LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Wednesday, December 15, 2021

e Arbitration and Conciliation Act, 1996,= The award passed by the Arbitrator awarding the amount/compensation at Rs.45,000/­ per km per month up to January, 2008 under claim Nos.1 and 8 is hereby confirmed. The award passed by the Arbitrator awarding the amount/compensation at Rs.45,000/­ per km per month from February, 2008 to 31.05.2010 i.e. till the end of the contract is hereby quashed and set aside.

 REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS.7379­7380 OF 2021

State of Haryana            ..Appellant (S)

VERSUS

M/s. Shiv Shankar Construction Co. & Anr.    ..Respondent (S)

J U D G M E N T 

M. R. Shah, J.

1. Feeling   aggrieved   and   dissatisfied   with   the   impugned

judgment and order dated 03.11.2015 passed by the High

Court of Punjab and Haryana at Chandigarh in FAO No.

4482 of 2011 (O&M), by which the High Court has dismissed

the appeal preferred by the appellant herein under Section

1

37 of the Arbitration and Conciliation Act, 1996, the State of

Haryana has preferred the present appeals. 

2. At the outset it is required to be noted that while issuing

notice   in   the   present   appeals,   this   Court   has   stayed   the

award   exceeding   Rs.1,03,50,263/­   insofar   as   claim   Nos.1

and 8 are concerned.  

3. The facts leading to the present appeals in a nutshell are as

under:­

3.1 That the appellant herein awarded the contract to respondent

No.1 herein – contractor for strengthening, up­gradation and

maintenance of road from Palwal to Hasanpur, Haryana for a

length of 31.17 kilometres on certain terms and conditions as

per   the   contract   entered   into   between   the   parties.   The

contract was for Rs.5,26,59,688/­. That as per the design

calculation   data,   the   specifications   as   prepared   by   the

appellant department were meant for 3364 traffic intensity

PCU   (Passenger   Car   Unit)/day.   The   contract   was   up   to

31.05.2010. That on 05.03.2005 due to the closing of the

Palwal Aligarh Road on account of the construction of the

railway bridge, the entire traffic was diverted from Palwal

2

Aligarh Road to the present road. That due to this diversion

of traffic from Palwal Aligarh Road, heavy traffic of 24418

PCUS per day was plying on the road as against the design of

3364 PCUS per day, which damaged the road. That according

to the contractor – respondent No.1 herein, he was required

to   do   heavy   repair   by   incurring   additional   expenditure.

Disputes arose between the parties. A legal notice was served

upon the appellant making the claims. Disputes were not

resolved and therefore respondent No.1 – contractor invoked

the   arbitration   clause   as   per   clauses   24   &   25   and

approached the High Court for appointment of an arbitrator

in exercise of power conferred under Section 11 (6) of the

Arbitration and Conciliation Act, 1996. 

3.2 Vide order dated 23.04.2007, the High Court appointed Shri

R.S.   Jindal,   retired   Chief   Engineer,   Delhi   Development

Authority as the sole Arbitrator to adjudicate upon all the

disputes between the parties. That the contractor submitted

various claims including claim Nos. 1 and 8. For the purpose

of   deciding   the   present   appeals,   claim   Nos.1   and   8   are

relevant.   The   sole   Arbitrator   awarded   a   total   sum   of

Rs.1,51,95,400/­ with respect to claim Nos.1 and 8.  

3

4. Feeling aggrieved and dissatisfied with the award declared by

the learned Arbitrator, the appellant preferred an application

before the Court under Section 34 of the Arbitration and

Conciliation Act, 1996, which came to be dismissed against

which   the   appellant   –   State   preferred   an   appeal   under

Section   37   of   the   Arbitration   and   Conciliation   Act,   1996

before the High Court. By the impugned judgment and order

the High Court has dismissed the said appeal. Hence, the

State of Haryana has preferred the present appeals.  

5. Shri Shyam Divan, learned Senior Advocate has appeared on

behalf   of   the   State   –   appellant   and   Shri   Ranjit   Kumar,

learned   Senior   Advocate   has   appeared   on   behalf   of   the

respondent No.1 – contractor. 

5.1 Shri Shyam Divan, learned Senior Advocate appearing on

behalf   of   the   appellant   submitted   that   the   appellant   has

already paid to respondent No.1 – contractor an amount of

Rs.1,03,50,263/­   pursuant   to   the   interim   order   dated

26.08.2016 passed by this Court.

