REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3814 OF 2007
M/s. DSR Steel (P) Ltd. …Appellant
Versus
State of Rajasthan & Ors. …Respondents
(With Civil Appeal No.4393/2007 and No.4396/2007)
O R D E R
T.S. THAKUR, J.
1. These appeals under Section 125 of the Electricity Act, 2003 call in
question the correctness of an order dated 23rd November, 2006, passed by
the Appellate Tribunal for Electricity whereby a batch of appeals including
those filed by the appellants against an order dated 8th June, 2006 passed
by the Rajasthan Electricity Regulatory Commission, have been dismissed.
2. Jaipur Vidyut Vitran Nigam Limited (‘JVVNL’ for short), Jodhpur
Vidyut Vitran Nigam Limited (‘JDVVNL’ for short) and Ajmer Vidyut Vitran
Nigam Limited (‘AVVNL’ for short), submitted separate applications before
the Rajasthan Electricity Regulatory Commission (for short ‘Commission’) at
Jaipur in terms of Sections 62 and 64 of the Electricity Act, 2003 for
revision of tariff to be effective from December 1, 2004. Each one of these
distribution companies (‘Discoms’ for short) had an existing tariff but in
their respective applications they sought an identical tariff revision
which requests were taken up by the Commission for consideration together
and disposed of in terms of a common order dated 17th December, 2004,
passed after notices regarding filing of the said applications were
published in different newspapers having circulation in the State of
Rajasthan. Several objections were filed and suggestions made by nearly 100
individuals and organisations in the course of the proceedings before the
Commission. All these objections were then considered by the Commission no
matter only 38 of those who had filed the same had complied with the
requirement laid down by the former. A large number of people and
organisations even applied for personal hearing and were heard on different
dates at different venues fixed for the purpose. Some of these objections
also related to individual problems of the consumers or disputes relating
to bills and other matters which were directed to be considered by the
Discoms and decision taken on the same under intimation to the persons
concerned. Other issues including those questioning the maintainability of
the petitions and alleging non-compliance with the regulations and
directions of the Commission were also raised. Issues touching reforms in
power sector, non-determination of the Rajasthan Vidyut Utpadan Nigam’s
tariff from whom the Discoms purchase electricity, poor performance of
Vidyut Vitran Nigams were also agitated. Similarly objections to the
proposed increase in tariff, interest charges, depreciation etc. too were
raised and examined by the Commission. Suggestions regarding improvement,
objections relating to high T&D losses, inadequacy of staff, continuation
of un-metered supply, issue of deemed licensee and tariff for deemed
licensee were also examined. Questions relating to high voltage supply,
segregation of mixed load, billing demand, demand based tariff for MIP
consumers, power factor and shunt capacitor surcharge, vigilance checking
of consumers, minimum billing, agriculture, domestic and industrial tariff
too were examined by the Commission apart from several other issues that
were placed before the Commission to which the Commission has made a
reference in its order dated 8th June, 2006. The Commission eventually
directed that the revised tariff determined by it will become effective
from 1st January, 2005 and remain in force till the same is amended by the
Commission by a separate order passed by it.
3. Aggrieved by the order passed by the Commission, the appellants and a
large number of other consumers in that category filed review petitions
under Section 94 (1)(f) of the Electricity Act, 2003 seeking review and
continuation of the incentive scheme. These review petitions were dismissed
by the Commission in terms of its order dated 8th June, 2006. The
Commission noted the contention urged on behalf of the petitioners that
they were affected by the withdrawal of the incentive scheme. It was also
urged that these consumers had made investments on the basis of the
incentive scheme bona fide believing that the same would continue for at
least three years. The review petitioners, therefore, sought continuation
of the said scheme by suitable review of the Commission’s order dated 17th
December, 2004. The Commission also noted the opposition of the Discoms to
the said prayer and the contention that the incentive scheme was to be
effective upto 31st March, 2003 or till the Commission issued a tariff
order whichever was earlier.
4. The Commission noted the submissions made on behalf of the Discoms
that the tariff petitions had been filed in August 2004 and the details of
the scheme had been published in newspapers including the incentive scheme
which was deliberated in the course of the public hearing and dealt with in
the Commission’s tariff order dated 17th December, 2004. It was also argued
on behalf of the Discoms that the modified incentive scheme was free from
any legal flaw.
