LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Wednesday, November 13, 2019

Concept of economic duress- when the discharge/final and full settlement letter was excuted involutarly - he is entitled for appointment of arbitrator under sec.11[6] for ascertaing his claim The Oriental Insurance Co. Ltd (hereafter “the insurer” or “the appellant”) appeals the decision of a single judge of the Bombay High Court, who allowed the respondent’s application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereafter “the Act”) and appointed an arbitrator. - The insurer’s objection about maintainability of the application on the ground that the respondent (hereafter “Dicitex”) had signed the discharge voucher and accepted the amount offered, thus, signifying accord and satisfaction, which in turn meant that there was no arbitrable dispute, was rejected. Apex court held that An overall reading of Dicitex’s application (under Section 11(6)) clearly shows that its grievance with respect to the involuntary nature of the discharge voucher was articulated. It cannot be disputed, that several letters – spanning over two years­ stating that it was facing financial crisis on account of the delay in settling the claim, were addressed to the appellant. This court is conscious of the fact that an application under Section 11(6) is in the form of a pleading which merely seeks an order of the court, for appointment of an arbitrator. It cannot be conclusive of the pleas or contentions that the claimant or the concerned party can take, in the arbitral proceedings. At this stage, therefore, the court­ which is required to ensure that an arbitrable dispute exists, has to be prima facie convinced about the genuineness or credibility of the plea of coercion; it cannot be too particular about the nature of the plea, which necessarily has to be made and established in the substantive (read: arbitration) proceeding. If the court were to take a contrary approach and minutely examine the plea and judge its credibility or reasonableness, there would be a danger of its denying a forum to the applicant altogether, because rejection of the application would render the finding (about the finality of the discharge and its effect as satisfaction) final, thus, precluding the applicant of its right event to approach a civil court. There are decisions of this court (Associated Construction v Pawanhans Helicopters Ltd. (2008) 16 SCC 128 and Boghara Polyfab (supra) upheld the concept of economic duress. Having regard to the facts and circumstances, this court is of the opinion that the reasoning in the impugned judgment cannot be faulted.

Concept   of   economic   duress- when the discharge/final and full settlement  letter was excuted involutarly - he is entitled for appointment of arbitrator under sec.11[6] for ascertaing his claim 

The   Oriental   Insurance   Co.   Ltd   (hereafter   “the insurer” or “the appellant”) appeals the decision of a single judge of   the   Bombay   High   Court,   who   allowed   the   respondent’s
application   under   Section   11(6)  of   the   Arbitration   and Conciliation  Act, 1996 (hereafter  “the Act”)  and  appointed  an arbitrator. - The insurer’s objection about maintainability of the application   on   the   ground   that   the   respondent   (hereafter “Dicitex”) had signed the discharge voucher and accepted the amount offered, thus, signifying accord and satisfaction, which in turn meant that there was no arbitrable dispute, was rejected.
Apex court held that 
 An   overall   reading   of   Dicitex’s   application   (under Section 11(6)) clearly shows that its grievance with respect to the involuntary nature of the discharge voucher was articulated. It
cannot   be   disputed,   that   several   letters   –   spanning   over   two years­ stating that it was facing financial crisis on account of the delay in settling the claim, were addressed to the appellant. This
court is conscious of the fact that an application under Section 11(6) is in the form of a pleading which merely seeks an order of the   court,   for   appointment   of   an   arbitrator.   It   cannot   be
conclusive of the pleas or contentions that the claimant or the concerned party can take, in the arbitral proceedings. 
At this stage, therefore, the court­ which is required to ensure that an arbitrable dispute  exists, has to be  prima facie  convinced about the genuineness or credibility of the plea of coercion; it cannot be
too particular about the nature of the plea, which necessarily has to be made and established in the substantive (read: arbitration) proceeding. If the court were to take a contrary approach and
minutely   examine   the   plea   and   judge   its   credibility   or reasonableness, there would be a danger of its denying a forum to the applicant altogether, because rejection of the application
would render the finding (about the finality of the discharge and its effect as satisfaction) final, thus, precluding the applicant of its right event to approach a civil court. 
There are decisions of this   court   (Associated   Construction   v   Pawanhans   Helicopters
Ltd. (2008) 16 SCC 128 and Boghara Polyfab (supra) upheld the concept   of   economic   duress.   Having   regard   to   the   facts   and circumstances, this court is of the opinion that the reasoning in
the impugned judgment cannot be faulted. 
1
REPORTABLE
  IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.   8550  OF 2019
(ARISING OUT OF SLP (C) NO. 34186 OF 2015)
THE  ORIENTAL INSURANCE CO. LTD.
& ANR.   ...APPELLANTS
VERSUS
DICITEX FURNISHING LTD.                          ...RESPONDENT
                                                               
J U D G M E N T
S. RAVINDRA BHAT, J.
1. Leave granted. With the consent of counsel, the appeal was
heard   finally.   The   Oriental   Insurance   Co.   Ltd   (hereafter   “the
insurer” or “the appellant”) appeals the decision of a single judge
of   the   Bombay   High   Court,   who   allowed   the   respondent’s
application   under   Section   11(6)  of   the   Arbitration   and
Conciliation  Act, 1996 (hereafter  “the Act”)  and  appointed  an
2
arbitrator. The insurer’s objection about maintainability of the
application   on   the   ground   that   the   respondent   (hereafter
“Dicitex”) had signed the discharge voucher and accepted the
amount offered, thus, signifying accord and satisfaction, which in
turn meant that there was no arbitrable dispute, was rejected.
2. The  relevant facts in this appeal are that on 17.09.2011,
Dicitex obtained a Standard Fire and Special Peril Policy; it was
issued by the appellant to cover the stocks of goods lying in its
three separate godowns located at Thane, Maharashtra, by three
separate endorsements. The total sum insured was @  13 crores. ₹
Clause   13   of   the   terms   and   conditions   of   the   said   policy
contained an arbitration clause. On 25.05.2012, a fire broke out
at night on the ground floor of the building occupied by RFCL,
which fire spread to the first floor of the building and completely
engulfed all of the appellant’s three godowns which had stored its
goods. All the stocks in all the three godowns were completely
destroyed. Dicitex informed the appellant on 26.05.2012, about
the fire and the consequential loss. The appellant appointed M/s.
