LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Sunday, May 2, 2021

after the enhancement of load, it was facing major trippings as well as continuous load shedding which was affecting the costly machineries and, therefore, the respondent decided to reduce the load from 4000 KVA to 1325 KVA. Accordingly, the respondent filed an application, on 20.09.2007, before the authority of the appellantsBoard for such reduction.

1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.6145 OF 2010

JHARKHAND STATE ELECTRICITY 

BOARD AND OTHERS …..APPELLANTS

VERSUS

M/S RAMKRISHNA FORGING 

LIMITED       .….RESPONDENT

                      J U D G M E N T

Vineet Saran, J.

The respondent is a small scale industry. For

running   its   industry,   it   had   a   contract

demand/sanctioned load of electricity of 4000 KVA from

the appellants­Jharkhand State Electricity Board (for

short ‘the Board’). The request of the respondent for

reduction of such sanctioned load to 1325 KVA having

been refused, the respondent filed a writ petition before

2

the High Court of Jharkhand, which has been allowed.

Aggrieved by the said judgment of the High Court, this

appeal has been preferred by the Board.

2. The brief facts, relevant for the present case,

are   that   the   respondent,   which   is   a   small   scale

industry, had entered into an agreement with the Board

on 14.04.2004 for High Tension (H.T.) connection of 325

KVA   load.     The   respondent   thereafter   applied   for

enhancement of load from 325 KVA to 1325 KVA, which

was   allowed   by   the   General   Manager­cum­Chief

Engineer of the Board on 14.03.2006.  The respondent

again applied for enhancement of load from 1325 KVA

to 3500 KVA, which was sanctioned by the Board on

26.12.2006.   On a further request of the respondent,

the load was again enhanced by 500 KVA to 4000 KVA.

For each enhancement of load, fresh agreements to that

effect were entered into between the respondent and the

Board, the last one being on 07.07.2007 for supply of

4000 KVA load.   The respondent alleges that after the

3

enhancement of load, it was facing major trippings as

well as continuous load shedding which was affecting

the costly machineries and, therefore, the respondent

decided to reduce the load from 4000 KVA to 1325 KVA.

Accordingly,   the   respondent   filed   an   application,   on

20.09.2007,   before   the   authority   of   the   appellantsBoard   for   such   reduction.     Vide   its   order   dated

08.11.2007,   the   Electrical   Superintending   Engineer

rejected   the   said   application   of   the   respondent   for

reduction of load from 4000 KVA to 1325 KVA informing

the respondent that from the date of enhancement of

supply of load, an agreement (dated 07.07.2007) would

be enforced for a period of three years and treating it to

be a case of determination of agreement, and quoting

the Clause 9B of the agreement, it was provided that

the agreement could not be permitted to be determined

prior to the completion of initial period of three years

from 07.07.2007 and that the respondent will have to

pay the minimum guarantee charges and other charges,

4

even   if   the   respondent   decides   to   terminate   the

agreement.  

3. Challenging the said order of the Board dated

08.11.2007, the respondent filed Writ Petition No.6651

of 2007, which has been allowed by the High Court vide

its judgment dated 23.07.2008, primarily on the ground

that the proviso contained in Regulation 9.2.1 of the

Jharkhand   State   Electricity   Regulatory   Commission

(Electricity Supply Code) Regulations, 2005 (for short,

‘the Regulations of 2005’), providing for no reduction of

load to be allowed by the Distribution Licensee before

expiry   of   the   initial   period   of   agreement   was

discriminatory, arbitrary and against the public policy.

Challenging   the   aforesaid   judgment,   this   appeal   has

been filed.

4. We   have   heard   Shri   Anup   Kumar,   learned

counsel   appearing   for   the   appellants   and   Shri   N.P.

Singh,   learned   Senior   Counsel   appearing   for   the

5

respondent,   assisted   by   Shri   Devashish   Bharuka,

Advocate­on­Record for the respondent.

5. It   is   noteworthy   that   after   the   initial

agreement   dated  14.04.2004,   which  came   into  effect

from 16.04.2004 whereby the contract demand of 325

KVA   was   allowed   in   favour   of   the   respondent,   the

Jharkhand State Electricity Regulatory Commission (for

short, ‘the Commission’) in exercise of power conferred

by   Section   181(2)(x)   read   with   Section   50   of   the

Electricity   Act,   2003,   framed   the   Jharkhand   State

Electricity   Regulatory   Commission   (Electricity   Supply

Code) Regulations, 2005, which came into effect from

28.07.2005.

