LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Wednesday, April 17, 2024

Tender – Notice inviting tender – Issuance of letter of intent in favour of the successful bidder by the tenderee – Challenge to, by the unsuccessful bidder – Cancellation of initial tender process by the tenderee and withdrawal of the letter of intent issued in favour of the successful bidder on account of pending litigations in the High Court – Thereafter, issuance of fresh NIT by tenderee – Challenge to – High Court disposed of the writ petition by merely accepting the statement of the tenderee that it had no objection to go ahead with the initial tendering process and the statement of the initial successful bidder that it was ready to execute the project on the same terms and conditions as initially agreed, though the said tender was already withdrawn by the tenderee in view of the irregularities and illegalities committed by it, as recorded by an independent committee appointed by the High Court in earlier writ petitions – Correctness:

* Author

[2024] 4 S.C.R. 1 : 2024 INSC 257

Level 9 Biz Pvt. Ltd.

v.

Himachal Pradesh Housing and Urban

Development Authority & Another

(Civil Appeal No. 4626 of 2024)

02 April 2024

[Bela M. Trivedi* and Pankaj Mithal, JJ.]

Issue for Consideration

Matter pertains to the correctness of the order passed by

the High Court disposing the writ petition by accepting the

statements of the respondent no. 1-tenderee and respondent

no. 2-successful bidder, permitting the respondent no.1 to

withdraw the cancellation of initial tendering process order and

permitting the respondent no. 2 to execute the project on the

same terms and conditions as in the initial tender, though the

said tender was already withdrawn by the respondent no.1 in

view of the report of the independent Committee confirming

gross irregularities and illegalities committed by the officers of

the respondent no.1.

Headnotes

Tender – Notice inviting tender – Issuance of letter of intent in

favour of the successful bidder by the tenderee – Challenge

to, by the unsuccessful bidder – Cancellation of initial tender

process by the tenderee and withdrawal of the letter of intent

issued in favour of the successful bidder on account of

pending litigations in the High Court – Thereafter, issuance of

fresh NIT by tenderee – Challenge to – High Court disposed

of the writ petition by merely accepting the statement of the

tenderee that it had no objection to go ahead with the initial

tendering process and the statement of the initial successful

bidder that it was ready to execute the project on the same

terms and conditions as initially agreed, though the said

tender was already withdrawn by the tenderee in view of the

irregularities and illegalities committed by it, as recorded by

an independent committee appointed by the High Court in

earlier writ petitions – Correctness:

2 [2024] 4 S.C.R.

Digital Supreme Court Reports

Held: No right whatsoever created in favour of the respondent no.

2-successful bidder, and the respondent no. 1 HIMUDA-tenderee

cancelled the tender and issued fresh NIT, as such the respondent

no. 1 could not have agreed to allow the respondent no. 2, who

was found to be not technically qualified, to go ahead with the

execution of the project in question and that too without giving

the other two parties any opportunity to negotiate – Respondent

no. 1 in collusion with the respondent no. 2, took the High Court

for a ride and misused the process of law for covering up the

irregularities and illegalities committed in the tender process by the

officers of the respondent no. 1 – High Court also could not notice

the ill-intention of the respondent nos. 1 and 2 and disposed of

the petition, permitting them to go ahead with the original tender

– Thus, the impugned order having been passed without proper

application of mind and without assigning any cogent reason for

brushing aside the findings recorded by the Independent Committee

and the observations made by the Single Bench, is quashed

and set aside – Also, the respondent no.1, though ‘State’ within

the meaning of Art. 12, acted malafide and in collusion with the

respondent no.2, and took the High Court for a ride, heavy cost

of Rs. 5,00,000/- imposed on the respondent no. 1 – Constitution

of India – Art. 12. [Paras 11-14]

Tender – Notice inviting tender – Letter of Intent – Nature of:

Held: Letter of Intent is merely an expression of intention to enter

into a contract – It does not create any right in favour of the

party to whom it is issued – There is no binding legal relationship

between the party issuing the LOI and the party to whom such

LOI is issued – Detailed agreement/contract is required to be

drawn up between the parties after the LOI is received by the

other party. [Para10]

List of Acts

Constitution of India.

List of Keywords

Cancellation of initial tendering process; Tender; Irregularities

and illegalities; Notice inviting tender; Letter of intent; Burden on

the public exchequer; Misuse process of law; Cost; Fresh tender

process; Agreement/contract.

