REPORTABLE

 IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 3807 OF 2020

(Arising out of SLP (C) NO(S). 28244 OF 2015)

CHIEF EXECUTIVE OFFICER AND

VICE CHAIRMAN GUJARAT MARITIME

BOARD ...APPELLANT(S)

VERSUS

ASIATIC STEEL INDUSTRIES LTD AND ORS. ...RESPONDENT(S)

J U D G M E N T

S. RAVINDRA BHAT, J.

1. Leave granted. With consent, the appeal was heard. This appeal is

directed against a judgment of the High Court of Gujarat dated 24.07.2015. The

respondent (hereafter “Asiatic Steel”) had filed a writ petition before the High

Court seeking refund of contract consideration of ₹3,61,20,000/- paid by them

to the appellant (hereafter “the Board”). The High Court allowed the writ

petition, in view of its earlier interim order, and directed the Board to pay

interest for the period from 08.11.1994 to 19.05.1998. The brief facts that arise

for consideration are as follows.

2

2. The Board issued a tender notice on 02.08.1994 for allotment of plots at

Sosiya (near Bhavnagar, Gujarat) for ship-breaking of „very large crude

carriers/ultra large crude carriers‟ (VLCC/ULCC). Asiatic Steel made the

highest bid, which was accepted and confirmed by the Board on 08.11.1994, for

₹ 3, 61, 20,000/- (hereafter the „Principal‟). Asiatic Steel was allotted Plot V-10.

The bid payment was made on 22.03.1995 in foreign currency, to the tune of

$1,153,000, while the earnest money deposit of ₹5,00,000/- was paid on

08.11.1994.

3. On 23.02.1995, Asiatic Steel and other allottees approached the Board

citing difficulties in commencing commercial operations, on account of the

connectivity to the plots and the existence of rocks inhibiting beaching of ships

on the plot for the purpose of ship-breaking. Through a letter dated 19.05.1998,

Asiatic steel intimated the Board that it wished to abandon the contract and

demanded that the payment be refunded (an amount of $1,153,000), with

interest at 10% per annum from the date of remittance. The Board, through a

notice dated 19.05.1998, stated that an amount of ₹3, 61, 20,000/- would be

refunded, but without interest. The Board also clarified that the refund would be

directed to the original allottee of the plot (i.e. the second respondent, i.e. M/s

Ganpatrai Jaigopal- hereafter referred to as “Ganpatrai”). Asiatic Steel then filed

a writ petition before the High Court, seeking (i) refund of USD $ 1,153,000

with interest of 12% per annum compounded quarterly, to the third respondent,

M/s Industeel Investment Holdings (hereafter “Industeel”, which had made the

payment originally on behalf of Asiatic Steel); and (ii) refund of earnest money

of ₹5,00,000/- with interest of 12% per annum, compounded quarterly to Asiatic

Steel.

4. Through an interim order dated 26.02.2002, the High Court held that

prima facie, Asiatic Steel was entitled to a refund with interest at 10% per

annum. Accordingly, the Board was directed to deposit the admitted amount, 

3

i.e., the Principal, with interest at 10% p.a. with the court‟s Registry on or

before 15.04.2002. The interest was to be calculated from 19.05.1998 up to

15.04.2002. The amount was permitted to be withdrawn by Respondent No. 3,

with the consent of the other respondents. The Board made this deposit, as

directed by the court.

5. On 17.09.2014, the High Court determined that the following issues

survived to be determined:

(a) Whether interest on payment should be calculated from 24.03.1995 to

15.04.2002, or from 19.05.1998;

(b) Whether the earnest money of ₹5,00,000 should be refunded;

(c) Whether interest should be calculated at 10% p.a. or 12% p.a.

6. The Board resolved, through a resolution dated 17.12.2014, to refund the

earnest money deposit with interest of 10% calculated from 19.05.1998. On

account of this development, the High Court examined the issue of

quantification of interest, and held that so far as the amount that had already

been refunded with interest at 10% was concerned, no grievance could be raised

by Asiatic Steel, as it had initially claimed an interest of 10%, in the letter to the

Board dated 19.05.1998. In the case of the refund already made of the Principal

and the earnest money deposit, it was held that Asiatic Steel was not justified in

claiming more than 10% interest. Neither party raised any grievance against the

High Court‟s interim order dated 26.02.2002 fixing the interest at 10%. The

only question then left to be decided was with respect to the date from which

interest on the Principal was to be calculated, and what the rate of interest was

to be.

