LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Saturday, September 20, 2025

Scope of appeal — Section 125, Electricity Act, 2003. — An appeal under Section 125 of the Electricity Act, 2003 lies only on substantial questions of law as envisaged by Section 100 CPC; concurrent findings of fact by expert regulatory bodies (CERC/APTEL) will not be disturbed unless shown to be perverse, arbitrary, in violation of statute or based on extraneous considerations.


  • Scope of appeal — Section 125, Electricity Act, 2003. — An appeal under Section 125 of the Electricity Act, 2003 lies only on substantial questions of law as envisaged by Section 100 CPC; concurrent findings of fact by expert regulatory bodies (CERC/APTEL) will not be disturbed unless shown to be perverse, arbitrary, in violation of statute or based on extraneous considerations.

  • Coal linkage and FSAs — project-wide allocation. — Where Standing Linkage Committee minutes, LOAs and Fuel Supply Agreements indicate allocation of firm and tapering linkage and captive coal for the generating station/project as a whole, such allocation is not PPA-specific and must be understood as for the station in aggregate.

  • FSA interpretation — ACQ tied to aggregate PPA capacity. — Clause 4.1.1 of the FSA making Annual Contracted Quantity (ACQ) “in proportion to the percentage of generation covered under long-term PPAs” means coal supplied under the FSA is to be released against total PPA capacity; ACQ is operationalised in relation to PPAs but the entitlement under the FSA is station-wide.

  • Apportionment of linkage and alternate coal costs — pro rata. — Shortfall in firm/tapering linkage met through imported or open-market coal and resultant additional cost must be apportioned pro rata among all beneficiaries (DISCOMs) in proportion to scheduled/ supplied energy; the CERC’s methodology for computing such adjustment is validly applied.

  • Impleading of parties — necessity of GRIDCO. — A cost-plus PPA under Section 62 need not be impleaded as a necessary party to petitions commenced under Section 63 (competitive-bidding PPAs) where the relief sought relates to Section 63 PPAs; absence of GRIDCO (a Section 62 procurer) in GKEL’s Petitions Nos. 79 and 105 did not vitiate the proceedings.

  • Doctrine of approbation and reprobation — estoppel by conduct. — A procurer (Haryana Utilities) which accepted a methodology or position before the regulatory forum cannot later adopt a contrary stance after adverse orders; approbation and reprobation will bar inconsistent litigation posture.

  • Avoidance of anomalous cross-subsidy and equal treatment. — Treating linkage coal as PPA-specific in the facts of the case would lead to anomalous cross-subsidisation among states and unequal treatment of beneficiaries; pro rata apportionment safeguards equity and prevents discriminatory allocations.

  • Judicial restraint in regulatory matters. — Courts should be slow to disturb reasoned decisions of expert regulatory bodies (CERC/APTEL) on technical and factual matters related to tariff, fuel allocation and computation of compensation unless the decision is shown to be legally unsustainable.

  • Conclusion / Order. — Appeals dismissed; the APTEL judgment of 20.12.2019 upholding the CERC order of 20.3.2018 (which directed pro rata payment of supplementary bills raised by GKEL for July 2016–March 2017 and late payment surcharge) is affirmed.

  • 2025 INSC 1079

     Civil Appeal No.1929 of 2020 etc. Page 1 of 57

    REPORTABLE

    IN THE SUPREME COURT OF INDIA

    CIVIL APPELLATE JURISDICTION

    CIVIL APPEAL NO. 1929 OF 2020

    HARYANA POWER PURCHASE

    CENTRE (HPPC) AND OTHERS … APPELLANTS


    versus

    GMR KAMALANGA ENERGY

    LIMITED AND OTHERS … RESPONDENTS

    with

    CIVIL APPEAL NO. 3429 OF 2020

    J U D G M E N T

    B.R.GAVAI, CJI.

    FACTUAL ASPECTS

    1. These appeals take exception to the judgment and final order

    dated 20th December 2019 passed by the Appellate Tribunal for

    Electricity, New Delhi1 in Appeal No. 135 of 2018 along with

    Appeal No. 54 of 2019, whereby the learned APTEL dismissed the

    said appeals and upheld the order dated 20th March 2018 passed

    by the Central Electricity Regulatory Commission, New Delhi2 in

    Petition No. 105/MP/20173.

    1 Hereinafter referred to as the ‘APTEL’

    2 Hereinafter referred to as the ‘CERC’

    33 Hereinafter referred to as ‘Petition No. 105’

     Civil Appeal No.1929 of 2020 etc. Page 2 of 57

    2. We have two appeals before us, both of which challenge the

    same judgment and final order of the learned APTEL. The first

    appeal being Civil Appeal No. 1929 of 2020 has been filed by

    Haryana Power Purchase Centre and two others4 whereas the

    second appeal being Civil Appeal No. 3429 of 2020 has been filed

    by one GRID Corporation of Orissa Limited5. For the sake of clarity

    and to avoid any confusion, the parties will be referred to

    according to their positions in the first of the two civil appeals.

    3. Before we proceed with the facts of the case, it would be

    apposite to give a brief overview of the parties before us.

    3.1 HPCC (Appellant No.1) is the nodal agency for the

    procurement of power on behalf of the distribution licensees in

    the State of Haryana, being Dakshin Haryana Bijli Vitran Nigam

    Limited (Appellant No.2) and Uttar Haryana Bijli Vitran Nigam

    Limited (Appellant No.3). Haryana Power Generation Corporation

    Limited (Proforma Respondent No.6) is the body corporate that

    was responsible for the initiation of the competitive bid process on

    behalf of Appellant Nos. 2 and 3 for procurement of power in the

    4 Hereinafter referred to as the ‘HPCC’

    5 Hereinafter referred to as ‘GRIDCO’

     Civil Appeal No.1929 of 2020 etc. Page 3 of 57

    State of Haryana. Together, the said parties may be referred to as

    the “Haryana Utilities”.

    3.2 GMR Kamalanga Energy Limited6 (Respondent No.1) is a

    generating company within the meaning of the Electricity Act,

    20037. Notably, GKEL is a special purpose vehicle of GMR Energy

    Limited8 which was the predecessor-in-interest of the Respondent

    No.1.

    3.3 PTC India Limited9 (Respondent No.2) is a trading licensee

    within the meaning of the 2003 Act. Respondent No. 2 had an

    arrangement with GKEL for the procurement of power.

    3.4 CERC (Respondent No.3) is the regulatory commission under

    the 2003 Act.

    3.5 GRIDCO (Respondent No.4) is a licensee under the 2003 Act

    which is responsible for procuring power for supply within the

    State of Odisha.

    3.6 Similarly, Bihar State Power (Holding) Company10

    (Respondent No.5) is a licensee under the 2003 Act which is

    6 Hereinafter referred to as ‘GKEL’

    7 Hereinafter referred to as the ‘2003 Act’

    8 Hereinafter referred to as ‘GEL’

    9 Hereinafter referred to as ‘PTC’

    10 Hereinafter referred to as ‘Bihar Utilities’

     Civil Appeal No.1929 of 2020 etc. Page 4 of 57

    responsible for procuring power for supply within the State of

    Bihar.

    4. Having given a brief overview of the parties in the civil

    appeals, we may now proceed to examine the facts which lead to

    the present appeals. The facts are as follows:-

    4.1 With the intention to set up a thermal power plant of about

    1,000 MW comprising of two units of about 500 MW each at village

    Kamalanga, Dhenkanal in the State of Odisha, GEL entered into

    a Memorandum of Understanding (MoU) with the Government of

    Odisha on 9th June 2006. Per the terms of the MoU, the power

    project as envisaged was to operate with coal as the primary fuel,

    for which purpose the State of Odisha was to either allot coal

    blocks upon receipt of sanction from the Government of India or

    allot long-term coal linkage of such quality and quantity as

    required for the project. The MoU further necessitated that a

    nominated agency authorized by the Government of Odisha would

    have the right to purchase up to 25% of power sent out from the

    thermal power plants. While initially, the MoU envisaged the

    setting up of thermal plants with an aggregate capacity of 1,000

    MW (500 x 2), by way of alteration carried out subsequently, it

    was decided that GKEL would develop four power plants each 

     Civil Appeal No.1929 of 2020 etc. Page 5 of 57

    having a capacity of 350 MW. Three out of the four said units have

    been installed, however, the fourth unit of 350 MW is yet to be

    installed. Subsequently, this project was accorded the Mega

    Power Project status by the Ministry of Power, Government of

    India vide its letter dated 1st February 2012.

    4.2 In terms of the MoU, on 28th September 2006, GKEL

    executed a Power Purchase Agreement with GRIDCO (Respondent

    No.4) being the nominated agency of the State of Odisha for the

    sale of 25% of the gross power generated by GKEL to GRIDCO,

    which came to 262.5 MW, upon the installed capacity reaching

    1050 MW (350 MW x 3).

    4.3 Thereafter, on 5th January 2007, GKEL addressed a letter to

    the Government of Odisha requesting the State Government for a

    recommendation to the Ministry of Coal, Government of India for

    the allotment of long-term coal linkage in favour of GKEL.

    Accordingly, the Department of Energy, Government of Odisha

    vide letters dated 19th December 2005 and 12th January 2007

    pursued the matter with the Government of India.

    4.4 While this was underway, on 1st March 2007, the Haryana

    Power Generation Corporation (Respondent No.6) issued a 

     Civil Appeal No.1929 of 2020 etc. Page 6 of 57

    Request for Proposal11 on behalf of the Haryana Utilities for

    procurement of 2,000 MW power on a long-term basis. The said

    RfP envisaged the procurement of power by way of a tariff-based

    bidding process as provided for under Section 63 of the 2003 Act.

