LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Friday, August 9, 2024

The statutory scheme of the Act makes a foreign arbitral award enforceable when the objections against it are finally decided. Therefore, as per the Act and the principle in Forasol (supra), the relevant date for determining the 42 conversion rate of foreign award expressed in foreign currency is the date when the award becomes enforceable. ii. When the award debtor deposits an amount before the court during the pendency of objections and the award holder is permitted to withdraw the same, even if against the requirement of security, this deposited amount must be converted as on the date of the deposit. iii. After the conversion of the deposited amount, the same must be adjusted against the remaining amount of principal and interest pending under the arbitral award. This remaining amount must be converted on the date when the arbitral award becomes enforceable, i.e., when the objections against it are finally decided.

2024 INSC 593

1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 7702 OF 2019

DLF LTD. (FORMERLY KNOWN AS

DLF UNIVERSAL LTD) AND ANR. ...APPELLANT(S)

VERSUS

KONCAR GENERATORS AND MOTORS LTD. …RESPONDENT(S)

J U D G M E N T

PAMIDIGHANTAM SRI NARASIMHA, J.

1. The issue arising in the present appeal relates to enforcement

of an arbitral award expressed in foreign currency. In this context,

two questions arise for consideration. First, what is the correct and

appropriate date to determine the foreign exchange rate for

converting the award amount expressed in foreign currency to

Indian rupees. Second, what would be the date of such conversion,

when the award debtor deposits some amount before the court

during the pendency of proceedings challenging the award. Two

uncertainties have a direct bearing on the question to be answered,

the time lapse between the date of the award and its enforceability-

2

a local factor, and the ever-fluctuating exchange rates- a global

factor.

1.1 Taking into account these two factors and the statutory

provisions, coupled with the decisions of this Court, we have

formulated twin principles: First, following the principle in Forasol

v. Oil and Natural Gas Commission1, the date when the arbitral

award becomes enforceable shall be the date for conversion. Under

the Arbitration and Conciliation Act, 19962 this date is when the

objections against the award are dismissed, and award attains

finality. Second, in the event that the award amount or part of it is

deposited in court pending objections, enabling withdrawal by the

decree holder, that date of such deposit shall be the relevant date

for conversion as per the principle in Renusagar Power Co Ltd v.

General Electric Co3. Before we consider the submissions of the

counsels representing the parties, followed by our reasons and

decision, we will refer to the relevant facts of the case.

2. Facts: The relevant facts are that the appellants are Indian

companies and the respondent is a Croatian company. The parties

entered a contract for the design, engineering, manufacturing, and

1 1984 Supp SCC 263.

2 Hereinafter ‘the Act’.

3 1994 Supp (1) SCC 644. 

3

supply of two generators by the respondent. Certain disputes arose

between them that were referred to arbitration before the

International Chamber of Commerce4, Paris. The three-member

arbitral tribunal passed its award dated 12.05.2004 in favour of

the respondent-claimant and held the appellants to be jointly and

severally liable to pay Euros 10,93,989, along with interest, as

follows:

i. Euros 9,60,308.41 with interest of 5% p.a. starting on

31.10.1999 until final repayment;

ii. Euros 18,411.40 for the storage and maintenance of the

goods with interest of 5% p.a. starting from the date of the

award;

iii. Euros 5,545.40 relating to lawyer expenses of the

claimant, euros 99,482.70 relating to arbitration fees paid

to the ICC, euros 3,389.57 as guaranty expenses relating

to the repayment of the appellants’ arbitration fee to the

ICC, euros 6,852 relating to the arbitration costs in Paris,

all these amounts with interest of 5% p.a. from the date of

the award.

4 Hereinafter “ICC”.

4

2.1 The respondent filed for execution of the award in 2004, while

the appellants filed a petition under Section 34 of the Act, which

was dismissed on 28.04.2010. In 2010, the appellants then filed

objections against the award under Section 48 of the Act and also

filed a Section 37 appeal against the Section 34 order. The High

Court dismissed the appeal by its order dated 15.10.2010, the

terms of which are important for our purpose and are hence

extracted:

“After arguing for some time learned counsel have reached

a consensus on the present appeal. It has been agreed by

learned counsel for the appellants that the appeal as well

as the application under Section 34 of the Arbitration and

Conciliation Act, 1996 would be dismissed as withdrawn. It

has been further agreed that the appellants would deposit

an amount of Rs.7.5 Crores before the Executing Court on

or before 08.11.2010.

It has been agreed by learned counsel for the respondent

that the application under Section 48 which has been filed

by the appellants would be decided on its own merits

without being influenced by any findings or observations in

the order on the application under Section 34 dated

28.04.2010. It has further been agreed by learned counsel

for the respondent that the amount of Rs. 7.5 Crores which

would be deposited by the appellants would be released to

it only consequent to furnishing a bank guarantee of a

scheduled bank of India in the amount of Rs. 7.5 Crores in

favour of the Executing Court and the said bank guarantee

would be kept alive during the proceedings under Section

48 and for a period of 60 days thereafter. The final order

thereon would obviously be passed by the Executing Court

after the conclusion of the proceedings under Section 48.”

2.2 In accordance with the above, the appellants deposited

Rs. 7.5 crores with the Executing Court on 22.10.2010. 

5

2.3 The Trial Court dismissed the objections filed under

Section 48 by order dated 02.04.2011. The appellants filed a

revision, which the High Court admitted by order dated

03.06.2011. By this order, the High Court also stayed the

operation of the Trial Court order dismissing objections, subject to

the appellants depositing a further amount of Rs. 50 lakhs, in

addition to Rs. 7.5 crores, with the Executing Court. The Court

directed that the amount shall be disbursed to the successful party

on the final adjudication of this lis. It also rejected the respondent’s

prayer for deposit of the amount in euros. Pursuant to this order,

the appellants deposited Rs. 50 lakhs on 15.07.2011.

Subsequently, the revision came to be dismissed by the High Court

on 01.07.2014, by which the award attained finality as this order

was not challenged any further.

2.4 In the execution proceedings, the Trial Court by order dated

24.08.2016 permitted the respondent to withdraw the entire

deposit of Rs. 8 crores as per the direction of the High Court. On

10.10.2016, the respondent received Rs. 11,60,12,100, including

the interest that had accrued on the deposited amount.

2.5 The execution petition was allowed by the Trial Court by its

order dated 03.02.2017, wherein it was held that the relevant date 

6

to convert the award amount expressed in euros to Indian rupees

(the foreign exchange rate) is 01.07.2014, i.e., the date on which

all the objections against the award were finally decided as it is

only on such date that the award is deemed to be a decree. The

Trial Court accepted the calculation as submitted by the

respondent.

