Department of Education
addressed to the Chief Commissioner of Delhi conveying
Page 13 of 34
the decision of the Government of India to ensure that no
tall   buildings   are   erected   inside   the   Delhi   University
Campus and also the necessity of protecting University
area, as an enclave.  The Senior Counsel then refers to the
Zonal Development Plan for Zone­“C” (Civil Lines Zone) of
the   DDA   as   approved   by   the   Ministry   of   Urban
Development   to   point   out   that   the   authorities   have
recognized   the   existence   of   number   of   old   historical
buildings of the colonial period within the Delhi University
Campus and effort should be made to convert the Delhi
University into an integrated Campus with restriction on
tall buildings.
13.       Shri   Shyam   Divan,   learned   Senior   Counsel   for
respondent   No.13­   M/s   Young   Builders     would   at   the
outset contend that though the learned Senior Counsel for
the   appellant   has   referred   to   the   merits   of   the   case,
keeping in view the position that the Division Bench of the
High Court has dismissed the LPA on the ground of delay
and   laches,   that   aspect   of   the   matter   would   require
consideration at the threshold.  He would assert that the
delay of 916 days is an inordinate delay of more than two
Page 14 of 34
and   a   half   years   and   in   such   event   the   principle   of
applying the usual test for “sufficient cause” would not
arise as it is not merely the number of days requiring
condonation but also amounts to laches in filing the writ
petition, as well as the LPA.   Mere contention that the
proceedings initiated by the appellant is in public interest
would   not   advance   the   case   inasmuch   as   the   learned
Single   Judge   having   adverted   to   all   these   aspects   has
arrived at the conclusion that the petition suffers from
laches in addition to there being no merit and in such
circumstance when the LPA was once again delayed by
916   days   the   Division   Bench   was   justified   in   its
conclusion.   It is pointed out that the said delay of 916
days is as against the period of 30 days which is allowed
in law for filing the LPA.  It is contended that the cause of
action if any should be construed on 23.09.2005 when the
area was converted into residential, but the writ petition
was filed only on 07.05.2012 and despite the writ petition
having been disposed of on 27.04.2015 the LPA was filed
only on 01.03.2018 after a delay of 916 days.  The reason
assigned that a decision to file the LPA could not be taken
Page 15 of 34
as   the   office   of   Vice­Chancellor   had   fallen   vacant   also
cannot   be   accepted   since   such   vacancy   arose   only   on
28.10.2015   while   the   writ   petition   had   already   been
disposed of on 27.04.2015 and there was sufficient time to
file the LPA if they had the intention to do so.  The learned
Senior Counsel further refers to the large number of cases
that was filed on behalf of the University during the said
period.  It is contended that while considering condonation
of delay the prejudice that would be caused to the opposite
side is also one of the aspects to be considered.   If that
situation is kept in view, in the instant case the request
for proposal in favour of the respondent No.13 was notified
on 23.06.2008 and the Letter of Acceptance was issued on
13.08.2008 and the lease being for 90 years, already 11
years have passed and by such belated proceedings the
project is prejudicially hampered.  The respondent No.13
has already spent Rs.233 crores being the lease amount
paid   to   the   DMRC   and   also   for   securing   appropriate
approvals.  It is contended that the respondent No.13 had
to face earlier litigation as well which has been taken note
by the learned Single Judge and the respondent cannot be
Page 16 of 34
exposed to such repeated litigations.
14. Shri Tushar Mehta, the learned Solicitor General
appearing   on   behalf   of   respondent   No.11­DMRC,   has
contended that the Ministry of Urban Development as a
matter of Policy of the Government of India had permitted
the   DMRC   to   generate   its     own   resources   through
property development and has accordingly permitted to
carry out property development on the land transferred to
it by the Government.  In such event when the DMRC has
taken such steps not only in the instant case but also in
several other projects, any interference at this stage more
particularly   when   there   is   belated   challenge   of   the
present nature, it would have a serious impact on the
projects   undertaken.     It   was   submitted   that   due   to
certain   changes   affected   in   the   manner   in   which   the
Metro Rail Project was to be implemented there was some
excess   land   which   has   been   put   to   use   to   generate
resources for the project and in that regard when there is
a contractual relationship with respondent No.13 if the
much belated petition is entertained at this stage, there
would be a great financial impact which is also a loss to
Page 17 of 34
the   public   exchequer   and   in   such   event   the   public
interest  would  be better  served  by not  condoning the
delay in such matters.  Moreover, it is not a case of mere
delay in filing the LPA but is a serious case of laches. It is
also noticed by the learned Single Judge that the writ
petition itself was filed after 7­8 years and in such event
if the discretionary orders passed in the writ jurisdiction
is interfered in the limited jurisdiction of this Court, it
would set a bad precedent.