4

5.2 Shri Shyam Divan, learned Senior Advocate appearing on

behalf of the appellant has submitted that the arbitral award

is liable to be set aside on the following grounds:­

(i) The award is in excess of claim;

(ii) The Arbitrator exceeded the scope of reference;

(iii) The Arbitrator has rewritten the contract with respect to

the amount payable which was specified in the contract.

5.3 Now, so far as ground No.1 that the award is in excess of

claim,   it   is   vehemently   submitted   by   Shri   Shyam   Divan,

learned Senior Advocate appearing on behalf of the appellant

that the contractor in its statement of claim had claimed an

amount of Rs. 1,03,50,263/­ only under the claim Nos.1 and

8. It is submitted that despite the above the Arbitrator has

awarded a total sum of Rs.1,51,95,400/­, which is in far

excess of amount claimed. It is submitted that the statement

of claim was never modified by the contractor and therefore,

the Arbitrator ought not to have awarded the sum/amount in

excess of the amount claimed.

5

5.3.1 It   is   submitted   that   the   differential   amount   of

Rs.48,45,137/­ is in excess of claim and to that extent the

arbitral award is invalid and liable to be set aside. Reliance

is placed on the decision of this Court in the case of ONGC

Ltd.   v.  Off­Shore   Enterprises   Inc.,  (2011) 14 SCC 147

(para 16). 

5.3.2 It is submitted that as held by this Court in the cases of

Associate   Builders   v.   Delhi   Development   Authority,

(2015)   3   SCC   49   (para   36)   and  J.C.   Budhraja   v.

Chairman,  Orissa  Mining  Corpn.  Ltd.  &  Anr.,  (2008) 2

SCC 444 (para 31­32), making an award in excess of claim

is clear cut an act exceeding the jurisdiction and amounts

to a misconduct of the Arbitrator.

5.4 Now,   so   far   as   ground   No.2   namely,   that   the   Arbitrator

exceeded the scope of reference, it is contended that the

Arbitrator cannot exceed the scope of reference.

5.4.1 It is submitted that the contractor invoked the arbitration

clause on 06.03.2006. The High Court appointed the sole

6

Arbitrator on 23.04.2007 and the Arbitrator entered upon

reference on 19.05.2007. It is urged that by allowing the

claims   for   a   period   beyond   19.05.2007,   the   Arbitrator

exceeded the scope of reference. 

5.4.2 It is submitted that an amount of Rs.57,96,000/­ (approx.)

has been awarded for claims arising between 19.05.2007 to

31.07.2008 (calculated as amount for maintenance of road

@   Rs.   45,000/­   per   kilometre   (km)   per   month).   It   is

submitted that it was not permissible for the Arbitrator to

exceed the scope of the reference beyond the date upon

entering reference and as a consequence the award is liable

to be set aside. 

5.4.3 Learned   senior   counsel   appearing   on   behalf   of   the

appellant has relied upon the decisions of this Court in the

cases of Indian Aluminium Cables Ltd. v. Haryana State

Electricity Board, 1996 (5) SCALE 708 (para 2) and MSK

Projects   India   (JV)  Ltd.   v.  State   of   Rajasthan  &   Anr.

(2011)   10   SCC   573   (para   15),   in   support   of   his   above

submissions that as the Arbitrator exceeded the scope of

reference and hence the award is liable to be set aside.

7

5.5 In   so   far   as   the   ground   No.3   is   concerned   namely,   the

Arbitrator   has   rewritten   the   contract   with   respect   to   the

amount payable which was specified in the contract, it is

submitted that the Arbitrator has rewritten the terms of the

contract by directing the appellant to pay the compensation

to respondent No.1 – contractor at the rate of Rs.45,000/­

per km per month instead of mutually agreed contractual

rate of Rs.1,000/­ per km per month. It is contended that it

was not open to the Arbitrator to rewrite the terms of the

contract and award the contractor a higher rate for the work

than the rate which was already fixed in the contract. It is

submitted that such an exercise is beyond the competence

and authority of the Arbitrator. Reliance is placed on the

decision   of   this   Court   in   the   case   of  Satyanarayana

Construction   Company   v.   Union   of   India   and   Others

(2011) 15 SCC 101 (para 11). 

5.6 It   is   further   contended   by   Shri   Divan,   learned   Senior

Advocate   appearing   on   behalf   of   the   appellant   that   even

otherwise,   the   amount   awarded   by   the   Arbitrator   at

8

Rs.45,000/­ per km per month beyond the time period of

additional traffic i.e. from 31.07.2008 to 31.05.2010 i.e. till

the end of contract is wholly impermissible. It is submitted

that diversion of traffic on 9.2 km stretch of the road which

gave rise to the cause of action ceased to exist w.e.f. January

2008.   It   is   submitted   that   however,   the   Arbitrator   has

directed the appellant to make payment at Rs. 45,000/­ per

km per month even beyond the time period of additional

traffic.   It   is   contended   that   the   aforesaid   is   wholly

impermissible. 