2.6 The appellants filed a revision petition against this order,

which was dismissed by the High Court by order dated

26.02.20185, which is impugned herein. The High Court rejected

the appellant’s reliance on this Court’s decision in Forasol (supra)

to submit that the date of decree shall be deemed as the relevant

date for conversion and since the award dated 12.05.2004 is a

deemed decree under the Act, the exchange rate as on the date of

the award should be applied. The Court reasoned that this Court’s

judgment in Forasol (supra) was passed under the Arbitration Act,

1940 and hence, does not apply in the present case. Instead, the

High Court referred to the Delhi High Court’s decision in Progetto

Grano S.P.A. v. Shri Lal Mahal Limited6, against which this Court

dismissed the SLP7, where it was held that the relevant date for

5

In CR No. 1827 of 2017 (O&M), Punjab and Haryana High Court (hereinafter “impugned judgment”).

6 2014 SCC OnLine Del 3348.

7 SLP No. 27041/2014, order dated 21.11.2014. 

7

conversion is when the objections filed under Section 48 are finally

decided. Further, the Court referred to Section 49 of the Act8 that

provides that the foreign arbitral award shall be deemed to be a

decree of the court when it is satisfied that it is enforceable under

Part II, Chapter I of the Act. It reasoned that such satisfaction

required under Section 49 is complete only when the objections

filed under Section 48 are finally decided, which was on

01.07.2014 in the present case (when the High Court dismissed

the revision). It also observed that the appellants delayed execution

of the award by initially filing under Section 34, despite such

application not being maintainable and then filing an appeal

against this order and subsequently withdrawing it. The appellants

cannot be permitted to benefit from the fluctuation in exchange

rates when the delay is attributable to them. Therefore, the

relevant date for conversion is 01.07.2014.

2.7 While issuing notice on the special leave petition filed by the

appellant on 10.09.20189, this Court confined the issue to

8 Section 49 of the Act reads:

“49. Enforcement of foreign awards.—Where the Court is satisfied that the foreign award is

enforceable under this Chapter, the award shall be deemed to be a decree of that Court.”

9 By order 10.09.2018, this Court ordered: “Issue notice, returnable within four weeks, limited to the conversion

rate that would be applicable on 15.10.2010 insofar as the deposit of Rs. 7.5 Crores is concerned. The same will

apply to the further deposit of Rs. 50,00,000/-.”

8

determining whether the foreign exchange rate as on 15.10.2010

would apply to the deposit of Rs. 8 crores.

3. Submissions: Learned senior counsel Mr. Pinaki Mishra

appeared on behalf of the appellants. Initially, he submitted that

01.07.2014 would not be the relevant date for conversion for the

entire amount and argued for using the exchange rate on

02.04.2011, when the Trial Court dismissed objections under

Section 48. However, he later restricted his submissions to the

exchange rate that applies when the amount of Rs. 8 crores was

deposited by the appellants on 22.10.2010 as per the order dated

15.10.2010. The crux of his argument is that the deposited

amount stands converted as on the date of its deposit, and this

amount then cannot be converted again as per the exchange rate

prevailing on 01.07.2014. He has submitted that the High Court

passed an order dated 15.10.2010 directing the appellants to

deposit Rs. 7.5 crores on the consent of both parties, and also

permitted the respondent to withdraw this amount on furnishing

a bank guarantee in Indian rupee for the entire amount, to which

the respondent had agreed at the time. He further submitted that

the appellants cannot be faulted for the respondent not

withdrawing the amount when it was deposited. In response to the 

9

respondent’s contention regarding their inability to furnish a bank

guarantee of a scheduled Indian bank, he submitted that the

respondent had agreed to this condition when the order was

passed, and in any case, it could have applied for a modification

but did not do so. Since the respondent consented to the deposit

of Rs. 7.5 crores and it was also permitted to withdraw the same,

the amount stood converted as on the date of its deposit on

22.10.2010. The exchange rate on this date was 1 euro = Rs.

59.17. While the arbitral award along with interest was euros

16,73,469.07, the deposited amount of Rs. 7.5 crores gets

converted to euros 12,67,534.22 at that exchange rate, and the

balance of the award would be euros 4,05,934.85 that remained

pending as on this date. Subsequently, pursuant to the High

Court’s interim order dated 03.06.2011 in revision against the

Trial Court dismissing the objections petition, the appellant

deposited an additional amount of Rs. 50 lakhs on 15.07.2011. As

on this date, the amount of arbitral award including interest

pending payment was euros 4,17,278.78, i.e., after converting and

adjusting the earlier deposit against the award. Using the

prevailing exchange rate of 1 euro = Rs. 62.89 as on 15.07.2011,

the appellant’s deposit amounts to euros 79,503.90. Therefore, a 

10

balance of euros 3,37,774.88, along with interest, remains pending

for which the exchange rate as on 01.07.2014 would apply.

3.1 Mr. Mishra concluded by submitting that the appellants

would be required to pay only Rs. 3.19 crores if their calculation is

accepted. On the other hand, if the impugned judgment is upheld,

they would be required to be pay more than double the amount,

i.e., Rs. 6.48 crores.

3.2 Mr. Abhay Mahajan, learned counsel, appearing for the

respondent submitted that the exchange rate on 01.07.2014 would

apply to the entire award amount. He submitted that the

respondent had not consented to the deposit of Rs. 7.5 crores and

that the High Court did not convert the amount but only directed

deposit of a lump sum amount. He relied on this Court’s decision

in P.S.L. Ramanathan Chettiar v. O.R.M.P.R.M. Ramanathan

Chettiar10 where it was held that the judgment debtor depositing a

sum in court during the pendency of the appeal does not pass the

title and vest the money with the decree-holder. The decree-holder

may withdraw the amount only on furnishing security, which

means that the payment is not in satisfaction of the decree.

Further, the judgment debtor can proceed against the security in

10 (1968) 3 SCR 367.

11

case he succeeds in the appeal. Rather, the purpose of the deposit

is to obtain a stay of execution and to put the money beyond the

reach of the parties pending the disposal of the appeal. On this

basis, Mr. Mahajan submitted that the deposit of Rs. 8 crores

during the pendency of the objections under Section 48 does not

pass the title of this amount to the respondent and such deposit

was not under the arbitral award as the award can be deemed to

be a decree only on 01.07.2014 when all the objections to the

award stood dismissed. Hence, this is the relevant date for

conversion.

3.3 As per the calculation sheet submitted by the respondent, the

exchange rate as on this date is 1 euro = Rs. 82.21 and this rate

must be used for converting the entire arbitral award and interest.

The amount of Rs. 11.6 crores withdrawn by the respondent on

10.10.2016 must first be appropriated towards interest and then

towards the principal sum. After adjusting this amount and after

accounting for interest, the respondent submits that it is entitled

to Rs. 6,57,62,057 from the appellants.