    In order to qualify for the bid, all the bidders were required to

    submit proof of fuel arrangements in terms of Clauses 2.1.5 and

    2.1.5 A of the RfP which read thus: -

    “2.1.5 All Bidders are required to submit copies of

    one or more of the following :-

    (a)Linkage letter from the fuel supplier; or

    (b)Fuel Supply Agreement between the Bidder and

    Fuel Supplier; or

    (c) Coal Block Allocation letter/In principle

    approval for allocation of captive block from

    Ministry of Coal; or

    (d)Other details submitted by Bidders subject to

    acceptance by the Procurer as sufficient proof for

    demonstration of ability,

    The above proof of fuel arrangement is not

    required in case the fuel to be used by the Bidder

    is imported fuel.

    2.1.5 A The Successful Bidder is required to show

    a firm fuel supply agreement/linkage by the time

    limit specified for fulfilment of Conditions

    Subsequent as mentioned in the PPA”

    11 Hereinafter referred to as ‘RfP’

     Civil Appeal No.1929 of 2020 etc. Page 7 of 57

    4.5 Subsequently, the Standing Linkage Committee (Long

    Term)12 of the Government of India in a meeting dated 2nd August

    2007 approved a firm coal linkage of 2.14 MTPA13 for a 500 MW

    power plant as had been originally envisaged under the 1,000 MW

    (500 MW x 2) configuration.

    4.6 In addition to the said approval, the Ministry of Coal,

    Government of India intimated its decision to allocate Rampia and

    Dip Side Rampia coal blocks in Odisha to a consortium of six

    generating companies including GEL. GEL’s share was 4.6 MTPA

    which corresponded to the project capacity of 1,000 MW. The

    approval came to pass when the Ministry of Coal, Government of

    India confirmed the allotment of the said coal blocks to the

    aforementioned consortium vide letter dated 17th January 2008.

    4.7 In the meanwhile, on 31st October 2007, GEL entered into

    an agreement with PTC in order to enable the latter to participate

    in the bidding process initiated by Haryana Power Generation

    Corporation (Respondent No. 6) by way of the RfP. In pursuit of

    the same, PTC submitted its bid for sale of 300 MW of power to

    the Haryana Utilities and the bid was accepted. Thereafter, vide

    12 Hereinafter referred to as ‘SLC-LT’

    13 Short for ‘million tonnes per annum’

     Civil Appeal No.1929 of 2020 etc. Page 8 of 57

    an order dated 31st July 2008, the Haryana Electricity Regulatory

    Commission (HERC) adopted the tariff successful bidders

    including PTC under Section 63 of the 2003 Act.

    4.8 Subsequently, upon the allocation of the Rampia and Dip

    Side Rampia coal blocks to GEL and the remaining allottees of the

    consortium, Mahanadi Coalfields Limited14 issued a Letter of

    Assurance15 dated 25th July 2008 in favour of GEL for providing

    firm linkage of 2.14 MPTA coal, being the normative requirement

    of one of the power plants having capacity of 500 MW.

    4.9 Thereafter, on 7th August 2008, PTC executed two separate

    Power Purchase Agreements16 with the Dakshin Haryana Bijli

    Vitran Nigam Limited (Appellant No.2) and Uttar Haryana Bijli

    Vitran Nigam Limited (Appellant No.3) for supply of 150 MW of

    power to each, aggregating to 300 MW with the Haryana STU-Inter

    Connection Point being the delivery point. Notably, the fuel type

    proposed to be utilized was Coal India Limited (CIL) coal linkage

    and it was proposed to be sourced from the MCL.

    4.10 As the captive coal from Rampia and Dip Side Rampia had

    not become available, on 12th November 2008, the SLC-LT

    14 Hereinafter referred to as ‘MCL’

    15 Hereinafter referred to as ‘LoA’

    16 Hereinafter referred to as ‘PPA’

     Civil Appeal No.1929 of 2020 etc. Page 9 of 57

    approved the tapering coal linkage of 2.384 MTPA for 550 MW of

    the power project, against the coal block allocation to the

    concerned project. In view of the same, on 8th July 2009, MCL

    issued a LoA to GEL providing tapering linkage as aforementioned

    till captive coal blocks became available.

    4.11 Subsequently, as aforementioned, GKEL and GRIDCO

    executed an amended and restated PPA on 4th January 2011

    which altered the configuration of the thermal power plants and

    their output capacity, while keeping intact the entitlement of

    GRIDCO to 25% gross power generated by GKEL.

    4.12 On 9th November 2011, GKEL entered into a PPA with Bihar

    State Electricity Board, being the predecessor to Bihar Utilities

    for supply of 260 MW of net power/282 MW of gross power. Per

    the said PPA, the fuel source proposed to be utilized was Coal

    India Limited (CIL) coal linkage and the coal was proposed to be

    sourced from MCL and the Rampia and Dip Side Rampia coal

    blocks allocated to GKEL.

    4.13 Thereafter, on 26th March 2013, MCL signed a Fuel Supply

    Agreement17 with GKEL for supply of coal to the power plants (3 x

    17 Hereinafter referred to as ‘FSA’

     Civil Appeal No.1929 of 2020 etc. Page 10 of 57

    350 MW) being 500 MW under normal linkage and 425 MW

    generation capacity covered under long term PPA i.e., an

    aggregate of 1.819 MTPA/18.19 lakh tonnes. The FSA was

    amended from time to time, initially to increase the quantum of

    coal supplied from 1.819 MTPA to 2.0009 MTPA for the same

    capacity of 425 MW and thereafter, the FSA was further amended

    on 18th September 2014 to increase the quantum of coal supplied

    to 2.14 MTPA on account of operationalization of the PPA with

    Bihar Utilities.

    4.14 Subsequently, on 28th August 2013, GKEL entered into

    another independent FSA with MCL for tapering linkage.

    4.15 In the meanwhile, on 23rd April 2013, GKEL preferred

    Petition No. 79/MP/201318 before the CERC against Haryana

    Utilities, being a petition under Section 79 of the 2003 Act read

    with the statutory framework governing the procurement of power

    through the competitive bidding process and Articles 12, 13 and

    17 of the PPA dated 7th August 2008 executed between PTC and

    the Haryana Utilities and the back-to-back PPA dated 12th March

    2009 executed between GEL and PTC for compensation due to

    18 Hereinafter referred to as ‘Petition No. 79’

     Civil Appeal No.1929 of 2020 etc. Page 11 of 57

    force majeure events and Change in Law during the operation

    period. In the said petition, the GKEL sought adjustment of tariff

    on account of events of Change in Law which affected the power

    project during the operation period in order to restore GKEL to the

    same economic position that it would have been in if the

    concerned events had never occurred. It is notable that GRIDCO

    was not made a party to this petition.

    4.16 Soon thereafter, Unit I of the power project achieved

    commercial operation and GKEL began supplying power to

    GRIDCO w.e.f. 30th April 2013. Within a few months, Unit II of the

    power project achieved commercial operation and GKEL

    commenced the supply of power to Haryana Utilities w.e.f. 7th

    February 2014. Subsequently, Unit III of the power project

    achieved commercial operation on 25th March 2014 and thereafter

    GKEL began supplying power to Bihar Utilities w.e.f. 1st

    September 2014.

    4.17 At this stage, it would be apposite to run through the

    quantum of power that was contracted to be delivered under each

    of the long-term PPAs, which are as follows:-

    (a) Supply of 350 MW of gross power (Stage 1: 262.5 MW and

    Stage 2: 87.5 MW) to GRIDCO in terms of PPA dated 28th

     Civil Appeal No.1929 of 2020 etc. Page 12 of 57

    September 2006 (as amended on 4th January 2011, with

    delivery point as Odisha STU Interconnection point).

    (b) Supply of 350 MW of gross power (300 MW net of

    transmission losses and auxiliary consumption) to Haryana

    Utilities based on PPA dated 7th August 2008 and back-toback PPA dated 12th March 2009 executed between GEL and

    PTC.

    (c) Supply of 282 MW of gross power (260 MW net of auxiliary

    consumption) to Bihar State Electricity Board in term of PPA

    dated 9th November 2011, with delivery point as the Bihar

    STU Interconnection point.

    4.18 The CERC vide order dated 3rd February 2016 disposed of

    the Petition No. 79 filed by GKEL in the following terms:-

    (i) At the time of bid submission, the notified rate of royalty on

    coal was Rs. 55+5% of ROM price per tonne. This was

    subsequently increased to an ad-valorem rate of 14% on

    price of coal. The CERC held that GKEL would be entitled to

    compensation for the same from Haryana Utilities.

    (ii) At the time of bid submission, there was no clean energy cess

    on coal. However, this was subsequently introduced by way

    of the Finance Act 2010 whereby statutory cess of Rs. 100 

     Civil Appeal No.1929 of 2020 etc. Page 13 of 57

    per tonne had been levied on coal. This was subsequently

    reduced to Rs. 50 per tonne. The CERC held that GKEL

    would be entitled to recover clean energy cess from Haryana

    Utilities in proportion to the coal consumed for generation

    and supply of electricity to the appellants.

    (iii) At the time of bid submission, there was no excise duty on

    coal. Excise duty @ 6% on the determined sale price of coal

    was introduced by the Finance Act 2012. The CERC held

    that GKEL would be entitled to compensation through

    adjustment in tariff on account of the freshly applicable

    excise duty on coal.

    (iv) Owing to shortfall in the linkage coal and also due to transfer

    of certain quantum of tapering linkage from MCL to Eastern

    Coalfields Limited, GKEL had to import coal and also source

    open market coal. This had led to an additional cost of Rs.

    46.10 crores in the generation of power for the Haryana

    Utilities during the months of February and May to July

    2014. The CERC held that GKEL would be entitled to

    compensation for the same and accordingly set out a

    mechanism for computing the actual additional cost

    incurred in a month to mitigate the shortfall in linkage coal. 

     Civil Appeal No.1929 of 2020 etc. Page 14 of 57

    The actual compensation payable was to be calculated and

    certified by the auditor in terms of the method laid down by

    the CERC.

