LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Wednesday, December 15, 2021

The Chardham Mahamarg Vikas Pariyojna = We thus allow MoD’s MA No 2180 of 2020 by permitting the DL-PS configuration for the three strategic highways in respect of which relief has been claimed. At the same time, we have also taken note of the environmental concerns which have been raised by the HPC for the entirety of the Project. We have noted the HPC’s unanimous recommendations for taking remedial measures and direct that they have to be implemented by the MoRTH and MoD, going forward. These specific recommendations have been mentioned in Section F.2.1 and are not being repeated here for the sake of brevity

 1

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

Miscellaneous Application No 1925 of 2020

In

Civil Appeal No 10930 of 2018

Citizens for Green Doon & Ors. …Appellants

Versus

Union of India & Ors. …Respondents

With

Miscellaneous Application No 2180 of 2020

In

Civil Appeal No 10930 of 2018

2

J U D G M E N T

Dr Dhananjaya Y Chandrachud, J

This judgment has been divided into sections to facilitate analysis. They are:

A The Project .....................................................................................................3

B Proceedings before the National Green Tribunal ...........................................5

C Proceedings before the Supreme Court .........................................................8

D Submissions .................................................................................................15

E Framework of Analysis .................................................................................23

E.1 Principles of Sustainable Development and Environmental Rule of Law....

................................................................................................................25

E.2 Circulars and Guidelines .........................................................................37

F Issues and Analysis......................................................................................45

F.1 Road-Width Issue....................................................................................45

F.1.1 HPC Report dated 13 July 2020 .......................................................45

F.1.2 HPC Report dated 31 December 2020.............................................51

F.1.3 Analysis on the width of road............................................................53

F.2 Environmental Issues..............................................................................67

F.2.1 HPC Report dated 13 July 2020 .......................................................67

F.2.2 Analysis of the Environmental Issues ...............................................76

G Conclusion....................................................................................................80

PART A

3

A The Project

1 The present case has a history fraught with litigation, with multiple

proceedings before the National Green Tribunal1 and this Court. Before going

into the history of the litigation, it is important to provide context for the public

project in question in the case.

2 The Chardham Mahamarg Vikas Pariyojna2 is a program of the Ministry of

Road Transport and Highways3

, which was announced on 23 December 2016.

The Project aims to widen the roads of approximately 900 kms of national

highways, in order to ensure safer, smoother and faster traffic movement. As the

name suggests, these highways connect the holy shrines which have been

labelled as the “Chote Char Dham” in the State of Uttarakhand – Yamunotri (NH94/134 up to Janki Chatti), Gangotri (NH-108), Kedarnath (NH-109, up to

Sonprayag), Badrinath (NH-58) and the Tanakpur-Pithoragarh stretch of the

Kailash Mansarovar Yatra route (NH-125).

3 These shrines represent different traditions of the Hindu religion – with

Yamunotri and Gangotri being Shakti or goddess shrines, Kedarnath being a

Shaiva temple, and Badrinath a Vaishnava site. They are located in an area

called Kedarkhand (largely today’s Garhwal) in the Skanda Purana. The locations

of these shrines were earlier considered to be occupied by glaciers (named

Champasar, Gangotri, Chorabari and Satopanth) in their entirety, which have

 1 “NGT” 2 “Project” 3 “MoRTH”

PART A

4

since started melting. Even today, they are stated to be located in paraglacial

zones, which are considered to be ecologically sensitive.

4 Till the 1950s, access to these shrines was limited and they could only be

accessed on foot. Hence, worshippers often undertook long and arduous

journeys to reach the shrines. However, since the 1960s, road connectivity to the

shrines has improved, where vehicles now ply up to the Badrinath and Gangotri

temples while Yamunotri and Kedarnath are 6 to 14 kms away from the nearest

motorable road. The improved connectivity has resulted in a greater influx of

worshippers. The four shrines typically open for worship in and around late April

or early May, and close in and around late October to early November.

5 The Project was conceptualized with the aim of improving accessibility to

these shrines by widening the existing roads, making travel safer, smoother and

faster. The Project seeks to widen the existing highways into a double lane with

paved shoulder configuration4 with 16 bypasses, realignments and tunnels, 15

flyovers, 101 small bridges and 3516 culverts. The MoRTH has divided the

Project into 53 individual projects, the length of each project being less than 100

kms, traversing the following national highways:

(i) NH-58 - Rishikesh to Rudraprayag - 141 kms;

(ii) NH-58 - Rudraprayag to Mana Village (Badrinath) - 140 kms;

(iii) NH-94 - Rishikesh to Dharasu - 120 kms;

(iv) NH-94 - Dharasu to Yamunotri - 75 kms;

(v) NH-108 - Dharasu to Gangotri - 110 kms;

 4 “DL-PS”

PART B

5

(vi) NH-109 - Rudraprayag to Gaurikund (Kedarnath) - 77 kms; and

(vii) NH-125 - Tanakpur to Pithoragarh - 161 kms.

A pictorial representation of the connecting routes of the Project is provided

below, as taken from the report of the High Powered Committee5 dated 13 July

20206

:

B Proceedings before the National Green Tribunal

6 An Original Application7 was filed before the Principal Bench of the NGT

on 27 February 2018 in public interest, challenging the construction under the

Project on the ground that the development activity has a negative impact on the

Himalayan ecosystem. The applicants argued that the Project will lead to

deforestation, excavation of hills and dumping of muck, which will lead to further

 5 “HPC” 6 “HPC Report” 7 OA No 99/2018

PART B

6

landslides and soil erosion, in an already sensitive environment. It was also

alleged that an Environment Impact Assessment8 under the Environment Impact

Assessment Notification 20069 had not been conducted and that to obviate the

requirement of conducting an EIA, the Project had been divided into smaller

stretches. The application alleged violations of the EIA Notification, Forest

(Conservation) Act 1980, Wildlife Protection Act 1972, Environment (Protection)

Act 1986 and Articles 14, 21 and 48A of the Constitution. Another Original

Application10 was filed seeking directions to take precautions for muck disposal

and for ensuring the stability of slopes.

7 In its order dated 26 September 2018, the NGT observed that the

bypasses and realignments to be made to the national highways, which

cumulatively fall under the Project, have been considered as stand-alone

projects. The length of each of these projects is less than 100 kms and thus, the

NGT held that the projects did not require an EIA approval or Environment

Clearance11 under the EIA Notification. However, given the fragile ecosystem

within which the Project was to be developed, the NGT directed the constitution

of an ‘Oversight Committee’ to monitor the environmental safeguards for the

execution of the Project.

8 The Oversight Committee was to be headed by a former Judge of the

Uttarakhand High Court, and had representatives from the Wadia Institute of

Himalayan Geology; National Institute of Disaster Management; Central Soil

 8 “EIA” 9 “EIA Notification” 10 OA No 431/2018 11 “EC”

PART B

7

Conservation Research Institute; GB Pant Institute of Himalayan Environment;

Forest Research Institute; the Secretary to the Forest Department, Uttarakhand;

and District Magistrates, who were to act as co-ordinators. The task of the

Oversight Committee, inter alia, was to oversee the implementation of the

Environment Management Plan to be prepared by an agency of the Ministry of

Environment, Forests and Climate Change12. The relevant portion of the order of

the NGT is produced below:

“54. Accordingly, we direct constitution of the following

Oversight Committee:—

1. Justice U.C. Dhyani, Former Judge, Uttarakhand High

Court, Chairman Public Service Tribunal, Dehradun.

2. Representative of Wadia Institute of Himalayan and

Geology.

3. Representative of National Institute of Disaster

Management.

4. Representative of Central Soil Conservation Research

Institute with expertise in Natural disasters, landslides, etc.

5. Representative of G.B. Pant Institute of Himalayan

Environment.

6. Representative of Forest Research Institute, Dehradun.

7. Secretary of Environment and Forest Department,

Uttarakhand, Dehradun to be Member

Secretary/convener/coordinator of the Committee.

8. Concerned District Magistrates of the Districts concerned

will act as co-coordinator and for arranging visits and

meetings at local level.”

 12 “MoEF&CC”

PART C

8

C Proceedings before the Supreme Court

9 An appeal13 was filed to challenge the NGT’s order dated 26 September

2018 before this Court. By an order dated 8 August 2019, a two-judge Bench,

comprising of Justice Rohinton F Nariman and Justice Surya Kant, modified the

order of the NGT and instead constituted an HPC to be chaired by Professor Ravi

Chopra, who would replace Justice UC Dhyani, and also added representatives

from various other bodies. The HPC was directed to make its decisions on the

basis of majority vote. The relevant portion of the order of this Court is as follows:

“We constitute a High Powered Committee (HPC) consisting

of the persons who are mentioned in para 54 of the said

order. However, the Committee is to be headed by Prof. Ravi

Chopra, who will replace Justice U.C. Dhyani, and will be the

Chairman of the Committee. In addition to this, we add a

representative of the Physical Research Laboratory,

Department of Space, Government of India, Ahmedabad; a

representative of the Wildlife Institute of India, Dehradun; a

representative of MoEF&CC, Regional Office, Dehradun; and

a representative of the Ministry of Defence dealing with

Border roads, not below the rank of Director. We direct

MoEF&CC to constitute the High Powered Committee within

two weeks from the date of this order. The HPC may co-opt

member(s) for effective discharge of its functions. The

MoEF&CC shall provide venue and secretarial assistance

to the HPC, who will make decisions by majority voting.”

(emphasis supplied)

The terms of reference of the HPC were also revised in the following terms:

“I. The Committee shall consider the cumulative and

independent impact of the Chardham [P]roject on the entire

Himalayan valleys and for that purpose, the HPC will give

directions to conduct EIA/rapid EIA by the Project

Proponent/MoRTH.

 13 CA No 10930/2018, CA Nos 8518-8520/2018 and MA No 2678-2680/2018

PART C

9

II. The HPC, with the help of the technical body and

engineers of implementation agency (MoRTH) should

consider whether revision of the full Chardham [P]roject

(about 900 Kms) should at all take place with a view to

minimize the adverse impact of the project on

environment and social life.

III. The HPC shall identify the sites in which work (i.e. hillcutting) has started and the stretches in which the work has

not yet started. As far as the sites in which work has started,

the High Powered Committee should recommend the

measures which are required for stabilizing the area where

hill-cutting has taken place, among others, the

environmentally safe disposal of muck which has been

generated so that it does not adversely affect the flora and

fauna of the catchment area of the river.

IV. As regards the stretches where work has not started, the

HPC will review the proposed project and recommend

measures which will minimize the adverse impact on

environment, social life and bring the project in conformity

with the steep valley terrain, carrying capacity, thus avoiding

any triggering of new landslides and ensuring conservation

and protection of sensitive Himalayan valleys.

V. The HPC will assess the environmental degradation in

terms of loss of forest land, trees, green cover, water

resources, dumping of muck and impacts on the wildlife and

will direct the mitigation measures. Specific attention will be

laid on protecting wildlife corridors, and rare and endangered

flora and fauna.

VI. The HPC will assess and quantify the impact on social

infrastructure/public-life due to triggering of fresh landslides,

air pollution, frequent road blocks etc. and will suggest

necessary measures for its redressal, including preparation of

disaster management plans prior to the monsoon season.

VII. In Bhagirathi Eco Sensitive Zone (Gangotri to Uttarkashi),

the HPC will make special provisions in its report keeping in

mind the guidelines given under the Notification of the

Bhagirathi Eco Sensitive Zone so as to avoid violations and

any environmental damage.

VIII. The HPC will also suggest the areas in which

afforestation measures should be taken. It will also suggest

the kind of saplings which have to be planted in different

terrains of Himalayas. A separate Committee be constituted

by the Forest Department of Uttarakhand to continuously

monitor and report on the website that the saplings which

have been planted have survived and grown. In case of nonsurvival of any sapling, further plantation should be done. 

PART C

10

Compensatory afforestation should be ten times the number

of trees which have been cut. The HPC shall prepare an

effective afforestation plan ensuring its proper

implementation.

IX. The HPC will invite experts from different fields and

consult local people or hold public meeting in the local areas

to take recommendations and suggestions, as it deems fit.

X. The HPC shall consider giving specific directions to the

concerned agencies to put in the public domain the landslideprone areas, and their treatment by the Project Proponent,

the total muck generated, and the places where it has been

disposed of in an environmentally sound manner.”

(emphasis supplied)

The HPC was directed to submit its report of recommendations in four months.

Following the submission of the report, the Court directed MoRTH to implement

its recommendations. For this purpose, the Court observed:

“The reports prepared by the HPC with its recommendations

shall be given to the project Proponent i.e. MoRTH for

implementation. The HPC shall hold quarterly meetings

thereafter to ensure timely and proper compliance of its

recommendations. The HPC may suggest any further

measure which may be required, in the interest protection and

conservation of environment, after each quarterly review

meeting.”

10 Pursuant to the order of this Court, a report dated 13 July 2020 was

submitted by the HPC to this Court. By an order dated 8 September 2020, a

three-judge Bench of this Court comprising of Justice Rohinton F Nariman,

Justice Navin Sinha and Justice Indira Banerjee took cognizance of the Report,

and noted that the conclusions in the HPC Report were unanimous, except for

the issue relating to the width of the road. A majority comprising thirteen

members of the HPC was in favour of applying a Circular dated 5 October 2012 

PART C

11

issued by MoRTH14, which stipulates that in all new projects of

widening/bypass/realignment, the width of the carriageway will be at least twolane with paved shoulder (DL-PS), irrespective of the traffic. According to the

2012 MoRTH Circular, the road-way width would be 12m comprising of 7m for

the double-lane carriageway, a 1.5m paved shoulder on either side of the

highway, and a 1m earthen shoulder on either side of the highway. A minority

comprising of 5 members, including the Chairperson, was of the view that a

subsequent Circular dated 23 March 2018 issued by the MoRTH15 should govern

the Project. The 2018 MoRTH Circular provides that in hills and mountainous

terrains, where the traffic volumes range from 3,000 to 8,000 Passenger Car

Units16 a day, the carriageway width should be of intermediate lane

configurations (Intermediate Width17 standard), i.e., of 5.5m width with two-lane

structures. The order of the Court accepted the view of the minority and

observed:

“We have perused the conclusions and recommendations of

the report, in particular, from pages 90-93 in Part I. We are of

the view that it is correct that the 2018 MORTH circular

should apply for the reasons given at page 93 of the

report. Consequently, the 2018 circular alone will apply.