6. The submission of the learned counsel for the

appellants­Board, is that in terms of Regulation 9.2.1 of

the Regulations of 2005, which relates to the reduction

of contract demand/sanctioned load, no reduction of

load could be allowed before the expiry of the period of

agreement which, according to the appellants, would be

6

07.07.2007 when a fresh agreement was executed for

enhanced load of 4000 KVA.   Learned counsel for the

appellants has thus submitted that the application for

reduction of load filed by the respondent on 20.09.2007,

which was well within the period of three years from

07.07.2007, was rightly rejected by the Board vide its

order dated 08.11.2007, as it was in conformity with

the provisions of the Regulations of 2005.

7. Per contra, learned Senior Counsel appearing

for the respondent has submitted that the agreement

was initially entered into on 14.04.2004 and thereafter

even   though   technically   fresh   agreements   may   have

been   executed   for   enhancement   of   load   of   the

respondent,   but   the   same   were   only

extension/amendment   of   the   initial   agreement   dated

14.04.2004, and the terms of each of these agreements

were identical, with the only change being that of the

increased contracted load.   It has been contended by

the learned Senior Counsel for the respondent that the

7

Regulations   do   not   permit   execution   of   a   fresh

agreement   in  case   of  enhancement   of  load,   and  the

enhancement   agreements   would   merely   be

supplementary agreements in continuation of the initial

agreement dated 14.04.2004 and cannot be treated as

fresh   agreement   because   it   is   the   same   electricity

connection, which was granted by the agreement dated

14.04.2004,   in   which   there   have   been   amendments

from   time   to   time   for   increase   of   load,   and   merely

executing a fresh agreement for enhancement of load

cannot be termed as fresh agreement for the purpose of

Regulations of 2005.  It has, thus, been submitted that

the application of the respondent for reduction of load

dated 20.09.2007 has to be treated as after a period of

three years from the date of initial agreement dated

14.04.2004 and thus, the application of the respondent

ought to have been allowed and/or should be deemed to

be allowed in terms of the provisions of Regulations of

8

2005.     In   this   regard,   reliance   has   been   placed   on

Regulations 2(l), 9.1 and 9.2 of the Regulations of 2005.

8. For   the   ready   reference,   the   relevant

provisions of the Regulations of 2005 are reproduced

below:­

“2. Definitions. 2.1 In these regulations,

unless the context otherwise requires:

(a)…..

(b)…..

(c)…..

……...

(l)   “Contract   Demand”  means

demand   in   Kilowatt   (KW)   or   Kilo   Volt

amperes   (KVA)   or   H.P   (Horse   Power)

mutually agreed between the Distribution

Licensee   and   the   consumer   as   entered

into   agreement  or   agreed   through   other

written communication. 

(m)…..

(n)…..

9.   Enhancement   and   Reduction   of

Contract Demand/Sanctioned Load. – 

9.1 Enhancement of Contract Demand

/Sanctioned Load

9.1.1 The application for enhancement of

Contract Demand/Sanctioned Load shall

be made in the prescribed form and in the

9

manner   as   specified   in   new   service

connection   in   Clause   5   of   these

Regulations. 

9.1.2 The application for enhancement of

load shall be disposed of in the manner

and within the time frame as prescribed

for   new   service   connection   in   Clause

6.2.11 of these Regulations.

Provided  that   the   application   for

enhancement   of   Contract

Demand/Sanctioned   Load   may   be

outright   rejected   by   the   distribution

licensee if the consumer is in arrears of

licensee’s   dues   and   the   same   have   not

been   stayed   by   a   court   of   law   or   the

Commission.

9.2   Reduction   of   Contract

Demand/Sanctioned Load. ­ 

9.2.1  The   application   for   reduction   of

Contract Demand/Sanctioned Load shall

made in the prescribed form specified for

the new service connection.

Provided  that no reduction of load shall

be   allowed   by   the   Distribution   Licensee

before   expiry   of   the   initial   period   of

agreement. 

9.2.2 The application for reduction of load

shall be accompanied by­

(i) Details of modification, alteration and

removal   of   electrical   installation   with

completion certificate and test report of the

Licensed Electrical contractor. 

(ii) Any other reason for reduction of load

10

(iii) Details of generator if any installed by

the   consumer   with   safety   clearance

certificate   from   competent   authority   as

applicable. 

9.2.3  The   Distribution   Licensee   shall

consider the application verify the same

and communicate in writing its decision on

reduction of Contract Demand/Sanctioned

Load   in   writing   within   30   days   of   the

application.

