LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Tuesday, February 19, 2019

No grounds to challenge the Majority Award =supplies of the Respondent’s copper rods made by the Appellant to Hindustan Transmission Products Ltd. (in short, “HTPL”) after April 1995. Payment for the same were not made by HTPL to the Appellant, who also subsequently failed to make payment for the supplied goods to the Respondent. Hence, the Respondent invoked the 3 arbitration clause under the agreement dated 14.12.1993 and the dispute was referred to a three­member arbitral tribunal.


Hon'ble Mr. Justice Mohan M. Shantanagoudar
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1862 OF 2014
MMTC LTD.  … APPELLANT
Versus
M/S VEDANTA LTD.  … RESPONDENT
J U D G M E N T
MOHAN M. SHANTANAGOUDAR, J.
This civil appeal arises out of the judgment and final order
dated 09.02.2009 passed by a Division Bench of the High Court
of Judicature at Bombay in Appeal No. 949 of 2002, affirming the
judgment   and   order   dated   05.08.2002   of   the   Learned   Single
Judge whereby the Appellant’s Objections Petition challenging
the Majority Award dated 27.06.2001 had been disallowed. Vide
the   Majority   Award,   the   Appellant   had   been   directed   to   pay
certain amounts to the Respondent under their agreement dated
14.12.1993.
2.  The brief facts leading to the instant appeal are as follows:
M/s Sterlite Industries (India) Ltd., (renamed M/s Vedanta Ltd.,
the Respondent herein) was a manufacturer of continuous Cast
1
Copper Rods. Vide the agreement dated 14.12.1993, MMTC Ltd.
(the Appellant herein), a government company, was appointed as
a   consignment   agent   from  whom   the   Respondent   could  avail
services such as storage, handling and marketing of the copper
rods produced by the Respondent. Such rods were to be stored at
various   godowns   of   the   Appellant.   The   agreement   dated
14.12.1993 contained an arbitration clause.
3.   Importantly,   under   the   aforementioned   agreement,   the
Appellant raised its own invoices in the name of the customers of
the products sold and delivered. Goods were to be sold only
against   payment   of   100%   advance   by   the   customer   to   the
Appellant, who then had to remit the same to the Respondent
after deducting service charges (i.e. commission) at the rate of Rs.
500/­ per metric tonne.
4.  The aforementioned agreement was materially altered for
the   first  time  on  06.01.1994,  in   terms  of   a  Memorandum   of
Understanding between the parties. This amendment enabled the
Appellant to supply goods to customers against a letter of credit
(usance   or   stand­by),   i.e.   without   advance   payment,   while
maintaining that it was the “total responsibility” of the Appellant
to ensure the bona fides of the letter of credit furnished and that
2
the principal and interest were paid on the due date for the
supplies made against the letter of credit. In case of a stand­by
letter of credit, it was further specified that it was the Appellant’s
responsibility, in the event of non­payment by the due date, to
negotiate the stand­by letter of credit in a timely way and credit
the sale proceeds to the Respondent. Interest was fixed at 18.25%
per annum.
5.  A further revision to the above terms was undertaken vide a
meeting between the parties on 20.01.1994, the minutes of which
indicate   that   the   Appellant   could   thereafter   extend   credit   to
customers on its own terms and responsibility, and in case of
credit being extended, payment to the Respondent was to be
effected by the Appellant upon delivery of the copper rods to the
customer.
6.  The dispute in the instant matter pertains to supplies of the
Respondent’s copper rods made by the Appellant to Hindustan
Transmission Products Ltd. (in short, “HTPL”) after April 1995.
Payment for the same were not made by HTPL to the Appellant,
who also subsequently failed to make payment for the supplied
goods to the Respondent. Hence, the Respondent invoked the
3
arbitration clause under the agreement dated 14.12.1993 and
the dispute was referred to a three­member arbitral tribunal.
7.  The majority of the arbitral tribunal found in favour the
Respondent,   and   vide   its   award   dated   27.06.2001,   inter   alia
directed the Appellant to pay to the Respondent a sum of Rs.
15,73,77,296/­   with   interest   at   the   rate   of   14%   p.a.   from
05.02.1997 till the date of the award and at the rate of 18% p.a.
thereafter, as well as an amount of Rs. 2.25 crores as interest on
overdue   payment   up   to   05.02.1996.   The   said   award   was
confirmed   by   the   learned   Single   Judge   of   the   High   Court   of
Bombay as well as the Division Bench thereof.