7. The High Court held that the Board never claimed that it suffered any

damage or loss due to Asiatic Steel‟s termination of the contract. The reasoning

of the impugned judgment was that hence, the Board was under a liability to

compensate or pay reasonable interest for the period during which the money 

4

was retained by it. The High Court took into consideration that Indusind was a

Singaporean company, and that the rate of interest was lower in developed

countries. Accordingly, the rate of interest was altered to 6% p.a., for the period

during which the money was enjoyed by the Board. The Board was directed to

(i) refund the earnest money of ₹5,00,000/- with interest at 10% p.a., in

accordance with the resolution of 17.12.2014; and (ii) pay interest of 6% on the

Principal from 08.11.1994 to 19.05.1998. This interest amount works out to

₹76,47,544/-. The Board is, hence, aggrieved by the impugned judgment.

Arguments Advanced

8. It was contended on behalf of the Board that the subject matter of the

present dispute was a contract. To determine whether the Board had to pay

compensation for any benefit received under the contract, it was imperative that

breach of such contract should have been proved. Sections 64 and 65 of the

Indian Contract Act, 1872 (hereinafter the „Contract Act‟), contemplate return

of benefit for a void/voidable contract. It was submitted that these provisions do

not apply when there is no allegation as to the contract being void. In any case,

the Board had already refunded the entire amount to Asiatic Steel. The learned

counsel for the Board went on to submit that Section 73 and 75 of the Contract

Act were inapplicable, as breach was not proven or found, and neither did the

high court make a finding of rightful rescission of contract by Asiatic Steel.

9. The sole basis of the High Court‟s direction to pay interest for the period

from 08.11.1994 to 19.05.1998 was the Court‟s view that the Board had an

obligation to compensate Asiatic Steel for its enjoyment of the principal during

this period, and because the Board had not shown that it suffered any loss on

account of termination of the contract. Counsel urged that Asiatic Steel accepted

and provided an undertaking of their satisfaction of the site, in the contract 

5

entered into between the parties. They then went on to abandon the contract on

grounds of the site being rocky/ unsuitable for their commercial activities.

10. Counsel for Asiatic Steel, on the other hand, submitted that the Board

took about 4 years to take action on its promise to create surrounding

infrastructure and clear the rocks as well as the rocky island near plot V-10,

which made it unviable for Asiatic Steel to commence business. The Board had

agreed, through its board meeting on 23.03.1995, to develop infrastructure and

remove the rocks; Asiatic Steel once again appraised the Board of the

importance of removing the rocks, through a letter dated 26.04.1996. Asiatic

Steel even stated that it could take up the task of removing the rocks, if the

Board so desired. The request for removal of the rocks and the rocky formation

near plot V-10 was repeated through another letter dated 22.05.1996. The other

successful bidders for plots V-6 to V-9 also raised similar issues, and

approached the courts for relief. Asiatic Steel did not join those bidders, and

sought to deal with the matter amicably. Counsel submitted that since the Board

did not actually carry out the promised work, Asiatic Steel could not commence

commercial production; they were left with no option but to abandon the project

and seek a refund. It was submitted that Asiatic Steel incurred heavy losses on

account of interest costs from the date of remittance, as well as losses on

account of depreciation of the rupee over a period of three years.

11. When the Board failed to make the refund or discharge its duties, Asiatic

Steel filed a petition before the High Court. A civil suit claiming damages was

also preferred at the City Civil Court, Ahmedabad, which was unconditionally

withdrawn, after seeking permission from the High Court, which was granted

through the order dated 26.02.2002.

12. The learned counsel submitted that on account of the Board‟s failure to

remove the rocks, Asiatic Steel could not take possession of the plot, and

therefore, that interest is due from the date of deposit till the date of payment. It 

6

was argued that the very fact that the Board agreed to refund the premium and

the earnest money shows their acceptance that they have been unable to provide

the promised plots. It was further submitted that all the other allottees had been

paid interest on the amounts deposited by them. It was urged that the Board

enjoyed the Principal amount from 08.11.1994 to 19.05.1998, and it was not a

case where the possession of the plot was handed over and the contract was

concluded. Asiatic Steel was deprived of a substantial amount that could not be

utilized elsewhere during that period. It was submitted that interest was

essentially compensation for denial of the right to utilize the money due.

