Limitation Act (36 of 1963), S. 5 — Condonation of delay — "Sufficient cause" — Liberal and justice-oriented approach — Cumulative assessment of circumstances. Expression "sufficient cause" must receive a liberal construction to advance substantial justice. Length of delay is not decisive; acceptability of the explanation matters. Internal administrative procedures, obtaining administrative approval, engaging panel counsel, and procuring certified copies cannot by themselves justify every delay, nor is lack of diligence approved, yet where steps taken to pursue the remedy are shown, there is no material of deliberate delay or undue advantage, and the net unexcluded delay (95 days after COVID-19 exclusion) is explained cumulatively rather than in isolation, refusal to condone delay is unduly restrictive. (Paras 6, 8, 9)

 Case Title: Delhi Development Authority v. Sudarshan Manjhi & Ors.


Citation: 2026 INSC 1254 | Civil Appeal arising out of SLP (Civil) No. 9105 of 2025 | Decided on November 20, 2026

Bench: Vikram Nath, J. and Aparesh Kumar Singh, J.

Facts of the Case

  • Allotment & Demand: Smt. Bachhi Devi (predecessor-in-interest of the respondents) applied for a residential flat under DDA's Expandable Housing Scheme, 1996. Following a draw of lots on 21.03.1997, she was allotted Flat No. 286, Sector B-4, Pocket 6, Narela, Delhi, and demand-cum-allotment letters (dated 12.01.2000 to 20.01.2000) were issued. (Para 3.1)

  • Cancellation: DDA claimed the demand-cum-allotment letter was sent to her correspondence address, which she denied receiving. After issuing a show cause notice on 09.08.2001 for non-payment, DDA informed her on 20.10.2003 that the allotment stood cancelled despite her representations. (Para 3.2)

  • District Forum & State Commission: The allottee filed Consumer Complaint No. 36 of 2009 before the District Forum-II, New Delhi, which dismissed it on 11.08.2015 finding due dispatch and justified cancellation. In First Appeal No. 462 of 2015, the State Commission allowed the appeal on 09.04.2021, holding that the demand-cum-allotment letter was not duly served, and directed allotment of an alternative flat at original allotment rates. (Paras 3.3–3.4)

  • NCDRC & High Court: DDA filed Revision Petition No. 1621 of 2022 on 02.12.2022 with a reported delay of 512 days. Excluding the COVID-19 limitation extension period (15.03.2020 to 28.02.2022), a net delay of 95 days remained, attributed to administrative approval, change of panel counsel, and obtaining a certified copy. On 07.06.2024, the National Commission refused to condone the 95-day delay and dismissed the revision petition. On 23.10.2024, the Delhi High Court dismissed DDA's Article 227 petition (CM(M) No. 3690 of 2024) for lack of due diligence. (Paras 3.5–3.7)

Headnotes 

Limitation Act (36 of 1963), S. 5 — Condonation of delay — "Sufficient cause" — Liberal and justice-oriented approach — Cumulative assessment of circumstances.

Expression "sufficient cause" must receive a liberal construction to advance substantial justice. Length of delay is not decisive; acceptability of the explanation matters. Internal administrative procedures, obtaining administrative approval, engaging panel counsel, and procuring certified copies cannot by themselves justify every delay, nor is lack of diligence approved, yet where steps taken to pursue the remedy are shown, there is no material of deliberate delay or undue advantage, and the net unexcluded delay (95 days after COVID-19 exclusion) is explained cumulatively rather than in isolation, refusal to condone delay is unduly restrictive. (Paras 6, 8, 9)

Limitation Act (36 of 1963), S. 5 — Condonation of delay — Conflicting findings by lower fora — Adjudication on merits.

Where the District Forum and State Commission have reached conflicting conclusions on the underlying dispute (service of demand-cum-allotment letter and validity of cancellation), permitting adjudication of the revision petition on merits serves substantial justice better than terminating proceedings at the threshold on limitation, without expressing any view on the merits of either forum's order. (Paras 8, 9, 11)

Constitution of India, Art. 227 — Supervisory jurisdiction — Affirming unduly restrictive refusal to condone delay.

Where the National Commission adopts an unduly restrictive approach in rejecting an explanation for net delay after excluding the suo motu COVID-19 limitation period, and the High Court under Article 227 affirms that order without giving sufficient weight to the cumulative circumstances, both orders are liable to be set aside and the revision petition restored to the National Commission for disposal on merits. (Paras 7, 9, 10, 11)

Ratio Decidendi

While internal administrative processes and changes of counsel do not automatically excuse delay and lack of diligence is not condoned, courts must evaluate explanations for delay cumulatively and pragmatically—factoring in excluded limitation periods, absence of mala fides or deliberate delay, and conflicting findings between lower consumer fora—so that substantial justice prevails over threshold dismissal, leaving all substantive contentions open for decision on merits. (Paras 6, 8, 9, 11)