Provided  that if the distribution licensee

rejects or refuses the reduction of Contract

Demand/Sanctioned Load it shall do so

after   affording   the   consumer   reasonable

opportunity of being heard in the matter

and   after   communicating   in   writing   the

reasons for such refusal. 

9.2.4  If the decision of the application for

reduction of Contract Demand/Sanctioned

Load is not communicated by the licensee

within   30   days   of   the   application,   the

consumer   shall   send   a   notice   to   the

licensee   requesting   for   disposal   in   the

matter   and   if   the   decision   is   still   not

communicated   within   15   days   of   the

notice.     The   reductions   of   Contract

Demand/   Sanctioned   Load   shall   be

deemed to have been sanctioned, from the

16th day after the issue of notice to the

licensee by the consumer.

9.2.5  The   reduction   of   Contract

Demand/Sanctioned Load shall come into

effect   from   the   first   day   of   the   month

following the month in which the reduction

of load has been sanctioned or have been

deemed to be sanctioned. 

11

9.2.6 After the sanction of the reduction of

Contract   Demand/Sanctioned   Load the

consumer shall execute a supplementary

agreement  and   the   licensee   shall

recalculate   the   Security   Deposit   excess

Security Deposit if any shall be refunded

by   way   of   adjustment   in   the   minimum

number   of   succeeding   bills   of   the

consumer.”

(emphasis supplied)

9. The communication dated 08.11.2007 of the

Electrical   Superintending   Engineer   of   the   Board,

refusing the prayer of the respondent for reduction of

load, is reproduced below:­

“Sub:     Regarding   the   reduction   of

load from 4000 KVA to 1325

KVA   in   respect   of     M/s   R.K.

Forging Ltd. Conn. No. HJAP185

Ref:    Your letter No. R.K.F.L/III and IV

182/07­08 dated 05.10.2007.

With respect to the above, you have

applied   for   reduction   of   C.D   from

4000KVA to 1325KVA.  It is to inform you

that C/9B of agreement may kindly be

seen.

‘C/9B­ The consumer shall not be at

liberty to determine this agreement before

the   expiration   of   three   years   from   the

12

date of commencement of the supply of

energy   (4000KVA   w.e.f.   12.07.2007).

The   consumer   may   determine   this

agreement with effect from any date after

the said period on giving to the Board not

less   than   twelve   calendar   months’

previous notice (this has charged not less

than   6   Month   Notice   vide   Secretary,

Jharkhand   State   Electricity   Board

Notification No.5058 dated 20.08.2002) in

writing   in   that   behalf   and   upon   the

expiration   of   the   period   of   such   notice.

This   agreement   shall   cease   and

determine without prejudice to any right

which   then   have   accrued   to   the   Board

herewith   provided   always   that   the

consumers   may   at   any   time   with   the

previous   consent   of   the   Board   transfer

and assign this agreement to any other

person   and   upon   subscription   of   such

transfer, this agreement shall be binding

on   the   transferee   and   Board   and   take

effect in all respects as if transferee had

originally   been   party   in   place   of   the

consumer   who   shall   henceforth   be

discharged from all liabilities under or in

respect thereof.’ 

Hence   your   request   for   reduction

cannot be done as per agreement.”

10. Heard   learned   Counsel   for   the   parties   and

have carefully gone through the record.

13

11. From   perusal   of   the   communication   dated

08.11.2007,   it   is   clear   that   the   application   of   the

respondent for reduction of load has been rejected in

terms of Clause 9(B) of the agreement, treating the date

of commencement of the agreement to be 7/12.07.2007

and only by considering the provision of determination

of the agreement, which could not have been without

giving notice of less than 12 calendar months.   It is

clear   that   the   said   communication/order   does   not

consider the provisions of the Regulations of 2005 with

regard   to   reduction   of   load,   but   only   treats   the

application for reduction of load to be an application for

determination of the agreement.

12. Chapter 9 of the Regulations of 2005 deals

with   the   enhancement   and   reduction   of   contract

demand/sanctioned   load.    Regulation  9.1   deals  with

enhancement   of   contract   demand/sanctioned   load,

whereas   Regulation   9.2   deals   with   the   reduction   of

contract demand/sanctioned load.  

14

13. Just   as   the   consumer   has   the   liberty   of

getting   its   load   enhanced   under   Regulation   9.1,   the

reduction of contract demand/sanctioned load can also

be prayed for and decided in terms of Regulation 9.2.

The proviso to Regulation 9.2.1, no doubt, provides that

no reduction of load shall be allowed before expiry of the

initial period of agreement, which is three years in the

present case. The question would be whether the initial

agreement is to be considered for such purpose, or the

subsequent agreements. 