6. Making   the   above   submissions,   it   is   prayed   to   allow   the

present appeals. 

7. Shri Ranjit Kumar, learned Senior Advocate appearing on

behalf   of   respondent   No.1   –   contractor,   has   vehemently

contended that the award passed by the Arbitrator cannot be

said to be (i) in excess of claim; (ii) exceeding the scope of

reference and (iii) rewriting the contract with respect to the

amount   payable   which   was   specified   in   the   contract,   as

submitted on behalf of the appellant. It is submitted that in

the statement of claim the contractor specifically stated that

9

the amount has been worked out up to the month of May,

2007 and the details of expenditure beyond May, 2007 will be

submitted   during   the   course   of   hearing.   It   is   therefore

submitted that it cannot be said that claim Nos.1 and 8 were

restricted   to   Rs. 1,03,50,263/­   only.   It   is   urged   that   on

appreciation of the evidence on record the Arbitrator has

awarded Rs. 1,51,95,400/­  for claim Nos.1 and 8, which in

any case cannot be said to be beyond the amount claimed in

the statement of claim. 

7.1 It is next contended that it also cannot be said that the

award passed by the Arbitrator was beyond  the scope of

reference. It is submitted that as such cause of action to

claim the additional amount arose due to over­expenditure

owing to maintenance of road due to diversion of traffic from

Palwal Aligarh Road to the present road which continued

even beyond 06.03.2006 and/or 23.04.2007 and 19.05.2007.

It is submitted that the amount awarded by the Arbitrator

under claim Nos.1 and 8 cannot be said to be exceeding the

scope of reference.

10

7.2 It is further submitted that even the award passed by the

Arbitrator   to   make   payment   at   Rs.45,000/­   per   km   per

month cannot be said to be rewriting of the contract with

respect to the amount payable which was specified in the

contract. It is urged that at the time when the contract was

written/entered into between the parties the contract rate of

Rs.1,000/­ per km per month was agreed against the design

of   3364   PCUS   per   day.   However,   after   the   contract   was

entered into and the contractor acted as per the contract

there was diversion of traffic from Palwal Aligarh Road to the

present road and the heavy traffic of 24418 PCUS per day

was plying on the road as against the design of 3364 PCUS

per day and therefore the contractor was required to incur

additional expenditure at Rs.45,000/­ per km per month. It

is submitted that the amount awarded by the Arbitrator at

Rs.45,000/­ per km per month cannot be said to be rewriting

the contract with respect to the amount payable than what

was   specified   in   the   contract   i.e.   Rs.1,000/­   per   km   per

month. 

7.3 However,   Shri   Ranjit   Kumar,   learned   Senior   Advocate

appearing on behalf of the contractor is not in a position to

11

justify the award by which the Arbitrator has awarded the

payment at Rs.45,000/­ per km per month even beyond the

time period of additional traffic i.e. up to 31.05.2010 i.e. till

the end of the contract. 

8. We   have   heard   the   learned   senior   counsel   appearing   on

behalf   of   the   respective   parties   at   length   and   given   our

thoughtful consideration.

9. That   the   contractor   was   awarded   the   contract   for

maintenance,   etc.   The   contract   amount   was   for

Rs.5,26,59,688/­. The rate of maintenance of the road as

accepted was Rs.12,000/­ per km per annum or Rs.1,000/­

per km per month. The maintenance contract was valid up to

31.07.2010.   When   the   contract   was   entered   into,   the

contract was meant for only 3364 PCUS per day. However,

due to diversion of traffic from Palwal Aligarh Road to the

present road, the contractor was required to incur additional

expenditure on the maintenance due to increase in the traffic

and plying the additional commercial vehicles. Therefore the

contractor   claimed   the   amount   towards   additional

expenditure for maintenance which was due to increase in

12

the   traffic   and   plying   more   commercial   vehicles.   On

appreciation of evidence the Arbitrator has determined the

loss at Rs.45,000/­ per km per month (claim Nos.1 and 8). 