The other directions that were issued by us on 08.08.2019

must be strictly complied with, including the holding of

quarterly meetings to ensure timely and proper compliance of

the recommendations.”

(emphasis supplied)

 14 “2012 MoRTH Circular” - No. NH-14019/6/2012-P&M 15 “2018 MoRTH Circular” - No. NH-15017/ 28/ 2018 - P&M 16 “PCU” 17 “IW”

PART C

12

11 Following the above order, a letter dated 5 October 2020 was received by

the Registry of this Court from the Chairperson of the HPC. Professor Chopra

highlighted the steps he had taken to notify MoRTH of the order of this Court. He

stated that he had requested MoRTH to submit a plan to bring the Project in

conformity with the 2018 MoRTH Circular and suspend all fresh hill-cutting

activities. The letter also highlighted that Professor Chopra had received reports

of tree-felling and fresh hill-cutting on various stretches on NH-58, NH-94, et al,

which was being carried out on the basis of the old road-width standard, i.e., DLPS with a 10m tarred road. The Chairperson stated that on 27 September 2020,

he had read a news report indicating that MoRTH had informed the Government

of Uttarakhand that the 2018 MoRTH Circular would be applicable only to the

proposed 13 projects where work had not yet begun. Through this letter,

Professor Chopra urged that the directions in the order of this Court dated 8

September 2020 should be strictly followed. The letter dated 5 October 2020 was

converted into MA No 1925 of 2020, which is the subject-matter of this judgment.

Further, another letter dated 2 November 2020 was received from Professor

Chopra, where he highlighted the non-compliance of the order of this Court and

raised issues regarding the functioning of the HPC.

12 An affidavit was filed by the seventh appellant (Swami Samvidanand)

seeking, inter alia, directions to MoRTH to:

(i) stop hill-cutting, tree-felling and activities in violation of the 2018 MoRTH

Circular;

(ii) compensate for hill-cutting beyond the IW standard with tree plantations

and footpath; and

PART C

13

(iii) render full secretarial assistance to the HPC.

13 An interlocutory application, IA No 6097 of 2021, was later filed by the sixth

appellant (Deepak Chand Ramola) seeking the following directions:

(i) that the amendment to the 2018 MoRTH Circular through the Circular

dated 15 December 202018, should be revoked;

(ii) that the IW standard be adhered to for the entire Project, both

prospectively and retrospectively, as mentioned in this Court’s order dated

8 September 2020;

(iii) that the Bhagirathi Eco Sensitive Zone19 be given special protection;

(iv) that the HPC be strengthened to ensure proper implementation of its

functions; and

(v) on the basis of the findings of the HPC, a committee be set up to direct an

inquiry against the persons responsible for wilful violations of the laws in

force.

14 Another miscellaneous application, MA No 2180 of 2020, was then filed by

the Union of India20, through the Ministry of Defence21, seeking modification of

this Court’s order dated 8 September 2020, which is also the subject matter of

this judgment. This application seeks permission for the widening of the national

highways from Rishikesh to Mana, Rishikesh to Gangotri, and Tanakpur to

Pithoragarh to a two-lane, DL-PS configuration. The application avers that a

minority of the members of the HPC, whose view was adopted by this Court in its

 18 “2020 MoRTH Circular” – No. NH-15017/28/2018-P&M 19 “BESZ” 20 “UOI” 21 “MoD”

PART C

14

order dated 8 September 2020, relied on a statement of the then Chief of Army

Staff which confirmed that the requirements of the Indian Army are fulfilled by the

existing roads. However, according to the Union Government, there has been a

material change in circumstances, necessitating an improvement of roads to

enable movement of troops and equipment to Army stations on the Indo-China

border. Thus, the application has urged that a double lane road having a

carriageway width of 7m (or 7.5m) is necessary to meet the Army’s requirement.

The relief which has been sought in the application, is extracted below:

“Modify the Order dated 08.09.2020 and direct that the

national highways from Rishikesh to Mana, from Rishikesh

to Gangotri and from Tanakpur to Pithoragarh may be

developed to 2 lane configuration in the interest of the

security of the nation and for the defence of its borders”.

(emphasis supplied)

15 By an order dated 2 December 2020, a three-judge Bench comprising of

Justice Rohinton F Nariman, Justice Navin Sinha and Justice KM Joseph

directed the HPC to consider the issues raised by its Chairperson in his letters

and applications, including the application by the MoD, and to submit a detailed

report. Pursuant to the order of this Court, the 11th meeting of the HPC was held

on 15 and 16 December 2020. The report22 of the deliberations and submissions

of the HPC was received by the Registry from the Secretary, Forest Department,

State of Uttarakhand through a letter dated 31 December 2020.

 22 “HPC Report II”

PART D

15

16 This is where the matter stands presently. We shall consider the

submissions urged by the parties.

D Submissions

17 Mr Colin Gonsalves, Senior Counsel appearing on behalf of the appellants,

urged the following submissions:

(i) Issues concerning the functioning of the HPC: The HPC was not

allowed to function independently and was given inadequate assistance by

the UOI:

(a) The HPC consisted of 8 District Magistrates, 5 State Government

officials, 2 Union Government officials and 5 representatives from

institutions funded by the State and Union Governments. The

members of the HPC linked to the government voted en bloc and

toed the ‘official line’, rather than basing their judgment on a

scientific basis; and

(b) The Chairperson of the HPC faced opposition from the UOI, as they

were unwilling to cooperate with the work of the HPC. The

Chairperson had repeatedly written to MoRTH, regarding the plan of

action for slope stabilisation, muck disposal and restoration of

damaged slopes; to the State, pointing out that the original order of

the NGT did not stipulate District Magistrates to be members of the

HPC and that their role was limited to coordination with the local

population; to the UOI, to provide inventory of vulnerable slopes and

muck; and to the MoEF&CC, regarding the continuing hill-cutting 

PART D

16

activities. However, no concrete action was taken by any of the

parties;

(ii) Violations committed by MoRTH: MoRTH has been constructing roads

and widening the highways in violation of the 2018 MoRTH Circular and

the order of this Court dated 8 September 2020:

(a) MoRTH started widening the highways according to the DL-PS

standard, in violation of the 2018 MoRTH Circular which provided

for adherence to the IW standard;

(b) During the deliberations of the HPC, massive hill-cutting and

deforestation activities were undertaken, which have caused

irreversible damage to the Himalayan environment;

(c) After the order of this Court dated 8 September 2020, MoRTH has

continued to undertake hill-cutting, tree-felling, tarring and unrelated

activities;

(d) Despite the order of this Court, MoRTH has taken a stand that the

order will only be implemented for the 13 projects where the work

has not yet started. However, the order of 8 September 2020 stated

that the 2018 MoRTH Circular alone has to be followed and will

apply retrospectively, i.e., it will be applicable to the entire Project,

even where the work had already been initiated;

(e) MoRTH, in a recent notification dated 10 September 2020 which

was advertised in the newspapers, proposed the acquisition of land

for a toll booth. The toll is only applicable on roads of DL-PS

standard;

PART D

17

(iii) Road-width: The minority view, adopted by this Court in its order dated 8

September 2020, to construct the highways with an IW standard must be

upheld as:

(a) According to the Manual of Specifications and Standards for Two

Laning of Highways with Paved Shoulder23 published by the Indian

Roads Congress24 in June 2015, the vehicle size in India cannot

exceed a width of more than 2.4m. Thus, an intermediate lane of

5.5m on a linear profile and 7m on curves, is sufficient for two large

vehicles to cross each other;

(b) The fragile environment of the Himalayas will be severely damaged

if the DL-PS standard is adopted. As opposed to this, the IW

standard will ensure reduction of green cover loss, reduce

landslides, land loss, and tree loss by 80-90 per cent;

(c) The 2012 MoRTH Circular is inappropriate for mountain roads as it

can cause massive instability and environmental damage. As

opposed to this, the 2018 MoRTH Circular is specific to hilly and

mountainous areas, and should be adopted instead; and

(d) The amendments made by the 2020 MoRTH Circular are arbitrary

as they reinstate the 2012 MoRTH Circular without engaging with

the rationale of having an IW standard for mountainous areas;

(iv) Security concerns: The national security concerns regarding the

widening of the strategic roads are also met as:

 23 “2015 IRC Guidelines” 24 “IRC”

PART D

18

(a) The arguments raised by the MoD were considered by the HPC

Report. It was after consideration of these views that the Court had

passed the order dated 8 September 2020;

(b) To meet the defence requirements, it is essential that disasterresilient roads be built, instead of disaster-prone roads;

(c) The Project was not an initiative of the MoD, and was a project to

increase the tourist inflow to over 9,000 vehicles per day. The HPC

Report has noted that this projection is an exaggeration as

Badrinath, which has the maximum tourist inflow, has only 1000

vehicles per day and has already reached its carrying capacity; and

(d) The Chief of Army Staff in an interview had commented on the allweather road project and stated that the needs of the Army are

being met by the existing infrastructure.

18 In opposition to this, Mr KK Venugopal, Attorney General for India, made

submissions in support of the application filed by the UOI and the MoD. The

application seeks a modification of the order dated 8 September 2020 to allow

the national highways from Rishikesh to Mana, Rishikesh to Gangotri, and

Tanakpur to Pithoragarh to be developed with a DL-PS standard. The following

submissions were urged:

(i) Requirement of DL-PS standard for strategic border roads:

(a) The national highways from Rishikesh to Mana, Rishikesh to

Gangotri, and Tanakpur to Pithoragarh act as feeder roads to the

Indo-China border and have strategic importance;

PART D

19

(b) The minority opinion in the HPC Report relied on the statement of

the Chief of the Army Staff, according to which the present

infrastructure was adequate for the needs of the Army. However,

there has been a change in the circumstances since, and it is

necessary that personnel and equipment move swiftly to Army

stations at the Indo-China border points. The movement requires

that vehicles returning from the border are able to cross vehicles

going in the opposite direction without causing road-blocks or

coming to a dead halt. Thus, a carriageway with a width of 7m is

necessary to meet the security concerns of the country;

(c) These road-posts have been in use since the war with China in

1962. With the increase in defence capability; the nature of

weapons, tanks and machinery; and the conditions at the border,

wider roads with a DL-PS standard are required;

(d) Neither the 2012 MoRTH Circular nor the 2018 MoRTH Circular

deal with the security needs of the country. The 2018 MoRTH

Circular, which is general in nature, is based on PCU traffic and is

applicable to all the hilly areas. However, it did not consider the

strategic requirement for movement of military vehicles in the

Himalayan regions, closer to the border areas;

(e) The Armed Forces have sufficient human-power, machinery and

equipment to deal with landslides on any of these roads and can

clear the way for movement of Army vehicles, machinery, tanks and

artillery;

PART D

20

(f) Prior to 2017, the development of these roads was under the Border

Roads Organization25. However, in 2017, to develop these roads in

a timebound manner, a portion was handed over to the Public

Works Department26 and the National Highways and Infrastructure

Development Corporation27. Before the commencement of the

Project, the road from Rishikesh-Mana already had a 7m wide

carriageway, except in some stretches where the width was 3.75-

5.5m;

(g) The Guidelines for the Alignment Survey and Geometric Design of

Hill Roads28 adopted by the IRC in 2019 also recommend a two lane

uniform design for strategic border roads; and

(h) This need is further highlighted, given that across the border in

China, Tibet, Nepal and in the China-Pakistan corridor, strategic

roads are built with the DL-PS standard;

(ii) The BESZ was notified by the Union Government through a notification

dated 18 December 2012. However, in 2018, the notification was amended

to state that work related to national security infrastructure can be

implemented without due study of environmental impacts;

(iii) All-weather roads are also necessary for connectivity of persons living in

remote border areas;

 25 “BRO” 26 “PWD” 27 “NHIDCL” 28 “2019 IRC Guidelines”

PART D

21

(iv) Mitigation measures: The following mitigation steps have been

undertaken to ensure that least environmental and ecological damage is

caused by the Project:

(a) The Geological Survey of India29 and MoRTH have signed a

Memorandum of Undertaking to conduct geological studies of

strategic roads near the Indo-China border;

(b) Tehri Hydroelectric Development Corporation30 is being engaged for

project management consultancy services for restoration of slopes;

(c) The Defence Geo-Informatics Research Establishment31 is providing

sustainable mitigation measures for snow avalanches and other

natural calamities; and

(d) Slope stabilisation works and protection measures and landslide

protection measures using soil nailing, ‘shotcreting’, secured

drapery, et al, are being undertaken;

(v) Compliance with the directions of this Court: No hill-cutting activities

for road-widening have been carried out by the executing agencies. In fact,

MoRTH took the following steps to comply with the order of this Court:

(a) Directions were issued to all executing agencies, such as BRO and

NHIDCL, to implement the order of this Court;

(b) A Draft Rapid EIA Report was submitted to the HPC on 16

September 2020;

 29 “GSI” 30 “THDC” 31 “DGIRE”

PART D

22

(c) Details of vulnerable slopes and muck disposal sites were submitted

to the HPC on 25 September 2020;

(d) A committee has been formulated to develop a permanent landslide

mitigation strategy;

(e) 12,75,813 plants have been planted in 797.28 hectares as

compensatory afforestation, and 5,45,268 plants are to be planted in

future;

(f) Secretarial assistance was provided to the HPC by the State of

Uttarakhand under an order dated 7 October 2020; and

(g) Out of the 40 sanctioned projects within the Project, 12m formation

cutting has already been carried out in 537 kms out of the total

sanctioned length of 662 kms, prior to the order of this Court dated 8

September 2020. In such a situation, where hill-cutting has already

been carried out for 12m formation and 10m tarred road has been

laid down, a substantial reduction of the width to 5.5m will result in

non-uniform carriageway in short stretches.