14. Regulation 9.2.6 of the Regulations of 2005

provides for execution of a supplementary agreement for

reduction of contract demand/sanctioned load of the

consumer. Similarly, for enhancement of load also, even

if a fresh agreement may have been executed between

the parties, the same could be treated as nothing but a

supplementary agreement of the initial agreement by

which   the   electricity   connection   was   granted   for   a

particular   load.   Clause   2(l)   of   the   Regulations   also

15

defines   “contract   demand”   to   be   demand   mutually

agreed in the agreement or agreed through other written

communication, meaning thereby that for variation of

the contract demand execution of a fresh agreement is

not essential and the same can be done otherwise also

by mere written communication. 

15.  It   is   noteworthy   that   the   Jharkhand   State

Electricity Board (‘the Board’) is a monopoly supplier of

electricity   which   has   laid   down   its   own   terms   and

conditions, regarding which the consumer has no say or

choice but to sign on the dotted lines, if it wants of get

electricity   load   varied   for   running   its   industry.   The

Board is an instrumentality of the State. It has to be fair

and reasonable. If the Regulations provide for contract

load   to   be   varied   even   through   a   written

communication,   then   in   our   considered   view,   in   all

fairness,   though   fresh   agreements   may   have   been

executed at the stage of enhancement of load of the

same electricity connection, the same cannot be treated

16

as   anything   but   an   extension/amendment   or

modification   of   the   initial   agreement   granting   the

electricity connection, which in the present case would

be the agreement dated 14.04.2004. On the dictates of

the Board, the consumer may have been required to

sign fresh agreements for each enhancement of load,

but   the   enhancement   being   for   the   same   electricity

connection which still continues, it would merely be

amendment of the initial agreement. This would also be

in consonance with the provisions of the Regulations of

2005, which have to be liberally interpreted in favour of

the consumer. 

16. Reverting   to   the   order   dated   08.11.2007,

which was impugned in the writ petition, we are of the

opinion that the Board has gone wrong in treating the

application   dated   20.09.2007   of   the   respondent   for

reduction of load to be that for determination of the

agreement under Clause 9B of the agreement, which

application,   in   fact,   ought   to   have   been   considered

17

under   Regulation   9.2   of   the   Regulations   of   2005.

Further, we are unable to accept the submission of the

learned Counsel for the appellant that the application of

the respondent for reduction of load was within the

period of three years, because as we have discussed

hereinabove,   the   agreement   to   be   considered   in   the

present case is the initial agreement dated 14.04.2004

and not the subsequent agreement dated 07.07.2007.  

17. The   judgments   of   this   Court   rendered   in

Bihar  State  Electricity  Board,  Patna   and  Others  v.

M/s.  Green  Rubber  Industries  and  Others, (1990) 1

SCC   731,  Orissa   State   Electricity   Board  v.  Orissa

Tiles Limited, (1993) Supp. 3 SCC 481, Andhra Steel

Corporation Ltd. and Others v. Andhra Pradesh State

Electricity Board and Others,  (1991) 3 SCC 263 and

Jharkhand State Electricity Board & Others v Laxmi

Business and Cement Company Private Limited and

Another, (2014) 5 SCC 236 as have been relied upon by

18

learned counsel for the parties, are distinguishable on

facts,   in   as   much   as   they   all   relate   to   minimum

guarantee charge, and that too under the old Electricity

Act of 1910, as is so in the first three cases. 

18. In view of the aforesaid, we are of the opinion

that the application of the respondent dated 08.11.2007

ought to have been allowed by the Board in terms of

Regulation 9.2 of the Regulations of 2005, treating the

application to be beyond the period of three years from

the date of the execution of the initial agreement dated

14.04.2004, by which the electricity connection of the

respondent had been initially granted.

19. While dismissing the appeal, we are not going

into   the   question   as   to   whether   the   provisions   of

Regulation   9.2.1   are   discriminatory,   arbitrary   and

against   the   public   policy,   as   has   been   held   by   the

Jharkhand   High   Court   vide   its   judgment   dated

23.07.2008.

19

20. The   appeal   is,   accordingly,   dismissed.     No

order as to costs.

21. The   application   of   the   respondent   dated

20.09.2007 for reduction of contract load/sanctioned

load from 4000 KVA to 1325 KVA would be deemed to

have been allowed under the provisions of Regulation

9.2 of the Regulations of 2005, and the respondent shall

be entitled to all consequential benefits.

………..………………………………..J

                     (L. NAGESWARA RAO)

                          ………..……………………………....J

(VINEET SARAN)

New Delhi

       April 30, 2021.