8.  There   were   several   grounds   of   challenge   raised   by   the
Appellant before the learned Single Judge of the High Court;
however, before the Division Bench as well as before this Court
the main ground raised concerns the arbitrability of the dispute
under   the   arbitration   clause   under   the   agreement   dated
14.12.1993. This ground encompasses all other arguments raised
by the Appellant. To elaborate, it is the case of the Appellant that
it used to  supply  the  goods of  the Respondent  to  customers
arranged   by   the   Appellant   as   per   the   Agreement   dated
14.12.1993 only. However, sometimes, the Appellant had to make
4
a deviation from this procedure at the request of the Respondent,
i.e. M/s Vedanta Ltd., by allowing customers arranged by M/s
Vedanta Ltd. to lift its goods stored in the Appellant’s godowns. It
is further the case of the Appellant that whenever it made this
deviation, the Appellant was not bound by the contract between
the Respondent and the relevant customer, inasmuch as such
contract   was   independent   of   and   totally   different   from   the
agreement   dated   14.12.1993.   Whenever   there   was   a   direct
agreement   between   the   Respondent   and   its   customers   (not
arranged through the Appellant), the payment was to be made
directly   by   the   customers   to   the   Respondent   for   which   the
Appellant would not be responsible. However, if the transaction
took place pursuant to the agreement dated 14.12.1993, i.e. if
the   Appellant   was   supplying   the   Respondent’s   goods   to
customers booked through the Appellant, the Appellant would be
responsible   for   collecting   the   sale   consideration   from   the
customers,   and   to   remit   the   same   to   the   Respondent   by
deducting commission as agreed. Therefore, the direct agreement
between the Respondent and its customer HTPL in the instant
case would not be binding on the Appellant, and consequently
5
could not have been subjected to the arbitration proceedings that
led to the arbitral award dated 27.06.2001.
9.  On the contrary, the case of the Respondent is that there is
no such distinction within the nature of transactions undertaken
by the Appellant on behalf of the Respondent. Moreover, it is
submitted   that   though   there   was   an   agreement   between   the
Respondent   and   HTPL,   the   terms   of   such   agreement   were
communicated to the Appellant, upon whose acceptance of such
terms the agreement dated 14.12.1993 stood modified to such
extent.
10.  Before proceeding further, we find it necessary to briefly
revisit the existing position of law with respect to the scope of
interference with an arbitral award in India, though we do not
wish   to   burden   this   judgment   by   discussing   the   principles
regarding   the   same   in   detail.   Such   interference   may   be
undertaken   in   terms   of   Section   34   or   Section   37   of   the
Arbitration and Conciliation Act, 1996 (for short, “the 1996 Act”).
While the former deals with challenges to an arbitral award itself,
the latter,  inter alia, deals with appeals against an order made
under Section 34 setting aside or refusing to set aside an arbitral
award.
6
11. As far as Section 34 is concerned, the position is well­settled
by now that the Court does not sit in appeal over the arbitral
award   and   may   interfere   on   merits   on   the   limited   ground
provided under Section 34(2)(b)(ii), i.e. if the award is against the
public policy of India. As per the legal position clarified through
decisions of this Court prior to the amendments to the 1996 Act
in 2015, a violation of Indian public policy, in turn, includes a
violation of the fundamental policy of Indian law, a violation of
the interest of India, conflict with justice or morality, and the
existence of patent illegality in the arbitral award. Additionally,
the concept of the “fundamental policy of Indian law” would cover
compliance   with   statutes   and   judicial   precedents,   adopting   a
judicial   approach,   compliance   with   the   principles   of   natural
justice, and Wednesbury reasonableness. Furthermore, “patent
illegality”   itself   has   been   held   to   mean   contravention   of   the
substantive  law  of  India,  contravention  of  the   1996  Act,  and
contravention of the terms of the contract.
It is only if one of these conditions is met that the Court
may interfere with an arbitral award in terms of Section 34(2)(b)
(ii), but such interference does not entail a review of the merits of
the dispute, and is limited to situations where the findings of the
7
arbitrator   are   arbitrary,   capricious   or   perverse,   or   when   the
conscience of the Court is shocked, or when the illegality is not
trivial but goes to the root of the matter. An arbitral award may
not be interfered with if the view taken by the arbitrator is a
possible view based on facts. (See  Associate  Builders  v. DDA,
(2015) 3 SCC 49). Also see ONGC Ltd. v. Saw Pipes Ltd., (2003)
5   SCC   705;  Hindustan   Zinc   Ltd.   v.   Friends   Coal
Carbonisation,   (2006)   4   SCC   445;   and  McDermott
International v. Burn Standard Co. Ltd., (2006) 11 SCC 181).