    (v) At the time of submission of the bid, the pricing of coal was

    based on the UHV19 method which was Rs. 400 per tonne for

    F-grade, run-of-mine coal. Thereafter, the Government of

    India directed a switchover from UHV-based pricing system

    to GCV20-based pricing system. This led to a significant

    increase in price. The resultant impact of the change was an

    increase in cost of Rs. 10.76 crores for a full year. The CERC

    disallowed this claim, holding that any decision affecting the

    price of inputs for generating electricity including coal could

    not be covered under Change in Law.

    (vi) GKEL had also raised claims for increase in rail freight

    charges owing to busy season surcharge and development

    surcharge. CERC disallowed this claim.

    (vii) GKEL also raised claims towards compensation/payment for

    increase in MAT21 rate from 11.33% to 20.01% as brought in

    by the Finance Act, 2012. This claim was also disallowed.

    19 Short for ‘Useful Heat Value’

    20 Short for ‘Gross Calorific Value’

    21 Short for ‘Minimum alternate tax’

     Civil Appeal No.1929 of 2020 etc. Page 15 of 57

    (viii) A claim was raised by GKEL for payment towards the

    increase in VAT22 from 4% to 5%. This claim was disallowed.

    (ix) A claim was also raised for payment/compensation owing to

    increase in water charges, which was disallowed.

    4.19 It is notable that GKEL had preferred a similar petition

    being Petition No. 112/MP/201523 against the Bihar Utilities with

    regard to the PPA executed between the said parties for

    compensation due to Change in Law which impacted revenues

    and costs during the operating period. Vide order dated 7th April

    2017, the CERC disposed of the petition by allowing all such

    claims which fell within the parameters of Change in Law events.

    4.20 Subsequently, in terms of the order dated 3rd February

    2016 passed in Petition No. 79, GKEL raised supplementary bills

    towards compensation for ‘Change in Law’ events as approved by

    the CERC, by pro-rating coal received from various sources for the

    period commencing from February 2014 onwards. The bills were

    accompanied by Form 15, detailed annexures and calculations

    which clearly showed apportionment of firm linkage coal

    corresponding to respective PPA capacities.

    22 Short for ‘Value added tax’

    23 Hereinafter referred to as ‘Petition No. 112’

     Civil Appeal No.1929 of 2020 etc. Page 16 of 57

    4.21 Disputing the supplementary bills raised by GKEL, Haryana

    Utilities wrote to PTC on 22nd September 2016 seeking certain

    clarifications as to whether the bills were as per the order of the

    CERC dated 3rd February 2016. GKEL responded to the letter on

    6th October 2016 wherein it contended that as per CERC’s order,

    it was entitled to claim additional cost incurred during a month

    in respect of imported coal, open market coal and tapering coal or

    any other coal purchased to make up the shortfall in the firm

    linkage coal supplied by MCL.

    4.22 Being dissatisfied with the response, Haryana Utilities

    refused to make payments. To resolve the issue, a meeting was

    held on 25th January 2017, however, the matter could not be

    resolved. In light of the same, it was decided by PTC that the

    supplementary bills raised by GKEL for the period between July

    2016 to November 2016 would be considered to be disputed bills.

    4.23 In order to resolve the issue, another meeting was convened

    between the parties on 24th April 2017 wherein it was jointly

    agreed that a clarificatory petition/review petition would be filed

    before the CERC.

    4.24 Thereafter, GKEL preferred Petition No. 105 before the

    CERC under Section 79(1)(b) and (f) of the 2003 Act read with 

     Civil Appeal No.1929 of 2020 etc. Page 17 of 57

    Articles 11.6 and 17 of the PPA dated 7th August 2008 for the

    recovery of the outstanding amount from the Haryana Utilities

    raised vide supplementary bills.

    4.25 The CERC vide order dated 20th March 2018 disposed of the

    said petition by directing the Haryana Utilities to pay the

    supplementary bills raised by GKEL for the period from July 2016

    to March 2017 along with late payment surcharge as per the

    provisions of the PPA executed between the parties within one

    month. The CERC held, in terms of the previous order dated 3rd

    February 2017 as well as the decision of this Court in Energy

    Watchdog v. Central Electricity Regulatory Commission and

    Others24, GKEL would be eligible for relief for any shortfall in the

    firm linkage and tapering linkage met through import and open

    market coal. To avoid putting GRIDCO and Bihar Utilities at a

    disadvantage, the CERC further directed that the firm and

    tapering linkage coal supplied to GKEL would have to be

    apportioned on a pro rata basis to all the beneficiaries of the

    project and the cost of procurement of coal from alternate sources

    24 (2017) 14 SCC 80

     Civil Appeal No.1929 of 2020 etc. Page 18 of 57

    to meet the shortfall would also be apportioned pro rata based on

    power supplied to beneficiaries.

    4.26 Aggrieved thereby, Haryana Utilities preferred Appeal No.

    135 of 2018 before the learned APTEL. Subsequently, GRIDCO

    preferred Appeal No. 54 of 2019 before the learned APTEL.

    4.27 The learned APTEL vide the common judgment and final

    order dated 20th December 2019 dismissed both the appeals and

    upheld the order of the CERC.

    4.28 Hence, these civil appeals under Section 125 of the 2003

    Act.

    SUBMISSIONS

    5. We have heard Shri M.G. Ramachandran, learned Senior

    Counsel appearing for the appellants, Dr. Abhishek Manu

    Singhvi, learned Senior Counsel and Shri Vishrov Mukherjee,

    learned counsel appearing for Respondent No.1, Ms. Prerna

    Singh, learned counsel appearing for Respondent No.2, Shri Raj

    Kumar Mehta, learned counsel appearing for Respondent No. 4

    and Shri S.B. Upadhyay, learned Senior Counsel appearing for

    Respondent No.5.

    6. Shri Ramchandran, learned Senior Counsel appearing on

    behalf of the Haryana Utilities submitted that from the perusal of 

     Civil Appeal No.1929 of 2020 etc. Page 19 of 57

    the RfP issued by Haryana Utilities in March, 2007 and the bid

    submitted by GKEL on 23rd November 2007 through PTC, it is

    clear that the bidders were required to submit the details with

    regard to fuel arrangement, source of fuel among other

    particulars. It is equally clear that while submitting the bid, GKEL

    had shown the source of fuel to be firm linkage granted by way of

    SLC-LT meeting held on 2nd August 2007. It is further submitted

    that the perusal of PPA dated 7th August 2008 between Haryana

    Utilities and PTC would also show that the PPA was based on firm

    linkage coal from MCL. It is submitted that as against this, the

    PPA dated 9th November 2011, entered into by GKEL with Bihar

    Utilities clearly indicated the sources of fuel as firm linkage as well

    as Rampia and Dip Side of Rampia coal block allotment (tapering

    linkage).

    7. Shri Ramchandran further submitted that FSA as well as the

    LoA in favour of GKEL for the first phase was unit specific. It is

    submitted that FSA becomes operational in proportion to the

    generation covered under long term PPAs. It is submitted that at

    the time when the FSA dated 26th March 2013 was signed, even

    though the linkage was for 500 MW, only 425 MW was considered

    as generation capacity. This was so since the PPAs with Haryana 

     Civil Appeal No.1929 of 2020 etc. Page 20 of 57

    Utilities for 300 MW as well as with GRIDCO for 125 MW were the

    only long term PPAs at that time. Shri Ramchandran further

    submitted that subsequently, when the Bihar PPA became

    operational, the capacity under the FSA vis-à-vis firm linkage was

    modified by specific additional 29.55 MW (out of a total Bihar PPA

    capacity of 260 MW).

    8. Shri Ramchandran contended that the Haryana Utilities

    would be entitled to supply of 300 MW of energy from the firm

    linkage whereas GRIDCO would be entitled to supply of 125 MW

    energy produced using the coal available from the firm linkage. It

    is, therefore, submitted that the Haryana Utilities cannot be

    burdened with the additional cost incurred on account of

    production of coal from the MCL tapering linkage. Shri

    Ramchandran submitted that the difference on account of the use

    of fuel from tapering linkage will have to be borne only by the

    GRIDCO and Bihar Utilities inasmuch as the said coal was used

    for production of power for Unit II of 200 MW and Unit III of 350

    MW. It is, therefore, submitted that both the CERC as well as the

    learned APTEL erred in putting the burden on the Haryana

    Utilities whereas the same should have been apportioned to Bihar

    Utilities and GRIDCO.

     Civil Appeal No.1929 of 2020 etc. Page 21 of 57

    9. Shri Raj Kumar Mehta, learned counsel appearing on behalf

    of GRIDCO submitted that it was the PPA with GRIDCO which

    came to be operationalized first in April 2013. It is submitted that

    even though GRIDCO’s share in the installed capacity of the

    thermal station of GKEL was 25%, the order dated 3rd February

    2016 in Petition No. 79 and order dated 20th March, 2018 in

    Petition No. 105 were passed without impleading GRIDCO. It is

    submitted that GRIDCO was a necessary and proper party as its

    rights were adversely affected. It is submitted that GRIDCO was

    also not impleaded in the appeal being Appeal No. 135 of 2018

    filed by the Haryana Utilities before the learned APTEL. It is

    submitted that on account of the order dated 28th November 2018

    of the learned APTEL, GRIDCO came to be impleaded in the said

    appeal.

    10. Shri Mehta further submitted that the reasoning given by the

    learned APTEL that since GRIDCO’s PPA was Cost Plus Tariff PPA

    under Section 62 of the 2003 Act whereas the proceedings before

    the CERC and the learned APTEL were initiated seeking

    compensation on the grounds of Change in Law with regard to

    Haryana Utilities and Bihar Utilities which fell under Section 63

    of the 2003 Act and therefore, GRIDCO was not necessary party,

     Civil Appeal No.1929 of 2020 etc. Page 22 of 57

    is wholly unsustainable. It is submitted that GKEL had

    specifically prayed for pro rating of linkage coal amongst all the

    three utilities namely GRIDCO, Haryana Utilities and Bihar

    Utilities and as such GRIDCO was a necessary party.