5. Consideration of the rival submissions led the Commission to the
conclusion that its order dated 17th December, 2004 had examined the
question raised by the petitioners regarding the continuation of the
incentive scheme and found that the scheme had a limited validity and its
withdrawal did not offend the principles of promissory estoppel. It also
held that the modification of the scheme was not without public notice and
the discontinuance of the old incentive scheme had been given wide
publicity pursuant to which large industries and associations had been
heard on the question of introduction of a new scheme in place of the old.
The Commission also held that the question of applicability of Promissory
Estoppel had been raised before the Commission at the hearing of the tariff
petitions and that the material sought to be introduced in support of the
said plea at the stage of review could not be taken into consideration. The
Commission, accordingly, concluded that there was no mistake or error
apparent on the face of the record in the order passed by it to call for a
review of the same. In support the Commission noted several decisions of
this Court on the question of Promissory Estoppel including those delivered
in M/s Motilal Padampat Sugar Mills Co. Ltd. v. State of Uttar Pradesh and
Ors. (1979) 2 SCC 409, Kasinka Trading and Anr. v. Union of India an Anr.
(1995) 1 SCC 274, Shrijee Sales Corporation and Anr. v. Union of India
(1997) 3 SCC 398, Union of India & Ors. v. Godfrey Philips India Ltd.
(1985) 4 SCC 369.
6. Aggrieved by the orders dated 17th December, 2004 and 8th June, 2006
passed by the Commission, the appellants and few others filed Appeal
Nos.180-197 of 2006 and Appeal No.226 of 2006 before the Appellate Tribunal
for Electricity, at New Delhi which were as noticed above dismissed by the
Tribunal by the order impugned in these appeals. The Tribunal noted that
there was no challenge before it as to the revision of the tariff order
issued by the Commission. It also found that the Regulatory Commission
could exercise its power of review in terms of Section 94(1)(f) of the
Electricity Act, 2003 read with Order XLVII of the Civil Procedure Code and
that it could review an order, provided a case for any such review was made
out. The Tribunal rejected the contention urged on behalf of the appellants
that the doctrine of Promissory Estoppel was attracted in the facts of the
case. It concurred with the view taken by the Commission that the
incentive scheme was applicable only upto 31st March, 2007 or till the
Commission issued a tariff order whichever was earlier. The Tribunal
observed:
“As has been held in Pawan Alloys & Casting Pvt. Ltd., Meerut v.
U.P. State Electricity Board And Others, (1997) 7 Supreme Court
Cases 251, in this case, no promise was held out to any new
industries nor there was an invitation for investments of large
scale fund but it only imposed a condition that existing industries
could avail of the incentive subject to the stipulations in the
scheme and nothing more. The tariff fixation is a statutory
function in terms of The Electricity Act 2003 and tariff is to be
fixed in the larger interest of consumer public at large. That
being the position and when in the very tariff scheme, it has been
specifically provided that the scheme will come to an end on
31.03.2007 or when the Regulatory Commission determines
distribution tariff which ever is earlier. This is only meaning it
is not known as to how the appellants could advance the said
contention that the scheme is to be given any other meaning is
impermissible. This sentence which is incorporated in the scheme
is fatal to the claim of the appellants and none of the precedents
pressed into service by the appellants will come to their rescue.
It will be sufficient to answer this point, however, as the
appellants on all the contentions pressed for a decision.”
7. We have heard learned counsel for the parties at considerable length.
An appeal under Section 125 of the Electricity Act, 2003 is maintainable
before this Court only on the grounds specified in Section 100 of the Code
of Civil Procedure. Section 100 of the C.P.C. in turn permits filing of an
appeal only if the case involves a substantial question of law. Findings of
fact recorded by the Courts below, which would in the present case, imply
the Regulatory Commission as the Court of first instance and the Appellate
Tribunal as the Court hearing the first appeal, cannot be re-opened before
this Court in an appeal under Section 125 of the Electricity Act, 2003.
Just as the High Court cannot interfere with the concurrent findings of
fact recorded by the Courts below in a second appeal under Section 100 of
the Code of Civil Procedure, so also this Court would be loathed to
entertain any challenge to the concurrent findings of fact recorded by the
Regulatory Commission and the Appellate Tribunal. The decisions of this
Court on the point are a legion. Reference to Govindaraju v. Mariamman (AIR
2005 SC 1008), Hari Singh v. Kanhaiya Lal (AIR 1999 SC 3325), Ramaswamy
Kalingaryar v. Mathayan Padayachi (AIR 1992 SC 115), Kehar Singh v. Yash
Pal and Ors. (AIR 1990 SC 2212), Bismillah Begum (Smt.) (Dead) by LRs. v.