It is relevant to note that after the 2015 amendments to
Section   34,   the   above   position   stands   somewhat   modified.
Pursuant to the insertion of Explanation 1 to Section 34(2), the
scope of contravention of Indian public policy has been modified
to the extent that it now means fraud or corruption in the making
of the award, violation of Section 75 or Section 81 of the Act,
contravention   of   the   fundamental   policy   of   Indian   law,   and
conflict   with   the   most   basic   notions   of   justice   or   morality.
Additionally, sub­section (2A) has been inserted in Section 34,
which provides that in case of domestic arbitrations, violation of
Indian public policy also includes patent illegality appearing on
8
the face of the award. The proviso to the same states that an
award   shall   not   be   set   aside   merely   on   the   ground   of   an
erroneous   application   of   the   law   or   by   re­appreciation   of
evidence.
12.  As far as interference with an order made under Section 34,
as per Section 37, is concerned, it cannot be disputed that such
interference   under   Section   37   cannot   travel   beyond   the
restrictions   laid  down   under  Section   34.   In  other   words,   the
Court   cannot   undertake   an   independent   assessment   of   the
merits of the award, and must only ascertain that the exercise of
power by the Court under Section 34 has not exceeded the scope
of the provision.  Thus, it is evident that in case an arbitral award
has been confirmed by the Court under Section 34 and by the
Court   in   an   appeal   under   Section   37,   this   Court   must   be
extremely cautious and slow to disturb such concurrent findings.
13.   Having noted the above grounds for interference with an
arbitral award, it must now be noted that the instant question
pertains to determining whether the arbitral award deals with a
dispute not contemplated by or not falling within the terms of the
submission   to   arbitration,   or   contains   decisions   on   matters
beyond the scope of the submission to arbitration. However, this
9
question   has   been   addressed   by   the   Courts   in   terms   of   the
construction of the contract between the parties, and as such it
can be safely said that a review of such a construction cannot be
made in terms of re­assessment of the material on record, but
only in terms of the principles governing interference with an
award as discussed above.
14.  It is equally important to observe at this juncture that while
interpreting the terms of a contract, the conduct of parties and
correspondences exchanged would also be relevant factors and it
is within the arbitrator’s jurisdiction to consider the same. (See
McDermott   International   Inc.   v.   Burn   Standard   Co.   Ltd.
(supra); Pure Helium India (P) Ltd. v. ONGC, (2003) 8 SCC 593,
D.D. Sharma v. Union of India, (2004) 5 SCC 325).
15. We have gone through the material on record as well as the
Majority Award, and the decisions of the learned Single Judge
and the Division Bench. The majority of the arbitral tribunal as
well as the Courts found upon a consideration of the material on
record,   including   the   agreement   dated   14.12.1993,   the
correspondence   between   the   parties   and   the   oral   evidence
adduced,   that   the   agreement   does   not   make   any   distinction
10
within the type of customers, and furthermore that the supplies
to   HTPL   were   not   made   in   furtherance   of   any   independent
understanding between the Appellant and the Respondent which
was not governed by the agreement dated 14.12.1993.
16.   The   Appellant   has   highlighted   before   us   several
correspondences addressed to it from the Respondent that refer
to   the   fact   that   sales   to   HTPL   had   been   made   under   the
Respondent’s contract with HTPL. Indeed, it is evident from the
agreement dated 28.07.1994 between HTPL and the Respondent
that a direct agreement existed between them. However, as is
undisputed, the Appellant received its commission in its entirety
for the HTPL transaction, and thus clearly was a beneficiary of
the agreement between the Respondent and HTPL. Moreover, in
this regard, it was rightly observed in the Majority Award that the
Appellant could not show under what separate agreement it was
entitled to commission from such sales other than the agreement
dated 14.12.1993, and for what services, if its only role in the
transaction was to allow HTPL to lift goods from its godowns.
17. Indeed,   it   is   not   the   case   of   the   Appellant   that   it   only
provided   storage   services   to   the   Respondent   by   allowing   the
Respondent to store its goods in the warehouse of the Appellant
11
(i.e. that it only acted as a warehouse for the Respondent). In
fact,   a   series   of   correspondences   amongst   the   Appellant,   the
Respondent and HTPL clearly reveals that the Appellant was also
actively   involved   in   the   transaction   in   question   entered   into
between   the   Respondent   and   HTPL,   and   as   such   was   a
beneficiary   under   their   agreement,   as   observed   supra.   The
Appellant released the Respondent’s goods to HTPL as per the
directions of the Respondent without raising any objection, and
thereafter   engaged   in   correspondence   in   respect   of   the
transaction.