19 Having addressed the rival submissions, we shall now analyse them.

PART E

23

E Framework of Analysis

20 Before we analyse the specific issues raised in the context of the Project, it

is important to consider the framework within which this Court must consider

them. It is important for us to take note of the relevant judicial pronouncements

on the subject, as well as understand the requirements of the circulars and

guidelines which have been issued in regard to these issues. However, given the

specific setting of the Project in the heart of the Himalayas, our framework has to

take into account the unique ecology of the Himalayas. The appellants have

provided this Court with examples from the past and the recent history of the

Himalayas, which demonstrate that a lack of foresight in development has led to

significant environmental harm.

21 Speaking about the Himalayas, the obvious place to begin is their

majesty. The Himalayas are considered to be India’s border in the north, just as

the vast Indian ocean is in its south. In laypersons’ geographical terms, it is

difficult to imagine that these majestic mountains are nothing more than the

debris created during the collision of the Indian and Eurasian tectonic plates

several million years ago. While the debris has solidified into rock in many places,

it continues to be soil and rubble in others. In comparison to many others, the

Himalayas are actually very young (when the point of reference is a comparison

of ages in the millions). This lends to them a comparative fragility32. The HPC

Report notes that “the still evolving Himalayan ranges consist of thrusted, jointed

or sheared, fissured or twisted rock material interspersed with soil. Shorn of

 32 Michael P Searle and Peter J Treloar, “Introduction to Himalayan tectonics: a modern synthesis” in Peter J

Treloar and Michael P Searle (eds), Himalayan tectonics: A Modern Synthesis (The Geological Society, 2019)

PART E

24

green cover, their slopes [are] even more fragile. When exposed to the monsoon

rains, weakened slopes often collapse”33.

22 The Himalayan range is in itself diverse and cannot be characterized

through one common idea or pattern. Broadly speaking, it is divided into three

categories: the Higher Himalayas (called “Himadri”), which contain some of the

highest mountain peaks, are often snowbound through the year and are sparsely

populated; the Lower Himalayas (called “Himachal”), which contains mediumsized mountains and highly populated regions; and the Sub-Himalayas (called

“Shivalik”), which are the southernmost ranges of the Himalayas. Each of these

have their own ecology, rainfall and snowfall distribution, flora and fauna. The

concerns associated with each of them are different and have to be accounted for

while adjudicating upon environmental issues raised with development projects.

23 In a 2018 report published by the NITI Aayog, these concerns were noted

with pointed reference to the effects of the tourism industry. The report noted34:

“Current forms of tourism in the [Indian Himalayan Region]

are unsustainable. They replace traditional and aesthetic

architecture with inappropriate, non-aesthetic and often

dangerous constructions, and compound other challenges

such as poorly designed roads and associated infrastructure,

inadequate solid waste management, air pollution,

degradation of watersheds and water sources, loss of natural

resources, biodiversity, and ecosystem services.”

Similarly, relying upon the NITI Aayog’s conclusions, the HPC Report also

notes35:

 33 HPC Report, page 34 34 “Contributing to Sustainable Development in the Indian Himalayan Region” (August 2018, NITI Aayog)

available at <http://164.100.94.191/niti/writereaddata/files/document_publication/doc6.pdf> accessed on 6

December 2021

PART E

25

“…the Himalaya call for a new development paradigm in

which development must be fully embedded in the

environmental, socio-cultural and sacred tenets of the IHR. It

has been observed that the present demand-driven,

uncontrolled economic growth has led to haphazard

urbanization, environmental degradation and increased risks

and vulnerabilities, seriously compromising the unique values

of Himalayan ecosystems.”

It is In the backdrop of these observations that we must consider the principles

applicable to the judicial review which this Court must undertake in the present

case.

E.1 Principles of Sustainable Development and Environmental Rule of

Law

24 Sustainable development is a common benchmark through which all

development projects are judged. Arguably finding its origin in global policy from

the Bruntland Report in 1987, it is often defined as “development that meets the

needs of the present without compromising the ability of future generations to

meet their own needs”36. Adopted globally as the standard for development by

nations, it is the bedrock upon which the Sustainable Development Goals37 have

been laid out. Their latest iteration, consisting of 17 SDGs, was adopted by all

United Nations member States in 2015. Titled as the “2030 Agenda for

Sustainable Development”38, these SDGs are broad, with their focus being on

overall development of society in a manner which comports with environmental

 35 HPC Report, page 43 36 “Report of the World Commission on Environment and Development: Our Common Future” (1987) available at

<https://sustainabledevelopment.un.org/content/documents/5987our-common-future.pdf> accessed on 6

December 2021

37 “SDGs” 38 Available at <https://sdgs.un.org/2030agenda> accessed on 7 December 2021

PART E

26

preservation now and in trust for the future. SDG13 specifically focuses on

“Climate Action”, which is to be balanced with the other SDGs (such as SDG9,

which encourages “Industry, Innovation and Infrastructure”).

25 The principle of sustainable development has found consistent application

in matters of environmental law. Sustainable development has a multidimensional approach, with a focus on the development of the economy,

protection of individual rights and environmental concerns, while ensuring both

inter and intra-generational equity. This allows the principle of sustainable

development to look beyond creating policy goals (which necessarily seek

specific outcomes) towards creating policy approaches (which rather seek to

provide better frameworks)39. The principle of sustainable development has been

explicitly recognized in multiple judgments of this Court.

26 In Indian Council for Enviro-Legal Action v. Union of India40, a threejudge Bench of this Court described the principle of sustainable development in

the following terms:

“31…While economic development should not be allowed to

take place at the cost of ecology or by causing widespread

environment destruction and violation; at the same time, the

necessity to preserve ecology and environment should not

hamper economic and other developments. Both

development and environment must go hand in hand, in other

words, there should not be development at the cost of

environment and vice versa, but there should be development

while taking due care and ensuring the protection of

environment. This is sought to be achieved by issuing

notifications like the present, relating to developmental

activities being carried out in such a way so that unnecessary

 39 J B Ruhl, ‘Sustainable Development: A Five-Dimensional Algorithm for Environmental Law’ (1999) 18 Stanford

Environmental Law Journal 31

40 (1996) 5 SCC 281

PART E

27

environmental degradation does not take place. In other

words, in order to prevent ecological imbalance and

degradation that developmental activity is sought to be

regulated.”

27 In Essar Oil Ltd. v. Halar Utkarsh Samiti41, a two-judge Bench of this

Court referred to the Stockholm Declaration while elucidating on the principle of

sustainable development. It noted that while socio-economic needs could be

fulfilled through development, environmental concerns will always remain.

However, these concerns should not be seen as a deadlock between

development and the environment but as an opportunity to harmonize both,

through the principle of sustainable development. Speaking through Justice

Ruma Pal, this Court observed:

“27. This, therefore, is the aim, namely, to balance economic

and social needs on the one hand with environmental

considerations on the other. But in a sense all development is

an environmental threat. Indeed, the very existence of

humanity and the rapid increase in the population together

with consequential demands to sustain the population has

resulted in the concreting of open lands, cutting down of

forests, the filling up of lakes and pollution of water resources

and the very air which we breathe. However, there need not

necessarily be a deadlock between development on the one

hand and the environment on the other. The objective of all

laws on environment should be to create harmony between

the two since neither one can be sacrificed at the altar of the

other…”

28 In N.D. Jayal & Anr v. Union of India & Ors42, a three-judge Bench held

that a balance between developmental activities and environmental protection

could only be maintained through the principle of sustainable development. Doing

 41 (2004) 2 SCC 392 42 (2004) 9 SCC 362

PART E

28

this was held to be necessary, without which the future generations could be in

jeopardy. Justice S Rajendra Babu (speaking for himself and Justice Mathur)

held:

“22. Before adverting to other issues, certain aspects

pertaining to the preservation of ecology and development

have to be noticed. In Vellore Citizen’' Welfare Forum v.

Union of India [(1996) 5 SCC 647] and in M.C. Mehta v.

Union of India [(2002) 4 SCC 356] it was observed that the

balance between environmental protection and

developmental activities could only be maintained by strictly

following the principle of “sustainable development”. This is a

development strategy that caters to the needs of the present

without negotiating the ability of upcoming generations to

satisfy their needs. The strict observance of sustainable

development will put us on a path that ensures development

while protecting the environment, a path that works for all

peoples and for all generations. It is a guarantee to the

present and a bequeath to the future. All environment-related

developmental activities should benefit more people while

maintaining the environmental balance. This could be

ensured only by strict adherence to sustainable development

without which life of the coming generations will be in

jeopardy.”

Justice Babu also noted that while the right to a clean environment is guaranteed

as an intrinsic part of the fundamental right to life and personal liberty, the right to

development can also be declared as a component of Article 21:

“24. The right to development cannot be treated as a mere

right to economic betterment or cannot be limited as a

misnomer to simple construction activities. The right to

development encompasses much more than economic wellbeing, and includes within its definition the guarantee of

fundamental human rights. The “development” is not related

only to the growth of GNP. In the classic work, Development

As Freedom, the Nobel prize winner Amartya Sen pointed out

that “the issue of development cannot be separated from the

conceptual framework of human right”. This idea is also part

of the UN Declaration on the Right to Development. The right

to development includes the whole spectrum of civil, cultural,

economic, political and social process, for the improvement of

people’' well-being and realization of their full potential. It is 

PART E

29

an integral part of human rights. Of course, construction of a

dam or a mega project is definitely an attempt to achieve the

goal of wholesome development. Such works could very well

be treated as integral component for development.”

29 More recently, in Rajeev Suri v. Delhi43, a three judge Bench of this Court

had to decide on the permissibility of the Central Vista Project. In considering the

use of the principle of sustainable development, Justice A M Khanwilkar

observed that the principle of sustainable development necessarily incorporates

within it the principle of development – development which is sustainable and not

environmentally degrading. He holds thus:

“507. The principle of sustainable development and

precautionary principle need to be understood in a proper

context. The expression “sustainable development”

incorporates a wide meaning within its fold. It

contemplates that development ought to be sustainable

with the idea of preservation of natural environment for

present and future generations. It would not be without

significance to note that sustainable development is

indeed a principle of development–- it posits controlled

development. The primary requirement underlying this

principle is to ensure that every development work is

sustainable; and this requirement of sustainability

demands that the first attempt of every agency enforcing

environmental rule of law in the country ought to be to

alleviate environmental concerns by proper mitigating

measures. The future generations have an equal stake in

the environment and development. They are as much

entitled to a developed society as they are to an

environmentally secure society. By Declaration on the

Right to Development, 1986, the United Nations has given

express recognition to a right to development. Article 1 of the

Declaration defines this right as:

“1. The right to development is an inalienable human right by

virtue of which every human person and all peoples are

entitled to participate in, contribute to, and enjoy economic,

social, cultural and political development, in which all human

rights and fundamental freedoms can be fully realized.”

 43 2021 SCC OnLine SC 7

PART E

30

508. The right to development, thus, is intrinsically connected

to the preservance of a dignified life. It is not limited to the

idea of infrastructural development, rather, it entails human

development as the basis of all development. The

jurisprudence in environmental matters must

acknowledge that there is immense inter-dependence

between right to development and right to natural

environment. In International Law and Sustainable

Development, Arjun Sengupta in the chapter “Implementing

the Right to Development [International Law and Sustainable

Development–- Principles and Practice, Edn. 2004, pg. 354]”

notes thus:

“… Two rights are interdependent if the level of enjoyment of

one is dependent on the level of enjoyment of the other…””

(emphasis supplied)

30 Similarly, in Municipal Corporation of Greater Mumbai v. Ankita

Sinha44, another three judge Bench of this Court ruled on the powers of the NGT

under the National Green Tribunal Act 2010. This Court noted the significance of

environmental justice and environmental equity, and highlighted how

environmental harms cause disproportionate implications for the economically or

socially marginalized groups. Thus, it was considered important to ensure that

environmental equity was achieved, through the use of principles such as

sustainable development. In this regard, speaking through Justice Hrishikesh

Roy, the Court held:

“XI. ENVIRONMENTAL JUSTICE AND ENVIROMENTAL

EQUITY

82. The conceptual frameworks of environmental justice and

equity should merit consideration vis-à-vis the NG’'s domain

and how its functioning and decisions can have wide

implications in socio-economic dimensions of people at large.

The concept of environmental justice is a trifecta of

distributive justice, procedural justice and justice as

 44 2021 SCC OnLine SC 897

PART E

31

recognition.[Schlosberg D, Defining Environmental Justice :

Theories, Movements, and Nature (Oxford University Press

2009)] Environmental equity as a developing concept has

focused on the disproportionate implications of

environmental harms on the economically or socially

marginalized groups. The concerns of human rights and

environmental degradation overlap under this umbrella term,

to highlight the human element, apart from economic and

environmental ramifications. Environmental equity thus

stands to ensure a balanced distribution of

environmental risks as well as protections, including

application of sustainable development principles.

83. Voicing concerns about the disproportionate harm for the

poor segments, Lois J. Schiffer (then Assistant Attorney

General, Environment & Natural Resources Division (ENRD),

U.S. Department of Justice) and Timothy J. Dowling (then

Attorney at ENRD) in their Reflections on the Role of the

Courts in Environmental Law, wrote the following evocative

passage on the concept of environmental justice,

“Environmental Justice, which focuses on whether minorities

and low-income people bear a disproportionate burden of

exposure to environmental harms and any resulting health

effects. In the past ten to fifteen years, this issue has

crystallized a grass-roots movement that combines civil rights

issues with environmental issues, with a goal of achieving

“environmental justice” or “environmental equity”, which is

understood to mean the fair distribution of environmental risks

and protection from environmental harms.”[Schiffer, L. J., &

Dowling, T. J. (1997). Reflections On The Role Of The Courts

In Environmental Law. Environmental Law, 27(2), 327-342]”

(emphasis supplied)

31 The principle of sustainable development is deep-rooted in the

jurisprudence of Indian environmental law. It has emerged as a multi-faceted

principle, which does not prohibit development, but structures it around what is

sustainable. Sustainable development incorporates two related ideas –

development which not only ensures equity between the present and the future

generations but also development which ensures equity between different

sections of society at present. However, while the principle has deep roots, there 

PART E

32

is a lack of consensus on how to ascertain whether a particular developmental

project abides by the principle of sustainable development. Without a common

benchmark or standard being applied by the Court in its analysis of the impact of

development projects, the principle of sustainable development may create

differing and arbitrary metrics (depending on the nature of individual projects).