    11. It is submitted that the project sought to be installed by

    GKEL was at the instance of the Government of Odisha. It is

    submitted that the State of Odisha had provided all the necessary

    facilities to GKEL to install the project. It is therefore submitted

    that it is the GRIDCO which had the first right to the power

    generated from the coal made available from the firm linkage.

    12. Dr. Abhishek Manu Singhvi appearing on behalf of the

    respondent No. 1 submitted that the appeals are liable to be

    dismissed on the short ground that they do not raise any

    substantial question of law as is required under Section 125 of

    the 2003 Act. It is further submitted that the order dated 20th

    March 2018 in Petition No. 105 is passed by the CERC on the

    basis of its earlier order dated 3rd February, 2016 in Petition No.

    79. It is submitted that the CERC in Petition No. 79 had clearly

    held that coal supplied to GKEL under linkage by Government of

    India is to be apportioned on pro rata basis to all the three 

     Civil Appeal No.1929 of 2020 etc. Page 23 of 57

    Distribution Companies25 i.e. Haryana Utilities, GRIDCO and

    Bihar Utilities. It is submitted that since the Haryana Utilities had

    not challenged the said order, it was not permissible for them to

    challenge the order passed in Petition No. 105. It is further

    submitted that supply of coal from all the modes of procurement

    has to be considered for the power project inasmuch as allocation

    by Government of India was for the whole project and not specific

    to any particular DISCOM.

    13. Dr. Singhvi further submitted that the concurrent orders

    passed by the CERC and the learned APTEL are equitable orders

    inasmuch as it has been held that coal supplied under the linkage

    is to be apportioned on pro rata basis to all the DISCOMS.

    However, if the contentions of the Haryana Utilities are accepted,

    it will amount to burdening the consumers in the State of Odisha

    and Bihar. It is further submitted that if the contentions of both

    Haryana Utilities and GRIDCO are accepted, it will amount to

    putting the total burden on the consumers in the State of Bihar.

    14. Dr. Singhvi further contended that the attitude of Haryana

    Utilities is of approbation and reprobation. It is submitted that in

    25 Hereinafter referred to as ‘DISCOMS’

     Civil Appeal No.1929 of 2020 etc. Page 24 of 57

    the case of Uttar Haryana Bijli Vitran Nigam Ltd. & Another

    v. Adani Power (Mundra) Limited and Others26, this Court

    noted that after accepting before the CERC that they would adopt

    the methodology as given in the case of GMR-Kamalanga Energy

    Limited v. Dakshin Haryana Bijli Vitran Nigam Ltd.27,

    Haryana Utilities changed their stand subsequently.

    15. In the totality, Dr. Singhvi submitted that the appeals

    deserve to be dismissed.

    16. Shri S.B. Upadhyay, learned Senior Counsel appearing on

    behalf of respondent No. 5 has supported the concurrent orders

    of the CERC and the learned APTEL.

    DISCUSSION AND ANALYSIS

    17. At the outset, it can be noticed that all three DISCOMS agree

    that GKEL is entitled to compensation on account of Change in

    Law event. However, the Haryana Utilities and GRIDCO argued

    that the said liability should not come to them but should instead

    be passed on to the other two. It is only the Bihar Utilities which

    agrees that the liability has to be equally shared by all three

    26 (2023) 14 SCC 736;

    27 (2016) SCC OnLine CERC 43

     Civil Appeal No.1929 of 2020 etc. Page 25 of 57

    DISCOMS in proportion to the energy supplied to them. We find

    it appropriate to deal with both the appeals separately.

    CIVIL APPEAL NO. 1929 OF 2020

    18. Undisputedly, the present appeal filed by Haryana Utilities

    challenges the impugned judgment and final order passed by

    learned APTEL whereby the learned APTEL has upheld the order

    of the CERC. The appeal to this Court has been filed under Section

    125 of the 2003 Act. The perusal of Section 125 shows that the

    appeal is tenable only on the grounds as available under Section

    100 of the Code of Civil Procedure, 190828, as such, it could be

    seen that appeal would be tenable only on a substantial question

    of law.

    19. One of us (B.R. Gavai, J, as he then was) had an occasion to

    deal with a large batch of electricity appeals pertaining to Change

    in Law event. This Court first decided the common issues involved

    in the said batch of appeals in Maharashtra State Electricity

    Distribution Company Limited v. Adani Power Maharashtra

    28 Hereinafter referred to as “CPC”

     Civil Appeal No.1929 of 2020 etc. Page 26 of 57

    Limited and Others29. It would be apposite to refer to following

    paragraphs of the said judgment:

    “118. It could thus be seen that two expert bodies i.e.

    CERC and the learned APTEL have concurrently

    held, after examining the material on record, that the

    factors of SHR and GCV should be considered as per

    the Regulations or actuals, whichever is lower. CERC

    as well as the State Regulatory bodies, after extensive

    consultation with the stakeholders, had specified

    SHR norms in the respective Tariff Regulations. In

    addition, insofar as GCV is concerned, the CEA has

    opined that the margin of 85-100 kcal/kg for a nonpit head station may be considered as a loss of GCV

    measured at wagon top till the point of firing of coal

    in boiler.

    119. In this respect, we may refer to the following

    observations of this Court in Reliance Infrastructure

    Ltd. v. State of Maharashtra [Reliance Infrastructure

    Ltd. v. State of Maharashtra, (2019) 3 SCC 352] :

    (SCC pp. 376-77, paras 38-39)

    “38. MERC is an expert body which is

    entrusted with the duty and function to frame

    regulations, including the terms and

    conditions for the determination of tariff. The

    Court, while exercising its power of judicial

    review, can step in where a case of manifest

    unreasonableness or arbitrariness is made

    out. Similarly, where the delegate of the

    legislature has failed to follow statutory

    procedures or to take into account factors

    which it is mandated by the statute to consider

    or has founded its determination of tariffs on

    29 (2023) 7 SCC 401, hereafter referred to as MSEDCL

     Civil Appeal No.1929 of 2020 etc. Page 27 of 57

    extraneous considerations, the Court in the

    exercise of its power of judicial review will

    ensure that the statute is not breached.

    However, it is no part of the function of the

    Court to substitute its own determination for

    a determination which was made by an expert

    body after due consideration of material

    circumstances.

    39. In Assn. of Industrial Electricity

    Users v. State of A.P. [Assn. of Industrial

    Electricity Users v. State of A.P., (2002) 3 SCC

    711] a three-Judge Bench of this Court dealt

    with the fixation of tariffs and held thus : (SCC

    p. 717, para 11)

    ‘11. We also agree with the High Court [S.

    Bharat Kumar v. State of A.P., 2000 SCC

    OnLine AP 565 : (2000) 6 ALD 217] that

    the judicial review in a matter with

    regard to fixation of tariff has not to be as

    that of an appellate authority in exercise

    of its jurisdiction under Article 226 of the

    Constitution. All that the High Court has

    to be satisfied with is that the

    Commission has followed the proper

    procedure and unless it can be

    demonstrated that its decision is on the

    face of it arbitrary or illegal or contrary to

    the Act, the court will not interfere.

    Fixing a tariff and providing for crosssubsidy is essentially a matter of policy

    and normally a court would refrain from

    interfering with a policy decision unless

    the power exercised is arbitrary or ex

    facie bad in law.’ ”

     Civil Appeal No.1929 of 2020 etc. Page 28 of 57

    **** **** ****

    121. Recently, the Constitution Bench of this Court

    in Vivek Narayan Sharma (Demonetisation Case-5

    J.) v. Union of India [Vivek Narayan Sharma

    (Demonetisation Case-5 J.) v. Union of India, (2023) 3 SCC

    1] has held that the Courts should be slow in interfering

    with the decisions taken by the experts in the field and

    unless it is found that the expert bodies have failed to take

    into consideration the mandatory statutory provisions or

    the decisions taken are based on extraneous

    considerations or they are ex facie arbitrary and illegal, it

    will not be appropriate for this Court to substitute its

    views with that of the expert bodies.”

    20. It can thus be seen that this Court has held that when

    various expert bodies like the CERC, the APTEL and the Central

    Electricity Authority after considering the relevant material on

    record have taken a particular view, the Court should be slow in

    interfering with the decisions taken by them. It has been held that

    unless the Court finds that the expert bodies have failed to take

    into consideration the mandatory statutory provisions or if their

    decisions are based on extraneous considerations or they are ex

    facie arbitrary and illegal, it will not be appropriate for this Court

    to substitute its views with that of the expert bodies.

    21. After deciding the common issues involved in the batch of

    electricity appeals in the case of MSEDCL (supra), this Court

     Civil Appeal No.1929 of 2020 etc. Page 29 of 57

    considered various additional issues involved in individual

    matters pertaining to the question of Change in Law event. One

    such case was GMR Warora Energy Limited v. Central

    Electricity Regulatory Commission (CERC) and Others30. This

    Court in the said case observed thus:

    “VI. Epilogue

    171. Before we part with the judgment, we must note

    that we have come across several appeals in the

    present batch which arise out of concurrent findings

    of fact arrived at by two statutory bodies having

    expertise in the field. We have also found that in

    some of the matters, the appeals have been filed only

    for the sake of filing the same. We also find that

    several rounds of litigation have taken place in some

    of the proceedings.