C.P. Mehta & Co. as Surveyors and Assessors to survey the loss
suffered by Dicitex and to report on the claim to be lodged upon
3
the insurer­appellant, by the said company. Dicitex lodged a total
and final claim upon the appellant for a sum of  14,88,14,327/­ ₹
comprising   13,52,85,752/­   towards   cost   of   the   materials ₹
destroyed and  1,35,28,575/­ as overheads. Dicitex claims also ₹
to   have   submitted   comprehensive   documentary   evidence   and
detailed work sheets in support of the claim made to the insurer.
On 14.08.2012, after visiting Dicitex’s factory and the godowns,
and after scrutinizing the materials submitted by it in support of
its claim, the Surveyor appointed by the insurer filed a Final
Survey Report recommending that the claim be settled for an
amount   of   12,93,26,704.98/­   and   that   after   deducting   an ₹
amount of 5% towards compulsory deduction for excess, a net
amount of  12,28,60,369/­ be paid over to Dicitex. The latter ₹
alleged that a copy of this survey report was not supplied to it, by
the insurer, or the surveyor.
3. On 20.09.2012, Dicitex addressed a letter to the appellant’s
chairman, informing him of the financial distress that it was
facing, requesting for settlement of the claim on priority basis.
Dicitex also informed him about a temporary loan obtained ­to
the tune of  10 crores­ from Union Bank of India for 3 months at ₹
4
a high rate of interest which was due for repayment in September
2012 and requested him that it would be a great financial help if
its claim could be settled on priority basis which would mitigate
their   hardship.   Again,   on   25.10.2012,   Dicitex   informed   the
insurer that the sale value of the goods destroyed was above  19 ₹
crores and that it had not only lost its goods but also its profits.
Dicitex   informed   that   it   had   already   submitted   all   the
documentary   evidence   supporting   the   claim   to   the   Surveyor,
M/s. C.P. Mehta & Co.,  yet another letter was addressed to the
appellant’s chairman on 31.10.2012 placing on record that it had
understood from the surveyor M/s. C.P. Mehta & Co. that the
Head Office of the appellant asked for some more information in
connection   with   the   claim.   Dicitex   stated   that   compiling,
organizing   and   sending   various   documents   totalling   around
35,000 in number, entailed voluminous work. It was stated that
the surveyor had already gone through those documents and had
picked   up   at   random,   sample   of   various   concerned   records.
Dicitex stated that it was arranging to compile the documents
and agreed to send them to the surveyor as soon as possible. In
other letters (dated 10.01.2012, 28.01.2013), again requests were
5
made to  the  insurer to  release  the  amounts.  Apparently, the
appellant appointed a Chartered Accountant (M/s Naveen Jhand
& Associates) to carry out a resurvey of the claim made by it
(Dicitex).   The   latter   had   already   furnished   37,700   documents
physically, which showed the exact quantity of furnishing fabrics
in meters. Dicitex brought to the notice of the Chairman­cumManaging Director that the new surveyors had asked for large
number of documents again and such documents could not be
supplied.  On   09.02.2013,   addressing   the   new   surveyor   M/s
Naveen   Jhand,   Dicitex   submitted   37,700   documents   and
submitted   further   documents   to   the   said   new   surveyor.   It
submitted   that   since   the   previous   9   months,   it   had   been
providing   different   documents/information   to   different   people
and submitted whatever was requested by the new surveyor in
broader form and requested them to submit their report at the
earliest.
4. In accordance with the format sent by the insurer and after
obtaining   Dicitex’s   signature,   a   cheque   for   3.5   crores   was ₹
handed   over   to   it.   Dicitex   signed   the   discharge   voucher   on
04.03.2013, when the insurer paid the said sum of  3.5 crores to ₹
6
Dicitex as 'on account payment' in the matter of its claim. Union
Bank of India endorsed the said discharge voucher. According to
Dicitex, all data that was requisitioned by the new surveyor, was
provided   by   it.   Several   meetings   took   place   between   the
representatives of the new surveyor, the appellant and Dicitex.
Dicitex,   mentioned   several   letters   to   the   appellant,   and   the
surveyor, in 2013 regarding the release of the amounts. Dicitex
had also stated that it felt strongly that the new surveyor was
just not satisfied with whatever was provided by it though all the
data it submitted had proved its genuine claim and the intention
of the new surveyor was to somehow reduce the claim. In other
letters (such as the one dated 21.02.2014), Dicitex informed the
appellant that the surveyor was refusing to commit to any fixed
date within which they would be submitting their report and also
the appellant’s officials had no answers to its questions with
regard to when its claim would be settled. Dicitex requested the
General Manager to set a deadline to settle their claim at the
earliest. It wrote several letters to the appellant’s officers about
the huge financial losses suffered by it due to delay in settlement
7
of the claim. Dicitex informed the General Manager to settle the
claim within 15 days.
5. On   27th  May,   2014,   Dicitex   received   an   email   from   the
appellant   stating   that   a   discharge   voucher   for   the   balance
amount of the claim payable as described was being enclosed. It
was   requested   to   execute   the   voucher   along   with   the   bank's
discharge on the space earmarked on the left side and send the
scanned   copy   back.  By   the   email   dated   28.05.2014,   Dicitex
replied to the email of 27.05.2014 and referred to the discharge
voucher sent by the appellant to it for signature. Dicitex placed
on record that its total claim was approximately  15 crores and ₹
the surveyor had assessed the same at approximately  12.93 ₹
crores. Dicitex stated that the basis for arriving at the figure of
₹7.16 crores was not explained (by the appellant). It requested
the   Regional   Manager   of   the   appellant   to   provide   the   claim
assessment working for their understanding to enable Dicitex to
take   up   the   matter   with   their   Board   of   Directors   for
consideration. The appellant, by email dated 29.05.2014, alleged
that M/s. C. P. Mehta & Co. had initially assessed the loss at
₹12,28,60,369/­. However, it had certain issues on the costing;
8
it, therefore, appointed M/s. Naveen Jhand and Associates to
have another look at the costing aspect and reconfirm/verify the
costing for loss assessment purpose. According to the said report
submitted by M/s. Naveen Jhand and Associates, the assessment
worked   to   7,16,30,148/­   and   accordingly,   the   competent ₹
authority   had   granted   the   claim.   The   appellant   enclosed   the
working of the claim and requested Dicitex to go through it and
send an unconditional discharge voucher duly signed by it and
the bankers. Dicitex, the insured did not do so and informed the
appellant that it had noticed that what was given was just a
statement   of   calculation,   without   explanation/basis,   that
adjustments had resultant deductions in Dicitex’s claim by more
than   50%   as   assessed   by   the   surveyor   appointed   by   the
appellant. Dicitex stated that since the appellant had taken 2
years to offer the final settlement of the claim, it (Dicitex) was
suffering from a huge financial constraint and had to pay bank
interest and installments, salaries and wages, hence, it was left
with   no   alternative   but   to   accept   the   offer   of   the   appellant
reluctantly   and   was   accordingly   sending   the   voucher   duly
discharged by Dicitex and their bankers for doing the needful.