This not only creates uncertainty within the law, but makes the application of the

principle of sustainable development selective, taking away from its potential to

drive sustained change.

32 A cogent remedy to this problem is to adopt the standard of the

‘environmental rule of law’ to test governance decisions under which

developmental projects are approved. In its 2015 Issue Brief titled “Environmental

Rule of Law: Critical to Sustainable Development”, the United Nations

Environment Programme45 has recommended the adoption of such an approach

in the following terms46:

“Environmental rule of law integrates the critical

environmental needs with the essential elements of the rule of

law, and provides the basis for reforming environmental

governance. It prioritizes environmental sustainability by

connecting it with fundamental rights and obligations. It

implicitly reflects universal moral values and ethical norms of

behaviour, and it provides a foundation for environmental

rights and obligations. Without environmental rule of law and

the enforcement of legal rights and obligations, environmental

governance may be arbitrary, that is, discretionary,

subjective, and unpredictable.”

 45 “UNEP” 46 Available at <https://wedocs.unep.org/bitstream/handle/20.500.11822/10664/issue-brieferol.pdf?sequence=1&amp%3BisAllowed=> accessed on 7 December 2021 

PART E

33

33 UNEP has further reiterated the importance of the ‘environmental rule of

law’ in its 2019 report titled “Environmental Rule of Law: First Global Report”,

where it notes:

“Environmental rule of law is key to achieving the Sustainable

Development Goals. Indeed, it lies at the core of Sustainable

Development Goal 16, which commits to advancing “rule of

law at the national and international levels” in order to

“[p]romote peaceful and inclusive societies for sustainable

development, provide access to justice for all and build

effective, accountable and inclusive institutions at all levels.”

[…]

Environmental law and institutions have grown dramatically in

the last few decades, but they are still maturing.

Environmental laws have taken root around the globe as

countries increasingly understand the vital linkages between

environment, economic growth, public health, social

cohesion, and security. Countries have adopted many

implementing regulations and have started to enforce the

laws. Too often, though, there remains an implementation

gap.

Environmental rule of law seeks to address this gap and align

actual practice with the environmental goals and laws on the

books. To ensure that environmental law is effective in

providing an enabling environment for sustainable

development, environmental rule of law needs to be nurtured

in a manner that builds strong institutions that engage the

public, ensures access to information and justice, protects

human rights, and advances true accountability for all

environmental actors and decision makers…”

34 Within the Indian context, environmental rule of law was first applied by

this Court in Hanuman Laxman Aroskar v. Union of India47. In that case, the

Government of Goa had mooted a new international airport at Mopa in Goa in

1997. While the MoEF&CC gave it an EC, it ultimately came to be challenged

before this Court. In its decision, a two-judge Bench of this Court found a lack of

 47 (2019) 15 SCC 401

PART E

34

information transparency in the disclosures filed by project proponents, and

directed a fresh exercise for a rapid EC to be carried out. In emphasizing on

environmental governance within a rule of law paradigm, Justice DY

Chandrachud observed:

“J. Environmental Rule of Law

[…]

144. The environmental rule of law provides an essential

platform underpinning the four pillars of sustainable

development — economic, social, environmental and

peace [United Nations Environment Programme, First

Environmental Rule of Law Report. Available at <https :

//wedocs.unep.org/bitstream/handle/20.500.11822/27279/Env

ironmental _rule_of_law.pdf?sequence=1&isAllowe d=y>] . It

imbues environmental objectives with the essentials of

rule of law and underpins the reform of environmental

law and governance [ United Nations Environment

Programme, First Environmental Rule of Law Report.

Available at <https :

//wedocs.unep.org/bitstream/handle/20.500.11822/27279/Env

ironmental _rule_of_law.pdf?sequence=1&isAllowe d=y>] .

The environmental rule of law becomes a priority particularly

when we acknowledge that the benefits of environmental rule

of law extend far beyond the environmental sector. While the

most direct effects are on protection of the environment, it

also strengthens rule of law more broadly, supports

sustainable economic and social development, protects public

health, contributes to peace and security by avoiding and

defusing conflict, and protects human and constitutional rights

[ United Nations Environment Programme, First

Environmental Rule of Law Report. Available at <https :

//wedocs.unep.org/bitstream/handle/20.500.11822/27279/Env

ironmental _rule_of_law.pdf?sequence=1&isAllowe d=y>] .

Similarly, the rule of law in environmental matters is

indispensable “for equity in terms of the advancement of

the Sustainable Development Goals (SDGs), the

provision of fair access by assuring a rights-based

approach, and the promotion and protection of

environmental and other socioeconomic rights [ “UN

Environment, Environmental Rule of Law”. Available at <https

: //www.unenvironment.org/explore-topics/environmentalrights-and-governance/what-we-do/promoting-environmentalrule-law-0>] .”

PART E

35

145. […] Thus35pprox.35terizedd, it encompasses the

preservation, and when possible even the expansion of

the substantive freedoms and capabilities of people

today without compromising the capability of future

generations to have similar — or more — freedoms. The

intertwined concepts of environmental rule of law thus

further intragenerational as well as intergenerational

equity.

(emphasis supplied)

Thus, the Court acknowledged that consistent decision-making on its behalf was

a crucial factor in upholding the environmental rule of law.

35 In Bengaluru Development Authority v. Sudhakar Hegde48, a two-judge

Bench of this Court observed that there was no winner in environmental litigation,

since both – development and protection of environment – are necessary. The

Court clarified that a framework created by environmental rule of law has to

balance both these considerations by creating transparent and accountable

institutions, while allowing for participatory democracy. Justice DY Chandrachud,

speaking for the Court, held:

“94. The adversarial system is, by its nature, rights based. In

the quest for justice, it is not uncommon to postulate a

winning side and a losing side. In matters of the

environment and development however, there is no

trade-off between the two. The protection of the

environment is an inherent component of development

and growth.

95. The protection of the environment is premised not only on

the active role of courts, but also on robust institutional

frameworks within which every stakeholder complies with its

duty to ensure sustainable development. A framework of

environmental governance committed to the rule of law

requires a regime which has effective, accountable and

transparent institutions. Equally important is responsive,

 48 (2020) 15 SCC 63

PART E

36

inclusive, participatory and representative decisionmaking. Environmental governance is founded on the

rule of law and emerges from the values of our

Constitution. Where the health of the environment is key

to preserving the right to life as a constitutionally

recognised value under Article 21 of the Constitution,

proper structures for environmental decision-making find

expression in the guarantee against arbitrary action and

the affirmative duty of fair treatment under Article 14 of

the Constitution. Sustainable development is premised

not merely on the redressal of the failure of democratic

institutions in the protection of the environment, but

ensuring that such failures do not take place.”

(emphasis supplied)

36 In H.P. Bus-Stand Management & Development Authority v. Central

Empowered Committee49, a three-judge Bench held that environmental rule of

law was no panacea which allowed for a clear set of solutions in every case,

since every case was unique and with differing levels of actual evidence.

However, it did provide a framework within which any case could be adjudicated

in a predictable manner, keeping in mind the principles of sustainable

development at its core. Justice DY Chandrachud, speaking for the Court, held:

“52. The need to adjudicate disputes over environmental

harm within a rule of law framework is rooted in a

principled commitment to ensure fidelity to the legal

framework regulating environmental protection in a

manner that transcends a case-by-case adjudication.

Before this mode of analysis gained acceptance, we

faced a situation in which, despite the existence of

environmental legislation on the statute books, there was

an absence of a set of overarching judicially recognised

principles that could inform environmental adjudication

in a manner that was stable, certain and predictable.

53. However, even while using the framework of an

environmental rule of law, the difficulty we face is this —

when adjudicating bodies are called on to adjudicate on

 49 (2021) 4 SCC 309

PART E

37

environmental infractions, the precise harm that has taken

place is often not susceptible to concrete quantification. While

the framework provides valuable guidance in relation to the

principles to be kept in mind while adjudicating upon

environmental disputes, it does not provide clear pathways to

determine the harm caused in multifarious factual situations

that fall for judicial consideration. The determination of such

harm requires access to scientific data which is often times

difficult to come by in individual situations.

54…the environmental rule of law calls on us, as Judges,

to marshal the knowledge emerging from the record,

limited though it may sometimes be, to respond in a

stern and decisive fashion to violations of environmental

law. We cannot be stupefied into inaction by not having

access to complete details about the manner in which an

environmental law violation has occurred or its full

implications. Instead, the framework, acknowledging the

imperfect world that we inhabit, provides a roadmap to

deal with environmental law violations, an absence of

clear evidence of consequences notwithstanding.”

(emphasis supplied)

37 Having now established the framework of judicial principles necessary for

this Court to adjudicate the present matter, it is important to consider the specific

set of circulars and guidelines which are applicable.

E.2 Circulars and Guidelines

38 A combined reading of Article 246 along with Entry 2350 of List I of

Schedule VII of the Constitution of India indicates that national highways fall

entirely within the ambit of the Parliamentary domain. The executive power of the

Union is co-extensive with the power of Parliament. In accordance with Section

2(2) of the National Highways Act 1956, the Union Government is empowered to

 50 “23. Highways declared by or under law made by Parliament to be national highways.”

PART E

38

declare any road as a national highway and issue directions for its development

and maintenance51. Within the Union Government, the specific responsibility lies

with MoRTH. Hence, we must first begin by analyzing the relevant circulars which

have been issued by MoRTH.

39 The first of these is the 2012 MoRTH Circular, which was titled “Capacity

building and lane width of National Highways”. It stated:

“I am directed to inform that Ministry intends to take up

development of such National Highways having

carriageway width less than the two lane width. These

roads are to be developed to a minimum level.

2. Generally, the carriageway width is dictated by the

expected traffic. National Highways which are the primary

route have higher expectation from the consideration of level

of service as well as from safety consideration. This aspect

was deliberated in the Ministry, and observed that the NHs

are serving the mixed traffic. Besides, India has the dubious

distinction in terms of fatalities on roads and there is need to

segregate slow moving traffic from fast moving traffic. ·

3. In the above back ground to ensure safe and smooth traffic

on NHs, it has been decided that efforts be made to

convert all the NHs to a minimum level of two lane with

paved shoulders. Towards implementation of this,

henceforth whenever new projects of

widening/bypass/realignment are taken up, the width of

the carriageway shall be at least two lane with paved

shoulders irrespective of the traffic thereon.”

(emphasis supplied)

The 2012 MoRTH Circular provides that every national highway, if it was

presently less than of a two-lane width (i.e., less than 7m) or if it was under

development, had to henceforth meet the requirement of the DL-PS standard in

 51 Project Implementation Unit v. P.V. Krishnamoorthy, (2021) 3 SCC 572

PART E

39

order to ensure safety and the smooth flow of traffic. Accompanying this circular,

was the following pictorial representation of the new national highway width:

As we can note from the above depiction, the highway would be of a two-lane

width (i.e., 7m) with each of its sides being flanked by 1.5m of paved shoulders,

which would be followed by 1m of earth/granular shoulders.

40 Following the 2012 MoRTH Circular, the IRC (an apex body of engineers

in relation to road development) issued its 2015 IRC Guidelines in relation to the

standards to be followed while developing highways with the DL-PS specification.

Section 13 of the Guidelines dealt with the special requirements for hilly roads.

While it is not necessary for us to explain the specific requirements, the 2015 IRC

Guidelines highlight that highways with the DL-PS standard could be constructed

for hilly roads.

41 The 2012 MoRTH Circular was modified by the 2018 MoRTH Circular,

which was titled “Standards for Lane width of National Highways and roads

developed under Central Sector Schemes in Hilly and Mountainous terrains”. As

the name suggests, the 2018 MoRTH Circular modified the 2012 MoRTH Circular

to the extent that it applied to national highways in hilly and mountainous terrains.

The relevant portions of the Circular read as follows:

“On the subject of “Capacity building and lane width of

National Highways”, it has been stipulated vide this Ministry’s

letter No. NH-14019/6/2012-P&M dated 05.10.2012 [2012

MoRTH Circular] that width of carriageway shall be at least 

PART E

40

two lane with paved shoulders irrespective of the traffic

thereon in new projects undertaken for widening of

carriageway/ bypasses/realignments.

2. However, challenges have come to the fore in adhering to

these standards in the context of National Highways and

roads in hilly and mountainous terrains. These challenges

arise on account of destabilization of hill slopes and

progressive damaging effects on road alignments and

structures in higher contours on hills due to excavation works,

requirement for large-scale felling of precious trees,

associated environmental damages. Resultantly, there arises

need to provide largescale protection works, acquisition of

additional land for Right of Way (ROW), etc.

[…]

4. The provisions of Ministry’s letter No. NH-14019/6/2012-

P&M dated 05.10.2012 [2012 MoRTH Circular], have,

accordingly, been reviewed and it has been decided with the

approval of the Competent Authority that the following

provisions shall be applicable henceforth for National

Highways and roads under Central Sector Schemes in hilly

and mountainous terrains until further orders:

[…]

4.4 Following specific provisions shall be made for traffic

volumes ranging from 3,000 PCUs/day to about

8,000/day:-

(i) The carriageway width shall be of intermediate lane

configurations, i.e. of 5.5 m width (18 ft), with two-lane

structures (23 ft.).

(ii) The passing places may have widths of 2.5 m and 12

m length and these may be provided on alternate sides of

the road. The length of the tapered section may be 6 m

on either side of their approaches. Accordingly, the

length of the passing places may be 24 m inclusive of the

tapered length.

[…]

(vii) The Roadway width for Hilly and Mountainous

Terrain as per IRC: SP-2015 (Manual of Specifications

and Standards for Two laning of Highways with paved

shoulder) [2015 IRC Guidelines] would stand amended

accordingly.