4. Analysis – Statutory Scheme: It is important to first set out

the statutory scheme for the enforcement of foreign arbitral awards

in India. Under the Act, Part II deals with the enforcement of

12

certain foreign arbitral awards. Chapter I deals with awards under

the New York Convention. Section 45 provides for the power of a

court to refer parties to arbitration.11 Section 46 provides that a

foreign award which is enforceable under this Chapter shall be

treated as binding for all purposes on the persons between whom

it is made.12 Section 47 provides for the evidentiary requirements

for enforcement of a foreign award.13 Section 48 sets out various

grounds on which the court may refuse the enforcement of a

foreign award.14 Section 49 provides that where the court is

11 Section 45 reads:

“45. Power of judicial authority to refer parties to arbitration.—Notwithstanding anything

contained in Part I or in the Code of Civil Procedure, 1908 (5 of 1908), a judicial authority, when

seized of an action in a matter in respect of which the parties have made an agreement referred to

in section 44, shall, at the request of one of the parties or any person claiming through or under

him, refer the parties to arbitration, [unless it prima facie finds] that the said agreement is null and

void, inoperative or incapable of being performed.”

12 Section 46 reads:

“46. When foreign award binding.—Any foreign award which would be enforceable under this

Chapter shall be treated as binding for all purposes on the persons as between whom it was made,

and may accordingly be relied on by any of those persons by way of defence, set off or otherwise in

any legal proceedings in India and any references in this Chapter to enforcing a foreign award shall

be construed as including references to relying on an award.”

13 Section 47 reads:

“47. Evidence.—(1) The party applying for the enforcement of a foreign award shall, at the time of

the application, produce before the court—

(a) the original award or a copy thereof, duly authenticated in the manner required by the law of

the country in which it was made;

(b) the original agreement for arbitration or a duly certified copy thereof; and

(c) such evidence as may be necessary to prove that the award is a foreign award.

(2) If the award or agreement to be produced under sub-section (1) is in a foreign language, the

party seeking to enforce the award shall produce a translation into English certified as correct by

a diplomatic or consular agent of the country to which that party belongs or certified as correct in

such other manner as may be sufficient according to the law in force in India.

[Explanation.—In this section and in the sections following in this Chapter, “Court” means the

High Court having original jurisdiction to decide the questions forming the subject-matter of the

arbitral award if the same had been the subject-matter of a suit on its original civil jurisdiction and

in other cases, in the High Court having jurisdiction to hear appeals from decrees of courts

subordinate to such High Court.]”

14 Section 48 reads:

“48. Conditions for enforcement of foreign awards.—(1) Enforcement of a foreign award may be

refused, at the request of the party against whom it is invoked, only if that party furnishes to the

court proof that—

13

satisfied that a foreign award is enforceable under this Chapter, it

shall be deemed to be a decree of that court. Section 50 provides

for appeal against certain orders, i.e., orders refusing to refer

parties to arbitration under Section 45 and orders refusing to

enforce a foreign award under Section 48.15 Finally, Section 5116 is

(a) the parties to the agreement referred to in section 44 were, under the law applicable to them,

under some incapacity, or the said agreement is not valid under the law to which the parties have

subjected it or, failing any indication thereon, under the law of the country where the award was

made; or

(b) the party against whom the award is invoked was not given proper notice of the appointment of

the arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or

(c) the award deals with a difference not contemplated by or not falling within the terms of the

submission to arbitration, or it contains decisions on matters beyond the scope of the submission to

arbitration:

Provided that, if the decisions on matters submitted to arbitration can be separated from

those not so submitted, that part of the award which contains decisions on matters submitted to

arbitration may be enforced; or

(d) the composition of the arbitral authority or the arbitral procedure was not in accordance with

the agreement of the parties, or, failing such agreement, was not in accordance with the law of the

country where the arbitration took place; or

(e) the award has not yet become binding on the parties, or has been set aside or suspended by a

competent authority of the country in which, or under the law of which, that award was made.

(2) Enforcement of an arbitral award may also be refused if the Court finds that—

(a) the subject-matter of the difference is not capable of settlement by arbitration under the law of

India; or

(b) the enforcement of the award would be contrary to the public policy of India.

[Explanation 1.—For the avoidance of any doubt, it is clarified that an award is in conflict with the

public policy of India, only if,—

(i) the making of the award was induced or affected by fraud or corruption or was in violation of

section 75 or section 81; or

(ii) it is in contravention with the fundamental policy of Indian law; or

(iii) it is in conflict with the most basic notions of morality or justice. ]

[Explanation 2.—For the avoidance of doubt, the test as to whether there is a contravention with

the fundamental policy of Indian law shall not entail a review on the merits of the dispute.]

(3) If an application for the setting aside or suspension of the award has been made to a competent

authority referred to in clause (e) of sub-section (1) the Court may, if it considers it proper, adjourn

the decision on the enforcement of the award and may also, on the application of the party claiming

enforcement of the award, order the other party to give suitable security.”

15 Section 50 reads:

“50. Appealable orders.—(1) [Notwithstanding anything contained in any other law for the time

being in force, an appeal] shall lie from the order refusing to—

(a) refer the parties to arbitration under section 45;

(b) enforce a foreign award under section 48, to the court authorised by law to hear appeals from

such order.

(2) No second appeal shall lie from an order passed in appeal under this section, but nothing in this

section shall affect or take away any right to appeal to the Supreme Court.”

16 Section 51 reads:

“51. Saving.—Nothing in this Chapter shall prejudice any rights which any person would have had

of enforcing in India of any award or of availing himself in India of any award if this Chapter had

not been enacted.”

14

a savings clause and Section 5217 provides that Chapter II of Part

II shall not apply to awards governed under this Chapter.

4.1 From the statutory scheme, it is clear that a foreign arbitral

award is binding between the parties when it is enforceable under

Part II, Chapter I of the Act (Section 46). The enforceability of the

award can be challenged under Section 48, and the order passed

on such an application can be appealed under Section 50 only if it

is allowed and the court refuses enforcement of the award.

Therefore, a foreign award can be enforced when the objections

against it are finally decided and dismissed. At this point, the

award is deemed to be a decree of the court as per Section 49.18

Unlike under the Arbitration Act, 1940, there is no requirement for

a separate decree by a court for making the award a rule of the

court.19

5. Case-law on Relevant Date for Conversion: Now, we will

discuss the case-law on the relevant date of conversion, both in

the context of arbitral awards and judgments where the decretal

amount is expressed in a foreign currency. The seminal case that

first decided this question was Forasol v. ONGC (supra). Forasol

17 Section 52 reads:

“52. Chapter II not to apply.—Chapter II of this Part shall not apply in relation to foreign awards

to which this Chapter applies.”

18 See Fuerst Day Lawson v. Jindal Exports Limited, (2001) 6 SCC 356, paras 30 and 31.

19 ibid.