15. Shri A.N.S. Nandkarni, learned Additional Solicitor
General would also refer to the aspect of delay and laches
and supplement the arguments advanced by the learned
Solicitor General.   He would further contend that the
Union of India being the owner of the land which was
acquired does not have objection for the project and in
such event interference at the instance of the appellant
herein would not be justified. Ms. Binu Tamta, learned
Counsel submitted in support of the contentions raised
by the respondents.
Page 18 of 34
16. Shri Mohan Parasaran, learned Senior Counsel in
reply   to   the   said   contention   would   reiterate   the
contentions put forth relating to the explanation of delay
and would contend that the conclusion of the learned
Single Judge that the writ petition was hit by laches is
fallacious inasmuch as the respondent No.13 themselves
had   filed  a  writ   petition   raising   certain   disputes  with
regard to the limit of FAR through the Notification dated
20.01.2005 and such challenge by the respondent No.13
had come to an end on 18.05.2011 and the NOC etc.
were obtained subsequently, after which the writ petition
was filed by the appellant herein in the year 2012.  Hence
the delay and laches has been explained and it is not a
case of negligence.  It is contended that the stand of the
DMRC that it would be put to financial loss cannot be
accepted at this point since the question as to whether
they would be liable to pay interest or not are matters
which   would   have   to   be   considered   in   appropriate
proceedings.   Hence, he contends that the High Court
ought to have condoned the delay and the matter should
have been considered on its merits.
Page 19 of 34
17. Though   we   have   exhaustively   referred   to   the
pleadings and the contentions of the parties, including
contentions put forth on merits, the same is only for
completeness and to put the matter in perspective before
considering the issue relating to delay and laches.  In the
instant case, considering that the Division Bench of the
High Court has dismissed the LPA on the ground of delay
of  916  days,  that  aspect  of  the  matter  would   require
consideration at the outset and the facts on merits is
noted to the limited extent to find out whether in that
background the public interest would suffer.  The learned
Senior Counsel for the appellant in order to impress upon
this   Court   the   principle   relating   to   consideration   of
“sufficient cause” for condonation of delay and the factors
that are required to be kept in view, has relied on the
decision   in   the   case   of  Collector,   Land   Acquisition,
Anantnag  &  Anr.vs.  Katiji  &  Ors.,  1987(2) SCC 107
wherein it is held as hereunder:
“3. The legislature has conferred the power to
condone delay by enacting Section 5 [ Any
appeal or any application, other than an
application under any of the provisions of Order
XXI of the Code of Civil Procedure, 1908, may be
Page 20 of 34
admitted after the prescribed period if the
appellant or the applicant satisfies the court that
he had sufficient cause for not preferring the
appeal or making the application within such
period.] of the Indian Limitation Act of 1963 in
order to enable the courts to do substantial
justice to parties by disposing of matters on
”merits”. The expression “sufficient cause”
employed by the legislature is adequately elastic
to enable the courts to apply the law in a
meaningful manner which subserves the ends of
justice — that being the life-purpose for the
existence of the institution of courts. It is
common knowledge that this Court has been
making a justifiably liberal approach in matters
instituted in this Court. But the message does
not appear to have percolated down to all the
other courts in the hierarchy. And such a liberal
approach is adopted on principle as it is realized
that:
“1. Ordinarily a litigant does not stand to
benefit by lodging an appeal late.
2. Refusing to condone delay can result in a
meritorious matter being thrown out at the very
threshold and cause of justice being defeated. As
against this when delay is condoned the highest
that can happen is that a cause would be
decided on merits after hearing the parties.
3. “Every day's delay must be explained” does
not mean that a pedantic approach should be
made. Why not every hour's delay, every
second's delay? The doctrine must be applied in
a rational common-sense pragmatic manner.
4. When substantial justice and technical
considerations are pitted against each other,
cause of substantial justice deserves to be
preferred for the other side cannot claim to have
vested right in injustice being done because of a
non-deliberate delay.
5. There is no presumption that delay is
occasioned deliberately, or on account of
culpable negligence, or on account of mala fides.