4.5 For traffic volume of more than 10,000 PCUs/day or

the existing traffic volumes likely to witness a fast growth

to reach this level within a period of 3 to 5 years, the 

PART E

41

carriageway width shall be of two lane NH configurations,

i.e. of 7 m width. The carriageway widths shall be of two

lane NH configurations with paved shoulders only in

cases where the traffic is likely to increase at about more

than 10 % per annum.

5. The provisions of Ministry’s letter No. NH-14019/6/2012-

P&M dated 05.10.2012 [2012 MoRTH Circular] shall continue

to be applicable in all other cases.”

(emphasis supplied)

The 2018 MoRTH Circular modifies its precursor of 2012 for hilly and

mountainous terrains in the following ways: (i) for areas where the PCUs are in

the range of 4,000-8,000 PCUs per day, the carriageway width cannot be of DLPS configuration but has to be of IW standard (i.e., 5m); (ii) along with this,

adequate passing places with 2.5m width have to be included; (iii) the 2015 IRC

Guidelines stood amended; (iv) for areas where the PCUs are more than 10,000

per day (or expected to reach that level within 3 to 5 years), the carriage way

width could be of double lane configuration (i.e., 7m); and (v) where the traffic is

likely to increase by more than 10 per cent per annum, the width could be of DLPS configuration.

42 Subsequently, the IRC issued its 2019 IRC Guidelines in relation to hilly

roads. Of particular importance is Clause 6.2.2, which reads as follows:

“6.2.2 Width of carriageway, shoulders and roadway for

various categories of roads are given in Table 6.2.

Table 6.2 Widths of Carriageway, Shoulder and Roadway

[…]

PART E

42

In Mountainous and Steep Terrain (in Hilly Area)

Highway

Classification

Type of Section Shoulder Width (m) Roadway

Width

(Carriageway

+ Shoulders)

excluding

extra width on

horizontal

curves, side

parapet and

drain &

median (m)

Paved

(m)

Earthen

(m)

Total

width of

shoulders

on one

side (m)

Total

width of

shoulders

on both

sides (m)

National

Highways and

State

Highways

MDRs/ODRs

i. Double

Lane (7.00 m)

Open

country with

isolated

built up

area

Hill

Side

1.5 m - 1.5 m 4.00 m 11.00

Valley

Side

1.5 m 1.00 m 2.50 m

Built up

area and

approaches

to grade

separated

structures

bridges

Hill

Side

0.25 m +

1.5 m

(Raised)

- 1.75 m 3.5 m 10.50

Valley

Side

0.25 m +

1.5 m

(Raised)

- 1.75 m

Notes:

[…]

6. On roads subject to heavy snow fall, where snow clearance

is done over long periods, roadway width may be increased

by 1.5 m. However, the requirement of such widening may be

examined with reference to ground conditions in each case

considering terrain traffic and other influencing conditions and

factors.

[…]

8. Strategic and border roads for military/paramilitary/security

forces operations/movements shall be constructed for not

less than two lane carriageway alongwith paved shoulder on

hill side + paved and earthen shoulder on valley side on same

lines of national highway.”

PART E

43

Clause (8) of the Notes attached to Clause 6.2.2 provides that if a road is a

strategic or a border road and is going to be used for

“military/paramilitary/security forces operations/movements”, then it must be of

DL-PS configuration (along with earthen shoulders), “on the same lines” as other

national highways.

43 Finally, the 2020 MoRTH Circular modifies the 2018 MoRTH Circular, in

view of the suggestions received from the MoD. The circular, titled “Standards for

Lane width of National Highways and roads developed under Central Sector

Schemes in Hilly and Mountainous terrains”, provides as follows, in so far as is

material:

“MoRT&H had issued circular on “Standards for Lane width of

National Highways and roads developed under Central Sector

Schemes in Hilly and Mountainous terrains” vide this

Ministry’s letter of even number dated 23rd March, 2018 [2018

MoRTH Circular]. The standards prescribed therein have

been further reviewed in the Ministry in light of the issues

raised by Ministry of Defence. A committee of Chief

Engineers considered the suggestions received in this regard

and have recommended modifications to the standards

prescribed in the circular referred above.

2. It is observed that the standards prescribed in the circular

referred above does not address the issues concerning

strategic roads as stipulated in clause 6.2.2 of IRC: 52-2019

(Guidelines for the Alignment Survey & Geometric Design of

Hill Roads) [2019 IRC Guidelines].

3. Accordingly, in partial modification of the circular cited

above, the following additional guidelines are notified with

immediate effect.

“For roads in hilly and mountainous terrain which act as

feeder roads to the Indo-China border or are of strategic

importance for national security, the carriageway width

should be 7m with 1.5m paved shoulder on either side.””

(emphasis supplied)

PART E

44

The 2020 MoRTH Circular amends the earlier circular of 2018 since its directions

were incompatible with the recommendations under Clause (8) of the Notes

attached to Clause 6.2.2 of the 2019 IRC Guidelines, according to which every

strategic and border road has to be of DL-PS configuration along with earthen

shoulders. Hence, the 2020 MoRTH Circular provides that roads which may be

located in hilly and mountainous regions but serve as feeder roads to the IndoChina border or are of strategic importance for national security should also be of

DL-PS configuration.

44 On a combined reading of the 2012, 2018 and 2020 MoRTH Circulars and

2015 and 2019 IRC Guidelines, it emerges that a road shall be of a DL-PS

configuration in the following circumstances: (i) if it is a national highway, other

than in hilly or mountainous terrain; (ii) in hilly or mountainous terrain, a national

highway can be double-laned if there are more than 10,000 PCUs per day or that

level will be reached in 3 to 5 years; (iii) in hilly or mountainous terrain, a national

highway can be of DL-PS configuration if the traffic is likely to increase more than

about 10 per cent per annum; and (iv) in hilly or mountainous terrain, any road

(including a national highway) can be of DL-PS configuration if it is strategic or a

border road serving as a feeder road to the Indo-China border or if it is of

strategic importance to national security.

PART F

45

F Issues and Analysis

F.1 Road-Width Issue

45 The issue that arises for consideration is regarding the road-width to be

adopted for the three strategic border roads, as indicated in MA No 2180 of 2020

filed by the MoD, namely: Rishikesh to Gangotri (NH-94 and NH-108), Rishikesh

to Mana (NH-58), and Tanakpur to Pithoragarh (NH-125). Broadly speaking, the

appellants have argued that the present road infrastructure is sufficient to meet

the needs of the Indian Army. Any further development, it has been urged, must

be balanced keeping in mind the fragility of the Himalayas, the excessive damage

caused to the environment and the need to ensure disaster-resilient roads. On

the other hand, the UOI has stressed on the necessity of developing these feeder

roads, for the security of the nation. Given the proximity of the roads to the IndoChina border, and the necessity of free movement for transport of trucks,

machines, equipment and personnel of the Indian Army, double lane

configuration must be allowed, according to the UOI. To analyse the issue, we

shall first advert to the findings of the HPC.

F.1.1 HPC Report dated 13 July 2020

46 The HPC report was finalized by its members functioning under Professor

Ravi Chopra as its Chairperson. For the preparation of the HPC Report, the

members conducted site-visits, held meetings, interacted with the officers of

MoRTH, district officials and the local communities. The Report is divided into 

PART F

46

twelve chapters, each of which touches upon various aspects of the Project such

as road-widening; hill cutting; bypasses; muck dumping; environment quality; loss

of forests and green cover; impact on wildlife; managing water courses; disaster

management and socio-cultural perspectives. For the purpose of the issue for

consideration, i.e., the width of roads on the national highways, Chapter II is of

utmost relevance. The remaining chapters have been briefly summarized in

Section F.2.1 of this judgment.

47 Chapter II of the HPC Report titled ‘Road Widening’ deals with the

construction of highways and the width of roads. For determining the width of the

road, the HPC highlighted the following factors are to be borne in mind:

ecological concerns, social concerns, traffic surveys, capacity of roads, geometric

design, terrain classification, design speed, sight distance or visibility, right of way

and setback distance at horizontal curves.

48 According to the Indian Roads Congress Hill Roads Manual 199852, the

following type of roads have been indicated, based on traffic volumes:

Sl.

No.

Type of Road Design service volume in PCU/day

Carriageway

Width (CW)

For low curvature (0-

200 degrees per km)

For high curvature

(above 200 degrees

per km)

1 Single lane 3.75 m 1,600 1,400

2 Intermediate

lane

5.5 m 5,200 4,500

3 Two lane 7 m 7,000 5,000

4 Two lanes with

paved shoulder

(NHDL with PS)

7 m 9,000 -

 52 “IRC Manual”

PART F

47

49 The 2012 MoRTH Circular, however, provided that for new projects of

widening/bypass/realignment, the width of the carriageway will be at least two

lane with paved shoulders, irrespective of the traffic.

50 During the field visit, the HPC observed that though the routes for the

Project are designed for the DL-PS standard, in certain stretches the formation

width varies from 12m to 20m depending on the geometric requirements. Further,

many of the existing stretches, which were already developed to an IW standard,

are being widened. Due to the uniform standard, in some areas large hill-cutting

has been undertaken resulting in vertical slopes without adequate slope

protection measures. This has led to landslides and reflects inadequate

assessment of slope vulnerability.

51 The discussion of the HPC revolved around the road-width that should be

adopted for the highways comprising of the Project. Factors such as the road

geometrics, traffic volume, ecological considerations (such as steep terrain, loss

of forest cover, et al) guided the discussion of the HPC. At present, the project

requirement envisages a DL-PS standard as given below:

Type of

Section

Carriageway

(m)

Paved Shoulder Earthen Shoulder Roadway

Hill Side Width (m)

(m)

Valley

Side (m)

Hill Side

(m)

Valley Side

(m)

Open

Locations

7.0 1.5 1.5-1.9 1.0 (drain

+ utility

duct)

0.6-1.0

(including

parapets)

12.0

Built-up Area 7.0-10.0 (with

paved

shoulder)

1.0–- 1.75

(foot path

cum drain

raised)

1.0–-

1.75

(foot

path cum

drain

raised)

- - 9.0-12.0

PART F

48

Thus, all the highways were to be widened to reflect a width between 9 – 12m.

52 A majority consisting of thirteen members of the HPC was of the opinion

that the DL-PS standard must be applied uniformly throughout the Project for the

following reasons:

(i) The IRC Manual recommends a uniform application of design standards

and any adjustments that need to be made to factor in the variability in

slopes, must be intended for short distances;

(ii) The roads of the hills require protective works such as retaining walls,

breast walls, catch drains, et al, which form a substantial part of the

construction cost. Once the roads have been constructed, the widening of

roads in the future is expensive, and at times impossible. Thus, the

highways must be widened bearing in mind the traffic volumes for the next

20-25 years;

(iii) Some of the highways of the Project are important feeder roads leading

towards border areas. The BRO has highlighted that the terrain in border

areas is in a snow bound region and feeder routes such as Helong-Mana

and Barethi-Gangotri must be double-laned. Further, the roads beyond

Joshimath and Uttarkashi are operationally sensitive and fall within 100

kms of the Line of Actual Control. Single-lane roads are closed during the

winter season due to accumulation of snow and hinder the movement of

logistics and medical aid to the Indian Army;

(iv) The 2019 IRC Guidelines also suggest that strategic border roads for

military and paramilitary forces be not less than two lanes with paved

shoulders; and

PART F

49

(v) Suitable adjustments can be made to the standard design after considering

vulnerability of slopes, identification of stretches vulnerable to floods,

mapping wildlife corridors and providing adequate safeguards.

53 A minority consisting of five members of the HPC, including the

Chairperson, was in favour of adopting the IW standard for the Project. Their

opinion was based on the following reasons:

(i) The type of road must be determined based on traffic surveys, capacity of

roads, and ecological considerations. The 2012 MoRTH Circular, however,

recommended only an operational standard;

(ii) The detailed project reports for the Project have based the choice of roadwidth on traffic survey data. However, the data is insufficient as the traffic

volume count of only April-May, which is a non-peak period, was taken into

account. Additionally, no traffic surveys were conducted for the Higher

Himalayas, which suggest that the DL-PS standard is extremely wide;

(iii) The current standard ignores the overall environmental considerations

such as geological fragility, slope de-stabilization and recurring landslides,

climate change and soil organic carbon loss. MoRTH has not conducted

an EIA for the Project which would suggest site-specific mitigation

measures;

(iv) Although border security concerns are a relevant factor, not all routes lead

to the international borders. To ensure that national security concerns are

addressed, more disaster-resilient highways are needed which would not

be achieved by cutting fragile slopes. Further, the Chief of Army Staff on 

PART F

50

20 September 2019 had made a statement that the current roads

adequately fulfilled the needs of the Army; and

(v) The 2018 MoRTH Circular acknowledges that the DL-PS standard has led

to issues in the mountainous terrains and recommended that road design

be based on traffic volume. The 2018 MoRTH Circular was not brought to

the notice of the members of the HPC during the discussion and was

received later, after the voting had taken place. It was circulated by the

Chairperson, after which two voting members and the Chairperson

recommended the adoption of the IW standard in all stretches where

widening remains to be done.

54 Since the 2018 MoRTH Circular, which was central to the discussion on

road-width, was inadequately considered by the HPC, it was suggested by the

Chairperson that a final decision on this issue must be taken by the Supreme

Court. Apart from the issue of road-width, the majority of members also

recommended that:

(i) To avoid the possibility of slope failures, valley side filling must be given

importance;

(ii) A footpath for walking along the highways of the Project must be made for

the pilgrims; and

(iii) In built-up areas where road side facilities and establishments exist, the

width of the roads should be kept at 10.5m (7m carriageway and 1.75m

paved shoulder on either side). 

PART F

51

55 With regard to the BESZ, the HPC noted that the Project has five

unsanctioned projects which run through it. MoRTH plans to upgrade 100.5 kms

from Uttarkashi to Gangotri to conform to the DL-PS standard. The following

recommendations were made:

(i) BRO, which is the implementing agency, must obtain all requisite

clearances under the relevant notifications of the MoEF&CC;

(ii) Road widening activities should only be undertaken after detailed EIAs and

mitigation measures;

(iii) The felling of deodar trees should be avoided;

(iv) Feasibility studies should be conducted in the short tunnels proposed

within the highways, and

(v) Vulnerability evaluations and terrain assessments must be conducted.