13. Reliance was placed on Union of India, Tr. Dir. of IT v. M/s Tata

Chemicals Ltd.1

, where this court held that interest „…is a kind of compensation

of use and retention of money collected unauthorizedly by the Department.

When the collection is illegal, there is corresponding obligation on the revenue

to refund such amount with interest in as much as they have retained and

enjoyed the money deposited.‟

14. With regard to the question of whether Asiatic Steel raised objections

regarding the unsuitability of the land for the purpose for which it had been

tendered, it was contended on its behalf that objections were raised, prior to

remitting a major part of the upset premium. The first objection on record was

immediately after payment of the earnest money deposit after the allotment of

the plot on 08.11.1994, through letter dated 23.02.1995. The payment of the

premium was made on 22.03.1995. It was argued that no time period under the

lease, was consumed for any activity whatsoever on the plot, and Asiatic Steel

did not derive any benefit at all. It was categorically acknowledged and

admitted in board meetings and letters that the plot was unusable and the

contract was to be mutually abandoned. Considering that the Board agreed to

refund the amount with interest, it was argued, that the consequence was that


1

(2014) 6 SCC 335. 

7

the money should be returned with interest from the date when it was enjoyed

by the Board.

15. Asiatic Steel urged that the limited issue to be determined by this court is

that of interest payment from when the remittance was made, i.e., 22.03.1995 to

19.05.1998, when the contract was abandoned. Finally, they submitted that this

amount works out to ₹1,32,44,729/- (at 10% interest p.a.), ₹1,06,95,783/- (at 8%

interest p.a.), and ₹81,46,837 (at 6% interest p.a.).

16. It was further submitted that the successful bidders of plots V-8

(Svaminarayan Ship Breaking Pvt. Ltd.) and V-9 (M/s Mazz Marine Pvt. Ltd.)

who were similarly situated to Asiatic Steel, had approached courts for a decree,

and been refunded their deposits with interest, pursuant to orders dated

14.08.1996 and 08.07.2002 respectively.

17. With this court‟s permission, Asiatic Steel filed copies of RTI queries

which had sought specific information with regard to (i) amount paid to

similarly placed bidders/plot holders during settlement with the Board; (ii)

whether interest was paid to the bidders/plot holders along with the principal,

and from what date this was paid; and (iii) the percentage of interest paid along

with principal.

18. A response to the RTI query was received on 20.02.2020, in respect of

the bidders for plots V-7, V-8 and V-9. The bidder for V-7 was paid an interest

at 12%, amounting to ₹22,80,743/-, for the period from 23.03.1995 –

30.11.1995. The bidder for V-8 was paid interest at 12%, amounting to

₹3,55,068/-, for the period from 27.03.1995 – 30.11.1995. The bidder for V-9

was paid interest at 9% amounting to ₹2,12,500/-, for the period from

23.03.1995 – 30.11.1995.

19. It was urged that in accordance with tender conditions, the primary

obligation to provide a suitable plot for ship breaking was that of the Board. 

8

Counsel for Asiatic Steel submitted that the „as is where is‟ clause cannot be

interpreted to mean that the Board can allot any piece of land that is of no utility

to the bidder, and be absolved of liability.

20. In response to Asiatic Steel‟s contentions that identically situated bidders

were paid interest at 10-12% were unsustainable, it was contended on behalf of

the Board, in a response, that interest was not payable under the terms of the

contract with the present respondents. Further, Asiatic Steel had allowed the

plot to remain unused for almost half of the license/concession period before

rescinding the contract. It had verified the site before casting a bid; it took a

conscious decision to make the bid and pay the upset premium.

21. It was further submitted that the Board had written to Asiatic Steel on

28.11.1995, informing them that the plot was ready in all respects and

possession was required to be taken before 30.11.1995. The bidders for V-7 and

V-8 were given interest only up till the date the plot holders were to take

possession – 30.11.1995. Asiatic Steel did not take possession.

22. It was urged that the present case is a contractual dispute where, without

breach being proved against the Board, interest was ordered as a „compensatory

measure‟, that too under writ jurisdiction.

Analysis

23. The Guidelines for Permission to Utilize Ship breaking Plots at Sosiya

provided that permission shall be granted for a period of ten years from the date

of issue of the permission letter, after which, the permission shall cease. The

conditions applicable for grant of permission are provided under Clause 13;

Clause 13(d) mandates that plot charges be paid in advance, before issuance of

the permission letter, and plot charges for the next year are to be paid before the

commencement of the relevant year. 