Rahmatullah Khan (Dead) by LRs. (AIR 1998 SC 970) should, however, suffice.
8. The Regulatory Commission has, in the case at hand recorded a clear
finding of fact that the old incentive scheme was limited only upto 31st
March, 2007 or till the Commission issued a tariff order whichever was
earlier. It has also recorded a finding that while considering revision of
tariff it had gone into the proposals regarding introduction of a new
incentive scheme and approved the same, effectively bringing to an end the
existing scheme and introducing a new scheme in its place. The Commission
had declined to accept the contention that the appellant companies had
altered their position to their detriment by making additional investments
or that there was any specific representation or promise made to them that
the old scheme would inevitably continue till 31st March, 2007. The
additional material which the appellants had sought to introduce belatedly
at the review stage had also been declined by the Commission. In its order
dated 17th December, 2004 revising tariff the Commission had dealt with the
question relating to the incentive scheme in the following words:
“70. The incentive scheme was proposed by the Nigams as a
stopgap arrangement to arrest the decline in industrial
consumption. The Commission while conveying its approval to
extension of the incentive scheme clearly stipulated that it shall
be valid till 31.3.07 or revision of tariff whichever was earlier.
The scheme itself had a limited validity and therefore, did not
attract the principle of promissory estoppel. The Commission had
envisaged review of incentive scheme at the time of tariff
revision, as the proceeding would have provided opportunity to
public to express their views to enable appropriate changes in
incentive scheme or tariff.
71. After considering the petitioners’ proposal and the views
expressed before us, the Commission is of the view that no separate
scheme is called for at this stage. The need to provide incentive
to promote consumption of electricity by large industrial power
(LIP) consumers should be taken care of by the tariff itself. An
incentive which encourages better load factor will serve the
purpose. Consequently, an incentive scheme linked to consumption
per KVA of contract demand is proposed. Accordingly we direct that
the incentive shall be available to all LIP consumers including
railways and public water works, and eligibility for incentive
shall be as follows:
(i) The annual consumption of the consumer for the
current financial year shall not be less than his annual
consumption of the previous financial year.
(ii) In respect of new LIP consumers and existing LIP
consumers who reduce their contract demand, incentive shall
be admissible from the quarter following six months from the
date of new connection or reduction of contract demand, as
the case may be.
(iii) Consumer should have no arrear outstanding against him.
72. Incentive shall be allowed to eligible consumers provisionally
on quarterly basis provided that consumption during the quarter is
not less than his consumption during the corresponding quarter
during the previous year. Incentive so allowed shall be subject to
final assessment at the end of the year, on year-to-year basis. If
consumption of a consumer in any quarter is less than that of the
corresponding quarter of the previous year but the annual
consumption is more than that of the previous year, he shall be
eligible for the incentive for the year as a whole. Incentive
shall be as under on energy charges:-
|(i) |Energy consumption of 250 KWh per| |
| |month per kVA of contract demand | |
| |and upto 400 KWh per month per | |
| |kVA of contract demand. |1.0% |
|(ii) |Energy consumption exceeding 400 | |
| |KWh per month per kVA of contract| |
| |demand and upto 550 KWh per month| |
| |per kVA of contract demand. |4.0% |
|(iii) |Energy consumption in excess of | |
| |550 KWh per Month per kVA of |7.0% |
| |contract demand.” | |
9. The Tribunal concurred with the above view taken by the Commission
and repelled the contention based on the principle of promissory estoppel
not only on the ground that there had been no unequivocal representation
regarding continuation of the scheme till 31st March, 2007 but also on the
ground that there was no material to support the contention that the
appellants had indeed made any investment or changed their position to
their detriment so as to attract the doctrine of promissory estoppel. In
coming to that conclusion the Commission has also relied upon several
decisions of this Court to which we have made a mention above. We do not
see any perversity in any one of those findings nor do we see any
substantial question of law arising in the fact situation of these appeals.
We have, therefore, no hesitation in dismissing these appeals on merits
although the same have been filed beyond the period stipulated for the
purpose under Section 125 of the Electricity Act, 2003.
10. We may before parting mention that in Civil Appeal No.3814 of 2007
filed by DSR Steel (P) Ltd., one of the questions that was urged before us
was whether the period of limitation would start running from the date of
pronouncement of the order or the date of communication thereof. Relying
upon the decision of this Court in Chhattisgarh State Electricity Board v.