9
Dicitex   alleged   that   since   the   appellant   did   not   relent,   and
insisted that any further payment would be made only if the
discharge voucher was executed exactly at the time and in the
form and manner as required by it as well as the letter dated
31.05.2014   was   withdrawn.   Dicitex   stated   that   as   it   was   in
urgent   need   of   funds   to   meet   its   mounting   liabilities,   it   was
coerced into withdrawing its earlier letter of 31.05.2014 and in
executing   the   discharge   voucher   exactly   as   dictated   by   the
respondents. By the letter dated 06.06.2014, addressed to the
Regional Manager, Dicitex withdrew the letter dated 31.05.2014
submitted along with the discharge voucher for a full and final
settlement of their claim. It requested the appellant to remit the
claim amount immediately. The discharge voucher was on the
letter head of the appellant, duly endorsed by Dicitex’s bankers.
In the discharge voucher, it was recorded that it accepted a sum
of  3,66,30,148/­ in full and final settlement of its claim. It was ₹
also recorded that Dicitex voluntarily gave discharge receipt in
full and final settlement of their claim, present or future, arising
directly/indirectly   in   respect   of   the   said   loss/accident   and
subrogated all their rights and remedies to appellant in respect of
10
the   loss/damages.   Further   correspondence   ensued   whereby
Dicitex   informed   the   appellant   that   since   there   was   a   huge
difference between the total amount claimed by it, and the final
claim settlement amount by the appellant, the same was required
to   be  discussed  and  resolved,  failing  which   Dicitex   would  be
required to invoke the arbitration, as per clause 13 of the terms
and conditions attached to the policy. The appellant, by the letter
dated   17.07.2014   addressed   to   Dicitex,   informed   that   it   was
surprised by the proposal to invoke arbitration after the clean
discharge voucher was signed for the sum of  7,16,30,148/­ in ₹
full and final settlement of the said loss. The respondents denied
that there existed any dispute of quantum in respect of the said
claim and contended that the amount due to Dicitex arising out
of   indemnity,   arising   from   the   policy   was   duly   verified   and
assessed   based   on   the   documents   submitted   by   Dicitex.   The
appellant did not agree to Dicitex’s request for any differential
amount or request for proceeding for arbitration under the policy.
On 24.07.2014, by a letter addressed to the appellant, Dicitex
denied that the amount received by it was a clean discharge
voucher in full and final settlement of their claim and reiterated
11
that it suffered a major loss of  14,16,94,329/­. The surveyor, ₹
M/s. C.P. Mehta & Co. had submitted their report assessing the
loss   at   12.93   crores.   Dicitex   also   placed   on   record   that   as ₹
against approximately the claim of   14.70 crores, the appellant ₹
released only  3.50 crores on 04.03.2013 i.e. almost 10 months ₹
after the loss had occurred, and after a lapse of 27 months, the
appellant made "a take it or leave it" offer of  7.16 crores towards ₹
full   and   final   settlement   of   their   claim,   the   discharge   was
accepted reluctantly by it. Dicitex alleged that upon meeting the
appellant’s officers, it was instructed to withdraw the letter of
protest and accept the claim settlement unconditionally which
was a proof of coercion.
6. The position taken by the appellant was that Dicitex was
paid   7,16,30,148/­   in   a   clean   discharge   and   full   and   final ₹
settlement of their claim and there existed no dispute with regard
to the quantum of claim and refused to appoint any arbitrator. In
these circumstances, Dicitex approached the Bombay High Court
under Section 11(6) of the Act, for appointment of an arbitrator.
Dicitex relied on the assessment of M/s C.P. Mehta & Co., which
had assessed the loss at  12.93 crores. It contended that the ₹
12
appellant released only   3.50 crores on 4.03.2013 i.e. almost 10 ₹
months after the loss suffered by Dicitex due to fire, and only
after a lapse of 27 months made "a take it or leave it" offer of
₹7.16 crores towards full and final settlement of their claim.
Dicitex stated that it had taken a loan of a substantial amount
and had to bear the extra burden of high interest and found itself
defaulting on timely loan repayments. It was further submitted
that Dicitex was unable to pay income tax on time, as a result of
which, it had to pay a sum of  23.90 lacs in the year 2012­2013 ₹
and   a   sum   of   11.10   lakhs   in   the   year   2013­2014   towards ₹
interest for  the delayed  payments  of income  tax. It  was also
argued, on behalf of Dicitex, that it was subjected to economic
duress   and   coercion   which   resulted   in   the   signing   of   the
discharge voucher, which could not preclude its invocation of the
arbitration agreement.
7. The   appellant   resisted   the   application,   contending   that
Dicitex   had   not   demonstrated   whether   the   second   discharge
voucher signed by it was under economical or financial duress
under the arbitration agreement. It was urged that since Dicitex
had  signed  the  discharge voucher and  accepted the  payment
13
made by the respondents unconditionally and confirmed that the
said payment was received in full and final settlement of their
claim, present or future, arising directly/indirectly in respect of
the   said   loss/accident   and   subrogated   all   their   rights   and
remedies to the appellant in respect of the loss/damages, there
exists no dispute between the parties which can be referred to
arbitration.   It   was   argued   that   Dicitex   having   signed   the
discharge voucher for  7,16,30,148/­ in full and final settlement ₹
due to alleged loss suffered by Dicitex, the arbitration application
was not maintainable. It was submitted that the appellant had
replied to the letter dated 21.06.2014 stating that Dicitex had
withdrawn   only   discharge   voucher   dated   31.05.2014.   The
appellant   also   stated   that  in   the   arbitration   agreement   itself,
Dicitex had to explain the exact correctness of the allegation of
coercion and duress with details and particulars about signing
the discharge voucher. It was further contended that though the
payment was received by Dicitex on 09.06.2014, it raised protest
only on 21.06.2014. Even in the letter dated 21st June 2014,
Dicitex referred to the discharge voucher dated 31.05.2014 which
was not admittedly acted upon by the insurer. Dicitex did not
14
resile from the discharge voucher dated 31.05.2014, and thus on
that ground also, this arbitration application is not maintainable.