F.1.2 HPC Report dated 31 December 2020

56 Following the filing of MA No 1925 of 2020 and MA No 2180 of 2020, this

Court by an order dated 2 December 2020 directed the HPC to consider the

issues raised by Professor Ravi Chopra and the MoD, and submit a detailed

report. The HPC Report-II was thereafter submitted. In relation to MA No 2180 of

2020 filed by the MoD, a majority of 21 members recommended that further work

to be undertaken by the MoRTH should be according to the 2020 MoRTH

Circular, as it is necessary for the security of the nation. A minority of three

members was not persuaded that the order of this Court dated 8 September 2020

should be modified. One member recommended that the work on the national 

PART F

52

highways from Rishikesh to Gangotri, Rishikesh to Mana, and Tanakpur to

Pithoragarh may be carried out according to the 2020 MoRTH Circular. However,

a flexible approach should be adopted where necessary, to minimize damage to

the forests and wildlife habitats. On the letters filed by the Chairperson, a majority

of members recommended that the letters be withdrawn.

57 The majority report indicates that:

(i) The concerns raised by the MoD had been deliberated by the HPC and the

majority view in the HPC Report indicated the adoption of the DL-PS

standard. However, the majority report was overridden by the views of 4

members;

(ii) The HPC Report discussed the strategic importance of the three national

highways: NH-34 (previously NH-94 +NH-108), NH-07 (previously NH-58)

and NH-125;

(iii) The District Magistrates of Uttarkashi, Chamoli and Champawat District

expressed concern that the local people wanted an all-weather reliable

road along with the requirement of the MoD; and

(iv) The Rapid EIA reports of the Rishikesh-Rudraprayag stretch indicated that

the impact of the Project is 32.25 per cent, which falls in the medium

impact category. Thus, from an EIA perspective, the widening of the

highways should be permitted.

PART F

53

58 The minority of members stated in their report that:

(i) On the three feeder highways mentioned by the MoD in their application,

161 landslides/vulnerable zones were created. Due to the new landslides,

the entire project would be counter-productive for defence-preparedness;

(ii) The requirement of the MoD for the feeder roads should be considered in

the context of the need for disaster resilient roads, capacity of roads to

ensure swift movement of Army vehicles, minimizing environmental and

social impact and long-term feasibility of the roads; and

(iii) The difference between the recommendation of the minority and the MA

filed by the MoD is in regard to the reduction of carriageway by 1.5m, with

due regard to the requirement of a footpath of 1.5m for the local population

and pilgrims.

F.1.3 Analysis on the width of road

59 Pursuant to the order of this Court of 8 September 2020, the issue of the

width of the national highways that are a part of the Project has been raised in

MA No 2180 of 2020 filed by the MoD, which seeks modification of the order

itself. The grounds listed in the MA indicate that the national highways from

Rishikesh to Mana, Rishikesh to Gangotri and Tanakpur to Pithoragarh are

feeder roads to border areas and are vital from the perspective of national

security. Thus, it has been urged that development of these highways should be

according to the two-lane configuration.

PART F

54

60 The details of these roads and their proximity to the international border

has been provided in the MA by the MoD, and is reproduced below:

“Table A

Feeder Road Distance from the

Chinese border

Details of Connecting Border Road (Not

part of Char Dham Project)

Rishikesh to

Gangotri (NH-94

and NH-108)

231 kms

• Bhaironghati (close to

Gangotri) to Muling

La Pass is 54 kms

(i) Bhaironghati to Nilapani (enroute

to Muling La Pass on Chinese

Border) 42 kms:

Bhaironghati to Naga- 32 kms (Being

developed to double lan[e]

specifications. Tarring is yet to be

completed for 11 kms and only hill

cutting has been completed in 1 km)

Naga to Nilapani- 10 kms (Already

developed to double lane

specifications)

Nilapani to Muling La Pass –

54pprox.x. 34 kms (no road at

present, only a track)

• Bhaironghati (close to

Gangotri) to Thagla

Pass is 78 kms

(ii) Bhaironghati to Sumla (enroute to

Thangla Pass on Chinese Border)

64 Kms: [Under construction]

Bhaironghati to Sonam- 44 kms

(Being developed to double lane

specifications- 32 kms tarring done,

11 kms formation cutting completed,

1 km under progress)

Sonam to Sumla- 23 kms (Single lane

completed)

Sumla to Thangla Pass- 11 kms (foot

track)

Rishikesh to Mana

(NH-58)

281 kms

• Distance from Mana

to Mana Pass is 54

kms.

(i) Mana to Mana Pass:

Mana-Ghastoli: 21 Kms (Already

Double Laned)

Ghastoli – Rattakona: 18 Kms

(Existing Single Lane, planned for

double laning under Bharatmala)

Rattakona-Mana Pass: 16 Kms (Hill 

PART F

55

Cutting completed for 12m wide

formation for double laning, tarring

yet to be done)

• Distance from

Joshimath to Niti

Pass is 82 kms.

(ii) Joshimath to Niti Pass:

Joshimath-Malari: 62 Kms (Already

Double Laned)

Malari-Niti Pass: 56 Kms (Existing

single lane is being upgraded to

Double Lane upto Niti village, i.e., for

20 kms. Ahead of Niti village, single

lane road under development upto

Geldung).

• Distance from

Joshimath to Tunjun

La Pass is 103 kms.

(iii) Joshimath to Tunjun La Pass:

Joshimath-Malari: 62 kms (Already

double [laned])

Malari-Girthidobala: 19 Kms (First 9

kms is already double laned; and 10

Km thereafter is a single lane)

Girthidobala – Rimkhim: 22 Kms

(Existing single lane road)

Rimkim-Tunjun La Pass55pprox.x. 5

kms (no road)

Tanakpur to

Pithoragarh (NH125)

162 kms

• Distance from

Pithoragarh to Lipulek

pass is55pprox.x. 209

kms

(i) Pithoragarh to Lipulekh Pass:

Pithorgarh to Tawaghat- 108 Kms

(Under development to double lane

specifications, of which 51 Kms

completed)

Tawaghat to Ghatiabgarh- 20 Km

(Under development to double lane

specifications)

Ghatiabgarh to Lipulekh- 79 Km

(Formation cutting to 10 to 12 m

width is under progress)

61 Based on the above description, it is evident that the national highways

provide vital connections to the establishments of the Armed Forces along the

Nelong Axis, Mana Pass, Rimkhim Pass, Niti Pass and Lipulekh Pass. The 

PART F

56

importance of the requirement of double-laned highways has been emphasized

as it is necessary for the movement of trucks, equipment and personnel of the

Armed Forces.

62 The above table also indicates that the MoD does not seek to widen only

the three national highways which act as feeder roads. Instead, the roads

connecting the national highways from Gangotri, Mana and Pithoragarh to the

Army establishments across the border are also in various stages of development

and attempts have been made to ensure double-laned highways as far as

possible. The MoD has also highlighted that these feeder roads from Rishikesh to

Gangotri and Joshimath to Mana were initially included in the Long-Term Roll on

Works Plan 2018-19 to 2022-23 of the BRO. This plan seeks to upgrade the

national highways to double lane specifications to meet the operational

requirements of the Indian Army. Prior to 2016, these roads were under the

purview of the BRO, which is an arm of the MoD. It is only after 2017 that

portions of these roads were handed over to PWD and NHIDCL for speedier

development, given the expansive works to be undertaken for the Project.

63 At the outset, therefore, we find that there are no mala fides in MA No

2180 of 2020 filed by the MoD. The allegation that the application filed by the

MoD seeks to re-litigate the matter or subvert the previous order of this Court are

unfounded inasmuch as MoD, as the specialized body of the Government of

India, is entitled to decide on the operational requirements of the Armed Forces.

These requirements include infrastructural support needed for facilitating the

movement of troops, equipment and machines. The bona fides of the MoD are

also evident from the fact that the issue of security concerns was raised during 

PART F

57

the discussions of the HPC and finds mention in the HPC Report. Thus, the MoD

has maintained the need for double-laned roads to meet border security

concerns.

64 The appellants have referred to a statement made by the Chief of the

Army Staff in 2019 in a media interview regarding the adequacy of infrastructure

for troop movement. We do not find it necessary to place reliance on a statement

made to the media, given the consistent stand of the MoD during the

deliberations of the HPC and before this Court. The security concerns as

assessed by the MoD may change over time. The recent past has thrown up

serious challenges to national security. The Armed Forces cannot be held down

to a statement made during a media interaction in 2019 as if it were a decree writ

in stone. Similarly, the appellants have also raised a challenge to the 2020

MoRTH Circular and have sought a direction that this circular be revoked, on the

ground that it recommends the DL-PS standard without application of mind.

65 This Court, in its exercise of judicial review, cannot second-guess the

infrastructural needs of the Armed Forces. The appellants would have this Court

hold that the need of the Army will be subserved better by disaster resistant

roads of a smaller dimension. The submission of the appellants requires the

Court to override the modalities decided upon by the Army and the MoD to

safeguard the security of the nation’s borders (it is important to remember that

the MoRTH issued the 2020 MoRTH Circular based upon the recommendations

received from the MoD). The submission of the appellants requires the Court to

interrogate the policy choice of the establishment which is entrusted by law with

the defence of the nation. This is impermissible.

PART F

58

66 We shall now advert to the position of law regarding the construction of

double-laned roads. The 2012 MoRTH Circular stipulated that all national

highways were to have a carriageway width of two lanes. While this circular

acknowledged that, generally, the carriageway width is dictated by the traffic

volume, but in an attempt to ensure smooth flow of traffic, all highways were

henceforth to be converted to two lanes with paved shoulders. Thus, according to

the 2012 MoRTH Circular, all highways were to conform to the DL-PS standard.

67 The 2018 MoRTH Circular modified the 2012 version. The Circular of

2018 stipulated that:

(i) In hills and mountainous terrains, for areas where the PCUs are in the

range of 4,000-8,000 PCUs per day, the carriageway width cannot be of

double lane configuration but has to be of intermediate configuration (i.e.,

5m); along with this, adequate passing places with 2.5m width have to be

included;

(ii) For areas where the PCUs are more than 10,000 per day (or expected to

reach that level within 3 to 5 years), the carriageway width could be of

double lane configuration (i.e., 7m); and

(iii) Where the traffic is likely to increase “at about more than” 10 per cent per

annum, the width could be of DL-PS configuration.

Thus, the 2018 MoRTH Circular did not entirely bar the construction of doublelaned highways in hilly and mountainous terrains. It only made the DL-PS

standard contingent on the current and projected traffic volume for the road.

PART F

59

68 The 2019 IRC Guidelines, in relation to the width of carriageway for

national highways, provided that that DL-PS standard should be adopted. More

specifically, the 2019 IRC Guidelines dealt with national highways in hills and

mountainous terrain that serve as strategic roads and border roads for military

and paramilitary operations. It provided that such roads should be constructed

with not less than a two lane carriageway with a paved shoulder on the hill side

and an earthen shoulder on the valley side. The relevant clause is reproduced

below:

“6.2.2 Width of carriageway, shoulders and roadway for

various categories of roads are given in Table 6.2.

Table 6.2 Widths of Carriageway, Shoulder and Roadway

[…]

Notes:

[…]

6. On roads subject to heavy snow fall, where snow clearance

is done over long periods, roadway width may be increased

by 1.5 m. However, the requirement of such widening may be

examined with reference to ground conditions in each case

considering terrain traffic and other influencing conditions and

factors.

[…]

8. Strategic and border roads for

military/paramilitary/security forces

operations/movements shall be constructed for not less

than two lane carriageway alongwith paved shoulder on

hill side + paved and earthen shoulder on valley side on

same lines of national highway.”

(emphasis supplied)

69 Given the lack of clarity on this issue in the MoRTH circulars, the 2020

MoRTH Circular was brought in. The Circular of 2020 reiterates the 2019 IRC 

PART F

60

Guidelines and states that roads in hilly and mountainous terrain, which act as

feeder roads to the Indo-China border should be of DL-PS standard, with a 7m

carriageway and 1.5m paved shoulder.

70 Neither the 2012 nor the 2018 MoRTH Circulars specifically addressed

the issue of strategic border roads. The considerations for development of

national highways in plains and in hilly and mountainous regions are not identical.

Similarly, the considerations governing the construction of highways that are

strategic roads from a defence perspective, and may be used by the Armed

Forces of the nation, cannot be the same as those for other roads in hilly and

mountainous regions. We must therefore arrive at a delicate balance of

environmental considerations such that they do not impede infrastructural

development, specifically in areas of strategic importance crucial to the security

of the nation.

71 Based on the above analysis, we find that the need for the development of

national highways of a DL-PS standard is proportionate to the object of fulfilling

the security concerns of the nation as assessed by the MoD. This is reinforced by

the fact that the roads beyond the highways in the Project, beyond Gangotri,

Mana and Pithoragarh are being developed by the MoD as double laned

highways.

72 Additionally, the current status of works for the three highways in question

is as follows:

PART F

61

Road Distance of Road Hill Cutting for 12m formation

completed

Double Laning/ black

topping completed

Rishikesh to

Gangotri

(NH-94 & NH108)

231 kms 119 kms (51.50%) 75 kms (32%)

Rishikesh to

Mana

(NH-58)

281 kms 215 kms (76.50%) 151 kms (54%)

Tanakpur to

Pithoragarh

(NH-125)

162 kms 127 kms (78%) 123 kms (76%)

From the above tabulated statement which has been provided by the MoD, it

appears that more than 50 per cent of the hill cutting has already been completed

in each of these national highways, and over 50 per cent of double-laning has

been completed on NH-58 and NH-125. In view of this, partial development of the

highway compliant with the IW standard and the remaining in conformity with the

DL-PS standard would not be suitable for the needs of the Armed Forces and

will, in fact, prolong the movement of troops and equipment.