Central Electricity Regulatory Commission and Ors. (2010) 5 SCC 23 it was
contended on behalf of the respondent that the date on which the order was
pronounced would also be the date on which the same is deemed to have been
communicated.
11. Section 125 of the Electricity Act, 2003 makes it abundantly clear
that the period of limitation commences from the date of communication of
the decision or order and not from the date of its pronouncement. As a
matter of fact, Rules 94 and 98 of the Rules framed under the Act make a
clear distinction between intimation regarding pronouncement of the order
on the one hand and the communication of the order so pronounced to the
parties on the other. While Rule 94 appears to us to provide for notice of
pronouncement of an order, it makes no mention about the ‘communication’ of
such an order as is referred to in Section 125 of the Act. Transmission of
the order by the Court Master to the Deputy Registrar of the Tribunal and
its onward communication to the parties is dealt with by Rule 98 of the
said Rules which communication alone can be construed as a communication
for purposes of Section 125 of the Electricity Act, 2003. The decision of
this Court in the Chattisgarh State Electricity Board’s case (supra) may in
that view require reconsideration if the same were to be understood to be
laying down that the date of pronouncement is also the date of
communication of the order. We would have, in the ordinary course, made a
reference to a larger Bench for that purpose but having regard to the fact
that we have dismissed the appeals on merits, we consider it unnecessary to
do so in the present case.
12. So also the question whether an order passed by the Tribunal in
appeal merges with an order by which the Tribunal has dismissed an
application for review of the said order was argued before us at some
length. Learned counsel for the appellants contended that since a review
petition had been filed by two of the appellants namely, J.K. Industries
Ltd. (Now known as J.K. Tyres and Industries Ltd.) and J.K. Laxmi Cement
Ltd. in this case, the orders made by the Tribunal dismissing the appeals
merged with the orders passed by it in the said review applications so that
it is only the order dismissing the review application that was appealable
before this Court. If that were so the period of limitation could be
reckoned only from the date of the order passed in the review applications.
13. Different situations may arise in relation to review petitions filed
before a Court or Tribunal. One of the situations could be where the review
application is allowed, the decree or order passed by the Court or Tribunal
is vacated and the appeal/proceedings in which the same is made are re-
heard and a fresh decree or order passed in the same. It is manifest that
in such a situation the subsequent decree alone is appealable not because
it is an order in review but because it is a decree that is passed in a
proceeding after the earlier decree passed in the very same proceedings has
been vacated by the Court hearing the review petition. The second situation
that one can conceive of is where a Court or Tribunal makes an order in a
review petition by which the review petition is allowed and the
decree/order under review reversed or modified. Such an order shall then
be a composite order whereby the Court not only vacates the earlier decree
or order but simultaneous with such vacation of the earlier decree or
order, passes another decree or order or modifies the one made earlier.
The decree so vacated reversed or modified is then the decree that is
effective for purposes of a further appeal, if any, maintainable under law.
14. The third situation with which we are concerned in the instant case
is where the revision petition is filed before the Tribunal but the
Tribunal refuses to interfere with the decree or order earlier made. It
simply dismisses the review petition. The decree in such a case suffers
neither any reversal nor an alteration or modification. It is an order by
which the review petition is dismissed thereby affirming the decree or
order. In such a contingency there is no question of any merger and anyone
aggrieved by the decree or order of the Tribunal or Court shall have to
challenge within the time stipulated by law, the original decree and not
the order dismissing the review petition. Time taken by a party in
diligently pursing the remedy by way of review may in appropriate cases be
excluded from consideration while condoning the delay in the filing of the
appeal, but such exclusion or condonation would not imply that there is a
merger of the original decree and the order dismissing the review petition.
15. The decisions of this Court in Manohar S/o Shankar Nale and Ors. v.
Jaipalsing S/o Shivalalsing Rajput (2008) 1 SCC 520 in our view, correctly
settle the legal position. The view taken in Sushil Kumar Sen v. State of
Bihar (1975) 1 SCC 774 and Kunhayammed and Ors. v. State of Kerala & Anr.
(2000) 6 SCC 359, wherein the former decision has been noted, shall also
have to be understood in that light only.
16. In the result, we dismiss these appeals as no substantial question of
law arises for our consideration. The respondent shall also be entitled to
cost of Rs.20,000/- in each case to be deposited in the SCBA Lawyers’
Welfare Fund within six weeks from today.
……………………..……………..…J.
(T.S. THAKUR)
……………………………….………J.
(GYAN SUDHA MISRA)
New Delhi
May 1, 2012