8. The appellant relied on some decisions of this court (New
Indian Assurance Co. Ltd v Genus Power Infrastructure Ltd. (2015)
2 SCC 424.     National Insurance Co. Ltd v Boghara Polyfab Pvt
Ltd  (2009) 1 SCC 267;  Union of India (UOI) and Ors. v Master
Construction Co. (2011) 12 SCC 349 etc. 
9. In the impugned judgment, while allowing the application,
the single judge analysed the decisions of this court, including
Boghara   Polyfab  (supra).   It   was   noted   that   a   perusal   of   the
correspondence  prima   facie  indicated   that   the   first   surveyor
appointed by the insurer had recommended the payment of more
than   12   crores   in   favour   of   Dicitex.   For   some   reasons,   the ₹
appellant did not accept the said report submitted by their own
surveyor   and   instead   appointed   M/s   Naveen   Jhand   and
Associates   to   re­compute   the   costings.   It   was   also   held   that
Dicitex   had   furnished   more   than   37,700   documents   to   the
surveyor for their appraisal for submitting the report. Dicitex had
placed on record from time to time, documents to show that it
had taken loans from the banks who were pressurising it for
15
repayment of those loans and interest. The account of Dicitex
with   those   banks   had   drawn   the   excess   amount.   The   final
amount was sanctioned by the respondents only after 27 months
of  the   fire  having  taken  place,  which  caused  loss  to  Dicitex.
Dicitex had produced about 11 letters addressed by the banks to
Dicitex, calling upon Dicitex to regularize their bank accounts
and showing the excess amount drawn by it in various accounts.
Dicitex had also placed on record, the conduct of the second
surveyor,   who   was,   according   to   it,   demanding   several   other
documents which were unwarranted and/or already submitted
by it. The learned judge noticed that  prima facie,  Dicitex was
facing financial distress and economical duress and in view of its
various urgent business liabilities, it apparently signed the said
discharge   voucher   reluctantly.   It   is   not   in   dispute   that   the
appellant refused to accept such discharge voucher signed by
Dicitex   with   letter   of   protest.   Therefore,   a   few   days   later,   a
discharge   voucher   was   signed   by   Dicitex.   It   was,   however,
Dicitex’s case that the appellant had insisted upon it to sign a
clean discharge voucher and to withdraw the letter of protest
addressed by it, failing which, the insurer would not release the
16
amount, even that was reflected in the discharge voucher. Dicitex
thereafter   withdrew   the   letter   dated   31.05.2014,   and   signed
another   discharge   voucher.   After   signing   another   discharge
voucher, Dicitex placed on record their objection that the same
was signed due to pressure of the respondents.
10. In view of the analysis made, the single judge allowed the
application, observing as follows:
“57.   On   perusal   of   the   large   number   of
correspondence   exchanged   between   Dicitex   and
the respondents which were not disputed by the
respondents, in my prima facie view, it indicates
that   Dicitex   was   facing   the   financial   constraint
and economical and financial duress on the part
of the respondents in not sanctioning and paying
the final claim for 27 months from the date of fire.
Dicitex having faced pressure from their bankers
and   suffering   from   other   business   liabilities
including the demand of income tax department,
Dicitex was under the economical and financial
duress and the said discharge voucher thus, in
my prima facie view, cannot be considered as an
unconditional   discharge   voucher   thereby   Dicitex
giving up their claim in future arising out of the
said discharge voucher.
58. In my view, if Dicitex would not have signed
such   discharge   voucher   acknowledging   the
payment   of   the   lesser   amount   than   what   was
alleged to be due to Dicitex after 27 months of the
loss   suffered,   the   respondents   would   not   have
released even the said amount mentioned in the
discharge voucher. In my view, if according to the
17
respondents, Dicitex was not entitled to recover
the amount as claimed by Dicitex, but the lesser
amount, the respondents could have released the
amount as payable according to the respondents,
but   could   not   have   insisted   for   execution   of   a
discharge   voucher   as   a   pre­condition   before
releasing such payment.
59. Learned counsel for the respondents could not
refer to any provision in the insurance policy or
any other provision of law in support of their claim
that  the  respondents  were  entitled  to  insist  for
execution   of   such   discharge   voucher   before
releasing any payment in favour of Dicitex with a
confirmation   not   to   make   any   claim   in   future
arising out of the said claim. The Supreme Court
has already deprecated the practice followed by
the   government   departments,   statutory
corporations   and   government   companies   for
obtaining such undated discharge voucher as the
condition   for   releasing   lesser   amount   and   has
held that the said procedure is unfair, irregular
and   illegal.   Though   the   Chief   Justice   or   his
designate is empowered to decide the  issue as to
whether the parties had concluded the contract by
recording satisfaction of their mutual rights and
obligations   thereby   receiving   the   final   payment
without objection based on the affidavits and the
pleadings   or   can   leave   the   said   issue   to   be
decided by the arbitral tribunal, in my view, it
would be appropriate if the issue raised by the
respondents   that   Dicitex   had   signed   such
discharge voucher unconditionally and the issue
raised by Dicitex that the same was under duress
and   coercion   is   conclusively   decided   by   the
arbitral tribunal and if necessary, by leading oral
evidence.   The   learned   designate   of   the   Chief
Justice in case of M/s.Yasho Industries Pvt. Ltd.
Vs. The New India Assurance Company Limited in
18
Arbitration   Petition   No.314   of   2014   decided   on
24th June 2015 which is relied upon by one of the
party   has   taken   a   similar   view.   Special   Leave
Petition against the said order is rejected.
60. In so far as the issue of arbitrability of the
claim raised by the respondents on the ground
that Dicitex proposed to make the claim amount
higher than the insured sum is concerned, if any
claim higher than the insured sum is made by
Dicitex   before   the   arbitral   tribunal,   the
respondents can raise such issue of arbitrability
and   the   same   can   be   decided   by   the   arbitral
tribunal. The issue of arbitrability of claim on such
ground cannot be decided in these proceedings.
61. Clause 13 of the arbitration agreement of the
policy   which   provides   that   if   any   dispute   or
difference shall arise as to the quantum to be paid
under the policy, such difference shall be referred
to the decision of a sole arbitrator to be appointed
in writing by the parties or if they cannot agree
upon a single arbitrator within 30 days of any
party   invoking   arbitration,   the   same   shall   be
referred to a panel of three arbitrators. Since the
respondents   have   refused   to   appoint   any
arbitrator out of the names suggested by Dicitex in
their letter dated  14th   July  2014  and  had   not
suggested any other name, this application filed
under   Section   11   (6) of   the   Arbitration   Act   is
maintainable.   In   my   view,   the   arbitration
agreement exists between the parties.”