    172. Recently, this Court in Maharashtra State

    Electricity Distribution Co. Ltd. v. Adani Power

    Maharashtra Ltd. [Maharashtra State Electricity

    Distribution Co. Ltd. v. Adani Power Maharashtra

    Ltd., (2023) 7 SCC 401] has noted that one of the

    reasons for enacting the Electricity Act, 2003 was

    that the performance of the Electricity Boards had

    deteriorated on account of various factors. The

    Statement of Objects and Reasons of the Electricity

    Act, 2003 would reveal that one of the main features

    for enactment of the Electricity Act was delicensing

    of generation and freely permitting captive

    generation. In the said judgment, we have recorded

    the statement of the learned Attorney General made

    in Energy Watchdog [Energy Watchdog v. CERC,

    30 (2023) 10 SCC 401

     Civil Appeal No.1929 of 2020 etc. Page 30 of 57

    (2017) 14 SCC 80 : (2018) 1 SCC (Civ) 133] that the

    electricity sector, having been privatised, had largely

    fulfilled the object sought to be achieved by the

    Electricity Act. He had stated that delicensed

    electricity generation resulted in production of far

    greater electricity than was earlier produced. The

    learned Attorney General had further urged the

    Court not to disturb the delicate balance sought to

    be achieved by the Electricity Act i.e. that the

    producers or generators of electricity, in order that

    they set up power plants, be entitled to a reasonable

    margin of profit and a reasonable return on their

    capital, so that they are induced to set up more and

    more power plants. At the same time, the interests of

    the end-consumers also need to be protected.

    173. However, we find that, in spite of this position,

    litigations after litigations are pursued. Though the

    concurrent orders of statutory expert bodies cannot

    be said to be perverse, arbitrary or in violation of the

    statutory provisions, the same are challenged.”

    22. It will also be appropriate to refer to the following

    observations made by this Court in paragraph 181 of the said

    judgment:

    181. It is further to be noted that the appeal to this

    Court under Section 125 of the Electricity Act, 2003

    is only permissible on any of the grounds as specified

    in Section 100 of the Code of Civil Procedure, 1908.

    As such, the appeal to this Court would be

    permissible only on substantial questions of law.

    However, as already observed herein, even in cases

    where well-reasoned concurrent orders are passed by

    the Electricity Regulatory Commissions and the

    learned APTEL, the same are challenged by 

     Civil Appeal No.1929 of 2020 etc. Page 31 of 57

    the DISCOMS as well as the generators. On account of

    pendency of litigation, which in some of the cases in

    this batch has been more than 5 years, non-payment

    of dues would entail paying of heavy carrying cost to

    the generators by the DISCOMS, which, in turn, will be

    passed over to the end-consumer. As a result, it will

    be the end-consumer who would be at sufferance. We

    are of the opinion that such unnecessary and

    unwarranted litigation needs to be curbed.

    23. This Court in clear terms noted that the appeal under

    Section 125 of the 2003 Act is only permissible on any of the

    grounds as specified in Section 100 of the CPC. As such, it is

    permissible only on substantial questions of law. This Court

    observed that even in cases where well-reasoned concurrent

    orders are passed by the Electricity Regulatory Commissions and

    the learned APTEL, the same are challenged by DISCOMS as well

    as the generators. It has been observed that on account of

    pendency of litigation which in some of the cases in the said batch

    had been for more than 5 years, non-payment of dues would

    result in paying of heavy carrying cost to the generators by the

    DISCOMS. It was observed that, in turn, this heavy cost is passed

    over to the end-consumers who are the ultimate sufferers. The

    Court had in unequivocal terms observed that such unnecessary

    and unwarranted litigations need to be curbed. In spite of the 

     Civil Appeal No.1929 of 2020 etc. Page 32 of 57

    aforesaid observations, this Court is flooded with such kind of

    litigations.

    24. In the present matter, there are concurrent findings of facts

    not only in the impugned judgment passed by the learned APTEL

    and the order passed by the CERC in Petition No. 105, but also in

    the order dated 3rd February 2016 passed by the CERC in Petition

    No. 79 during the first round of litigation. The Court will,

    therefore, have to be very slow in interfering with the said findings

    of fact. Unless it is found that the findings are perverse, arbitrary

    or in violation of the statutory provisions, it will not be permissible

    for this Court to interfere with the same.

    25. Though, it was sought to be argued on behalf of the

    appellants that in the present case question of interpretation of

    the documents arises and the same question would fall in the

    category of substantial question of law, we do not find that any

    substantial question of law arises for consideration in the present

    appeal.

    26. Be that as it may, since the present appeal is pending since

    2020 having been admitted on 3rd June 2020, we propose to deal

    with the merits of the matter.

     Civil Appeal No.1929 of 2020 etc. Page 33 of 57

    27. It will be relevant to refer to the Petition No. 79 filed by GKEL

    before the CERC. GKEL contended in the said petition that it had

    entered into three long term PPAs as under:

    a) Supply of 350 MW gross power (Stage 1: 262.5 MW and Stage

    2: 87.5 MW) to Grid Corporation of Odisha Limited (GRIDCO)

    in terms of PPA dated 28th September 2006 (as amended on 4th

    January 2011 with delivery point as Odisha STU

    interconnection point).

    b) Supply of 282 MW gross power (260 MW net of auxiliary

    consumption) to Bihar State Electricity Board in terms of PPA

    dated 9th November 2011, with delivery point as the Bihar STU

    interconnection point.

    c) Supply of 350 MW gross power (300 MW net of transmission

    losses and auxiliary consumption) to Haryana Discoms based

    on the competitive bidding through back-to-back

    arrangements:

    (i) The PPAs dated 7th August, 2008 entered into between

    PTC India Limited and Haryana Discoms with delivery

    point as Haryana STU bus bar;

     Civil Appeal No.1929 of 2020 etc. Page 34 of 57

    (ii) Back-to-back PPA dated 12th March, 2009 between GMR

    Energy Limited (holding company of GKEL) and PTC India

    Limited.

    28. The petition was filed by GKEL seeking relief on account of

    Change in Law on various grounds. One of the grounds was with

    regard to deviations from the New Coal Distribution Policy, 2007

    (the NCDP) and changes in coal distribution policy of the

    Government of India and Coal India Limited.

    29. The issue with regard to firm linkage and tapering linkage in

    favour of GKEL and allocation of captive coal mines in favour of a

    consortium of six companies including GKEL also fell for

    consideration in the said petition. It will also be relevant to refer

    to the following submissions of GKEL recorded by the CERC:

    “6…..

    (a) As regards the firm linkage, the Standing

    Linkage Committee (Long Term) (SLC-LT)

    approved a coal linkage for the project on 2.8.2007

    which was communicated to the petitioner on

    24.9.2007. Letter of Assurance (LOA) was issued

    in favour of GEL on 25.7.2008 for 2.14 MTPA of

    coal for 500 MW capacity of the Power Project.

    LOA was transferred in the name of GEKL by

    Ministry of Coal on 17.2.2011.

    (b) On 6.11.2007, Ministry of Coal conveyed its

    decision to allocate Rampia and Dip Side Rampia 

     Civil Appeal No.1929 of 2020 etc. Page 35 of 57

    coal blocks in Odisha to a consortium comprising

    of GEL and five other companies (M/s Sterlite

    Energy Ltd, M/s Mittal Steel India Limited, M/s

    Lanco Group Limited, M/s Navbharat Power

    Private Ltd, and M/s Reliance Energy Ltd).

    Ministry of Coal vide its letter dated 17.1.2008

    made the allocation under Section 3(3)(a) (iii) of

    the Coal Mines (Nationalisation) Act, 1973 for

    captive use in the specified end use projects by the

    allocatees. A joint venture company in the name

    of Rampia Coal Mine and Energy Private Limited

    was formed by the allocattees to carry out coal

    mining in early 2008.

    (c) On 12.11.2008, SLC-LT approved tapering coal

    linkage for the power project based on the

    recommendation of CEA that development of coal

    block allocated to GEL alongwith others was likely

    to take time. On 8.7.2009, LOA was issued for

    tapering coal linkage of 2.384 MTPA for 550 MW

    capacity in favour of GEL till coal from Rampia

    coal block was available. LOA was transferred in

    the name of GEKL by Ministry of Coal on

    17.2.2011.

    (d) On 26.3.2013, Mahanadi Coalfield Limited

    (MCL) signed the Fuel Supply Agreement with

    GEKL for supply of 1.819 MTPA of coal per

    annum.

    7. According to the petitioners, the financial

    closure of the power project was achieved on

    29.5.2009 and the petitioners went ahead with

    execution of the project with the expected COD of

    Unit 1 as 25.4.2013 as on the date of filing the

    present petition.

     Civil Appeal No.1929 of 2020 etc. Page 36 of 57

    30. In the said petition, the Haryana Utilities had raised a

    preliminary objection on the ground that impact of Change in Law

    can be ascertained only during the operation period, i.e. after the

    power project has been declared under commercial operation.

    The CERC with following observations rejected the said

    preliminary objection:

    “17. According to the Haryana Discoms, the

    present petition is premature since the impact of

    "Change in Law" can be ascertained only during

    the operation period, that is, after the power

    project has been declared under commercial

    operation. In this regard, it is noted that 1st Unit

    of the power project was commissioned on

    30.4.2013 and has been taken note of by the

    Haryana Power Purchase Centre (which is

    responsible for purchase of power on behalf of

    the Haryana Discoms) in its letter dated

    20.5.2013. Subsequently, in its letter dated

    8.8.2013, HPCC in response to the petitioner's

    offer contained in the letter dated 4.7.2013,

    consented for scheduling of power from the

    Project. The 2nd Unit achieved COD on

    12.11.2013 and supply to the Haryana Discoms

    commenced on 7.2.2014. 3rd Unit achieved COD

    on 25.3.2014. Since all units of the power project

    have achieved COD, the operating period has

    already commenced, making the petitioners

    eligible for compensation under Change in Law

    during the operating period. The objections of

    Haryana Discoms on this count are disposed of

    accordingly.”

     Civil Appeal No.1929 of 2020 etc. Page 37 of 57

    31. The perusal of paragraphs 54, 55 and 73 of the order passed

    by the CERC dated 3rd February 2016 would reveal that it devised

    a formula for computing the Energy Charge Rate31 which required

    pro rata allocation of coal among all three DISCOMS. It is

    pertinent to note that the Haryana Utilities did not challenge the

    said order and paid the amounts due in terms of the said order

    till June 2016. The Haryana Utilities had accepted the bills which

    were submitted in pursuance to the order passed in Petition No.