A litigant does not stand to benefit by resorting
to delay. In fact he runs a serious risk.
6. It must be grasped that judiciary is
respected not on account of its power to legalize
injustice on technical grounds but because it is
Page 21 of 34
capable of removing injustice and is expected to
do so.
Making a justice-oriented approach from this
perspective, there was sufficient cause for
condoning the delay in the institution of the
appeal. The fact that it was the “State” which
was seeking condonation and not a private party
was altogether irrelevant. The doctrine of
equality before law demands that all litigants,
including the State as a litigant, are accorded
the same treatment and the law is administered
in an even-handed manner. There is no warrant
for according a step-motherly treatment when
the “State” is the applicant praying for
condonation of delay. In fact experience shows
that on account of an impersonal machinery (no
one in charge of the matter is directly hit or hurt
by the judgment sought to be subjected to
appeal) and the inherited bureaucratic
methodology imbued with the note-making, filepushing and passing-on-the-buck ethos, delay on
its part is less difficult to understand though
more difficult to approve. In any event, the State
which represents the collective cause of the
community, does not deserve a litigant-nongrata status. The courts therefore have to be
informed with the spirit and philosophy of the
provision in the course of the interpretation of
the expression “sufficient cause”. So also the
same approach has to be evidenced in its
application to matters at hand with the end in
view to do even-handed justice on merits in
preference to the approach which scuttles a
decision on merits. Turning to the facts of the
matter giving rise to the present appeal, we are
satisfied that sufficient cause exists for the
delay. The order of the High Court dismissing the
appeal before it as time-barred, is therefore, set
aside. Delay is condoned. And the matter is
remitted to the High Court. The High Court will
now dispose of the appeal on merits after
affording reasonable opportunity of hearing to
both the sides.”
Page 22 of 34
18. Further the decision in the case of   M/s   Dehri
Rohtas   Light   Railway   Company   Ltd.   Vs.   District
Board, Bhojpur & Ors. (1992) 2 SCC 598 is relied upon,
wherein   this   Court   has   indicated   the   real   test   to
determine the delay is that the petitioner should come to
Court before a parallel right is created and that the lapse
of time is not attributable to any laches or negligence.
19.  The learned Senior Counsel for respondent No.13, on
the other hand, has relied upon the decision in the case
of   Postmaster General & Ors. vs. Living Media India
Limited & Anr. 1992 (3) SCC 563 wherein it is held as
hereunder:
“28. Though we are conscious of the fact that in
a matter of condonation of delay when there was
no gross negligence or deliberate inaction or lack
of bona fides, a liberal concession has to be
adopted to advance substantial justice, we are of
the view that in the facts and circumstances, the
Department cannot take advantage of various
earlier decisions. The claim on account of
impersonal machinery and inherited
bureaucratic methodology of making several
notes cannot be accepted in view of the modern
technologies being used and available. The law
of limitation undoubtedly binds everybody,
including the Government.
Page 23 of 34
29. In our view, it is the right time to inform all
the government bodies, their agencies and
instrumentalities that unless they have
reasonable and acceptable explanation for the
delay and there was bona fide effort, there is no
need to accept the usual explanation that the file
was kept pending for several months/years due
to considerable degree of procedural red tape in
the process. The government departments are
under a special obligation to ensure that they
perform their duties with diligence and
commitment. Condonation of delay is an
exception and should not be used as an
anticipated benefit for the government
departments. The law shelters everyone under
the same light and should not be swirled for the
benefit of a few.”
20. From  a consideration  of the  view taken  by  this
Court through the decisions cited supra the position is
clear that, by and large, a liberal approach is to be taken
in the matter of condonation of delay.  The consideration
for condonation of delay would not depend on the status
of the party namely the Government or the public bodies
so   as   to   apply   a   different   yardstick   but   the   ultimate
consideration should be to render even­ handed justice to
the parties. Even in such case the condonation of long
delay should not be automatic since the accrued right or
the adverse consequence to the opposite party is also to
be   kept   in   perspective.       In   that   background   while
considering condonation of delay, the routine explanation
Page 24 of 34
would not be enough but it should be in the nature of
indicating “sufficient cause” to justify the delay which will
depend on the backdrop of each case and will have to be
weighed   carefully   by   the   Courts   based   on   the   fact
situation.     In   the   case   of  Katiji  (Supra)   the   entire
conspectus   relating   to   condonation   of   delay   has   been
kept in focus.  However, what cannot also be lost sight is
that the consideration therein was in the background of
dismissal of the application seeking condonation of delay
in   a   case   where   there   was   delay   of   four   days   pitted
against the consideration that was required to be made
on merits regarding the upward revision of compensation
amounting to 800 per cent.