11. The appellant urges that the impugned judgment is
erroneous. It is pointed out that the effect of the decisions in
Boghara   Polyfab,   Master   Construction  and  Genus   Power
Infrastructure  (supra)   and   having   regard   to   the   facts
19
and circumstances of this case, there can be no question
that   any   arbitrable   dispute   existed   between   the   parties.
Having   accepted   the   proffered   amounts,   and   having
withdrawn the reservation and protest, Dicitex could not
have argued that it was subjected to coercion or that the
appellant   forced   it   to   sign   the   final   discharge   voucher.
Emphasis is placed on Dicitex’s letter dated 06.06.2014,
whereby it withdrew the previous letter dated 31.05.2014,
which had contained reservations about the amount offered
in full settlement.
12. Counsel for Dicitex urges that this court should not
interfere with the impugned judgment. It was urged that the
material   in   the   form   of   the   record,   particularly   the
consistent trend of letters, prior to the letter of 06.06.2014
as well as the correspondence after that, clearly reveal that
Dicitex was undergoing severe financial crisis and that the
prolonged process of settlement claim constrained it to issue
the said letter of 06.06.2014. However, the fact remained
that at the relevant time, it faced a crisis of existence. Its
acceptance   was   under   financial   compulsion   which
20
amounted   to   economic   coercion.   Therefore,   the   learned
single judge very properly analysed all these materials and
held that prima facie, there was no full and final settlement
or discharge.
Analysis & Conclusions
13. The main theme of the appellant’s argument in this
case is that Dicitex could not have invoked the arbitration
clause, since it had fully and finally accepted the amount
offered (i.e..) and withdrawn its protests and reservations,
by the letter dated 06.06.2014. It cites the decisions in
Boghara   Polyfab,   Master   Construction  and  Genus   Power
(supra) in this regard.
14. The   issue   of   the   court’s   jurisdiction   to   examine
whether   a   dispute   is   arbitrable,   in   the   context   of   no
objection certificates or discharge vouchers, was examined
in  Boghara Polyfab  for the first time. This court  in the
context of an application under Section 11(6) dealt with the
issue, holding that if there was accord and satisfaction due
to a no dues certificate, a reference under Section 11 was
not maintainable. It held, inter alia, that:
21
"51. Let us consider what a civil court would have
done in a case where the defendant puts forth the
defence of accord and satisfaction on the basis of
a full and final discharge voucher issued by the
plaintiff,   and   the   plaintiff   alleges   that   it   was
obtained by fraud/coercion/undue influence and
therefore not valid. It would consider the evidence
as to whether there was any fraud, coercion or
undue influence. If it found that there was none, it
will accept the voucher as being in discharge of
the   contract   and   reject   the   claim   without
examining the claim on merits. On the other hand,
if it found that the discharge voucher had been
obtained   by   fraud/undue   influence/coercion,   it
will   ignore   the   same,   examine   whether   the
plaintiff had made out the claim on merits and
decide the matter accordingly. The position will be
the   same   even   when   there   is   a   provision   for
arbitration.
52. Some illustrations (not exhaustive) as to when
claims   are   arbitrable   and   when   they   are   not,
when   discharge   of   contract   by   accord   and
satisfaction   are   disputed,   to   round   up   the
discussion on this subject:
(i) A claim is referred to a conciliation or a prelitigation Lok Adalat. The parties negotiate and
arrive at a settlement. The terms of settlement are
drawn  up and  signed  by both  the  parties  and
attested by the Conciliator or the members of the
Lok Adalat. After settlement by way of accord and
satisfaction,   there   can   be   no   reference   to
arbitration.
(ii) A claimant makes several claims. The admitted
or   undisputed   claims   are   paid.   Thereafter
negotiations   are   held   for   settlement   of   the
disputed   claims   resulting   in   an   agreement   in
writing   settling   all   the   pending   claims   and
disputes. On such settlement, the amount agreed
22
is paid and the contractor also issues a discharge
voucher/no claim certificate/full and final receipt.
After the contract is discharged by such accord
and   satisfaction,   neither   the   contract   nor   any
dispute survives for consideration. There cannot
be   any   reference   of   any   dispute   to   arbitration
thereafter.
(iii)   A   contractor   executes   the   work   and   claims
payment   of   say   Rupees   Ten   Lakhs   as   due   in
terms of the contract. The employer admits the
claim only for Rupees six lakhs and informs the
contractor either in writing or orally that unless
the contractor gives a discharge voucher in the
prescribed   format   acknowledging   receipt   of
Rupees Six Lakhs in full and final satisfaction of
the contract, payment of the admitted amount will
not   be   released.   The   contractor   who   is   hard
pressed for funds and keen to get the admitted
amount released, signs on the dotted line either in
a   printed   form   or   otherwise,   stating   that   the
amount is received in full and final settlement. In
such   a   case,   the   discharge   is   under   economic
duress on account of coercion employed by the
employer.   Obviously,   the   discharge   voucher
cannot be considered to be voluntary or as having
resulted  in  discharge  of  the  contract  by accord
and satisfaction. It will not be a bar to arbitration.
(iv) An insured makes a claim for loss suffered.
The claim is neither admitted nor rejected. But the
insured   is   informed   during   discussions   that
unless the claimant gives a full and final voucher
for a specified amount (far lesser than the amount
claimed by the insured), the entire claim will be
rejected.   Being   in   financial   difficulties,   the
claimant   agrees   to   the   demand   and   issues   an
undated   discharge   voucher   in   full   and   final
settlement.   Only   a   few   days   thereafter,   the
admitted   amount   mentioned   in   the   voucher   is
paid. The accord and satisfaction in such a case
23
is not voluntary but under duress, compulsion and
coercion. The coercion is subtle, but very much
real.   The   `accord'   is   not   by   free   consent.   The
arbitration agreement can thus be invoked to refer
the disputes to arbitration.
(v) A claimant makes a claim for a huge sum, by
way   of   damages.   The   respondent   disputes   the
claim.   The   claimant   who   is   keen   to   have   a
settlement   and   avoid   litigation,   voluntarily
reduces the claim and requests for settlement. The
respondent   agrees   and   settles   the   claim   and
obtains a full and final discharge voucher. Here
even   if   the   claimant   might   have agreed   for
settlement   due   to   financial   compulsions   and
commercial   pressure   or   economic   duress,   the
decision was his free choice. There was no threat,
coercion   or   compulsion   by   the   respondent.