    79 and a total of about Rs. 140 crores were paid till June, 2016.

    However, in September 2016, the Haryana Utilities raised the

    issue of pro rata allocation of coal. After due deliberations,

    Haryana Utilities and GKEL agreed that the latter would approach

    the CERC for clarification in this regard. As such, GKEL filed

    Petition No. 105. The argument of Haryana Utilities in the said

    petition was that coal received under FSA dated 26th March 2013

    should be considered for Haryana Utilities only and shortfall in

    supply thereof should be met through imported, open market or

    tapering coal. However, it was submitted on behalf of GKEL that

    the allocation of coal was made for the entire plant of GKEL and

    31 Hereinafter referred to as ‘ECR’

     Civil Appeal No.1929 of 2020 etc. Page 38 of 57

    therefore, coal shall be used proportionately for generation and

    supply of power to all beneficiaries namely GRIDCO, Haryana

    Utilities and Bihar Utilities.

    32. The CERC vide order dated 20th March 2018 passed in

    Petition No. 105 considered the rival submissions as under:

    “31. On perusal of the documents on record, it

    emerges that the Petitioner was granted firm

    linkage of 500 MW and linkage from captive coal

    mine for 550 MW for its plant which was envisaged

    to have capacity of 1050 MW(3x350 MW),

    Subsequently, LOA dated 25.7.2008 was issued

    for firm linkage of 2.14 MTPA for 500 MW and LOA

    dated 8.7.2009 was issued for tapering linkage of

    2.384 MTPA for 550 MW by Ministry of Coal.

    Perusal of the Standing Linkage Committee (SLC)

    Minutes of Meeting dated 14.2.2012 reveals that

    the tapering linkage of 2.384 MTPA was allocated

    to the Petitioner for all three beneficiaries i.e.

    GRIDCO, Bihar Discoms and Haryana Discoms.

    The Committee noted that in some cases like GMR

    Kamalanga Energy Ltd., two separate LoAs were

    recommended by the SLC (LT) in different

    meetings, due to change in the

    configuration/capacity of the unit. The 2nd LoA

    was recommended by the SLC (LT) for the

    remaining capacity arising out of the changed

    configuration. On the recommendation of SLC

    (LT), the LoAs dated 25.7.2008 and 8.7.2009 were

    issued to the Petitioner for 500 MW and 550 MW

    respectively to meet the coal requirement for the

    entire capacity of 1050 MW.

     Civil Appeal No.1929 of 2020 etc. Page 39 of 57

    32. FSA dated 26.3.2013 was entered into by the

    Petitioner with Mahanadi Coalfield Limited for 500

    MW of firm linkage coal. The Tapering Linkage

    FSA with MCL was signed on 20.5.2014 and

    Tapering linkage FSA with ECL was signed on

    29.5.2014. Paras 4.1.1 and 4.2 of the FSA dated

    26.3.2013 provide as under:

    "4.1.1 The Annual Contracted Quantity of

    Coal agreed to be supplied by the Seller and

    undertaken to be purchased by the

    Purchaser, shall be 18.19 lakh Tes. Per Year

    from the Seller's mines and/or from import,

    as per Schedule I. For part of Year, the ACQ

    shall be prorated accordingly. The ACQ shall

    be in proportion of the percentage of

    Generation covered under long term Power

    Purchase Agreements executed by the

    Purchaser with the DISCOMs either directly

    or through PTC(s) who has/have signed the

    back to back long term PPA(s) with

    DISCOMs. Whenever, there is any change in

    the percentage of PPA(s), corresponding

    change in ACQ shall be effected through a

    side agreement. Such changes shall be

    allowed to be made only once in a year and

    shall be made effective only from the

    beginning of the next quarter. However, in no

    case ACQ should exceed the LOA quantity as

    mentioned in Schedule I.

    4.2. The total quantity of coal supplied

    pursuant to this Agreement is meant for use

    at Power Plant (3X350 MW), 500 MW under

    Normal Linkage (425 MW generation

    capacity covered under long term PPA).

    Located at Village-Kamalanga, Dt. 

     Civil Appeal No.1929 of 2020 etc. Page 40 of 57

    Dhenkanal, Odhisha as listed in Schedule I.

    The Purchaser shall not sell/divert and/or

    transfer the Coal to any third party for any

    purpose whatsoever and the same shall be

    treated as material breach of Agreement, for

    which the Purchaser, shall be fully

    responsible and each act shall warrant

    suspension of coal supplies by the Seller in

    terms of Clause 14.1 (b)."

    It is evident from the above provisions of the FSA

    that the total quantum of coal supplied pursuant

    to the FSA is meant for use at the power plant

    (3x350 MW) of the Petitioner. Further, ACQ would

    be in proportion to the percentage of generation

    covered under long term PPAs either with the

    DISCOMs directly or through PTC which have

    been signed by the Petitioner. Therefore, the FSA

    cannot be for a particular PPA as contended by

    HPPC. As on the date of the FSA, only 425 MW

    were to be operationalised under long term PPAs

    with PTC/Haryana DISCOMs and GRIDCO and

    accordingly, only 425 MW covered under the long

    term PPAs was mentioned in the FSA. The FSA

    further provides that whenever there is any

    change in the percentage of PPAs, corresponding

    changes in the ACQ shall be effected through side

    agreements. The FSAs for the tapering linkage

    were signed with MCL on 20.5.2014 and with ECL

    on 29.5.2014. These FSAs were signed before the

    commencement of supply under Bihar PPA. The

    Petitioner was receiving 2.58 MTPA of coal from

    both firm and tapering linkage to meet the

    requirement for 618 MW and after

    operationalization of Bihar PPA, the Petitioner

    received 3.63 MTPA of coal to meet the

    requirement of 905 MW. Therefore, any shortfall 

     Civil Appeal No.1929 of 2020 etc. Page 41 of 57

    in the firm linkage as well as tapering linkage met

    through import and open market coal shall be

    eligible for relief under the Change in law in the

    light of the order dated 3.2.2016 and the Hon'ble

    Supreme Court's judgment in Energy Watchdog

    case.

    33. In the light of the above discussion, it cannot

    be inferred from the language of para 48 of the

    order dated 3.2.2016 that the requirement of

    Haryana PPA shall be met from the firm linkage

    under the FSA dated 26.3.2013 and shortfall

    thereof shall be met through import and open

    market coal. Such an interpretation goes against

    the coal allocation by Ministry of Coal to power

    plant of the Petitioner as a whole and will put the

    GRIDCO PPA and Bihar PPA at a disadvantage visa-vis Haryana PPA. In fact, the Commission in

    para 73 (b) of the order dated 3.2.2016 in Petition

    No. 79/MP/2013 had observed as under:

    “73……

    (b) The additional cost incurred in a

    month due to shortage of linkage coal

    shall be computed on ex-bus scheduled

    energy and shall be pro-rated

    corresponding to the scheduled

    generation for Haryana Discoms as per

    methodology given in para 56 above."

    Therefore, in light of the allocation of firm as well

    as tapering linkage for all three beneficiaries and

    our order dated 3.2.2016 in Petition No.

    79/MP/2013, the firm and tapering linkage coal

    supplied to the Petitioner has to be apportioned on 

     Civil Appeal No.1929 of 2020 etc. Page 42 of 57

    pro rata basis to all beneficiaries of the project and

    the cost of procurement of coal from alternate

    sources to meet the shortfall of firm and tapering

    linkage coal has also to be apportioned pro rata

    based on power supplied to these beneficiaries.

    Accordingly, the contention of Haryana Discoms

    to appropriate the coal supplied under firm

    linkage towards the capacity being supplied to

    them instead of pro-rata apportionment to all the

    beneficiaries is not correct. The order dated

    3.2.2016 has to be read in its entirety and HPPC

    is not correct to pick up an observation in para 48

    of the said order to claim that Its liability is limited

    to imported/open market coal for the shortage in

    firm linkage coal only. In our view, the Petitioner

    has correctly apportioned the linkage coal to

    Haryana Discoms proportionate to the capacity

    being supplied to them and has issued

    Supplementary Bills in accordance with the

    formula devised in order dated 3.2.2016 in

    Petition No. 79/MP/2013. Accordingly, we direct

    the respondents to pay the supplementary bills

    raised by the Petitioner for the period from July,

    2016 to March, 2017 along with late payment

    surcharge as per the provisions of the PPA within

    one month from the date of issue of the order.”

    33. The said order came to be challenged by the Haryana

    Utilities. However, at the instance of the learned APTEL, GRIDCO

    came to be impleaded as party respondent in the appeal filed by

    the Haryana Utilities. Subsequently, GRIDCO also filed its own

    appeal before the learned APTEL. It was sought to be contended 

     Civil Appeal No.1929 of 2020 etc. Page 43 of 57

    on behalf of the Haryana Utilities that the order passed in Petition

    No. 105 was beyond the order dated 3rd February 2016. Rejecting

    the said contention, the learned APTEL by a well-reasoned

    judgment and order observed thus:

    “8.16 The Appellants contention that the Impugned

    Order has gone beyond Order dated 03.02.2016 is

    incorrect. It is evident from Paragraph 33 of the

    Impugned Order that CERC has merely reiterated its

    earlier Order and upheld the bills raised by GKEL in

    terms of Order dated 03.02.2016 in Petition No.

    79/MP/2013.

    Coal supply to Plant as whole and not Procurer

    Specific

    8.17 GKEL had quoted tariff for Haryana PPAs

    considering coal availability for the Project from

    linkage coal and its own Captive Coal blocks based

    on

    (a) SLC-LT approval dated 02.08.2007 for 500 MW;

    and

    (b) Ministry of Coal decision dated 06.11.2007 to

    allocate Rampia and Dip side Rampia coal blocks to

    GKEL.