73 We shall now turn to the findings and recommendations of the HPC

regarding the issue of road-width. As reflected by this Court’s order dated 8

August 2019, the HPC comprised of representatives from governmental bodies,

including the MoD who could highlight the requirements of border roads. The

broad terms of reference of the HPC were as follows:

(i) To consider the cumulative and independent impact of the Project on the

entire Himalayan valleys;

PART F

62

(ii) To consider whether revision of the full Project (about 900 kms) should at

all take place with a view to minimize the adverse impact of the Project on

the environment and social life;

(iii) To identify the sites in which work (i.e., hill-cutting) has started and the

stretches in which the work has not yet started. As far as the sites in which

work has started, the HPC was to recommend the measures which are

required for stabilizing the area where hill-cutting has taken place,

including the environmentally safe disposal of muck which has been

generated so that it does not adversely affect the flora and fauna of the

catchment area of the river;

(iv) As regards the stretches where work has not started, the HPC was to

review the proposed project and recommend measures which would

minimize the adverse impact on the environment and social life; bring the

project in conformity with the steep valley terrain and carrying capacity and

avoid triggering new landslides; and ensuring conservation and protection

of sensitive Himalayan valleys;

(v) To assess environmental degradation in terms of loss of forest land, trees,

green cover, water resources, dumping of muck and impacts on the wildlife

and direct mitigation measures; and

(vi) To asses and quantify the impact on social infrastructure/public-life due to

triggering of fresh landslides, air pollution, frequent road blocks, et al, and

suggest measures for redressal, including preparation of disaster

management plans prior to the onset of the monsoon. 

PART F

63

74 While the HPC was empowered to assess the environmental and social

impact of the Project, it was not competent to address, assess or review the

security needs of the nation. The work of the HPC was limited to giving

recommendations to improve the Project in terms of its environmental impact and

to suggest mitigation strategies to implement the Project. The competing interests

that the HPC had to evaluate were environmental concerns as against

infrastructural development, the primary reason of which in this Project was

focused on increasing tourism, providing an impetus to the economy, and ease of

transportation for undertaking the Char Dham pilgrimage. Balancing the interests

of defence as against environmental considerations was outside the ambit of the

HPC.

75 Be that as it may, the HPC Report does highlight that certain highways

(NH-94, 108, 58 and 125) form the feeder roads to border locations in the districts

of Uttarkashi, Chamoli and Pithoragarh. An extract of the relevant portion of the

HPC Report is reproduced below53:

“Roads beyond Joshimath and Uttarkashi are operationally

very sensitive as they fall within 100 Km of the LAC. The

border terrain lies in high altitude, snow bound regions. Indian

Army and ITBP units maintain continuous vigil on the borders

and important passes. To ensure better national security, the

Government of India has given impetus for the development

of double lane roads towards the border. Roads beyond

Bhaironghati and Mana are already double-laned but the

important feeder roads Helong-Mana and Barethi-Gangotri

are generally single lane (except some intermittent stretches

which are improved to two lane) with steep gradients, sharp

curves, narrow hairpin bends, avalanche prone locations and

weak bridges which pose major challenges to vehicle

movements in these areas. The single lane roads get closed

due to snow accumulation and hinder the movement of

 53 HPC Report, pages 82-83

PART F

64

soldiers even by foot for provisions of logistic and medical

aid.”

Bearing the above observations in mind, a majority of the members of the HPC

recommended the adoption of the DL-PS standard as road-width for the Project.

This opinion was reiterated in HPC Report II, which considered the MA No 2180

of 2020 filed by the MoD.

76 We find ourselves to be in agreement with this finding of the HPC. Based

on the above reasons, we modify the order of this Court dated 8 September 2020

to the extent that the national highways from Rishikesh to Mana, Rishikesh to

Gangotri, and Tanakpur to Pithoragarh be developed according to the doublelane carriageway width with paved shoulder standard as provided in the 2020

MoRTH Circular.

77 An ancillary issue regarding the width of the roads of the Project, apart

from the above highways which are strategic feeder roads to border areas, is

regarding the interpretation of the order dated 8 September 2020. This Court in

its order held that:

“We have perused the conclusion and recommendations of

the report, in particular, from pages 90-93 in Part I. We are of

the view that it is correct that the 2018 MORTH circular

should apply for the reasons given at page 93 of the

report. Consequently, the 2018 circular alone will apply.

The other directions that were issued by us on 08.08.2019

must be strictly complied with, including the holding of

quarterly meetings to ensure timely and proper compliance of

the recommendations.

Shri Tushar Mehta, learned Solicitor General, persisted with

his arguments that the 2018 circular is only prospective in

nature. We are well aware of the distinction between

something which is retrospective in the sense that it applies

for the first time to projects which are already completed as 

PART F

65

opposed to ongoing projects, where it is necessary to take

stock of the current situation and then move forward. Having

taken stock of the current situation and of the fragility

generally of the eco system in mountain terrain, we are of the

view that this argument has no legs to stand on.”

(emphasis supplied)

78 One of the arguments raised by the appellants in their MA 1925 of 2020 is

that pursuant to this order, MoRTH has stated that the order will only be

implemented for the 13 projects which have not been sanctioned and where work

has not been initiated. In its affidavit dated 15 February 2021, MoRTH has stated:

“3. […] showing the status of road construction work in the

Chardham Pariyojna which would show that in almost every

sanctioned project of the Chardham Pariyojna, hill cutting has

been carried out at various stretches as the old formation

width of 12 mts, leaving unfinished stretches in between. It is

submitted that in a particular sanctioned project, due to

operational difficulties, hill cutting and laying down of a tarred

road is often not carried out simultaneously and/or in linear

form. Thus, reducing the width of the road to 5.5 mts in the

those unfinished stretches at this stage would cause a

serious road safety hazard. The details of the same is also

reproduced hereinbelow:

SNO. PARTICULARS LENGTH

1. Total Length of The Chardham

Pariyojna

825 KMS

2. Total Sanctioned Length 662 KMS

3. Hill Cutting (Keeping 12 Mts in Mind)

Completed As On 08.09.2020

537 KMS

4. Tarred Road With 10 Mtr. Width

Completed As On 09.09.2020

365 KMS

5. The Length For Which Hill Is Already

Cut Prior to 08.09.2020 But Tarred

Road With 10 Mts Width is Yet To Be

Laid

172 KMS

6. The Length For Which Hill Cutting Is

Yet Be Commenced (Which Stopped

On 08.09.2020)

125 KMS

PART F

66

4. It is further stated that out of the total length of 825 kms of

the Chardham pariyojna, only 151 Kms consist of nonstrategic roads, whereas the rest of the pariyojna having a

length of 674 Kms have immense strategic importance being

feeder roads to the Indo-china border roads under the control

of Ministry of [D]efence. The details of the same are also

reproduced hereinbelow:

1. Total Length of The Chardham

Pariyojna

825 Kms

2. Total Length Of Roads With Strategic

Importance/Defence Roads

674 Kms

3. Total Length Of Non-Defence Roads 151 Kms

Dharasu To

Janaki Chatti

75 Kms 36 Kms

(Hill

Cutting

Done)

Rudraprayag

To Gauri

Kund

76 Kms 53 Kms

(Hill

Cutting

Done)

79 The order of this Court dated 8 September 2020 clarified that the 2018

MoRTH Circular will hold the field, regardless of whether works on a highway had

been completed or were ongoing. By allowing the MA filed by the MoD for

modification of this order, we have permitted the widening of the national

highways from Rishikesh to Mana, Rishikesh to Gangotri, and Tanakpur to

Pithoragarh, which are strategic feeder roads to border areas. To this extent, the

order dated 8 September 2020 will stand modified. However, we grant liberty to

the respondents to pursue appropriate legal proceedings and seek reliefs in the

event that it is necessary to implement the DL-PS standard for the entire Project.

PART F

67

F.2 Environmental Issues

80 While we have permitted the UOI and MoD to apply a DL-PS configuration

to the highways mentioned in MA No 2180 of 2020, it is not the end of this matter.

There may have been a disagreement between the members of the HPC in

relation to the road-width issue but they unanimously agreed on other

environmental issues in the manner in which the Project was being implemented

by MoRTH. Some of these issues have also been pointed out by the appellants in

MA No 1925 of 2020 and their affidavits thereafter, often based upon news

reports in relation to the Project. We shall first note these issues as flagged by

the HPC, consider their recommendations and based on that, we will issue

directions to MoRTH and MoD.

F.2.1 HPC Report dated 13 July 2020

81 The environmental and social concerns arising from the Project have been

dealt with in Chapter III-XI of the HPC Report, along with the recommendations

and conclusions in Chapter XII. Apart from Chapter II on the issue of road-width

as provided in Section F.1.1 above, the findings of the HPC on all other issues

have been unanimous.

82 Chapter III of the HPC Report deals with hill cutting and highlights that

slope instability is one of the most frequent disasters in mountains. Hill cutting in

the Himalayas is also a major reason for landslides and rockfalls. During field

visits, the HPC observed that there were large stretches of hill-cutting with steep 

PART F

68

slopes and no protection measures, no slope drainage measures had been

taken, the debris was falling downhill, further destabilizing the slope. The HPC

recommended the following measures which could be adopted to mitigate the

damage and prevent landslides:

(i) In many locations, hill-cutting can be avoided by filling material on the

valley side to widen the road;

(ii) Sufficient vulnerability analysis must be conducted before further hillcutting and plans for maintenance of slopes must be made;

(iii) Roadside drainage measures and protection against toe-erosion must be

undertaken;

(iv) In case of near vertical to vertical cutting, a breast wall may be erected to

avoid landslides; and

(v) Damaged gabion structures must be repaired through back-filling, et al.

83 Chapter IV of the HPC Report concerns the 20 bypasses, realignments

and tunnel projects that have been proposed for some segments of the national

highways as they are geologically unstable or in congested passages. The HPC

observed that geological infirmities and the felling of deodar and oak trees are a

critical issue in these bypasses. It recommended that feasibility studies may be

conducted for some of the bypasses, along with their impact on local area

residents.

84 Chapter V of the HPC Reports concerns a critical area of the Project –

muck dumping. Muck-dumping or muck management requires safe disposal of

the muck generated due to the material excavated, tunneled, and dislodged. 

PART F

69

Within the Project, 435 muck-dumping sites have been identified for the 53

projects. However, the following issues were identified by the HPC in relation to

muck-disposal:

(i) Most of these projects do not have adequate muck dumping capacity. In 5

out of the 7 packages, the authorized muck dumping capacity is below the

muck volumes anticipated. In one-third of the projects, the expected

generation of muck is more than the carrying capacity of the sites;

(ii) Most of the muck dumping sites are located in gorges or natural drains,

along the concave sections of rivers, in or adjacent to forests, near

agricultural fields or habitations which may not have been authorized;

(iii) There are many large and tall sites, with high slope angles but attempts to

stabilize them have not been made; and

(iv) There is no financial provision for environmentally safe disposal of muck

and no guidelines have been provided by MoRTH to the EPC Contractors

regarding its proper management, leading to variations in selection of sites

and adoption of environmentally safe disposal practices by contractors,

who also dump it on private land on request.

85 For adequate disposal of muck, the HPC recommended the following

measures to be taken:

(i) Muck dumping should generally be located downwind of habitation;

(ii) Topsoil should be kept separately in a proper manner for later use in

rehabilitating muck disposal;

PART F

70

(iii) A large quantity of boulders (locally available) should be checked for their

mechanical properties and used appropriately;

(iv) Before muck is dumped at identified locations and construction of

protection measures, it should be ensured that the substratum has enough

shear strength to sustain the load without creating a slip hazard. The

gabion/protection walls should preferably be constructed along the

contours for better stability and above the highest flood level at a safe

distance;

(v) Muck dumping sites should not be located on the concave side of river

meanders. Gorges and natural drainage also need to be avoided;

(vi) Plantation of locally available plant species should be preferred for

rehabilitation of dump sites along with help from local people and forest

department;

(vii) MoRTH and the implementing agencies must immediately coordinate with

district authorities to acquire additional muck dumping sites and necessary

clearances to ensure that muck generation equals carrying capacities of

muck dumping sites;

(viii) Capacities of sites fully utilized must be stabilized at the earliest, preferably

before the onset of the rainy season;

(ix) Muck which has fallen on roads after landslides must not be pushed down

slope; and

(x) All natural drains/streams blocked with dumped muck should be cleared

before the monsoons.

PART F

71

86 Chapter VI of the HPC Report deals with the environment quality of the

Project, which can be divided into short-term and long-term impacts. Short-term

impacts occur due to road construction activities like land clearing, ground

excavation and cut and fill operations, and are visible in the vicinity of the

construction activity. Meanwhile, long-term impacts include climate warming due

to soil organic carbon loss as a result of road construction and traffic problems.

During their field visits, the HPC were unable to assess the impact of the project

on the environmental quality due to stoppage of work prior to the visit. However, it

observed dust pollution where debris had not been cleared from the road. The

HPC also identified long-term impacts such as vehicular pollution, black soot

emission, soil erosion from hill-cutting and muck-dumping and soil organic carbon

loss, due to the Project.

87 On the basis of its observations, the HPC made the following

recommendations:

(i) Reliable data should be obtained to formulate strategies to control pollution

during the construction phase effectively;

(ii) Continuous air quality monitoring stations must be placed at each of the

Char Dham locations;

(iii) A reduction in diesel and petrol vehicles is warranted in view of the

ecological sensitivity of the Higher Himalayas; and

(iv) Robust stabilization measures are needed in the Lesser Himalayas and

the Shivaliks to conserve their vast forests and SOC, as they are major

carbon sinks.