Therefore, the accord and satisfaction is binding
and valid and there cannot be any subsequent
claim or reference to arbitration.
52. Let us now examine the receipt that has been
taken in this case. It is undated and is in a pro
forma   furnished   by   the   appellant   containing
irrelevant and inappropriate statements. It states:
"I/we hereby assign to the company, my/our right
to the affected property stolen which shall, in the
event   of   their   recovery,   be   the   property   of   the
company". The claim was not in regard to theft of
any property nor was the claim being settled in
respect of a theft claim. We are referring to this
aspect only to show how claimants are required to
sign on the dotted line, and how such vouchers
are   insisted   and   taken   mechanically   without
application of mind."
15. In Master Construction (supra), this Court held that:
24
"20. The Bench in Boghara Polyfab Private Limited
in paragraphs 42 and 43, with reference to the
cases cited before it, inter alia, noted that there
were   two   categories   of   the   cited   cases;   (one)
where the Court after considering the facts found
that there was a full and final settlement resulting
in   accord   and   satisfaction,   and   there   was   no
substance   in   the   allegations   of   coercion/undue
influence   and,   consequently,   it   was   held   that
there   could   be   no   reference   of   any   dispute   to
arbitration and (two) where the court found some
substance in the contention of the claimants that
`no   dues/claim   certificates'   or   `full   and   final
settlement discharge vouchers' were insisted and
taken (either in printed format or otherwise) as a
condition   precedent   for   release   of   the   admitted
dues   and   thereby   giving   rise   to   an   arbitrable
dispute.
21.   In   Boghara   Polyfab   Private   Limited,   the
consequences of discharge of the contract were
also considered. In para 25 (page 284), it was
explained   that   when   a   contract   has   been   fully
performed,   then   there   is   a   discharge   of   the
contract by performance and the contract comes to
an   end   and   in   regard   to   such   a   discharged
contract, nothing remains and there cannot be any
dispute   and,   consequently,   there   cannot   be
reference to arbitration of any dispute arising from
a   discharged   contract.   It   was   held   that   the
question   whether   the   contract   has   been
discharged   by   performance   or   not   is   a   mixed
question of fact and law, and if there is a dispute
in   regard   to   that   question,   such   question   is
arbitrable. The Court, however, noted an exception
to this proposition. The exception noticed is that
where both the parties to a contract confirm in
writing that the contract has been fully and finally
discharged by performance of all obligations and
there   are   no   outstanding   claims   or   disputes,
25
courts   will   not   refer   any   subsequent   claim   or
dispute to arbitration. Yet another exception noted
therein is with regard to those cases where one of
the parties to the contract issues a full and final
discharge voucher (or no­dues certificate, as the
case may be) confirming that he has received the
payment in full and final satisfaction of all claims,
and he has no outstanding claim. It was observed
that issuance of full and final discharge voucher
or   no­dues   certificate   of   that   kind   amounts   to
discharge   of   the   contract   by   acceptance   or
performance and the party issuing the discharge
voucher/certificate   cannot   thereafter   make   any
fresh claim or revive any settled claim nor can it
seek   reference   to   arbitration   in   respect   of   any
claim.
22. In paragraph 26 (pages 284­285), this Court in
Boghara   Polyfab   Private   Limited   held   that   if   a
party   which   has   executed   the   discharge
agreement or discharge voucher, alleges that the
execution of such  document was  on account of
fraud/coercion/undue influence practiced by the
other   party,   and   if   that   party   establishes   the
same, then such discharge voucher or agreement
is rendered void and cannot be acted upon and
consequently, any dispute raised by such party
would be arbitrable.
23.   In   paragraph   24   (page   284)   in   Boghara
Polyfab   Private   Limited,   this   Court   held   that   a
claim for arbitration cannot be rejected merely or
solely on the ground that a settlement agreement
or discharge voucher has been executed by the
claimant. The Court stated that such dispute will
have   to   be   decided   by   the   Chief   Justice/his
designate in the proceedings under Section 11 of
the 1996 Act or by the Arbitral Tribunal.
24. In our opinion, there is no rule of the absolute
kind. In a case where the claimant contends that
26
a   discharge   voucher   or   no­claim   certificate   has
been obtained by fraud, coercion, duress or undue
influence   and   the   other   side   contests   the
correctness   thereof,   the   Chief   Justice/his
designate must look into this aspect to find out at
least, prima facie, whether or not the dispute is
bona fide and genuine. Where the dispute raised
by   the   claimant   with   regard   to   validity   of   the
discharge   voucher   or   no­claim   certificate   or
settlement agreement, prima facie, appears to be
lacking in credibility, there may not be necessity
to refer the dispute for arbitration at all. It cannot
be overlooked that the cost of arbitration is quite
huge ­ most of the time, it runs in six and seven
figures. It may not be proper to burden a party,
who contends that the dispute is not arbitrable on
account of discharge of contract, with huge cost of
arbitration merely because plea of fraud, coercion,
duress or undue influence has been taken by the
claimant. A bald plea of fraud, coercion, duress or
undue influence is not enough and the party who
sets up such plea must prima facie establish the
same   by   placing   material   before   the   Chief
Justice/his   designate.   If   the   Chief   Justice/his
designate  finds   some  merit  in   the  allegation   of
fraud,   coercion,   duress   or   undue   influence,   he
may decide the same or leave it to be decided by
the Arbitral Tribunal. On the other hand, if such
plea is found to be an after­thought, make­believe
or lacking in credibility, the matter must be set at
rest then and there."
16. In Genus Power  (supra), the relevant observations of
this court are as follows:
"8. It is therefore clear that a bald plea of fraud,
coercion, duress or undue influence is not enough
and the party who sets up a plea, must prime
facie   establish   the   same   by   placing   material
27
before   the   Chief   Justice/his   designate.   Viewed
thus, the relevant averments in the petition filed
by the Respondent need to be considered, which
were to the following effect:
          **************                 *************
(g) That the said surveyor, in connivance with the
Respondent   Company,   in   order   to   make   the
Respondent Company escape its full liability of
compensating   the   Petitioner   of   such   huge   loss,
acted   in   a   biased   manner,   adopted   coercion
undue influence and duress methods of assessing
the loss and forced the Petitioner to sign certain
documents   including   the   Claim   Form.   The
Respondent Company also denied the just claim
of   the   Petitioner   by   their   acts   of   omission   and
commission and by exercising coercion and undue
influence and made the Petitioner Company sign
certain   documents,   including   a   pre­prepared
discharge   voucher   for   the   said   amount   in
advance,   which   the   Petitioner   Company   were
forced to do so in the period of extreme financial
difficulty which prevailed during the said period.