    8.18 At the time of bid submission for Haryana, the

    SBD did not permit inclusion of different sources of

    coal - linkage, captive etc. Therefore, GKEL had cited

    linkage from CIL/MCL. Use of coal from the Captive

    Coal block was envisaged for the entire Plant as

    evident from the allocation letter dated 17.01.2008

    wherein GKEL share of coal reserves is 138 MT @ 4.6 

     Civil Appeal No.1929 of 2020 etc. Page 44 of 57

    MT for 30 years to meet coal requirement of the

    Project as a whole.

    8.19 Coal supply was to the Project as a whole and

    not Procurer Specific is supported by:-

    (a) The SLC minutes dated 14.02.2012 clearly state

    that the tapering linkage coal of 2.384 MTPA is to be

    utilized for all three PPAs with GRIDCO, Haryana and

    Bihar Discoms.

    (b) Clause 4.2 of the FSA dated 26.03.2013 signed

    with MCL clearly states that:-

    "the total quantity of coal supplied pursuant

    to this Agreement is meant for use at Power

    Plant (3x350 MW), 500 MW under Normal

    Linkage (425 MW generation capacity

    covered under long term PPA)."

    8.20 It is submitted that LoA and FSA are for the

    station and never for a particular PPA as contended

    by the Appellants. Further, the Appellant's

    contention that the apportionment of coal (from firm

    linkage) is to be done proportionally between the

    Appellants (300 MW), GRIDCO (150 MW) and Bihar

    (29.55 MW) is erroneous. It is submitted that the enduse stated in these documents is for the Station/

    Plant. This was confirmed by MCL in terms of letter

    dated 02.05.2018 which stated that the Coal is

    released for the total PPA capacity and not bifurcated

    on the basis of individual PPAs.

    8.21 In terms of Clause 4.1 of the FSA, the ACQ shall

    be in proportion of the percentage generation covered

    under long term PPAs with Discoms. The relevant

    portion of Clause 4.1 is reproduced below:-

     Civil Appeal No.1929 of 2020 etc. Page 45 of 57

    "4.1.1... The ACQ shall be in proportion of the

    percentage of Generation covered under long

    term Power Purchase Agreements executed by

    the Purchaser with the DISCOMs either

    directly or through PTC(s) who has/ have

    signed the back to back long term PPA(s) with

    DISCOMS."

    It is only commencement of supply of coal which is

    linked to commencement of supply under the PPA.

    For example, if supply of power to Bihar commenced

    before Haryana, the ACQ would have been

    allocated/operationalized similarly.

    8.22 In view of the above, contention of Haryana that

    the tapering linkage granted in relation to coal block

    cannot be linked to 300 MW is wrong. In fact, the

    linkage coal/ coal block or tapering linkage are

    allocated for the station and to be utilized for all three

    PPAs. In fact, allocating coal under the FSA to

    Haryana Discoms to the exclusion of Bihar and

    GRIDCO will be contrary to the provisions of the FSA.

    8.23 As brought out above, the allocation of coal was

    for the Project as a whole and not Procurer/PPA wise.

    This is evident from the following:-

    (a) LOAs dated 25.07.2008 and 08.07.2009 were for

    the plant as a whole.

    (b) Allocation letter dated 17.01.2008 for the Captive

    Coal mine is for 4.6 MT which is sufficient for 1050

    MW, being the installed capacity of the Project.

    (c) Minutes of the SLC-LT dated 14.02.2012 note that

    the entire linkage (firm and tapering) is for all the 3

    PPAs.

     Civil Appeal No.1929 of 2020 etc. Page 46 of 57

    (d) Letter dated 02.05.2018 issued by Mahanadi

    Coalfields Limited ("MCL") states that CIL and its

    subsidiaries had allocated coal to the Project on prorata basis vis-à-vis the operational capacities and not

    on basis of procurers. The letter specifically states

    that "in case of multiple PPAs, coal is released to the

    IPPs considering the total PPA capacity and not

    bifurcated on the basis of individual PPAs". The

    aforesaid only confirms the provision of clause 4.1.1

    of the FSAs which also talks of allocation of coal on

    pro-rata basis to long term PPAs executed by the

    Discoms directly through PTC.

    8.24 If the Appellant's contention is upheld, it will

    lead to an anomalous situation wherein GRIDCO and

    Bihar Discoms will end up cross-subsidizing supply

    of power to Haryana Discoms. It is submitted that the

    Ld. Central Commission has rightly allowed pro-rata

    allocation of linkage and alternate coal so as to

    ensure that the impact is equally apportioned.

    8.25 Since the allocation is not PPA specific,

    allocation of coal to one procurer to the exclusion of

    others will be contrary to the terms of such allocation.

    8.26 Further, such action will also be contrary to

    Article 14 of the Constitution of India since it will

    result in equals being treated unequally.”

    34. It could thus be seen that the present appeal challenges the

    concurrent findings arrived at by the CERC on two different

    occasions and the learned APTEL in the impugned judgment. The

    perusal of the aforesaid judgment and orders would reveal that

    they are based upon interpretation of various documents and 

     Civil Appeal No.1929 of 2020 etc. Page 47 of 57

    considering the following factual aspects with respect to fuel

    arrangements for the Project:

    (i) The original SLC-LT allocation dated 2nd August 2007

    for firm linkage was made prior to the Haryana PPA;

    (ii) Letter dated 6th November 2007 issued by Ministry of

    Coal intimating its decision to allocate Rampia and Dip

    Side Rampia coal blocks in Odisha to a consortium

    comprising of GKEL and five other allotees;

    (iii) Allocation letter dated 17th January 2008 for the captive

    coal mine is for 4.6 MT which is sufficient for 1050 MW,

    being the installed capacity of the Project; and

    (iv) SLC-LT minutes dated 14th February 2012 noted that

    the firm linkage capacity was intended for Odisha,

    Bihar and Haryana.

    35. It will also be relevant to refer to letter dated 7th February

    2022 issued by MCL in response to the clarification sought by

    GKEL on the letters dated 2nd May 2018 and 22nd June 2021 of

    MCL with regard to supply of coal to GKEL under FSA dated 26th

    February 2013. The relevant extracts of the said letter are as

    under:

     Civil Appeal No.1929 of 2020 etc. Page 48 of 57

    “As per the provision of FSA dated 26/03/2013, Annual

    Contracted Quantity (ACQ) under FSA is in proportion

    to the percentage of Generation covered under long

    term Power Purchase Agreement(s) executed by the

    Purchaser (IPP) with DISCOMs against the total LOA

    quantity. In case of multiple PPAs, coal is allocated/

    released as per the ACQ against the total PPA capacity

    and not segregated on the basis of any specific PPA. The

    same was clarified vide MCL's letter dated 02.05.2018.

    It is pertinent to mention that letter dated of

    22/06/2021 of MCL was issued to all concerned

    DISCOMs, with whom M/s GKEL has signed PPA, for

    the purpose of intimating the DISCOMs the quantum

    of coal procured by M/s GKEL under FSA from the

    sources of MCL to ensure proper utilization of coal. The

    said letter indicates the overall, quantity of coal

    supplied for all the PPAs.”

    36. As mentioned earlier, after deciding the common issues

    involved in a batch of electricity appeals in the case of MSEDCL

    (supra), this Court decided various individual matters involving

    additional issues. Another such matter was Uttar Haryana Bijli

    Vitran (supra). It would be pertinent to note that the Haryana

    Utilities had approached this Court challenging the concurrent

    judgment and order passed by learned APTEL dated 3rd November

    202032 and CERC dated 31st May 201833.

    32 2020 SCC OnLine APTEL 92

    33 2018 SCC OnLine CERC 411

     Civil Appeal No.1929 of 2020 etc. Page 49 of 57

    37. In the said proceedings Adani Power (Mundra) Ltd.34 had

    filed Petition No. 97/MP/201735 before the CERC pursuant to the

    orders passed by this court in Energy Watchdog (supra). The

    CERC vide order dated 31st May 2018 had allowed the said

    petition and directed the working out of the relief. It will be

    relevant to refer to the following paragraphs of the Uttar Haryana

    Bijli Vitran (supra):

    48. The grievance of Haryana Utilities is that the

    methodology for granting benefit on account of the

    change in law adopted by CERC and affirmed by the

    learned APTEL is contrary to the one which was

    previously arrived at in the earlier cases of GMR, DB

    Power, etc.

    49. Perusal of the order passed by the

    learned APTEL would reveal that AP(M)L had

    proposed a methodology based on the methodology

    approved by CERC in the GMR-Kamalanga Energy

    Ltd. v. Dakshin Haryana Bijli Vitran Nigam

    Ltd. [GMR-Kamalanga Energy Ltd. v. Dakshin

    Haryana Bijli Vitran Nigam Ltd., 2016 SCC OnLine

    CERC 43] considering the quoted tariff under the

    PPAs as the base.

    50. The learned APTEL had referred to the record of

    proceedings of CERC dated 10-8-2017, which read

    thus : (Uttar Haryana Bijli Vitran Nigam case [Uttar

    Haryana Bijli Vitran Nigam Ltd. v. Adani Power

    (Mundra) Ltd., 2020 SCC OnLine APTEL 92] , SCC

    OnLine APTEL para 7.3)

    34 Hereinafter referred to as AP(M)L

    35 Hereinafter referred to as ‘Petition No. 97’

     Civil Appeal No.1929 of 2020 etc. Page 50 of 57

    “7.3. … (a) … ‘3. In response to the

    Commission's query as to whether the

    methodology adopted by the petitioner in the

    light of the methodology given in GMR

    case [GMR-Kamalanga Energy

    Ltd. v. Dakshin Haryana Bijli Vitran Nigam

    Ltd., 2016 SCC OnLine CERC 43] is

    acceptable to Haryana Utilities, learned

    counsel replied in the positive.’ ”

    (emphasis in original)

    51. The learned APTEL had also referred to the order

    of CERC dated 28-9-2017 [Adani Power Ltd. v. Uttar

    Haryana Bijli Vitaran Nigam Ltd., 2017 SCC OnLine

    CERC 305] in IA No. 57 of 2017 in Petition No.