[2024] 4 S.C.R. 3

Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban

Development Authority & Another

Case Arising From

CIVIL APPELLATE JURISDICTION : Civil Appeal No. 4626 of 2024

From the Judgment and Order dated 18.10.2022 of the High Court of

Himachal Pradesh at Shimla in CWP No. 1481 of 2021

Appearances for Parties

P.S. Patwalia, Sr. Adv., Ritesh Khatri, Ms. Deveshi Chand, Advs. for

the Appellant.

Anoop G. Chaudhari, Navin Pahwa, Sr. Advs., Shankar Divate, J. P.

Mishra, D. K. Thakur, Rajeev Kumar Gupta, Tavleen Singh, Joginder

Mann, Ms. Vallabhi Shukla, Divyansh Thakur, Bimlesh Kumar Singh,

Kanwal Chaudhary, Neeraj Agarwal, Santosh Kumar Yadav, Ms.

Niharika, Nishant Anand, Advs. for the Respondents.

Judgment / Order of the Supreme Court

Judgment

Bela M. Trivedi, J.

1. Leave granted.

2. The Appellant – Level 9 BIZ Pvt. Ltd., who was not a party to the

proceedings, being Civil Writ Petition No. 1481 of 2021, filed by

the Respondent No.2 – M/s. Vasu Constructions in the High Court

of Himachal Pradesh at Shimla, has challenged the impugned

order dated 18.10.2022 passed by the High Court in the said

proceedings. The High Court passed the impugned order disposing

of the said CWP by merely accepting the statement made on behalf

of the Respondent No.1 – Himachal Pradesh Housing and Urban

Development Authority (HIMUDA) that it wanted to withdraw the

cancellation of initial tendering process order dated 05.02.2021,

and the statement made on behalf of the Respondent No. 2 that it

was ready to execute the project on the same terms and conditions

and the rates as per the initial tender dated 15.11.2018, though

the said tender was already withdrawn by the Respondent no. 1

HIMUDA in view of the irregularities and illegalities committed by it,

as recorded by an independent committee appointed by the High

Court in earlier writ petitions filed by the present appellant and one

Dalip S. Rathore.

4 [2024] 4 S.C.R.

Digital Supreme Court Reports

3. The broad facts giving rise to the present appeal may be stated

as under: -

DATES EVENTS

15/16.11.2018 Notice Inviting Tender (NIT) was issued by

HIMUDA (R-1) for the construction of proposed

commercial complex of Vikas Nagar, Shimla, at

estimated cost of Rs.45,05,62,074/-

15.12.2018 Technical Bids were opened and on the same

day Financial Bids were also opened. (Appellant

& R-2 were the only found to be qualified – But

the Appellant was L2)

17.12.2018 LOI was issued by the R-1 in favour of R-2.

24.12.2018 One Unsuccessful bidder Dalip S Rathore

filed Writ Petition being CWP 3021 of 2018

challenging the technical specifications &

ineligibility of Respondent No.2, also seeking

cancellation of the Tender. The High Court

issued notice.

02.01.2019 R-1 HIMUDA withdrew the LOI dated 17.12.2018

of R-2 M/S Vasu Constructions stating that the

case is pending in the High Court and the work

will be awarded only as per the decision of the

High Court.

05.01.2019 R-1 HIMUDA constituted a committee, which

reviewed the tender process and concluded that

there were many lapses which warranted actions

against the erring officials.

07.01.2019 Another Committee constituted by R-1

submitted a report that Shri Dalip Singh was

not qualified and M/s. Vasu Constructions was

qualified.

23.02.2019 Appellant – Level 9 BIZ Pvt. Ltd. filed a writ

petition CWP 363 of 2019, praying for rejection

of Technical Bid and Financial Bid of the R-2 M/s.

Vasu Constructions

[2024] 4 S.C.R. 5

Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban

Development Authority & Another

25.11.2020 High Court passed a detailed order on 25.11.2020

in CWP No. 3021/2018 and 363/2019.

In Para 29 High Court observed-

“[..] this Court is prima facie of the

view that some of the officers manning

high positions in HIMUDA have not

acted responsibly and in the interest

of organization, rather have attempted,

directly or indirectly, to give undue

benefit to some of the contractors.

Having seen the record, this Court is

compelled to draw a conclusion that the

officers responsible for evaluation of the

tender in question, did not scrutinize the

documents submitted by the tenderers

along with their bids properly and, with

a view to ensure ouster of some eligible

contractors and awarding the same to

their favourites, have made an attempt

to justify their action by giving totally

implausible reasoning.”

In para 31, High Court observed-

“But, for the reasons, best known

to the authority, it still proceeded to

award the tender in favour of M/s. Vasu

Construction Company.”