As stated aforesaid, the Petitioner Company was
forced to sign several documents including a letter
accepting the loss amounting to Rs. 6,09,55,406/­
and   settle   the   claim   of   Rs.   5,96,08,179/­   as
against   the   actual   loss   amount   of   Rs.
28,79,08,116/­   against   the   interest   of   the
Petitioner   company.   The   said   letter   and   the
aforesaid pre­prepared discharge voucher stated
that the Petitioner had accepted the claim amount
in full and final settlement and thus, forced the
Petitioner   company   to   unilateral   acceptance   the
same. The Petitioner company was forced to sign
the said document under duress and coercion by
the   Respondent   Company.   The   Respondent
Company   further   threatened   the   Petitioner
Company to accept the said amount in full and
final or the Respondent Company will not pay any
28
amount toward the fire policy. It was under such
compelling   circumstances   that   the   Petitioner
company was forced and under duress was made
to sign the acceptance letter.
9. In our considered view, the plea raised by the
Respondent   is   bereft   of   any   details   and
particulars, and cannot be anything but a bald
assertion. Given the fact that there was no protest
or demur raised around the time or soon after the
letter of subrogation was signed, that the notice
dated   31.03.2011   itself   was   nearly   after   three
weeks   and   that   the   financial   condition   of   the
Respondent was not so precarious that it was left
with   no   alternative   but   to   accept   the   terms   as
suggested,   we   are   of   the   firm   view   that   the
discharge in the present case and signing of letter
of subrogation were not because of exercise of any
undue influence. Such discharge and signing of
letter of subrogation was voluntary and free from
any   coercion   or   undue   influence.   In   the
circumstances, we hold that upon execution of the
letter   of   subrogation,   there   was   full   and   final
settlement of the claim. Since our answer to the
question,   whether   there   was   really   accord   and
satisfaction, is in the affirmative, in our view no
arbitrable dispute existed so as to exercise power
Under Section 11 of the Act. The High Court was
not therefore justified in exercising power Under
Section 11 of the Act."
17. In Velugubanti Hari Babu v. Parvathini Narasimha Rao
& Anr. (2016) 14 SCC 126, the line of judgments in Boghara
Polyfab   (supra)  was   followed.  Later, in  ONGC   Mangalore
29
Petrochemicals Ltd. v ANS Constructions Ltd. and Anr. (2018)
3 SCC 373, the court held as follows:
"24. From the materials on record, we find that the
contractee­ Company had issued the "No Dues/No
Claim Certificate" on 21.09.2012, it had received
the full amount of the final bill being Rs. 20.34
crores   on   10.10.2012   and   after   12   days
thereafter,   i.e.,   only   on   24.10.2012,   the
contractee­Company   withdrew   letter   dated
21.09.2012   issuing   "No   Dues/No   Claim
Certificate". Apart from it, we also find that the
Final Bill has been mutually signed by both the
parties to the Contract accepting the quantum of
work done, conducting final measurements as per
the Contract, arriving at final value of work, the
payments made and the final payment that was
required   to   be   made.   The   contractee­Company
accepted   the   final   payment   in   full   and   final
satisfaction   of   all   its   claims.   We   are   of   the
considered opinion that in the presents facts and
circumstances, the raising of the Final Bill and
mutual agreement of the parties in that regard, all
claims, rights and obligation of the parties merge
with the Final Bill and nothing further remains to
be done. Further, the Appellant­Contractor issued
the   Completion   Certificate   dated   19.06.2013
pursuant to which  the Appellant­Contractor has
been discharged of all the liabilities. With regard
to   the   issue   that   the   "No­Dues   Certificate"   had
been given under duress and coercion, we are of
the opinion that there is nothing on record to prove
that   the   said   Certificate   had   been   given   under
duress   or   coercion   and   as   the   Certificate   itself
provided a clearance of no dues, the contractee
could   not   now   turn   around   and   say   that   any
further payment was still due on account of the
losses   incurred   during   the   execution   of   the
30
Contract.   The   story   about   duress   was   an
afterthought   in   the   background   that   the   losses
incurred during the execution of the Contract were
not   visualised   earlier   by   the   contractee.   As   to
financial duress or coercion, nothing of this kind is
established prima facie. Mere allegation that noclaim   certificates   have   been   obtained   under
financial duress and coercion, without there being
anything more to suggest that, does not lead to an
arbitrable dispute. The conduct of the contractee
clearly shows that "no­claim certificate" was given
by   it   voluntarily;   the   contractee   accepted   the
amount   voluntarily   and   the   contract   was
discharged voluntarily.
Conclusion:
25.   Admittedly,   No­Dues   Certificate   was
submitted   by   the   contractee­Company   on
21.09.2012   and   on   their   request   Completion
Certificate   was   issued   by   the   AppellantContractor.   The   contractee,   after   a   gap   of   one
month, that is, on 24.10.2012, withdrew the No
Dues Certificate on the grounds of coercion and
duress and the claim for losses incurred during
execution of the Contract site was made vide letter
dated 12.01.2013, i.e., after a gap of 3 1/2 (three
and a half) months whereas the Final Bill was
settled   on   10.10.2012.   When   the   contractee
accepted   the   final   payment   in   full   and   final
satisfaction of all its claims, there is no point in
raising the claim for losses incurred during the
execution of the Contract at a belated stage which
creates an iota of doubt as to why such claim was
not settled at the time of submitting Final Bills
that too in the absence of exercising duress or
coercion   on   the   Contractee   by   the   AppellantContractor. In our considered view, the plea raised
by the contractee­Company is bereft of any details
and  particulars, and  cannot be anything but a
bald assertion. In the circumstances, there was
31
full and final settlement of the claim and there
was   really   accord   and   satisfaction   and   in   our
view   no   arbitrable   dispute   existed   so   as   to
exercise power Under Section 11 of the Act. The
High   Court   was   not,   therefore,   justified   in
exercising power Under Section 11 of the Act."