9

24. Asiatic Steel was the highest bidder in an auction for five shipbreaking

plots, held on 08.11.1994. The Board received payment of the earnest money

deposit of ₹5,00,000/- on this day. Plot V-10 was allotted to Respondent No. 1

(Asiatic Steel Industries Ltd.). M/s Ganpatrai were the Indian shareholders of

Asiatic Steel, while M/s Industeel was a foreign shareholder based in Singapore.

The upset premium was remitted by Industeel in US currency (dollars $), on

22.03.1995.

25. The minutes of the meeting dated 23.02.1995 record that the shipbreakers

(including Asiatic Steel herein), informed the Board that certain rocks were

required to be removed along plots V-6 to V-10, which hinder the beaching of

ships. The Board agreed to prepare an estimate and invite tenders for the

removal of these rocks.

26. The record shows that the notice inviting tenders issued by the Board

expressly stated in para 14 that:

“14. The tenderer may inspect the site at his own cost and shall be

deemed to have acquainted himself, fully with all the site conditions.

15. Tenderer shall be deemed to have read and understood the

guidelines at Annexure one and the terms and conditions at annexure

to.”

27. Such being the position, it was nobody‟s case that Asiatic Steel was

unaware about the site conditions. This is particularly important because it was

willing to commit a substantial amount in foreign exchange for the plot which it

bid for and was eventually granted. Likewise, the requisite undertaking too was

furnished on its behalf. It is in this background of circumstances, that the claim

for interest for the period in question requires examination.

28. The record relied upon by Asiatic Steel is in the form of three office

orders issued by the Board. The first office order is dated 06.05.1996. This 

10

order relates to Nyankaran Investment and Leasing Pvt. Ltd. This company had

successfully bid for Plot Number V-7 and paid ₹ 2.74 crores. This company had

deposited the entire amount on 23.03.1995. Upon being dissatisfied with the

plot, the company filed CA 8287/1995, in proceedings under Article 226 of the

Constitution of India, before the Gujarat High Court. Having regard to the

observations made by the High Court, the board sanctioned refund of the entire

amount along with 12% interest, by its order dated 06.05.1996. The amount

paid by the Board as interest was ₹ 22.80 lakhs. The second instance relates to

Svaminarayan Shipbreaking (P) Ltd, Surat, which had bid for a plot (V-8) and

paid ₹50 lakhs in two equal instalments. This company filed proceedings before

the Gujarat High Court, (i.e. CA 3122/1995). The Board, therefore decided to

refund the principal along with interest at 12% per annum for two different

periods, based on the deposit of the two payments of ₹ 25 lakhs. The total

interest sanctioned on 08.08.1996 (and later paid) was ₹ 3.55 lakhs. The last

instance is of Maaz Marine (P) Ltd, Surat, which had bid for a plot (V-9) and

paid the instalments. This company filed proceedings before the Gujarat High

Court, (i.e. CA 3211/1995). The Board, therefore decided to refund the principal

along with interest @ 9% per annum for the period, based on the deposit of the

payment of ₹ 25 lakhs. The total interest sanctioned on 08.08.1996 (and later

paid) was ₹2.12 lakhs. This amount was sanctioned by office order dated

27.03.2000, even though the Board had decided to refund earlier (on

21.03.1996, due to the court proceedings and orders); however, the amount was

sanctioned later, awaiting the decision of the civil court, in an inter se dispute

between the directors of Mazz Marine, (i.e. in Suit No. 1200/1997). Upon the

decision in that case, the amount was released, including the interest at 9% p.a.

for one year.

29. The correspondence on the record reveals that the last payment towards

the plot was tendered by Asiatic Steel under cover of a letter dated 22.03.1995 

11

for an amount of US$ 1,153,000/-. The other letters placed on record are the

one dated 23.04.1995, to the Board indicating that the full payment for the

consideration of ₹ 3,61,20,000/- had been made towards a plot. Other than this,

in the writ petition, Asiatic Steel argued that it made efforts several times to ask

the board to clear the beachfront rocks to make the plot functional. It was also

argued that three other entities which had bid for and secured different plots

were dissatisfied by the Board‟s inaction and had approached the High Court.