    97/MP/2017, which reads thus : (Uttar Haryana

    Bijli Vitran Nigam case [Uttar Haryana Bijli Vitran

    Nigam Ltd. v. Adani Power (Mundra) Ltd., 2020 SCC

    OnLine APTEL 92] , SCC OnLine APTEL para 7.3)

    “7.3. … (b) … ‘7. … Haryana Utilities who is

    the only respondent has not objected to the

    calculation made by the applicant.’ ”

     (emphasis in original)

    52. The learned APTEL had also referred to the order

    dated 3-12-2018 [Uttar Haryana Bijli Vitran Nigam

    Ltd. v. Adani Power (Mundra) Ltd., 2018 SCC OnLine

    CERC 237] passed by CERC in review petition

    bearing No. 24/RP/2018, which reads thus : (Uttar

    Haryana Bijli Vitran Nigam case [Uttar Haryana Bijli

    Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd.,

    2020 SCC OnLine APTEL 92] , SCC OnLine APTEL

    para 7.4)

    “7.4. … ‘25. … It is apparent from the above

    that the Commission, after due

    consideration of the submissions of the

    Adani Power and Prayas had consciously 

     Civil Appeal No.1929 of 2020 etc. Page 51 of 57

    decided on the methodology for

    computation of relief due to shortage of

    domestic coal under change in law for the

    period from 1-4-2013 to 31-3-2017 in para

    46 of the impugned order [Adani Power

    (Mundra) Ltd. v. Uttar Haryana Bijli Vitran

    Nigam Ltd., 2018 SCC OnLine CERC 411]

    . The review petitioners had not suggested

    any methodology of calculation of the relief

    due to shortage of domestic coal. On the

    other hand, the review petitioners in their

    reply dated 28-7-2017 in Petition No.

    97/MP/2017 had stated that “the reliance

    to the decision of GMR is wholly

    inappropriate”. The review petitioners are

    now suggesting an alternative formula for

    computation of the relief under change in

    law. As already reiterated in the earlier part

    of the order, the review cannot be used for

    substitution of a view already taken with a

    new view. Therefore, the review on the

    ground is not maintainable.’ ”

    53. We find that Haryana Utilities are indulging into

    approbation and reprobation. They cannot be

    permitted to blow hot and cold at the same time.

    After accepting before CERC that they would adopt

    the methodology as given in GMR-Kamalanga

    Energy [GMR-Kamalanga Energy Ltd. v. Dakshin

    Haryana Bijli Vitran Nigam Ltd., 2016 SCC OnLine

    CERC 43] , it would not be appropriate, in our view,

    on the part of the appellants, which are, after all,

    instrumentalities of the State, to change its stand

    after final orders are passed by CERC.”

     Civil Appeal No.1929 of 2020 etc. Page 52 of 57

    38. It could thus clearly be seen that the learned APTEL had

    referred to the record of proceedings of the CERC dated 10th

    August 2017 wherein to the Commission’s query as to whether the

    methodology adopted by the petitioner in the light of the

    methodology given in GMR Kamalanga (supra) was acceptable to

    Haryana Utilities, learned counsel replied in the positive. The

    learned APTEL also referred to the order of the CERC dated 28th

    September 201736 in IA No. 57 of 2017 in Petition No. 97 wherein

    Haryana Utilities had not objected to the calculation made by the

    applicant. It could further be seen that the learned APTEL had also

    referred to the order dated 3rd December 201837 passed by the

    CERC in Review Petition No. 24/RP/2018 filed by the Haryana

    Utilities against the order dated 31st May 2018 of the CERC. The

    CERC in the said review petition referred to the affidavit filed by

    the Haryana Utilities stating that ‘the reliance to the decision of

    GMR is wholly inappropriate”. The learned APTEL, observing that

    the Review Petitioners are now suggesting an alternative formula

    for computation of the relief under change in law, rejected the

    review petition.

    36 (2017) SCC OnLine CERC 305

    37 (2018) SCC OnLine CERC 237

     Civil Appeal No.1929 of 2020 etc. Page 53 of 57

    39. This Court in Uttar Haryana Bijli Vitran (supra) had

    observed that the Haryana Utilities are indulging in approbation

    and reprobation. It has been observed that they cannot be

    permitted to blow hot and cold at the same time. It has further

    been observed that after accepting before the CERC that they

    would adopt the methodology as given in GMR Kamalanga

    (supra), it would not be appropriate on the part of Haryana Utilities

    to change its stand after final orders were passed by the CERC.

    This Court had therefore dismissed the appeal of the Haryana

    Utilities observing that the interference would be warranted only if

    the concurrent findings have failed to take into consideration the

    mandatory statutory provisions or if the decision had been taken

    by them on extraneous consideration or that they were ex facie

    arbitrary and illegal. As a matter of fact, this Court in the said case

    had approved the methodology applied by the CERC and affirmed

    by the learned APTEL which was based on the decision of the

    CERC in the case of GMR Kamalanga (supra).

    40. In that view of the matter and considering the concurrent

    findings of fact by the CERC on two different occasions and the

    learned APTEL in impugned order and also taking into note of the

    communication dated 2nd February 2022 issued by MCL, we see 

     Civil Appeal No.1929 of 2020 etc. Page 54 of 57

    no merit in the appeal of Haryana Utilities and the same is liable

    to be dismissed.

    Civil Appeal No. 3429 of 2020

    41. Insofar as the appeal by GRIDCO is concerned, the main

    contention of GRIDCO is that the order dated 3rd February 2016

    in Petition No. 79 and order dated 20th March 2018 in Petition No.

    105 were passed without impleading GRIDCO. It will be relevant

    to note that the PPA with GRIDCO is under Section 62 of the 2003

    Act whereas the PPAs with the Haryana Utilities and Bihar

    Utilities are under Section 63 of the 2003 Act. As such there was

    no occasion for GKEL to implead GRIDCO as a party to the said

    petitions.

    42. It is further to be noted that the petitions filed by GKEL

    before the CERC were filed seeking compensation on account of

    Change in Law events affecting Haryana and Bihar PPAs which

    were concluded by following provisions prescribed under Section

    63 of the 2003 Act. Section 63 of the 2003 Act provides for the

    determination of tariff by bidding process whereas under Section

    62, the tariff is determined on Cost Plus basis. It can thus be seen

    that proceedings under Sections 62 and 63 of the 2003 Act are

    entirely different. 

     Civil Appeal No.1929 of 2020 etc. Page 55 of 57

    43. It is also relevant to note that GKEL had filed a petition being

    Petition No. 77/GT/201338 for approval of the tariff for supply of

    electricity to the GRIDCO. The CERC vide order dated 12th

    November 2015 had determined the tariff payable by the GRIDCO

    to GKEL for the period of 1st April 2013 to 1st March 2014. Being

    aggrieved by the said order, GRIDCO filed Appeal No. 45 of 2016

    before the learned APTEL. The learned APTEL vide judgment and

    order dated 1st August 2017 did not find any merit in the

    methodology adopted by CERC for determining the tariff. The

    learned APTEL found that the CERC had calculated ECR in

    accordance with the CERC (Terms and Conditions of Tariff)

    Regulations, 2009. The methodology adopted by the CERC for

    determining the tariff payable by GRIDCO to GKEL has been duly

    approved by the learned APTEL. In that view of the matter, we find

    that GRIDCO was neither a necessary nor a proper party to the

    proceedings initiated by GKEL by way of Petition Nos. 79 and 105.

    44. On merits, it is the contention of the GRIDCO that it was its

    PPA which was executed first on 28th September 2006 and was

    operationalized in April 2013. It is therefore contended that

    38 Hereinafter referred to as ‘Petition No. 77’

     Civil Appeal No.1929 of 2020 etc. Page 56 of 57

    GRIDCO has the first right over the firm linkage FSA dated 26th

    March 2013. GRIDCO further contended that allocation under

    SLC-LT meeting dated 2nd August 2007 and LOA dated 25th July

    2008 was against long term PPAs and the only PPA at that time

    was with GRIDCO, therefore, the firm linkage was for GRIDCO.

    While considering GRIDCO’s appeal, the learned APTEL found

    that the supply of coal from all modes of procurement has to be

    considered for the power plant as a whole and not for specific PPAs

    as prayed by the appellants.

    45. In the foregoing paragraphs, while considering the appeal of

    Haryana Utilities, we have already upheld the concurrent findings

    of the CERC and the learned APTEL that the coal supply from all

    the sources has to be apportioned amongst all the three DISCOMS

    in proportion to the energy supplied to them. None of the

    DISCOMS can claim a priority for supply of power based either on

    the prior date of agreement or the recital as to the source of coal.

    In view of the findings given by us while discussing the appeal of

    the Haryana DISCOMS, we find no merit in the present appeal as

    well. The same is therefore liable to be dismissed. 

     Civil Appeal No.1929 of 2020 etc. Page 57 of 57

    CONCLUSION

    46. In the result, we pass the following orders:

    I. Civil Appeal No. 1929 of 2020 filed by Haryana Utilities and

    Civil Appeal No. 3429 of 2020 filed by GRIDCO are dismissed

    sans merit; and

    II. The impugned judgment and order dated 20th December

    2019 passed by the Appellate Tribunal for Electricity, New

    Delhi in Appeal No. 135 of 2018 along with Appeal No. 54 of

    2019 is upheld.

    47. Pending application(s), if any, shall stand disposed of.

    ..…………..……………...CJI.

    (B.R.GAVAI)

    …….........…………………...J.

     (K. VINOD CHANDRAN)

    NEW DELHI;

    SEPTEMBER 8, 2025