18. It is clear that in Boghara Polyfab (supra), no rule of
universal application was indicated. No doubt, subsequent
judgments which followed it, were in the context of the
facts as were presented to the court. Proposition (iii) of the
conclusions recorded in  Boghara Polyfab  (supra) visualize
duress or coercion on account of withholding of payments
due. The court – in more places than one, recognized that
an aggrieved party can be the victim of economic coercion
which results in its signing a document which discharges
the   other   party   of   its   obligations.  Master   Construction
(supra) placed the matter in perspective, when the court
enunciated the principle in the following terms:
“In our opinion, there is no rule of the absolute
kind. In a case where the claimant contends that
a   discharge   voucher   or   no­claim   certificate   has
been obtained by fraud, coercion, duress or undue
influence   and   the   other   side   contests   the
correctness   thereof,   the   Chief   Justice/his
designate must look into this aspect to find out at
least, prima facie, whether or not the dispute is
32
bona fide and genuine. Where the dispute raised
by   the   claimant   with   regard   to   validity   of   the
discharge   voucher   or   no­claim   certificate   or
settlement agreement, prima facie, appears to be
lacking in credibility, there may not be necessity
to refer the dispute for arbitration at all.”
Likewise, in Genus Power (supra), the court cautioned that a
“bald plea” of coercion, without any supporting material is
insufficient for a court to hold that the accord/satisfaction
or no dues certificate was involuntarily given.
19. A close look at the facts in the present case would
show that though the pleadings in the initial application
under Section 11(6) are weak, nevertheless, the materials
on   the   record,   in   the   form   of   copies   of   the  inter   se
correspondence of the parties – which span over 2 years,
clearly show that Dicitex kept repeatedly stating that it was
facing financial crisis; it referred to credits obtained for its
business and the urgency to pay back the bank. It is a
matter   of   record   that   the   Surveyor’s   report,   dated
14.08.2014, recommended payment of  12,93,26,704.98/­ ₹
to   Dicitex.   Equally,   it   is   a   matter   of   record   that   the
appellant referred the matter to a chartered accountant’s
33
firm, to verify certain inventory and sales figures. It went
by the report of the latter, who stated that the estimate of
loss could not be more than  7,16,30,148/­. This is what ₹
was offered to Dicitex, by May, 2014. Dicitex’s application
under   Section   11(6)   is   replete   with   references   to   the
number of letters written to the appellant, seeking release
of amounts; it also averred to inability to pay its income tax
dues,   the   pressure   from   bankers   (in   support   of   which,
copies of letters of bankers were produced along with the
application).
20. The   averments   by   Dicitex,   regarding   the
circumstances   which  led   it   to   execute   the  no   objection
discharge voucher, are reproduced below:
“31. The Respondents did not pay anything to
the Petitioner after the submission of its letter,
dated 31st May, 2014 and the submission of its
letter,   dated   31st  May,   2014   and   therefore
several telephonic calls were made on behalf of
the   Petitioner,   to   the   Respondent’s   Regional
Office at Mumbai in an effort to persuade the
Respondents to increase the settlement amount
so as to include the differential amount of about
Rs.   7   crores.   The   Petitioner   also   specifically
requested the Respondents not to, in any event,
insist on the execution of the Discharge Voucher
strictly as prescribed as a condition precedent
34
for   the   payment   of   any   part   of   the   balance
amount of claim.
32. Since, on the one hand, the Respondents
did not show any inclination to relent on any
count and instead continued to insist continued
to   insist   that   any   further   payment   would   be
made   to   the   Petitioner   if   and   only   if   the
Discharge Voucher was executed exactly at the
time and in the form and manner as required by
the Respondents as well as the letter dated 31st
May, 2014 withdrawn and, on the other hand,
the Petitioner was  in urgent need of funds  to
meet its mounting liabilities the Petitioner was
forced to withdraw its earlier letter dated 31st
May,   2014   and   coerced   into   executing   the
Discharge   Voucher   exactly   as   dictated   by   the
Respondents. Accordingly, the Petitioner wrote a
letter dated 6th June, 2014 to the Respondent No.
2   stating   therein   that   it   was   withdrawing   its
letter dated 31st  May, 2­14 and also enclosing
the   duly   executed   discharge   Voucher.   The
Petitioner also requested that the claim amount
be paid over to it, immediately.”
The   averments   in   the   application,   later   are   that   the
appellant paid the amount.  Dicitex, nevertheless later, by three
letters questioned the basis of reduction of the amount of claim.
It later alleged that it wrote a letter “dated 14th July, 2014 to the
respondents stating therein, inter alia, that since they were forced
to accept the offered amount and that since there was a dispute on
the   quantum   of   claim   settlement   paid   to   the   Petitioner,   the
35
Petitioner was invoking arbitration proceedings under Clause 13 of
the said Policy to recover the differential amount.”
21. An   overall   reading   of   Dicitex’s   application   (under
Section 11(6)) clearly shows that its grievance with respect to the
involuntary nature of the discharge voucher was articulated. It
cannot   be   disputed,   that   several   letters   –   spanning   over   two
years­ stating that it was facing financial crisis on account of the
delay in settling the claim, were addressed to the appellant. This
court is conscious of the fact that an application under Section
11(6) is in the form of a pleading which merely seeks an order of
the   court,   for   appointment   of   an   arbitrator.   It   cannot   be
conclusive of the pleas or contentions that the claimant or the
concerned party can take, in the arbitral proceedings. At this
stage, therefore, the court­ which is required to ensure that an
arbitrable dispute  exists, has to be  prima facie  convinced about
the genuineness or credibility of the plea of coercion; it cannot be
too particular about the nature of the plea, which necessarily has
to be made and established in the substantive (read: arbitration)
proceeding. If the court were to take a contrary approach and
minutely   examine   the   plea   and   judge   its   credibility   or
36
reasonableness, there would be a danger of its denying a forum
to the applicant altogether, because rejection of the application
would render the finding (about the finality of the discharge and
its effect as satisfaction) final, thus, precluding the applicant of
its right event to approach a civil court. There are decisions of
this   court   (Associated   Construction   v   Pawanhans   Helicopters
Ltd. (2008) 16 SCC 128 and Boghara Polyfab (supra) upheld the
concept   of   economic   duress.   Having   regard   to   the   facts   and
circumstances, this court is of the opinion that the reasoning in
the impugned judgment cannot be faulted. 
22. In view of the foregoing discussion, the appeal is held
to be unmerited; it is dismissed, without order as to costs. 
........................................J.
                                             [ARUN MISHRA]
........................................J.
                                            [S. RAVINDRA BHAT]
New Delhi,
November 13, 2019.