The High Court therefore to instill confidence in

the general public and to ensure transparency in

the system, constituted an independent committee

to enquire into the tender process in question, and

directed the committee to submit its report in a

sealed cover to the Court.

02.01.2021 Committee constituted by High Court filed its report.

08.01.2021 High Court disposed of both Petitions being Nos.

3021/2018 and 363/19 and directed registry

to initiate separate proceedings against erring

officials, observing as under: -

6 [2024] 4 S.C.R.

Digital Supreme Court Reports

14. Since the committee, after having

perused the records, has arrived at

a definite conclusion that on account

of shortcomings/irregularities, tender

in question requires to be cancelled,

nothing much is left for this court to

adjudicate in these matters. Leaving

everything aside, learned counsel for the

petitioners in both the petitions, being

satisfied with the findings of enquiry

committee as well as suggestions made

therein, are not willing to prosecute

the cases further and have prayed to

dispose of the same as having been

rendered infructuous.

15. In view of aforesaid, both the

petitions are disposed of as infructuous

alongwith all pending applications.

Interim directions, if any, stand vacated.

However, liberty is reserved to the

parties to file fresh petition(s), if any, if

they still remain aggrieved.

16. However, this court, having taken

note of the fact that the enquiry committee

despite having found officers lacking in

discharge of their duties, has failed

to fix responsibility and recommend

action, criminal or departmental, deems

it necessary to direct the Registry

of this Court to register separate

proceedings, enabling this Court to pass

appropriate orders so as to ensure strict

compliance of recommendations given

in the report of enquiry committee and

pass appropriate orders with regard

to initiation of criminal/ departmental

proceedings against the erring officials.

[2024] 4 S.C.R. 7

Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban

Development Authority & Another

Registry is directed to register separate

proceedings and list the same on

17.3.2021. The order dated 25.9.2020,

this judgment and the enquiry report

submitted by the committee constituted

by this Court, shall form part of the fresh

proceedings.

05.02.2021 Respondent No.1 cancelled the Tender in view

of the Order dated 08.01.2021 passed by the

High Court.

03.03.2021 Respondent No.2 filed a new Writ Petition against

Respondent No.1, i.e., CWP 1481 of 2021

challenging order dated 05.02.2021.

Respondent no. 2 also filed separate two LPAs

being LPA No. 6/2021 and 12/2021 against the

common order dated 08.01.2021 passed in CWP

No. 3021/2018 and CWP No. 363/2019 by the

Single Bench.

17.11.2021 R-1 HIMUDA issued fresh NIT for the same work.

01.12.2021 The Division Bench of High Court passed an

interim order in LPA No. 6/2021, 12/2021 and CWP

No. 1481/2021 staying the NIT dated 17.11.2021

till further orders.

18.10.2022 The Division Bench disposed of the Writ Petition

No. 1481/2021 upon statement of the Executive

Engineer of Respondent No.1 observing as under:

7. Learned counsel for the respondent on

instructions of Mr. Rajesh Thakur, Executive

Engineer, HIMUDA, Division, Shimla-9, has

submitted that the competent authority wants

to withdraw the cancellation of initial tendering

process order dated 5th February, 2021, bearing

No. 5806-11, as the public is deprived from the

facilities, which would have been available to them

after completion of the project. The project cost is

going to be enhanced due to delay in execution

of the project, which will cause additional burden

8 [2024] 4 S.C.R.

Digital Supreme Court Reports

on the public exchequer. The various Government

departments/PSUs are facing acute shortage of

office accommodation, therefore, in larger public

interest, the authority has no objection to go ahead

with initial tendering process, in case the petitioner

is ready to execute the work at the same rate and

terms and conditions as were agreed at the time

of finalization of the initial NIT dated 15.11.2018

(Annexure P-2). The time period for execution

of work will start from date of fresh award letter

which will be issued in favour of the petitioner

within 15 days.

8.Learned Senior counsel for the petitioner, on

instructions from the petitioner, has submitted

that offer made by the respondent is acceptable

to the petitioner and petitioner is ready to execute

the project on the same terms and conditions

and rates as per initial tender dated 15.11.2018

(Annexure P-2).

Nov. 2022 Contract Agreement was signed between

Respondent 1 & 2. Work started.

12.12.2022 The Appellant filed the SLP challenging the

impugned order dated 18.10.2022 and the Court

while issuing notice, granted stay of operation of

the impugned order dated 18.10.2022.