18.  It   would   be   appropriate   to   refer   to   some   such
communications   amongst   the   Appellant,   the   Respondent   and
HTPL for illustrative purposes. For instance, as mentioned by the
Respondent in a communication dated 19.09.1994 addressed to
HTPL, the Appellant was to honour the terms and conditions of
the   agreement   between   the   Respondent   and   HTPL.   The   said
communication also referred to negotiations about issuance of a
letters of credit in favour of the Appellant. Additionally, as can be
seen   from   the   correspondence   from   the   Appellant   to   the
Respondent   dated   26.08.1994,   the   Appellant   wrote   to   it   to
confirm that credit had to be supplied to HTPL at the discounted
12
interest   rate   of   16.25%   p.a.,   which   was   affirmed   by   the
Respondent   on   the   same   day.   At   the   same   time,   the
correspondence dated 28.03.1995 from the Respondent to the
Appellant discloses that a letter of credit issued by HTPL initially
sent  to   the   Respondent   was  forwarded  to   the   Appellant   with
directions  to  despatch  goods  after  verification  of  the letter of
credit and other related papers.
19.  The issuance of letters of credit in the name of the Appellant
with respect to the HTPL transaction was similar to the practice
adopted in case of letters of credit or demand drafts issued in all
other   transactions,   whether   directly   negotiated   by   the
Respondent, or procured through the Appellant, which suggests
that it was the duty of the Appellant in this case as well to ensure
that usance letter of credits issued were bona fide, and in case of
stand­by letters of credit, that they were negotiated in time in
case  of  failure  of  payment  on  the  due  date,  in  terms  of  the
agreement dated 14.12.1993.
20.  The   Courts   also   rightly   relied   upon   the   communication
dated 06.12.1995 from the Respondent to the Appellant adverting
to the terms and conditions of the contract between the parties
and referring to the fact that in respect of the sales made to HTPL
13
in the period of April, May and July 1995, an amount of Rs. 9.2
crores   together   with   interest   was   still   to   be   received.   The
response to the above communication, from the Appellant to the
Respondent, dated 08.12.1995, stated that the Appellant had
taken steps to set the matter right, and that the Appellant had
had certain internal difficulties which had since been resolved
and   the   Respondent   would   have   no   grounds   to   complain
thereafter. This communication clearly demonstrates the duty of
the Appellant to recover the dues from HTPL and forward the
same to the Respondent.
21.  Another important communication rightly relied upon by
the   Courts   is   the   Appellant’s   letter   dated   24.01.1996   to   the
Respondent,   informing   it   about   the   institution   of   a   suit   for
damages   by   HTPL   with   respect   to   the   quality   of   the   goods
supplied.   This   correspondence   refers   to   HTPL   as   a   customer
introduced to the Appellant by the Respondent. Crucially, it was
addressed in terms of the agreement dated 14.12.1993, which
amounts to a clear admission that the sales made to HTPL were
in terms of the said agreement.
22. In this view of the matter, it is not open to the Appellant to
argue that the agreement between the Respondent and HTPL was
14
independent   of   the   agreement   dated   14.12.1993   between   the
Appellant and the Respondent and that the latter did not apply to
such transaction.
23. Moreover, as noticed in the Majority Award and also by the
Courts, the oral evidence of the officers of the Appellant indicates
that the Appellant did not make any effort to ensure that the
letters of credits pertaining to the supplies made to HTPL were
honoured, pointing towards gross negligence on the part of the
Appellant.
24. Based upon the above discussion, in our opinion, the view
taken in the Majority Award, as confirmed by the High Court in
the exercise of its powers under Sections 34 and 37 of the 1996
Act, is a possible view based upon a reasonable construction of
the   terms   of   the   agreement   dated   14.12.1993   between   the
Appellant and the Respondent and consideration of the material
on   record.   We   are   also   of   the   opinion   that   the   dispute   was
covered   under   the   agreement   between   the   Appellant   and   the
Respondent   dated   14.12.1993,   and   as   such   the   dispute   is
governed by the arbitration clause under the said agreement.
Thus, we find no reason to disturb the Majority Award on the
ground that the subject matter of the dispute was not arbitrable.
15
25. Appeal is, therefore, dismissed and the order of the High
Court of Judicature at Bombay in Appeal No. 949 of 2002 is
affirmed.
        ……………..…………………..J.
    [Mohan M. Shantanagoudar] 
…………………………………J.
[Vineet Saran]
New Delhi;
February 18, 2019.
16