15

was a French company that was awarded a tender for structural

drilling of oil for exploration by ONGC. Pursuant to certain

disputes that arose between the parties, the matter was referred to

arbitration and on 21.12.1974, an arbitral award was passed in

Forasol’s favour where the amount was expressed in French

francs. This award was made under the Arbitration Act, 1940. The

Court held that the award can be enforced either in foreign

currency or in Indian rupee. The principles for determining

conversion to Indian rupee are as follows:

5.1 Where the contract provides for a rate of exchange, the same

must be used to convert the amount in accordance with the

wording of the contractual clause. In this case, article IX-3.1 of the

contract provided for the exchange rate of FF 1.033 = Re. 1.000,

which the Court held as applying to only 20% of the fees and

charges computed in French francs based on contractual

interpretation.20 Further, the arbitral award provided for an

enhanced rate of conversion of FF 1.000 = Rs. 1.5178 as applicable

to payments in Indian rupee on or after 30.11.1966 as the Indian

rupee was depreciated at this time. The Court interpreted the

arbitral award and held this exchange rate to apply in place of what

20 Forasol (supra), para 16. 

16

was provided in article IX-3.1 to the extent of payments made in

Indian rupee on and after 30.11.1966.21

5.2 For the remaining amount that still required to be converted

to Indian rupee for which no exchange rate was provided in the

contract or the arbitral award, the Court considered six possible

dates as the proper date for fixing the rate of exchange22:

i. the date when the amount became due and payable;

ii. the date of the commencement of the action;

iii. the date of the decree;

iv. the date when the court orders execution to issue;

v. the date when the decretal amount is paid or realised;

vi. and in cases where a decree is passed by the court in terms

of an arbitral award in foreign currency, the date of the

award.

5.3 After an extensive discussion of English jurisprudence on the

point, the Court noted the position of law in England at the time.

23

Briefly stated, the position is as follows: Both courts and

arbitrators in England have the jurisdiction to make a judgment/

award in foreign currency in certain circumstances. In the

21 ibid, paras 17-22.

22 ibid, paras 24-25.

23 ibid, para 39. 

17

Jugoslavenska case24, the Court of Appeal held that in cases of

arbitral awards, the date of award is the relevant date for

determining the exchange rate. This was a departure from the

‘breach date rule’, i.e., the conversion must be as per the exchange

rate on the date when the debt was payable, which principle was

laid down by the House of Lords in the Havana case25.

Subsequently, in the Schorsch Meier case26 (this was not a case of

arbitration but a claim for payment of price of goods in a foreign

currency filed before English courts), the Court of Appeal held that

the date of conversion should be the date of payment, i.e., the date

on which the court authorises enforcement of the judgment in

terms of sterling. Finally, in the Miliangos case27, the House of

Lords also held that the date of conversion should be the date

when the court authorises enforcement of the judgment in terms

of sterling pound. While Jugoslavenska (supra) was not expressly

overruled by the House of Lords, its correctness was doubted.

5.4 The Court held that there is no bar on courts in India to pass

a decree for a sum expressed in foreign currency. However, for the

purpose of payment of such amount, the limitations and

24 Jugoslavenska Oseanska Plovidba v. Castle Investment Co. Inc., [1973] 3 All E.R. 498.

25 In re United Railways of the Havana and Regia Warehouses, Ltd.,[1959] 1 All E.R. 214 (CA).

26 Schorsch Meier GmbH v. Hennin, [1975] 1 All E.R. 152

27 Miliangos v. George Prank (Textiles) Ltd., 1976 AC 443.

18

restrictions under the Foreign Exchange Regulation Act, 1973

(that was in force at the time) must be considered. If permission is

not granted by the authorities to pay the decretal amount in

foreign currency, the amount would have to be converted to Indian

rupees for payment of an equivalent amount. The date of

conversion becomes relevant here, as the “court must select a date

which puts the plaintiff in the same position in which he would have

been had the defendant discharged his obligation when he ought to

have done, bearing in mind that the rate of exchange is not a

constant factor but fluctuates, and very often violently fluctuates,

from time to time.”

28 These are the guiding principles and

considerations for the Court to determine the relevant date, which

are apposite even today.

5.5 The Court then undertook a detailed examination of each of

the 6 dates that it set out earlier and held that the date of the

decree (the third option) is the most appropriate amongst them.

The Court adopted the approach of eliminating other possible

dates, on the following grounds:

i. The date when the amount becomes due and payable does

not have the same effect of putting the plaintiff in the same

28 Forasol (supra), para 40.

19

position that he would have been in if the defendant had

discharged his obligation. Due to the fluctuations in

exchange rate, using this date could result in the decreeholder only receiving a fraction of or a lot more than what

he is entitled to.

29

ii. The second date – when the action or suit commenced –

was rejected for the same reason as above, considering

that there is usually a large period of time between the

filing of the suit, the decree by the Trial Court, subsequent

appeals, revisions, and reviews, and the final decision.30

iii. The Court favourably discussed the third option, i.e., the

date of the decree or judgment. It held that the decree

crystallises the amount payable to the decree-holder. To

account for appeals and revisions, the date when the

action is finally disposed of and when the decree becomes

final and binding on both parties, after exhausting all

remedies, can be used. However, it observed that the only

objection to be considered against this date is that there is

29 ibid, para 41.

30 ibid, para 42.

20

a significant lapse of time between the decree and its

execution.31

iv. The Court rejected the fourth date, i.e., the date of court

order for execution, despite the same being used in English

law as per the decision in Miliangos (supra). It noted that

the process of execution in India is a lengthy one that may

require attachment of property, deciding third party claims

to such property, proclamation with particulars, and

auction sale. Moreover, multiple applications for execution

may be required if the initial attachment and sale does not

cover the decretal amount. Hence, it may lead to a

situation where there are multiple execution orders,

meaning multiple exchange rates would have to be

considered. Another difficulty is that the execution

application itself requires the amount to be expressed in

Indian currency.

32

v. The date of payment was also rejected as the proper date

due to practical and procedural difficulties of having to pay

court fees on a determined amount in Indian rupee; the

pecuniary limit of the jurisdiction of courts would depend

31 ibid, para 43.

32 ibid, paras 44-46.

21

on the amount claimed, which must again be in Indian

rupee; and execution is for a specific sum expressed in

Indian rupee. For these reasons, the Court held that the

conversion of the amount to the domestic currency cannot

be left to the date of payment as the legal procedures in

India require the amount to be determined in domestic

currency before that.33

vi. Among the remaining dates, the Court was of the opinion

that the date of the judgment/decree is the most

appropriate.34 It rejected the date of the arbitral award as

the proper date while observing that the Jugoslavenska

case (supra), where this date was used, was doubted even

by the House of Lords in Miliangos (supra). If the law laid

down in Miliangos (supra) were to be applied to arbitral

awards, the date of conversion would be when the court

grants leave under Section 26(1) of the Arbitration Act,

1950 (UK) to enforce such award in the same manner as a

judgment or to the same effect.35 Further, noting the

differences between the statutory scheme for enforcement

33 ibid, paras 47-52.