As a result, the High Court passed orders which led to refund of the amounts

deposited by those concerns, with some interest. On the record, the minutes of a

discussion presided over by the Chief Minister of the state regarding

outstanding amounts of premium payable by plot holders in the shipbreaking

yard, dated 29.04.1998, would show that the state authorities were pressing for

payment of overdue premium instalments. It is after these events, that Asiatic

Steel claimed refund of the amount through a letter dated 19.05.1998. In that

letter, Asiatic Steel stated as follows:

“..there were 4 other successful bidders for plots V- 6 to V-9. These

4 bidders similarly complained of non-availability of basic

infrastructure. They subsequently approached the High Court of

Gujarat for interim relief and for directions to GMB to develop

basic infrastructure and to remove rocks in front of lots V-6 to V-9.

They approach the High Court to direct GMB to fulfil all these

obligations before asking for payment of upset premium. We

understand that the Hon‟ble High Court granted them some relief.

We may point out that we did not join the actions of these 4 bidders

in the High Court. Instead prefer to deal with the matter amicably

via discussions directly with GMB.”

30. Asiatic Steel‟s letter dated 26.04.1996, a copy of which has been placed

on the record, shows that it expressed willingness to remove the beachfront

rocks, provided the Board bore the expenses. The Board, however, was silent.

31. The contemporaneous situation, and the correspondence between Asiatic

Steel and the Board after the entire amount was deposited, reveals that other 

12

concerns approached the court seeking refund of their principal amounts, with

interest, which forced the Board to take a decision and comply. The final

decision by Asiatic Steel demanding refund was later, in May, 1998. In the

meanwhile, the other concerns, which had bid successfully for three plots had

approached the court (in 1995) and the Board had decided to refund the

amounts with one years‟ interest. Asiatic Steel, therefore, for reasons best

known to it, approached the court for refund (which it was undoubtedly entitled)

to and interest, first by filing a suit in 2001.

32. In this court‟s opinion, the claim for interest by Asiatic Steel – and the

response of the Board, on that issue, is to be judged in the light of both parties‟

conduct and what was expected of the Board as a state instrumentality. The

claim in this case is essentially a monetary one, and would ordinarily be

premised upon breach of contract. Asiatic Steel, therefore, correctly approached

the civil court by filing a suit2

. Later, apparently it was advised to resort to

proceedings under Article 226 of the Constitution of India. When its writ

petition was considered, the suit was permitted to be withdrawn; the High Court

directed the Board to deposit the entire principal amount, with interest at 10%

per annum.

3 By the final impugned judgment, that order was confirmed. In an

earlier order, the court had in fact crystallized the precise issue, to be whether

interest was payable from 24.03.1995 or from 19.05.1998, or whether it was

payable from the latter date, till the date of deposit in court, i.e., 15.04.2002.

33. Two important aspects need to be noticed at this stage: first, on the one

hand, that Asiatic Steel was aware of the condition of the plot, at an early stage,

when it bid for it. In this regard, its conduct is to be judged in the light of the

Board‟s inaction in regard to the unfitness of the allotted site, as in the case of

the other concerns. Two, Asiatic Steel was no better and no worse than the other


2

Suit No. 2961/2001

3By its order dated 26.02.2002

13

plot lessees, who demanded refund of their amounts. The difference between

them, and Asiatic Steel was that the latter chose to demand refund on

19.05.1998. Asiatic Steel‟s final letter discloses its awareness that the other

concerns approached the court earlier, but that it waited as it wished to have the

issue resolved amicably, rather than moving the court for relief.

34. In the opinion of this court, that fact that Asiatic Steel and other concerns

bid for the plots knowing the state they were in, cannot be disputed. However,

the conduct of all the successful bidders consistently suggests that they expected

that the plots would be given in usable condition, within reasonable time.

Clearly, the Board could not and most certainly did not rectify the conditions by

removing the beachfront rocks. The Board is not forthcoming about the reasons

for its inaction. It urged two defences in its reply to the writ petition: one, that

the dispute was in the realm of contract and two, that even though like in other

cases, the Board was prepared to consider a refund, Asiatic Steel was a joint

venture company. These, in the opinion of this court are wholly insubstantial

reasons.

35. It is clear from the Board‟s conduct that it never responded to the letters

written by Asiatic Steel; at least, no reply has been placed on record. Even

Asiatic Steel‟s request for permission to carry-out the necessary clearance work

at the cost of the board, was not responded to - either positively or negatively.

