Citation: 2026 INSC 1238 | Civil Appeal No. 14303 of 2026 (with Civil Appeal No. 14304 of 2026) | Decided on November 18, 2026
Bench: J.B. Pardiwala, J. and K. Vinod Chandran, J.
Facts of the Case
Contract & Additional Work: The contractor was awarded work for dredging/evacuation of the approach channel and basin project of a shore-based pilot station at Sagar Island within 18 months. Of ₹2,86,56,200/- payable for the original work, ₹2,79,32,865/- had been paid, and the channel was put into use from 17.04.2001 when inaugurated by the Chairman of the Port Trust. Additional work (re-dredging) arose following the Port Trust's letter dated 19.07.2000 due to adverse force majeure weather, mismatch of soil constitution data supplied by the Port Trust, and failure to construct protective walls against siltation. (Paras 3, 6, 7)
Arbitral Award & Section 34 Challenge: The Arbitrator passed an award dated 03.11.2003 for additional work based on measurements and invoices raised by the contractor. A Single Judge under Section 34 of the Arbitration and Conciliation Act, 1996 affirmed the award. (Paras 2, 6, 12)
Section 37 Appeal & Supreme Court Appeals: On the Port Trust's appeal under Section 37, a Division Bench of the Calcutta High Court overturned the Section 34 order and modified the award to 50% of the quantified sum with 6% interest from 08.02.2002, reasoning that additional work claims exceeding 70% of the original contract shocked the conscience of the Court—despite recording that the award was not based on "no evidence" or "insufficient evidence" and was neither perverse, patently illegal, nor contrary to the fundamental policy of Indian law. Cross-appeals were filed by the contractor and the Port Trust. (Paras 2, 4)
Headnotes
Arbitration and Conciliation Act (26 of 1996), Ss. 34, 37 — Scope of appellate interference — "Shocking the conscience" and conflict with basic notions of morality or justice.
Under Section 37, a court cannot modify an arbitral award on a subjective invocation of "shocking the conscience" or conflict with basic notions of morality or justice merely because bills for additional work exceed 70% of the original contract value, especially where the court itself finds the award supported by adequate evidence and neither perverse, patently illegal, nor against the fundamental policy of Indian law. Expressions such as "shocking the conscience" require substantive reasons demonstrating a blatant conflict with basic notions of morality or justice, not mere lip service or merits re-adjudication prohibited post the 2015 Amendment. (Paras 2, 8, 9, 10, 12)
Arbitration and Conciliation Act (26 of 1996), Ss. 34, 37 — Additional dredging work — Non-issuance of completion certificate and absence of severability.
Where additional re-dredging work is identical in nature to the original dredging contract, necessitated by force majeure, mismatched soil data, and non-construction of protective walls, and quantified from measurements and invoices rather than damages, refusal by the awarder to issue a completion certificate under the GCC does not defeat payment, nor can unified measurements and invoices for such work be artificially severed into valid and invalid silos. (Paras 5, 7, 8, 11, 12)
Arbitration and Conciliation Act (26 of 1996), Ss. 34, 37 — Equality of parties — Award debtor being a State or public body.
Parties to arbitration must be treated equally without giving special treatment or leniency to a Government or statutory entity merely because the award debtor is a State body or the quantified claim appears large without substantiated statutory grounds for interference. (Para 13)
Ratio Decidendi
A court exercising narrow jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996 cannot modify or scale down an evidence-backed arbitral award for additional dredging work on a subjective impression that the claim exceeds 70% of the original contract value or because the award debtor is a public authority, where the work is substantiated by measurements/invoices and no valid statutory ground under the Act for setting aside or severing the award is established. (Paras 8–15)