34 ibid, para 53.

35 ibid, paras 61-62.

22

of foreign arbitral awards in the UK and in India, it held

that the Jugoslavenska case (supra) will not apply in the

Indian context considering the procedure under Section 17

is different from the procedure under English law.

36

Section 17 of the Arbitration Act, 194037 required a

judgment and decree to give an award the status of a

decree, i.e., making it a rule of court, for the award to

become enforceable. On the other hand, English law38 did

not require a judgment to be passed in all cases and it was

sufficient for the court to grant leave to enforce the award

in the same manner as a judgment. In Indian law, it was

not the arbitral award but only the decree of the court that

could be enforced by an application for execution.39 Hence,

the Court found that rather than the date of the arbitral

award, the date of the judgment and decree under Section

17 is the most appropriate one to determine the conversion

36 ibid, paras 63-65.

37 Section 17 reads:

“17. Judgment in terms of award.—Where the Court sees no cause to remit the award or any of

the matters referred to arbitration for reconsideration or to set aside the award, the Court shall,

after the time for making an application to set aside the award has expired, or such application

having been made, after refusing it, proceed to pronounce judgment according to the award, and

upon the judgment so pronounced a decree shall follow and no appeal shall lie from such decree

except on the ground that it is in excess of, or not otherwise in accordance with, the award.”

38 See Section 26(1) of the Arbitration Act, 1950, which provides:

“26. Enforcement of award.—(1) An award on an arbitration agreement may, by leave of the High

Court or a Judge thereof, be enforced in the same manner as a judgment or order to the same effect,

and where leave is so given, judgment may be entered in terms of the award…”

39 Forasol (supra) paras 65-66. 

23

rate as it was only then that the arbitral award became

enforceable.

6. The above extensive discussion on Forasol (supra) is

necessary to understand the principles set out by this Court to

determine the relevant date for conversion. The law laid down in

this case was subsequently affirmed by a 3-judge bench of this

Court in Renusagar Power Co. Ltd v. General Electric Co40 in

the context of the Foreign Awards (Recognition and Enforcement)

Act, 1961. A foreign arbitral award in favour of the respondentclaimant, which is an American company, was passed where the

amount was expressed in US dollars. The respondent then filed for

enforcement of this award before the Bombay High Court under

the Foreign Awards (Recognition and Enforcement) Act, 1961 as

the appellant was an Indian company. Both the single judge and

division bench of the High Court allowed the enforcement of the

award and dismissed Renusagar’s objections under Section 7 of

this Act. The matter was then appealed to this Court, which dealt

with several issues on objections to the enforceability of foreign

awards, including the scope of inquiry under Section 7 and the

meaning of ‘public policy’. The most relevant issues framed by the

40 Renusagar (supra), see paras 131-133. 

24

Court, for our purpose, are which law would govern the rate of

exchange for conversion in proceedings for enforcement of a

foreign arbitral award and whether Forasol (supra) required

reconsideration. The Court held that the applicable law to

determine the proper date for conversion is the lex fori41, which

would be Indian law. After extensively discussing the principles

under English law as well as the reasoning in Forasol (supra), the

Court rejected the contention that Forasol (supra) required

reconsideration42.

7. The law laid down in Forasol (supra) has also been used in

other cases though they do not pertain to arbitration but involved

an issue of a debt expressed in foreign currency that required to

be converted to Indian rupee. United India Insurance Co. Ltd. v.

Kantika Colour Lab43 involved a consumer complaint for

payment of an insurance claim due to the damage of a printer in

transit. This Court did not cite Forasol (supra) but used the date

of its judgment as the proper date for conversion of the cost of the

printer that was expressed in Singaporean dollars. In Meenakshi

Saxena v. ECGC Limited44, again was a consumer complaint for

41 ibid, paras 107-108.

42 ibid, para 133.

43 (2010) 6 SCC 449.

44 (2018) 7 SCC 479.

25

payment under an insurance contract for loss suffered during

export of goods, the Court noted that the contract provided for a

date on which the exchange rate must be determined and followed

Forasol (supra) to hold that this is the proper date.

7.1 In certain other cases, the principle in Forasol (supra) has

been considered but not applied due to the peculiar facts of those

cases. For example, in cases of motor accident deaths where the

deceased was earning in foreign currency, the Court has refused

to use the date of the judgment as the proper date and has instead

used the date of filing the claim as the claims in these cases were

filed in Indian rupee and the Tribunal also decided the cases in

Indian rupee. Hence, it was held that the amount already stood

converted in the claim itself.45 Similarly, in Triveny Kodkany v.

Air India Limited46 involving claim for compensation due to the

death of an airline passenger, the Court considered Forasol (supra)

and Renusagar (supra) but did not apply them. It differentiated the

facts in those cases as in both of them, the award holders were

foreign companies. However, in this case, the claimants seeking

compensation were residing in India. Further, like in motor

45 See United India Insurance Co. Ltd v. Patricia Jean Mahajan, (2002) 6 SCC 281; Jiju Kuruvila v. Kunjujamma

Mohan, (2013) 9 SCC 166.

46 (2021) 19 SCC 214. 

26

accident cases, it found that the claim for payment was itself in

Indian rupees and interest was also provided on such amount.

Hence, it found that the date of filing the complaint is the proper

date for conversion.

8. It is therefore clear from the above-referred analysis of

judicial determinations that the principle and law laid down in

Forasol (supra) has been widely considered and followed by this

Court in various types of matters. There is no impediment for us

to apply this decision to cases under the 1996 Act, even though it

was decided under the Arbitration Act, 1940. We therefore disagree

with the High Court that Forasol (supra) does not apply to cases

under the 1996 Act.

9. The Delhi High Court has also relied on Forasol (supra) in

several cases on the enforcement of domestic and foreign arbitral

awards where the amount is expressed in foreign currency:

9.1 In Fuerst Day Lawson v. Jindal Exports Ltd47, the High

Court relied on Forasol (supra) and analogised that the date on

which the objections to the enforcement of the award are finally

rejected and the foreign award becomes enforceable would be the

47 2012 SCC OnLine Del 5647.

27

date that it is deemed to be a decree under Section 49. Hence, this

would be the relevant conversion date.

9.2 This case was followed in Progetto (supra), where the

relevant date was held to be when this Court dismissed the SLP in

the objections petition. The award debtor herein had deposited the

entire amount only after the dismissal of the SLP by using the

exchange rate as on the date of deposit, which was higher than the

rate as on date of dismissal of SLP. Hence, the High Court while

deciding the execution petition directed refund of the excess

amount by using the date of this Court’s order as the relevant date.