PART F

72

88 Chapter VII of the HPC Report deals with the loss of forests, trees and

green cover. Cutting of mountain slopes to widen roads leads to a reduction in

the green cover in the State. A total area of 689.23 hectares has been diverted

from forest land for the Project. This loss of green cover leads to a loss of riverine

vegetation, top soil, wildlife habitats, ecosystem services, et al. To redress the

loss of forest cover, the Uttarakhand Forest Department raised a plantation as

part of the Compensatory Afforestation program. In addition to this, a Draft Action

Plan focusing on afforestation on degraded waste land and forest land along the

national highways, restoration of muck disposal, soil conservation works,

rejuvenation of existing water resources, and landscaping has also been

proposed. The HPC has also recommended the following measures to be taken:

(i) Felling of deodar trees should be avoided;

(ii) Road-width in dense forest patches may be reduced;

(iii) In stretches that are yet to be widened, the top soil must be separately

stored from the remaining muck to facilitate regeneration;

(iv) Regeneration of riverine vegetation should be included in the Draft Action

Plan; and

(v) The Net Present Value rates of forests needs to be revised.

89 Chapter VIII of the HPC Report discusses the impact of the Project on

wildlife habitats. The Project lies close to the wildlife protected areas of Gangotri

National Park, Kedarnath Wildlife Sanctuary, Govind National Park and Wildlife

Sanctuary and Rajaji National Park. These protected areas have four highly

endangered species – snow leopard, Tibetan Argali, Eurasian lynx, Himalayan

brown bear and Western Tragopan. Other threatened species include the Asiatic 

PART F

73

black bear, Tibetan wolf, Himalayan musk deer, pheasant and Cheer pheasant.

The Alaknanda and Bhagirathi river basins also host a wide range of habitats.

90 During the field visits, the HPC observed that improper muck management

resulted in destruction of vegetation cover, which has threatened aquatic

habitats. Accordingly, it recommended the following measures:

(i) Safe wildlife passage should be maintained and included in road building;

(ii) Gentle slopes shoulders on either side of the road, particularly around

sharp bends/blind curves should be avoided. Box-type pre-fabricated

culverts could be used by wildlife;

(iii) A comprehensive study of the carrying capacities of the uppermost

stretches of the Project and the wildlife movement should be conducted;

(iv) Opening of Char Dham locations in the winter season should be

considered only after a thorough wildlife impact study;

(v) Road widening work on NH-109, NH-94, NH-94/134 and NH-07/58, which

are located in the eco-sensitive zones, should be conducted after due

approvals; and

(vi) Deterrent action must be taken against unauthorized muck dumps and

compensatory afforestation should be carried out.

91 Chapter IX of the HPC Report, titled ‘Managing Mountain Water Courses’

pertains to the management of springs, streams and surface drainage. The HPC

observed that there was poor management of subsurface flows at many locations

due to improper structures. In places where perennial flow of water is there, toe

drains had not been constructed. Further, due to the huge quantity of muck 

PART F

74

generated because of the cut and dump method and disposal into water courses,

the water has been deemed unfit for human consumption. Accordingly, the HPC

recommended that:

(i) Culvert design should be based on hydrological investigation in order to

avoid under designing or over designing of the structure;

(ii) Immediate action be taken to clear all natural drains/streams blocked with

muck dumping;

(iii) The perennial streams should be managed properly by constructing

adequate structures;

(iv) A diversion drain should be provided above the head of the hill cut area to

safely drain out the water away from the unstable or landslide prone areas;

(v) Toe drains or catch-drains must be provided on the uphill side of a road

and connected to a culvert or a main drain to dispose of the water into a

natural valley. Additionally, a breast wall or a toe wall should be provided

to prevent blockage of toe drains by accumulation of fallen over burden

soil/boulders from the uphill slope; and

(vi) There must be safe disposal of heavy runoff and debris through discharge

channels/gullies.

92 Chapter X of the HPC Report concerns the disaster management

measures that must be taken to prevent any disasters owing to the infrastructure

activity from the Project. These disasters include natural hazards such as slope

failures, flash floods, avalanches, forest fires; engineering hazards when poor

quality protection measures are taken; and mass tourist hazards. The significant

disaster in the Project has been due to the vulnerability of slopes. One of the 

PART F

75

main reasons for this occurrence is muck-dumping which results in landslides,

toe-erosions and other consequences. Further, no effort has been made to

stabilize the slopes already cut. Additionally, in a number of locations, such as at

Badrinath, the carrying capacity (that is the number of biological species that can

survive in a particular environment) has been reached. In view of this, the HPC

recommended the following measures:

(i) A comprehensive study regarding the carrying capacity at various locations

in the Project must be conducted;

(ii) Given the large number of tourists, Char Dham Early Warning System

Network, connecting all villages, should be developed such that timely

action can be taken in case of a disaster;

(iii) A survey of vulnerable muck dumping sites must be undertaken, natural

streams must be cleared, slope protection measures should be taken;

(iv) Climate vulnerability risk assessment must be conducted; and

(v) Protective measures such as well-constructed breast walls, retaining walls,

soil nailing, geotextiles sheathing, negative slopes and half-tunnels in hard

rock areas should be observed.

93 Chapter XI of the HPC Report focusses on socio-cultural perspectives.

During the field visits, the HPC members observed that there was broad support

for the Project as it would economically benefit the people of the State. However,

some of the issues that have not been addressed are the lack of footpaths for the

traditional padyatra or pilgrimage, impact on traditional forest conservation

methods, loss of livelihoods due to hill-cutting without adequate safeguards, 

PART F

76

increase in threat to lives and agriculture in case of heavy rainfall or cloud burst,

and damage to schools and infrastructure due to slope failures.

94 Based on these concerns, the HPC, inter alia, recommended the following:

(i) Project authorities should initiate formal mechanisms to facilitate dialogue

and receive feedback and grievances from the local community;

(ii) A comfortable pathway for the pilgrims must be constructed; and

(iii) Conservation of traditions should be encouraged.

95 In Chapter XII of the HPC Report, the HPC summarized the conclusions

and recommendations made in each of the preceding chapters.

F.2.2 Analysis of the Environmental Issues

96 The analysis conducted by the HPC in the unanimous segment of its report

is not only comprehensive, but it is based upon empirical and scientific data. The

HPC took time to visit all project sites, and individually identified a variety of

issues with them. While these have been divided into chapters in the HPC Report

(as noted in Section F.2.1), the underlying themes of all them are evident:

(i) In many instances, MoRTH has gone ahead with the Project based on its

assertions that the Project is compatible with environmental guidelines or

that its developmental benefits are proportionate to the harm. However, to

reality-test these assertions, the HPC has recommended that the State

carry out relevant studies to ascertain the true reality (such as for creation 

PART F

77

of bypasses, maintenance of environmental quality, protection of wildlife

habitats and disaster management preparedness);

(ii) The HPC Report also notes that best-practices are not being followed in

some areas of concern (such as hill cutting or muck dumping). It has thus

recommended best practices for the MoRTH to implement;

(iii) In other areas of concern, the HPC has noted the harms which have

already been caused due to the Project, has recommended remedial

measures (such as protection of wildlife habitats (especially in context of

ecologically-sensitive zones) and maintenance of water resources) and

has also suggested future action to reduce its effects (such as for hill

cutting, muck dumping and protection of forest cover);

(iv) For some areas, the HPC has highlighted that constant monitoring by the

MoRTH would be required and necessary systems should be set up (such

as for maintenance of environmental quality and for disaster management

preparedness); and

(v) The HPC has also noted the Project’s effect on socio-cultural communities,

and has mandated MoRTH to create avenues for dialogue through which

concerns can be understood and resolved.

97 The verdict of the HPC in its report indicates that the Project is riddled with

environmental issues, which need to be resolved in order to make it

environmentally sustainable. Unfortunately, due to the ongoing litigation in

relation to the road-width issue, these concerns seem to have taken a back seat.

However, that cannot be the case, going forward.

PART F

78

98 The Attorney General has informed the Court that MoRTH and MoD are

presently undertaking measures to address the concerns raised by the HPC,

which have been noted in paragraphs 18(iv) and (v) of our judgment. While we

appreciate the measures which have been initiated, they are limited in scope and

have been late in coming. In comparison to the issues which have been raised by

the HPC in its Report, the measures adopted have only begun to scratch the

surface. Indeed, they do not address crucial issues such as muck disposal, which

not only affects the environment directly but also causes issues for wildlife and

availability of water resources. Even the remedial measures in relation to hillcutting and landslides have been tardy and limited and, from the submissions,

seem to have been limited only to the roads which are the subject matter of the

MoD’s MA No 2180 of 2020, which only concerns the roads which are of strategic

importance to India’s national security. However, it is important to remember that

the Project consists of 53 individual projects, not all of which are such roads.

However, that does not mean that the environmental effect on these roads and

their surroundings will be any less important and does not need to be remedied.

The State has tried to justify the efficacy of its current measures solely by noting

their benefits directly to the Armed Forces. Indeed, while that is a crucial factor

(as this judgment acknowledges in Section F.1.3), it is not the only thing at stake

in a Project of this scale, which was conceived to provide a more efficient route

for those undertaking the Char Dham pilgrimage. What is at stake in this Project

is also the health of the environment, and its effects on all individuals who inhabit

the area.

PART F

79

99 It is thus important that there must be a significant alteration in the

approach to this Project by adopting sustainable measures. Piecemeal

implementation of some mitigation measures for protection of the environment,

without any concrete strategy in place, cannot pass muster. While we have

granted our approval to the DL-PS configuration for the roads mentioned in

MoD’s MA No 2180 of 2020, it is made conditional upon MoRTH and MoD

implementing the recommendations made by the HPC, which have been outlined

by this Court in Section F.2.1. These recommendations are unanimous. A

majority of the members of the HPC comprised of government officials and

experts. In line with the HPC’s recommendations, there has to be an assessment

of the nature of the problem by obtaining actual data through relevant studies for

all individual projects. Specific mitigation measures then should be implemented

for all projects, keeping in mind their unique concerns. In doing so, the general

recommendations issued by the HPC should form the baseline, i.e., they should

be implemented at the very least, along with anything over and above that is

deemed necessary based on the studies so conducted.

100 More than anything else, this requires a concerned shift in the approach

which has been adopted till date. Making the Project environmentally compliant

should not be seen a “checkbox” to be obtained on the path to development, but

rather as the path to sustained development itself. Thus, the measures adopted

have to be well thought out and should actually address the specific concerns

associated with the Project. Understandably, this may make the Project costlier,

but that cannot be a valid justification to not operate within the framework of the

environmental rule of law and sustainable development. In its bid to make the

PART G

80

project more environmentally conscious, it is also imperative that the MoRTH and

MoD be transparent in the measures they adopt, in order for them to be held

publicly accountable by spirited citizens. Thus, we direct that the MoRTH and

MoD can proceed with the Project subject to the condition that it addresses all the

concerns which have been raised by the HPC and enumerated by this Court in

Section F.2.1 of this judgment, through the recommendations mentioned

accompanying these concerns (in paragraphs 82, 83, 85, 87, 88, 90, 91, 92 and

94 of this judgment).

G Conclusion

101 We thus allow MoD’s MA No 2180 of 2020 by permitting the DL-PS

configuration for the three strategic highways in respect of which relief has been

claimed. At the same time, we have also taken note of the environmental

concerns which have been raised by the HPC for the entirety of the Project. We

have noted the HPC’s unanimous recommendations for taking remedial

measures and direct that they have to be implemented by the MoRTH and MoD,

going forward. These specific recommendations have been mentioned in Section

F.2.1 and are not being repeated here for the sake of brevity.

102 Further, in order to ensure implementation of these recommendations, we

also set up an ‘Oversight Committee’, which shall report directly to this Court.

This Committee shall be chaired by Shri Justice Arjan Kumar Sikri, former Judge 

PART G

81

of this Court. In order to enable the Chairperson to receive technical assistance,

he shall be aided by:

(i) A representative of the National Environmental Engineering Research

Institute (‘NEERI’) to be nominated by the Director; and

(ii) A representative of the Forest Research Institute, Deemed to be

University, Dehradun to be nominated by its Director General.

The Oversight Committee shall receive all logistical and administrative assistance

from the UOI, the Government of Uttarakhand, MoRTH, MoD and MoEF&CC.

The Secretary of the Environment and Forest Department, Uttarakhand shall

ensure that logistical assistance is provided to the Committee. MoRTH, MoD and

MoEF&CC shall also nominate nodal officers for rendering assistance to the

Committee, providing information and co-operating with the work of the

Committee. The District Magistrates for the Districts forming a part of the Project

shall also provide facilitation and assistance to the Committee.

103 The objective of this Oversight Committee is not to undertake an

environmental analysis of the Project afresh but to assess the implementation of

the recommendations already provided by the HPC (which we have noted in

Section F.2.1). A formal notification in terms of these directions shall be issued by

the UOI within two weeks. Within four weeks thereafter, MoRTH and MoD shall

place before the Committee the steps taken by them to adhere to the HPC’s

recommendations, along with a projected timeline for complying with the 

PART G

82

remaining recommendations. Monthly reports of this nature shall be placed

before the Oversight Committee by MoRTH and MoD. The Oversight Committee

shall then report on the progress undertaken to this Court every four months. In

case of any issues with the implementation of the recommendations, the

Chairperson of the Committee shall be at liberty to approach this Court. The

honorarium for the Chairperson and members of the Oversight Committee shall

be determined by the Chairperson and the payment shall be disbursed by

MoRTH.

104 We further note that by the order dated 8 August 2019 of this Court, the

HPC was tasked with overseeing the implementation of its recommendations and

to suggest any further measures which may be required. To avoid any overlap

between the scope of work of the HPC and the Oversight Committee formed

above in paragraph 102 and 103, we clarify that the HPC shall continue with its

work on overseeing the implementation of its recommendations for the Project,

except for the national highways from Rishikesh to Mana, Rishikesh to Gangotri,

and Tanakpur to Pithoragarh, which shall now fall under the purview of the

Oversight Committee.

105 With these directions, we allow MoD’s MA No 2180 of 2020, conditional

upon the fulfillment of the conditions outlined above in our judgment and

accordingly, MA No 1925 of 2020 is disposed of.

PART G

83

106 Pending application(s), if any, shall stand disposed of.


……….….....................................................J.

 [Dr Dhananjaya Y Chandrachud]

.…..….….....................................................J.

 [Surya Kant]

.…..….….....................................................J.

 [Vikram Nath]

New Delhi;

December 14, 2021