Further, whenever any bidder approached the court complaining that the plot

allotted was unusable, the Board decided, mostly contemporaneously, to refund

the amount, even with interest. In the case of Asiatic Steel, however, when the

demand was made for refund on 19.05.1998, the Board did not act, forcing the

company to approach the court, firstly through a civil suit which was later

withdrawn, and then in a writ petition.

36. In the opinion of this court, the Board‟s complete silence in responding to

Asiatic Steel‟s demand for refund, coupled with the absence of any material 

14

placed on record by it suggesting that the complaints had no substance leaves it

vulnerable to the charge of complete arbitrariness. The Board‟s conduct or

indifference in regard to the refund sought (in respect of which there was no

meaningful argument on its part before the High Court) can be only on the

premise that it wished the parties to approach the court, till a decision could be

taken to refund the amounts received by it.

37. In this court‟s considered view, the Board‟s action is entirely

unacceptable. As a public body charged to uphold the rule of law, its conduct

had to be fair and not arbitrary. If it had any meaningful justification for

withholding the amount received from Asiatic Steel, such justification has not

been highlighted ever. On the other hand, its conduct reveals that it wished that

the parties should approach the court, before it took a decision. This behavior of

deliberate inaction to force a citizen or a commercial concern to approach the

court, rather than take a decision, justified on the anvil of reason (in the present

case, a decision to refund) means that the Board acted in a discriminatory

manner.

38. Long ago, in Dilbagh Rai Jarry v. Union of India 4

this court had quoted

from a decision of the Kerala High Court, approvingly5

:

“25. … But it must be remembered that the State is no ordinary party

trying to win a case against one of its own citizens by hook or by

crook; for the State's interest is to meet honest claims, vindicate a

substantial defence and never to score a technical point or overreach

a weaker party to avoid a just liability or secure an unfair

advantage, simply because legal devices provide such an

opportunity. The State is a virtuous litigant and looks with unconcern

on immoral forensic successes so that if on the merits the case is

weak, Government shows a willingness to settle the dispute

regardless of prestige and other lesser motivations which move

private parties to fight in court. The layout on litigation costs and

executive time by the State and its agencies is so staggering these


4

(1974) 3 SCC 554

5 P.P. Abubacker v. Union of India, AIR 1972 Ker 103

15

days because of the large amount of litigation in which it is involved

that a positive and wholesome policy of cutting back on the volume

of law suits by the twin methods of not being tempted into forensic

showdowns where a reasonable adjustment is feasible and ever

offering to extinguish a pending proceeding on just terms, giving the

legal mentors of Government some initiative and authority in this

behalf.”

Again, in Gurgaon Gramin Bank v. Khazani6

this court stated that:

“2. The number of litigations in our country is on the rise, for small

and trivial matters, people and sometimes the Central and the State

Governments and their instrumentalities like banks, nationalised or

private, come to courts may be due to ego clash or to save the

officers' skin. The judicial system is overburdened which naturally

causes delay in adjudication of disputes. Mediation Centres opened

in various parts of our country have, to some extent, eased the

burden of the courts but we are still in the tunnel and the light is far

away. On more than one occasion, this Court has reminded the

Central Government, the State Governments and other

instrumentalities as well as to the various banking institutions to take

earnest efforts to resolve the disputes at their end. At times, some

give-and-take attitude should be adopted or both will sink. Unless

serious questions of law of general importance arise for

consideration or a question which affects a large number of persons

or the stakes are very high, the courts' jurisdiction cannot be invoked

for resolution of small and trivial matters. We are really disturbed by

the manner in which those types of matters are being brought to

courts even at the level of the Supreme Court of India and this case

falls in that category.”