In so far as the present appeal is concerned, we have already

mentioned that the respondent was permitted to withdraw 7.5

crores during the pendency of the proceedings.

9.3 Similarly, in Trammo AG v. MMTC Limited48, the date of

dismissal of review by this Court in the proceedings to set aside

the award was held to be the relevant date.

9.4 In Voith Hydro v. NTPC Limited49, the award debtor had

paid some part of the arbitral award amount during the pendency

of proceedings to set aside the award. It paid 75% of the amount

on 06.11.2018, against bank guarantees by the award holder, in

48 2019 SCC OnLine Del 7337.

49 2021 SCC OnLine Del 1325. 

28

accordance with a Niti Aayog Circular. Subsequently, this Court

dismissed the SLP in the 22.09.2020. The High Court held that the

exchange rate as on 06.11.2018 would apply insofar as 75% of the

deposit is concerned as the claimant had received this partpayment and the exchange rate on 22.09.2020 was higher than on

06.11.2018. Relying on Forasol (supra), Renusagar (supra), and

Fuerst Day Lawson (supra), it held that the exchange rate on

22.09.2020 would apply to the remaining amount.

9.5 In Karamchand Thapar & Bros. (Coal Sales) Ltd. v.

MMTC Ltd.50, the date on which the arbitral award attained finality

(when the SLP in the Sections 34 and 37 proceedings was

dismissed) was determined as the relevant date for the exchange

rate. Here, the award debtor had deposited an amount subsequent

to the dismissal of the SLP at the exchange rate as on date of

deposit, which was higher than the exchange rate when the SLP

was dismissed. The High Court therefore also directed the award

holder to refund the excess amount paid by the award debtor. This

case does not involve deposit during the pendency of the

objections.

50 2022 SCC OnLine Del 949. 

29

10. Applying the Principle in Forasol under the 1996 Act: The

reason that this Court in Forasol (supra) determined the date of

the decree under Section 17 of the 1940 Act as the proper date is

that it is only then that the arbitral award becomes enforceable.

However, as set out earlier, the statutory scheme under the 1996

Act does not require such a judgment or decree to be passed for a

foreign award to be enforceable. Rather, the enforceability of a

foreign award is automatic and deemed under Section 49 after the

objections against such an award under Section 48 are finally

decided and disposed of. At this point, the award is enforceable as

a decree of a court (Section 49). Hence, the date on which the

objections are finally decided and dismissed would be the proper

date for determining the exchange rate to convert an amount

expressed in foreign currency.

10.1 In the present case, this date is 01.07.2014 – when the

High Court dismissed the revision petition against the Trial Court

order dismissing the appellants’ objections. No further appeal was

preferred from this order and hence, it attained finality. While the

learned counsels have not contested this issue, it was necessary

for us to delve into the reason and principle behind selecting this 

30

date and to settle the position of law on the applicability of Forasol

(supra) under the 1996 Act.

11. Conversion of Deposited Amounts: The primary contention by

the learned counsels was regarding the proper date to determine

the exchange rate to the extent of Rs. 8 crores that was deposited

in the court pursuant to certain orders. The learned counsels have

both referred to decisions by the Delhi High Court on this point.

Mr. Mishra heavily relied on Voith Hydro (supra), where the arbitral

award was partly paid against bank guarantees under a Niti Ayog

circular, before the objections were finally decided. The High Court

here held that the paid amount stood converted as on the date of

payment as it was received by the award-holder and the exchange

rate increased by the time the objections were finally decided. On

the other hand, Mr. Mahajan has relied on Karam Chand Thapar

(supra), where again a deposit of some part of the amount was

made, albeit after the final decision on objections. Here the High

Court held that the date on which the SLP in the objections was

dismissed would be the proper date.

11.1 In the present case, it is important to note the terms on

which the two deposits of Rs. 7.5 crores and Rs. 50 lakhs were

made. From the order of the High Court dated 15.10.2010, it is 

31

clear that such order for deposit of Rs. 7.5 crores and for

furnishing a bank guarantee of an Indian bank for the release of

the deposit was made in accordance with the consent of the

parties. Mr. Mahajan’s submission that the respondent did not

consent to the deposit hence cannot be accepted. The further

deposit of Rs. 50 lakhs was made pursuant to an interim order of

the High Court dated 03.06.2011, which stayed the Trial Court

order dated 02.04.2011 and directed the deposit. However, unlike

the previous order, neither was this order passed on the consent

of the parties nor did it permit the respondent to withdraw the

money during the pendency of the proceedings. Rather, it directed

that the amount shall be deposited in a fixed deposit receipt and

shall be disbursed to the successful party on the final adjudication

of the objections.

11.2 We will first deal with the deposit of Rs. 7.5 crores.

Despite being permitted to withdraw this amount by furnishing a

bank guarantee, the respondent did not do so until 2016. Mr.

Mahajan contended that being a foreign company, it was unable

to obtain a bank guarantee from an Indian bank. However, the

order of 15.10.2010 clearly records the respondent’s consent to

this condition. Further, when it was unable to comply with the 

32

same, it also did not apply for a modification or removal of the

condition. Hence, the respondent, in its own discretion, did not

withdraw Rs. 7.5 crores when it was deposited in 2010.

11.3 A similar situation arose in this Court’s decision in

Renusagar (supra) as well. This Court was deciding an appeal

against the dismissal of Renusagar’s objections under Section 7 of

the Foreign Awards Act, 1961. During the pendency of the appeal,

by order dated 21.02.1990, this Court stayed the operation of the

High Court order subject to deposit of one-half of the decretal

amount calculated as on date. General Electric was permitted to

withdraw the deposited amount by furnishing security by way of

bank guarantee for the sum to be withdrawn in excess of Rs. 4

crores. It also directed that 10% interest p.a. would be payable by

Renusagar on the balance of the decretal amount in case the

appeal is dismissed, and the same interest would be payable by

General Electric on the amount withdrawn by it if the appeal is

allowed. Pursuant to this order, Renusagar deposited Rs. 9.69

crores on 20.03.1990, which was withdrawn by the respondent on

furnishing necessary bank guarantee. In a subsequent order, this

Court directed a further deposit of Rs. 1 crore and bank guarantee

of Rs. 1.92 crores to be furnished by Renusagar. The deposit was 

33

made on 03.12.1990, which was also withdrawn51. However,

General Electric contended that it was unable to use a large part

of this amount as it had not received permission from the Reserve

Bank of India to convert the same into US dollars due to the

pendency of the appeals.