21.  As against the same, the delay in the instant facts
in   filing   the   LPA   is   916   days   and   as   such   the
consideration to condone can be made only if there is
reasonable explanation and the condonation cannot be
merely because the appellant is public body. The entire
explanation noticed above, depicts the casual approach
unmindful of the law of limitation despite being aware of
Page 25 of 34
the position of law.   That apart when there is such a long
delay and there is no proper explanation, laches would
also come into play while noticing as to the manner in
which a party has proceeded before filing an appeal.   In
addition in the instant facts not only the delay and laches
in   filing   the   appeal   is   contended   on   behalf   of   the
respondents seeking dismissal of the instant appeal but
it is also contended that there was delay and laches in
filing the writ petition itself at the first instance from
which the present appeal had arisen.   In that view, it
would be necessary for us to advert to those aspects of
the matter and notice the nature of consideration made
in the writ petition as well as the LPA to arrive at a
conclusion as to whether the High Court was justified.
22. The entire explanation for the inordinate delay of
916 days is twofold, i.e. the non­availability of the ViceChancellor   due   to   retirement   and   subsequent
appointment of new Vice­Chancellor, also that the matter
was placed before the Executive Council and a decision
was taken to file the appeal and the said process had
Page 26 of 34
caused the delay.  The reasons as stated do not appear
very convincing since the situation was of availing the
appellate   remedy   and   not   the   original   proceedings
requiring   such   deliberation   when   it   was   a   mere
continuation of the proceedings which had already been
filed   on   behalf   of   the   appellant   herein,   after   due
deliberation.  Significantly, the Vice­Chancellor who was
at the helm of affairs when the writ petition was filed,
prosecuted and disposed of on 27.04.2015 was available
in the same office till 28.10.2015, for about six months
which was a long enough period as compared to 30 days
limitation period for filing appeal.  In that circumstance
when the said Vice­Chancellor who had prosecuted the
writ petition was available, the submission of the learned
Senior Counsel for the appellant that unseen hands are
likely   to   have   prevented   the   filing   of   the   appeal   also
cannot be accepted.  Secondly, the reason sought to be
put forth about the decision required to be taken by the
Executive Council is also not acceptable when it was just
the matter of filing the appeal.  In fact, in the writ petition
an affidavit was filed referring to Resolution No.56 and
Page 27 of 34
173   of   Academic   Council   and   Executive   Council
authorising for filing writ petition.  When the writ petition
was filed based on such authorisation and the stand of
the appellant, as the writ petitioner was put forth and
had failed in the writ petition, it cannot be accepted that
the appellant with all the wherewithal was unable to file
the appeal, that too when the same Vice­Chancellor was
available   for   six   months   after   dismissal   of   the   writ
petition.     Hence   the   reasons   put   forth   cannot   in   our
opinion constitute sufficient cause.
23. That   apart,   as   rightly   noticed   by   the   Division
Bench   in   the   LPA,   the   approval   from   the   Executive
Council was obtained on 28.02.2017 / 07.03.2017, the
appeal was ultimately filed on 01.03.2018 after an year
from   the   said   date   which   only   indicates   the   casual
approach which is now sought to be overcome with the
plea of public interest despite there being no explanation
for the delay at every stage.  It is true that as held in the
case of Mst. Katiji (supra) that every day’s delay need not
be explained with such precision but the fact remains
Page 28 of 34
that   a   reasonable   and   acceptable   explanation   is   very
much necessary.  The Division Bench apart from noticing
these   aspects   had   also   noted   that   the   learned   Single
Judge too found the writ petition to be hit by delay and
laches.
24. In   that   backdrop,   a   perusal   of   the   order   dated
27.04.2015 passed by the learned Single Judge would
indicate that the learned Single Judge in para – 65 of the
order with reference to his earlier observation has arrived
at   the   categorical   conclusion   that   the   petition   suffers
from laches and has been filed with delay of 7­8 years.
The   learned   Senior   Counsel   for   the   appellant   while
seeking to dispel such conclusion by the learned Single
Judge contended that the respondent No. 13 themselves
had filed a writ petition being aggrieved by the restricted
FAR   and  the  said  writ   petition   was  disposed  only   on
18.05.2011 and the need for the appellant herein to file
the   writ   petition   arose   only   thereafter.     The   said
contention is also not acceptable if the entire sequence is
noticed.