39. In State of A.P. v. Pioneer Builders7

this Court referred to the 27th Report

of the Law Commission on the Code of Civil Procedure, and held as follows:

“14. From a bare reading of sub-section (1) of Section 80, it is

plain that subject to what is provided in sub-section (2) thereof, no

suit can be filed against the Government or a public officer unless

requisite notice under the said provision has been served on such


6

2012 (8) SCC 781

7

(2006) 12 SCC 119

16

Government or public officer, as the case may be. It is well settled

that before the amendment of Section 80 the provisions of

unamended Section 80 admitted of no implications and exceptions

whatsoever and are express, explicit and mandatory. The section

imposes a statutory and unqualified obligation upon the court and in

the absence of compliance with Section 80, the suit is not

maintainable. (See Bhagchand Dagadusa v. Secy. of State for India

in Council [Bhagchand Dagadusa v. Secy. of State for India in

Council, 1927 SCC OnLine PC 48 : (1926-27) 54 IA 338 : AIR 1927

PC 176] ; Sawai Singhai Nirmal Chand v. Union of India [Sawai

Singhai Nirmal Chand v. Union of India, (1966) 1 SCR 986 : AIR

1966 SC 1068] and Bihari Chowdhary v. State of Bihar [Bihari

Chowdhary v. State of Bihar, (1984) 2 SCC 627] .) The service of

notice under Section 80 is, thus, a condition precedent for the

institution of a suit against the Government or a public officer. The

legislative intent of the Section is to give the Government sufficient

notice of the suit, which is proposed to be filed against it so that it

may reconsider the decision and decide for itself whether the claim

made could be accepted or not. As observed in Bihari

Chowdhary [Bihari Chowdhary v. State of Bihar, (1984) 2 SCC

627], the object of the Section is the advancement of justice and the

securing of public good by avoidance of unnecessary litigation.

15. It seems that the provision did not achieve the desired results

inasmuch as it is a matter of common experience that hardly any

matter is settled by the Government or the public officer concerned

by making use of the opportunity afforded by the said provisions. In

most of the cases, notice given under Section 80 remains

unanswered. In its 14th Report (reiterated in the 27th and 54th

Reports), the Law Commission, while noting that the provisions of

this section had worked a great hardship in a large number of cases

where immediate relief by way of injunction against the Government

or a public officer was necessary in the interests of justice, had

recommended omission of the Section. However, the Joint Committee

of Parliament, to which the Amendment Bill, 1974 was referred, did

not agree with the Law Commission and recommended retention of

Section 80 with necessary modifications/relaxations.

16. Thus, in conformity therewith, by the Code of Civil

Procedure (Amendment) Act, 1976 the existing Section 80 was

renumbered as Section 80(1) and sub-sections (2) and (3) were

inserted with effect from 1-2-1977. Sub-section (2) carved out an 

17

exception to the mandatory rule that no suit can be filed against the

Government or a public officer unless two months' notice has been

served on such Government or public officer. The provision mitigates

the rigours of sub-section (1) and empowers the court to allow a

person to institute a suit without serving any notice under subsection (1) in case it finds that the suit is for the purpose of obtaining

an urgent and immediate relief against the Government or a public

officer. But, the court cannot grant relief under the sub-section

unless a reasonable opportunity is given to the Government or public

officer to show cause in respect of the relief prayed for. The proviso

to the said sub-section enjoins that in case the court is of the opinion

that no urgent and immediate relief should be granted, it shall return

the plaint for presentation to it after complying with the requirements

of sub-section (1). Sub-section (3), though not relevant for the

present case, seeks to bring in the rule of substantial compliance and

tends to relax the rigour of sub-section (1).”

40. In this case, conduct of the Board betrays a callous and indifferent

attitude, which in effect is that if Asiatic Steel wished for its money to be

returned, it had to approach the court. This was despite its knowledge that at

least three other identically placed entities had asked for return of money and,

upon approaching the court, were refunded the amounts given by them

promptly. In view of these facts, nothing prevented the Board from deciding to

refund the amount, without forcing Asiatic Steel to approach the court.

41. This court notes that the High Court directed payment of interest for the

entire period (i.e. starting from 08.11.1994 and ending on 19.05.1998).

However, it is evident that Asiatic Steel had not paid the entire amount on

08.11.1994; in fact the sum of $1,153,000 /- i.e. the principal consideration,

excluding the earnest money deposit, was deposited on 24.03.1995. Therefore,

the impugned judgment erred in directing payment of interest on the entire

amount from 08.11.1994; instead, the direction to pay interest on ₹3,61,20,000/-

shall operate with effect from 22.03.1995 to 19.05.1998.

18

42. The appeal is dismissed, subject to the modification indicated above, to

the impugned judgment of the High Court.

.......................................................J

 [INDIRA BANERJEE]

.......................................................J

 [S. RAVINDRA BHAT]

New Delhi,

November 24, 2020.