4. The question that has been posed before us in the instant appeal

is, whether the High Court could have disposed of the CWP filed

by the respondent no. 2 by simply accepting the statements

made on behalf of the learned advocates for the respondent no.

1 and respondent no. 2, virtually permitting the respondent no.1

HIMUDA to withdraw the cancellation of initial tendering process

order dated 05.02.2021 and permitting the respondent no. 2 M/s

Vasu Constructions to execute the project on the same terms

and conditions and at the rates as per the initial tender dated

15.11.2018, though the said tender was already withdrawn by

the Respondent No.1 HIMUDA in view of the report made by the

independent Committee constituted by the High Court confirming

gross irregularities and illegalities committed by the officers of 

[2024] 4 S.C.R. 9

Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban

Development Authority & Another

HIMUDA and in view of the order dated 08.01.2021 passed by

the Single Bench?

5. As could be seen from the chronology of events, the appellant and

the respondent No. 2 were declared qualified in the Technical Bids

opened on 15.12.2018 and on the same day, the financial bid of the

said two parties were also opened. The respondent no.2 being L-1,

the Letter of Intent dated 17.12.2018 was issued by the Respondent

No.1 in favour of the respondent no.2. Subsequently, an unsuccessful

bidder M/s Dalip Singh Rathore filed a writ petition being No.

3021/2018 in the High Court, alleging irregularities and illegalities in

the tender process and challenging the eligibility of the respondent

no. 2, also seeking cancellation of the Tender. The appellant also

filed CWP No. 363/2019 praying for the rejection of the Technical

and Financial Bids of the respondent no.2. The respondent no.1

HIMUDA in the meantime appointed a committee on 01.01.2019 to

review the tender process. The respondent no.1 also vide the letter

dated 02.01.2019 withdrew the Letter of Intent issued in favour of

the respondent no.2. Subsequently, the High Court also appointed

an Independent Committee to look into the alleged illegalities and

irregularities vide the order dated 25.11.2020, in order to instill

confidence in the general public and to ensure transparency in the

system.

6. As transpiring from the order dated 08.01.2021, the said Independent

Committee submitted the report, arriving at a definite conclusion that

the officers responsible for evaluation of the tender had not acted

responsibly and fairly, as a consequence of which both M/s Vasu

Constructions Company (respondent no.2 herein) and M/s Level 9

Biz Pvt. Ltd. (the appellant herein) were wrongly declared eligible in

the Technical Bid. The Committee had concluded that since both the

bidders were not technically qualified as per the terms and conditions

of the NIT, the tender needed to be cancelled. The recommendations

made by the said Committee, except the recommendation for deletion

of condition with regard to NPA, were stated to have been accepted

by the Enquiry Committee of the respondent no. 1 HIMUDA. The High

Court recorded the statements of the concerned counsels for the

parties and disposed of the petitions being CWP Nos. 3021/2018 and

363/2019 vide Order dated 08.01.2021 observing that the petitions

had been rendered infructuous, however reserved a liberty for the

parties to file fresh petition(s), if any, if they still remained aggrieved.

10 [2024] 4 S.C.R.

Digital Supreme Court Reports

7. Subsequently, the respondent no.1 HIMUDA cancelled the tender

on 05.02.2021 in view of the said order dated 08.01.2021 passed

by the High Court. The said action of the respondent no.1 came to

be challenged by the Respondent No.2 M/s Vasu Constructions by

filing a petition being CWP No. 1481/2021. The respondent no. 2

also filed two LPAs being 6/2021 and 12/2021 being aggrieved by

the common Order dated 08.01.2021 passed by the Single Bench.

The Division Bench of the High Court disposed of the CWP No.

1481/2021 vide the impugned order dated 18.10.2022 accepting the

statements made by the learned counsels for the respondent nos.

1 and 2 as stated hereinabove.

8. We are at loss to understand as to how the said petition filed by

the respondent no.2 could have been disposed of by the Division

Bench by merely recording and accepting the statements of the

learned counsels for the respondent nos. 1 and 2, when the tender

in respect of NIT dated 15.11.2018 was cancelled by the respondent

no.1 HIMUDA on account of the gross irregularities and illegalities in

the tender process found by the Independent Committee constituted

by the High Court and on account of the order passed by the High

Court on 08.01.2021? We are also at loss to understand as to how

the Executive Engineer of HIMUDA, could have made the statements

before the Division Bench that the competent authority of the

respondent no.1 wanted to withdraw the cancellation of the initial

tendering process order dated 05.02.2021 and that the respondent

no. 1 had no objection to go ahead with the initial tendering process,

in case the respondent no.2 was ready to execute the work on

the same terms and conditions as were agreed at the time of

finalization of NIT dated 15.11.2018, when the respondent no. 1

itself had decided to cancel and in fact cancelled the initial tendering

process vide its order dated 05.02.2021 accepting the findings of

the committee constituted by the High Court to the effect that there

were irregularities and illegalities committed by the officers of the

HIMUDA in processing the tender and that the respondent no. 2 was

not technically qualified?