11.4 After rejecting various submissions by the appellant

regarding the enforceability of the award, this Court decided the

question of the amount in Indian rupee that was to be paid. The

relevant portion on this point is extracted:

“141. As indicated earlier, in pursuance to the orders of this Court

dated February 21, 1990, Renusagar deposited a sum of Rs

9,69,26,590 on March 20, 1990 and a further amount of Rs

1,00,00,000 was deposited by Renusagar in pursuance to the order

dated November 6, 1990 on December 3, 1990. These amounts have

been withdrawn by General Electric. The question is how and at what

rate the said amount should be adjusted against the decretal amount.

It is not disputed that on the date when the said deposits were made

by Renusagar and were withdrawn by General Electric, rupee-dollar

exchange rate was Rs 17 per dollar. Shri Shanti Bhushan has,

however, submitted that although General Electric had withdrawn

the amount deposited by Renusagar, it was not able to use the same

because the Reserve Bank of India did not grant the permission to

General Electric to remit the amount by converting the same into U.S.

dollars on account of the pendency of these appeals in this Court…

Shri Shanti Bhushan has, therefore, submitted that the amounts

deposited by Renusagar should be converted from Indian rupees into

U.S. dollars at the exchange rate prevalent on the date of the

judgment of this Court and not on the basis of the rate of exchange

prevalent at the time of the said payments by Renusagar. We are

unable to agree with this submission. The convertibility into U.S.

dollars of money paid by Renusagar in Indian rupees is not the

condition for discharge of the decree and as laid down in Forasol

case the decree can be discharged by payment in Indian rupees and

it is for General Electric to obtain the necessary permission from the

Reserve Bank of India for such conversion of Indian rupees to U.S.

51 Renusagar (supra), para 18. 

34

dollars and the transfer thereof to the United States. If General

Electric were finding a difficulty in such transfer on account of the

pendency of these appeals in this Court they could have moved this

Court and obtained necessary clarification in this regard. They did

not choose to do so. In these circumstances, the amount of Rs

10,69,26,590 which has been paid by Renusagar in pursuance to the

orders dated February 21, 1990 and November 6, 1990 has to be

converted into U.S. dollars on the basis of the rupee-dollar exchange

rate of Rs 17.00 per dollar prevalent at the time of such payment and

calculated on that basis the said amount comes to US $ 6,289,800.00.

142. The judgment of the High Court passing a decree in terms of the

award is, therefore, affirmed… The amount paid by Renusagar

during the pendency of these appeals will have to be adjusted against

the said decretal amount and the present liability of Renusagar under

this decision has to be determined accordingly. Calculating on this

basis the amount payable by Renusagar under the decree in terms of

U.S. dollars is:

Amount awarded by the Arbitral

Tribunal

: 12,215,622.14

Interest on US $ 2,716,914.72

(the total amount awarded under

item Nos. 1, 3 and 5) @ 8% per

annum from 1-4-1986 to 15-10-

1986 in terms of the award

: 117,733.00

12,333,355.14

Less: Amount paid by Renusagar

in pursuance of the orders dated

21-2-1990 and 6-11-1990 during

the pendency of the appeals in

this Court

6,289,800.00

6,043,555.14

143. In accordance with the decision in Forasol case the said amount

has to be converted into Indian rupees on the basis of the rupee-dollar

exchange rate prevailing at the time of this judgment. As per

information supplied by the Reserve Bank of India, the Rupee-Dollar

Exchange (Selling) Rate as on October 6, 1993 was Rs 31.53 per

dollar.”

35

11.5 From the above, it is clear that the Court adjusted the

amounts deposited during the pendency of the proceedings and

against security by converting them to US dollars as on the date of

their deposit. It applied the date of its own judgment only for

converting the remaining portion of the award in accordance with

Forasol’s (supra) ruling that the date of decree or judgment, after

exhausting all remedies, is the proper date. It rejected the

respondent’s argument regarding its inability to convert the

amount on the grounds that a decree in foreign currency can be

validly satisfied by payment in Indian rupee and the respondent

did not move the Court for necessary clarification.

12. The facts in this case are similar to Renusagar (supra) for an

analogy to be drawn. Here as well, the deposit was made during

the pendency of the proceedings under the objections petition. It

was permitted to be withdrawn against a bank guarantee of an

Indian bank. Here the respondent was entirely unable to withdraw

the amount, while the issue there was that it was only unable to

convert the amount to US dollars. However, in both cases, the

respondent failed to move the Court for necessary orders to be able

to receive and utilise the amount. In this case, there is the added

fact that the respondent consented to the deposit and the condition 

36

requiring security. In light of these similarities, it is appropriate for

us to adopt the Court’s approach in Renusagar (supra).

13. We therefore hold that the deposit of Rs. 7.5 crores stands

converted as on the date of deposit (22.10.2010), when the rate of

exchange as submitted by the appellants is 1 euro = Rs. 59.17. We

also reject the submission by Mr. Mahajan that the respondent

was unable to furnish a bank guarantee of an Indian bank. This

argument is only to serve its own interest to be able to benefit from

a higher exchange rate but does not address the principle that

operates while enforcing a sum expressed in foreign currency.

14. It is important to appreciate the consequence and effect of

deposit during the pendency of proceedings to understand the

need to convert this amount on that date. Through a deposit, the

award debtor parts with the money on that date and provides the

benefit of that amount to the award holder. Provided that the

award holder is permitted to withdraw this amount, it can convert,

utilise, and benefit from the same at that point in time.

Considering that the deposited amount inures to the benefit of the

award holder, it would be inequitable and unjust to hold that the

amount does not stand converted on the date of its deposit.

37

15. A similar logic underscores the statutory provisions in Order

21, Rule 1 and Order 24 of the Code of Civil Procedure, 190852 to

determine whether interest will continue to operate on an amount

deposited before a court. It would be relevant for us to briefly

discuss the law on this point:

15.1 A constitution bench of this Court in Gurpreet Singh v.

Union of India53 extensively discussed the rules governing interest

calculation when the defendant/ judgment-debtor deposits some

part of the amount. Order 24 governs deposits at the pre-decretal

stage and Order 21, Rule 1 at the post-decretal stage.54 The

essence of these provisions is that on any amount deposited into

the court, interest shall cease to run from the date when the

depositor serves a notice to the plaintiff/decree-holder. Similarly,

when payment is tendered to the decree-holder outside the court,

interest ceases on such amount even if the payment is refused.55

15.2 Order 21, Rule 1 embodies a rule of prudence that once

the amount is tendered to the decree-holder by the judgmentdebtor, whether in the form of a court deposit or other forms of

52 Hereinafter “CPC”.

53 (2006) 8 SCC 457.

54 ibid, para 14.

55 ibid, paras 15, 25 and 26.