Page 29 of 34
25. In that regard there can be no dispute to the fact
that   the   Respondent   No.   13   being   aggrieved   by   the
decision   of   DDA   had   filed   a   petition   bearing   W.P.
No.3135/2010 assailing the letter dated 19.08.2009 and
the same was disposed of only on 18.05.2011 but the
appellant cannot take shelter under the same to explain
the laches.  This is because much water had flown under
the bridge before the said development and those events
ought   to   have   triggered   action   from   the   appellant   in
challenging, more so when there were other litigations
relating to the same subject, as noticed in the order of
the learned Single Judge.
26. In the present matter, the land was converted to
residential use in 2005 and Respondent No.11 – DMRC
had invited bids and public auction was conducted on
28.07.2008 which ought to have awakened the appellant
herein for the first time since the fact of conversion of the
land into residential development was in public domain
even if is assumed that the earlier process of approval
etc. by the DDA on the approval request of DMRC are
Page 30 of 34
internal process and not be known to the appellant.  In
fact, the learned Single Judge while taking note of the
challenge raised by the appellant herein has also taken
note of an earlier petition bearing W.P (C) No.8675/2011
filed by the Association of Metro Commuters wherein also
the residential development was an issue, which came to
be   dismissed   by   order   dated   14.02.2011.     Similarly,
another petition in W.P(C) No.6624­6625/2012, though
challenging the acquisition was filed, the same was also
dismissed.   Thereafter the writ petition of the appellant
filed in the year 2012 was pending till it was disposed on
27.04.2015.
27.   Despite   the   writ   petition   having   been   filed
belatedly   in   respect   of   certain   actions   which   had
commenced in the year 2005 and even though the writ
petition   was   filed   after   obtaining   approval   of   the
Executive Council, no steps were taken to file the writ
appeal for 916 days after disposal of the writ petition.  In
such circumstance, the cumulative effect of the delay and
laches cannot be ignored.  The decisions referred by the
Page 31 of 34
learned Senior Counsel for the appellant noted Supra
cannot, therefore, be applied in the present facts and
circumstance inasmuch as the consideration hereunder
was not merely the explanation for the delay of few days
in filing the appeal.  Though contention is put forth that
the delay is required to be condoned since public interest
is involved, the nature of the proceedings that have taken
place thus far would indicate that the matter has been
examined at different stages in the earlier litigations and
if the grounds on which the appellant was assailing the
action of the respondents were to be examined on merits,
they ought to have been more diligent in prosecuting the
matter before the Court. 
28. In the matter of condonation of delay and laches,
the well accepted position is also that the accrued right of
the opposite party cannot be lightly dealt with.  In that
regard,   rather   than   taking   note   of   the   hardship   that
would be caused to the respondent No.13 as contended
by the learned Senior Counsel, what is necessary to be
taken note is the manner in which the respondent No.11
Page 32 of 34
DMRC has proceeded in the matter. The respondent
No.11­   DMRC   is   engaged   in   providing   the   public
transport   and   for   the   said   purpose   the   Government
through policy decision has granted approval to generate
resources   through   property   development   and   in   that
regard the development as earlier indicated, is taken up.
Pursuant thereto the respondent No.11 has received a
sum of Rs.218.20 crores from respondent No.13 as far
back as in the year 2008.  The said amount as indicated
is used for its projects providing metro rail service to the
commuting public.  In such circumstance, if at this stage
the   inordinate   delay   is   condoned   unmindful   of   the
lackadaisical   manner   in   which   the   appellant   has
proceeded in the matter, it would also be contrary to
public interest. 
29.   Therefore,   taking   into   consideration   all   these
aspects of the matter, we are of the opinion that not only
the learned Single Judge was justified in holding that the
writ petition inter alia is hit by delay and laches but the
decision of the Division Bench in dismissing the LPA on
Page 33 of 34
the ground of delay of 916 days is also justified and the
orders do not call for interference. 
30. Accordingly,   the   appeals   being   devoid   of   merits
stand dismissed with no order as to costs.   All pending
applications shall stand disposed of. 
……………………….J.
(R. BANUMATHI)
……………………….J.
                                              (A.S. BOPANNA)
          ……………………….J.
                                                  (HRISHIKESH ROY)
New Delhi,
December 17, 2019
Page 34 of 34