9. When the common order dated 08.01.2021 was passed in the Writ

Petition No. 3021 of 2018 filed by the petitioner Dalip Singh and Writ

Petition No.363 of 2019 filed by the present appellant, recording the

said findings of the committee appointed by it, pursuant to which

order, the respondent no.1 had cancelled the tender on 05.02.2021, 

[2024] 4 S.C.R. 11

Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban

Development Authority & Another

and had issued a fresh NIT on 17.11.2021, it was incumbent on the

part of the respondent no. 2 to implead the said two petitioners as

the party respondents in the new petition filed by it i.e. 1481/2021,

and it was also incumbent on the part of the High Court to give

opportunity of hearing to the said petitioners before passing the

impugned order disposing of the said petition merely recording the

statements of the learned counsels for the respondent nos. 1 and

2, and permitting the respondent nos. 1 and 2 to go ahead with

execution of the work as per the initial tender which was already

cancelled by the respondent no.1.

10. Though it is true that initially an LOI was issued by the respondent

no. 1 in favour of the respondent no. 2 on 17.12.2018, but the same

was withdrawn by the respondent no. 1 as per the letter dated

02.01.2019 on account of pending litigations in the High Court. In

any case, it hardly needs to be reiterated that the Letter of Intent is

merely an expression of intention to enter into a contract. It does not

create any right in favour of the party to whom it is issued. There

is no binding legal relationship between the party issuing the LOI

and the party to whom such LOI is issued. A detailed agreement/

contract is required to be drawn up between the parties after the LOI

is received by the other party more particularly in case of contract

of such a mega scale.

11. Since, there was no right whatsoever created in favour of the

respondent no. 2, and since the respondent no. 1 HIMUDA had

already accepted the recommendations of the Committee appointed

by the High Court and the order dated 08.01.2021 passed by the

High Court, and had cancelled the tender and issued fresh NIT on

17.11.2021, the respondent no. 1 could not have agreed to allow the

respondent no. 2, who was found to be not technically qualified, to

go ahead with the execution of the project in question and that too

without giving the other two parties any opportunity to negotiate. If the

respondent no. 1 was so keen to provide the facilities to the public

without causing any additional burden on the public exchequer, all

the three parties who had participated in the original tender should

have been given the opportunity to negotiate with it.

12. Having regard to the entire chain of events, and the conduct of

the respondent nos. 1 and 2, we have no hesitation in holding that

the respondent no. 1 in collusion with the respondent no. 2, had 

12 [2024] 4 S.C.R.

Digital Supreme Court Reports

taken the High Court for a ride and misused the process of law for

covering up the irregularities and illegalities committed in the tender

process by the officers of the respondent no. 1, and for anyhow

awarding the contract to the respondent no. 2 under the guise of

the court’s order. It is a matter of surprise for us that the High Court

also could not notice the ill-intention of the respondent nos. 1 and 2

and disposed of the petition, permitting them to go ahead with the

original tender, ignoring the reports of the independent committee

and the observations made by the Single Bench in the Order dated

08.01.2021 with regard to the irregularities and illegalities committed

by the officers of the respondent no. 1 HIMUDA.

13. The impugned order having been passed without proper application of

mind and without assigning any cogent reason for brushing aside the

findings recorded by the Independent Committee and the observations

made by the Single Bench in the order dated 08.01.2021, the same

deserves to be quashed and set aside. Since, we have found that

the respondent no.1 HIMUDA, though ‘State’ within the meaning

of Article 12 of the Constitution of India, had acted malafide and in

collusion with the respondent no.2, and had taken the High Court for

a ride, the present appeal deserves to be allowed with heavy cost.

14. In that view of the matter, the impugned order passed by the High

Court is set aside. The appeal is allowed with cost of Rs. 5,00,000/-

to be deposited by the respondent no. 1 HIMUDA with the Supreme

Court Advocates-on-Record Association, within two weeks from today.

However, it is clarified that the respondent no.1 shall be at liberty

to initiate a fresh tender process in accordance with law and after

following the due process of law.

Headnotes prepared by: Nidhi Jain Result of the case:

Appeal allowed.