9.1 The case on behalf of the appellant that as in the statement

of   claim,   the   claimant   claimed   an   amount   of

Rs.1,03,50,263/­   under   the   claim   Nos.   1   and   8   and   the

Arbitrator has awarded Rs.1,51,95,400/­, the same is in far

excess   of   amount   claimed   and   therefore   the   award   is   in

excess   of   amount   claimed   has   no   substance.   When   the

statement of claim submitted by the contractor is seen, it is

specifically   stated   by   the   claimant   that   the   amount   of

Rs.1,03,50,263/­ has been worked out up to May, 2007 and

the   details   of   expenditure   beyond   May,   2007   will   be

submitted   during   the   course   of   hearing.   It   is   specifically

stated that expenditure incurred up to May, 2007 works out

to Rs.1,03,50,263/­. Therefore, the amount awarded by the

Arbitrator cannot be said to be in excess of the claim. 

9.2 Now so far as the submission on behalf of the appellant that

the Arbitrator exceeded the scope of reference while awarding

an amount beyond 19.05.2007 – the date on which the High

13

Court appointed the sole Arbitrator is concerned, the same

has no substance. The case on behalf of the appellant that

the Arbitrator ought to have restricted the claim either up to

06.03.2006 – the date on which the contractor invoked the

arbitration clause or 23.04.2007, the date on which the High

Court   appointed   the   sole   Arbitrator   or   at   least   up   to

19.05.2007 – the date on which the Arbitrator entered into

reference, is concerned, it is required to be noted that the

claim made by the Arbitrator was till the traffic was diverted

which was up to January, 2008. Therefore, the Arbitrator

was justified in awarding the amount beyond the aforesaid

periods and till the additional traffic was diverted due to the

closure of Palwal Aligarh Road.

9.3 Now the submission on behalf of the appellant is that by

awarding Rs.45,000/­ per km per month the Arbitrator has

rewritten the contract with respect to the amount payable

than what was specified in the contract. It is urged that

under   the   contract   mutually   agreed   contractual   rate   was

Rs.1,000/­  per km per  month  and  therefore  any amount

higher than Rs.1,000/­ per km per month is beyond the

terms   and   conditions   of   the   contract,   is   also   without

14

substance. It is noted that at the time when the contract was

entered   into   the   mutually   agreed,   the   rate   fixed   was

Rs.1,000/­ per km per month and the estimated traffic was

3364 PCUS per day. The cause of action arose subsequently

due   to   diversion   of   traffic   from   Palwal   Aligarh   Road   and

plying of more heavy vehicles due to which the contractor

was required to incur additional expenditure for maintenance

of the road. Therefore, the contractor was entitled to the loss

on   account   of   the   additional   expenditure   incurred   for

maintenance   of   the   road   due   to   increase   in   the   traffic

because   of   the   closure   of   the   Palwal   Aligarh   Road   and

diversion of the traffic to the present road. Therefore, by no

stretch of imagination it can be said that there was rewriting

the   terms   of   the   contract   as   submitted   on   behalf   of   the

appellant. 

9.4 In view of the above findings, none of the decisions of this

Court relied upon by the learned senior counsel appearing on

behalf of the appellant are applicable to the facts of the case

on   hand   as   the   same   are   not   of   any   assistance   to   the

appellant. 

15

9.5 However,   at   the   same   time   Shri   Divan,   learned   Senior

Advocate, appearing on behalf of the appellant is justified in

submitting that the Arbitrator ought not to have awarded an

amount of Rs.45,000/­ per km per month beyond the time

period of additional traffic. The Arbitrator has awarded the

loss/amount   at   Rs.45,000/­   per   km   per   month   up   to

31.05.2010 i.e. till the end of the contract which is wholly

impermissible diversion  of  the  additional  traffic ceased  to

exist w.e.f. January, 2008. Therefore, the Arbitrator ought

not to have awarded any amount beyond the above time

period   beyond   January,   2008.   To   that   extent   the   award

passed by the Arbitrator can be said to be perverse and to

that extent the present appeals are required to be allowed.

10. In view of the above and for the reasons stated above, the

present appeals are allowed in part. The award passed by the

Arbitrator   awarding   the   amount/compensation   at

Rs.45,000/­ per km per month up to January, 2008 under

claim Nos.1 and 8 is hereby confirmed. The award passed by

the   Arbitrator   awarding   the   amount/compensation   at

Rs.45,000/­   per   km   per   month   from   February,   2008   to

31.05.2010 i.e. till the end of the contract is hereby quashed

16

and set aside. The amount due and payable has to be worked

out accordingly. The present appeals are partly allowed to the

aforesaid extent. In the facts and circumstances of the case

there shall be no order as to costs.        

…………………………………J.

(M. R. SHAH)

…………………………………J.

 (B.V. NAGARATHNA)

New Delhi, 

December  14, 2021.

17