38

payment such as demand draft or cheque, the judgment-debtor

cannot be made liable to then pay interest on such amount.56

15.3 The rationale for this rule has been explained in Nepa

Limited v. Manoj Kumar Agrawal57 through a similar logic of the

decree-holder being able to benefit from the deposited amount. In

this case, the award-debtor deposited 50% of the awarded amount

before the executing court to obtain a stay on the execution

proceedings of the arbitral award during the pendency of appeal

under Section 37 of the 1996 Act. This amount was withdrawn by

the award holder, and the issue before this Court was whether

interest is payable on the deposited amount even after the date of

deposit. The Court held as follows:

“21. In the present case, the appellate court, on the appeal preferred

under Section 37 of the Act did grant stay, subject to the condition

that the appellant would deposit 50% of the amount. Rs. 7,78.280/-

was deposited by the appellant on 05.11.2001. The stay, therefore,

only operated for the balance amount. On the balance amount,

certainly, the appellant would be liable to pay interest @ the rate of

18% per annum till the date of actual payment. However, on Rs.

7,78,280/- paid, after adjusting/appropriating payment due on the

interest accrued, on the balance principal amount paid to the

respondent, interest would not be payable.

24. The respondent submits that the payment of Rs. 7,78,280/- being

conditional, the respondent would have been under an obligation to

refund the said amount in case the appellant had succeeded in the

appeal under Section 37 of the Act, 1996. This argument does not

impress, as in the event the appellant had succeeded in their appeal,

the entire amount paid would have been refundable. The undertaking

was not onerous, and was to operate only if the amount of Rs.

7,78,280/- was not refunded by the respondent. The respondent had

56 KL Suneja v. Dr Manjeet Kaur Monga, (2023) 6 SCC 722, para 36.

57 2022 SCC OnLine SC 1736.

39

obviously used and utilized the money. The appellant did not have

any right on the money paid to the respondent, who could use it in a

manner and way he wanted. There was no charge. Money is fungible

and would have gotten mixed up with the other amounts available

with the respondent. Right to restitution would not make the payment

conditional. Interest has been jurisprudentially defined as the price

paid for money borrowed, or retained, or not paid to the person to

whom it is due, generally expressed as a percentage of amount in one

year. It is in the nature of the compensation allowed by law or fixed

by parties, for use or forbearance or damage for its detention. In the

context of the present case, interest would be the compensation

payable by the appellant to the respondent, for the retention or

deprivation of use of money. Therefore, once the money was paid to

the respondent, interest as compensation for deprivation of use of

money will not arise.”

(emphasis supplied)

15.4 Therefore, the ability of the decree-holder to access and

use the money in a manner he deems fit was considered by this

Court while deciding the issue.

15.5 Here, the Court also differentiated P.S.L. Ramanathan

Chettiar (supra), which has also been relied on by the respondent

in the present matter, and another decision by this Court in Delhi

Development Authority v. Bhai Sardar Singh and Sons58. P.S.L.

Ramanathan Chettiar (supra) holds that a deposit is only a way to

obtain a stay on execution and does not pass title to the decreeholder, and hence, is not in satisfaction of a decree. The decreeholder in Delhi Development Authority (supra) was not permitted to

withdraw the deposited amount and hence, interest was calculated

on the same. The Court in Nepa Limited (supra) however held that

58 C.A. 3867 of 2010. 

40

these cases do not apply in its facts as the respondent here was

permitted to withdraw the deposited sum and did so. Hence, the

Court instead relied on the ability of the respondent to use the

deposited money as it deems fit.

16. These cases demonstrate that once there is a deposit by the

award debtor and the award holder is permitted to withdraw the

same, even if such withdrawal is conditional and subject to the

final decision in the matter, the court must consider that the

award holder could access and benefit from such deposit. It is then

the burden of the award holder to furnish security, as required by

the court’s orders, to utilise the amount or to make an application

for modification of the condition if it is unable to fulfil the same.

17. In furtherance of the above, we therefore reiterate that the

deposit of Rs. 7.5 crores must be converted as on the date of such

deposit, i.e., 22.10.2010, when the rate of exchange as submitted

by the appellants was 1 euro = Rs. 59.17.

18. The second deposit of Rs. 50 lakhs pursuant to the High

Court order dated 03.06.2011 stands on a different footing from

the first deposit. This order did not permit the respondent to

withdraw this amount till the completion of the proceedings.

Hence, the amount cannot be converted as on the date of deposit 

41

as the respondent could not have benefitted from the same. This

amount could be withdrawn only in 2016, pursuant to the

Executing Court’s order dated 24.08.2016. The respondent

withdrew the entire deposit of Rs. 8 crores, along with the interest

that accrued on this amount, on 10.10.2016.

19. From the above discussion on the first deposit, it is clear that

the exchange rate on 22.10.2010 would apply to that extent and

non-withdrawal by the respondent of Rs. 7.5 crores was in its own

discretion and inaction. However, since the order of 03.06.2011

permits withdrawal of Rs. 50 lakhs on the completion of the

proceedings, that would be the appropriate date for determining

the exchange rate. Here, the revision proceedings were complete

on 01.07.2014. Hence, it would be appropriate to apply the

exchange rate as on this date to convert the deposit of Rs. 50 lakhs.

20. Our conclusions from this judgment can be summarised as

follows:

i. The statutory scheme of the Act makes a foreign arbitral

award enforceable when the objections against it are finally

decided. Therefore, as per the Act and the principle in

Forasol (supra), the relevant date for determining the 

42

conversion rate of foreign award expressed in foreign

currency is the date when the award becomes enforceable.

ii. When the award debtor deposits an amount before the

court during the pendency of objections and the award

holder is permitted to withdraw the same, even if against

the requirement of security, this deposited amount must

be converted as on the date of the deposit.

iii. After the conversion of the deposited amount, the same

must be adjusted against the remaining amount of

principal and interest pending under the arbitral award.

This remaining amount must be converted on the date

when the arbitral award becomes enforceable, i.e., when

the objections against it are finally decided.

21. As per these conclusions, the first deposit of Rs. 7.5 crores

must be converted as on the date of deposit being 22.10.2010. The

second deposit of Rs. 50 lakhs as well as the remaining amount

due under the award must be converted when the objections

proceedings attained finality on 01.07.2014. The Executing Court,

being the Additional District Judge cum Commercial Court, must

determine the amount payable by taking into account the

exchange rate as on 01.07.2014.

43

22. In light of the above, we partly allow the appeal, and set aside

the findings of the High Court in the impugned judgment to the

extent that Forasol (supra) does not apply under the 1996 Act and

that the exchange rate on 01.07.2014 must be used for converting

the entire arbitral award and interest.

23. Pending applications, if any, stand disposed of.

24. No order as to costs.

………………………………....J.

[PAMIDIGHANTAM SRI NARASIMHA]

………………………………....J.

[ARAVIND KUMAR]

NEW DELHI;

AUGUST 08, 2024.