LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Friday, March 29, 2019

Section 11(6) of the Arbitration and Conciliation Act, = prima facie no dispute subsisted after the discharge voucher being signed by the respondent without any demur or protest and claim being finally settled with accord and satisfaction and after 11 weeks of the settlement of claim a letter was sent on 27th July, 2016 for the first time raising a voice in the form of protest that the discharge voucher was signed under undue influence and coercion with no supportive prima facie evidence being placed on record in absence thereof, it must follow that the claim had been settled with accord and satisfaction leaving no arbitral dispute subsisting under the agreement to be referred to the Arbitrator for adjudication. 22. In our considered view, the High Court has committed a manifest error in passing the impugned order and adopting a mechanical process in appointing the Arbitrator without any supportive evidence on record to prima facie substantiate that an 19 arbitral dispute subsisted under the agreement which needed to be referred to the arbitrator for adjudication. 23. Consequently, the appeals are allowed and the order passed by the High Court is accordingly set aside. No costs.

REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
  CIVIL APPEAL NO(s). 3284  OF 2019
(Arising out of SLP(C ) No(s). 23956 of 2017)
UNITED INDIA INSURANCE CO. LTD.  .…Appellant(s)
VERSUS
ANTIQUE ART EXPORTS PVT. LTD.         .…Respondent(s)
WITH
     CIVIL APPEAL NO(s). 3285  OF 2019
       (Arising out of SLP(C ) No(s). 23963 of 2017)
J U D G M E N T
Rastogi, J.
Leave granted.
2. These appeals have been filed by the Insurance Company
assailing the order dated 30th  May, 2017 passed by the High
Court   of   Delhi   appointing   an   Arbitrator   in   exercise   of   power
under   Section   11(6)   of   the   Arbitration   and   Conciliation   Act,
1
1996(hereinafter being referred to as “the Act”) to adjudicate the
dispute between the parties. 
3. The facts in brief manifest from the record and relevant for
the   present   purpose   are   that   the   respondent   claimant   was
running   its   factory   situated   at   78,   Kilo   Mile   Stone,   Karhans
Village, Main GT Road, Samalakha, Panipat and purchased two
Standard Fire and Special Perils Policies dated 29th June, 2013
and 10th October, 2013.  On 25th September, 2013 and thereafter
on 25th October, 2013, a fire took place in the factory on account
of a short circuit as claimed by the respondent claimant. The
appellant Company on receipt of the information appointed M/s.
Protocol Surveyors & Engineers Pvt. Ltd. as surveyors and also
appointed their investigator to submit the fact finding report.
After the report was submitted by the authorised surveyor, the
appellant Company sent an e­mail to the respondent with an
intimation that it has approved its claim for an amount of Rs.
2,81,44,413/­   on   account   of   fire   dated   25th  October,   2013
towards full and final settlement with complete details of the
amount   computed.     The   extract   of   the   e­mail   sent   by   the
appellant Company to the respondent has been placed on record
2
at Annexure P­2 in Civil Appeal arising out of SLP(C ) No. 23956
of 2017 and is reproduced as under:­
“From: Jaiprakash1@uiic.co.in
Sent: Thursday, May 05, 2016 1:23 PM
To: Vimal Singh
CC: sangeetagupta@uiic.co.in; vijaysharma@uiic.co.in;
   nareshchandolia@uiic.co.in
Subject: Fire Claim dated 25.10.2013
Sir/Madam,
This is to inform you that the Competent Authority has
approved   your   claim   for   an   amount   of   Rs.
2,81,44,413/­ (building Rs. 88,18,691   P & M   Rs.
7,32,382    FFF      Rs.   3,61,049   Finished  Goods,  Rs.
1,95,66,389   Fire   Fighting   Ex.   Rs.   59,000     Cost   of
Debris Removal Rs. 88,187 Total Rs. 2,96,25,698)
Less Excess 5% Rs. 14,81,285 = Rs. 2,81,44,413) of
loss   dated   25.10.2013   (Claim   No.
0407001113C101515001)
In order to release the payment we require following
from your end.
1. Confirmation   from   the   concerned   bank   “Indian
Overseas Bank, Defence Colony Branch.
Through mail that in which Account the payment has
to be made through NEFT.
2. Deposit Re­instatement premium of Rs.19100/­
3. Fire Fighting expenses bills in original
4. Debris Removal bills in original.
5. Full and final settlement discharge voucher for Rs.
2,81,44,413/­ duly endorsed by the bank  also
without any Subjectivity.
Please furnish.
3
Jaiprakash
Divisional Manager
United India Insurance Company Limited
10203, IIIrd Floor, Jamuna House,
Padam Singh Road
New Delhi­110005
Mobile : 9910791508
Phone : 28755967, 28755419
jaiprakash@uiic.co.in”
4. On the same date, i.e. 5th May, 2016, the respondent sent a
reply accepting the computation and provided the desired details
with final discharge voucher and details of the bank account in
which the payment was to be credited.  The extract of the e­mail
and the discharge voucher sent by the respondent is reproduced
hereunder:­
“ANTIQUE ART
Exports Pvt. Ltd.
(A Govt. of India Recognized Export House)
PANIPAT OFFICE: 78 K.M. Stone, G.T. Road, karhans Village, Tehsil
Samalkha, Panipat­132103(INDIA)
T:0091­180­3003300 (100 Lines), F: 0091­180­3003311
E:Info@antiqueartexports.com, :www.antiqueartexports.com
The Divisional Manager 05.05.2016
United India Insurance Co. Ltd.
10203, 3rd Floor, Jamuna House
Padam Singh Road
Karol Bagh, New Delhi.
Kind Attn: Mr. Jaiprakash
Subject : Fire Claim dated 25.10.2013
Dear Sir,
4
We   are   in   receipt   of   your   email   of   today’s   date,
wherein   you   have   asked   to   furnish   certain
documents/information for doing the needful at your
end.  Accordingly, we are submitting herewith desired
information/documents for your necessary action.
1. We   have   already   requested   our   bank   to   confirm
account   details,  in which  payment  has  to be made
through NEFT. Hopefully, you must have received the
same directly from Bank on your email.
2. Regarding re­instatement premium of Rs.19100/­, we
request you to deduct the same from claim payment.
3. Original   Fire   Fighting   expenses   bills   are   submitted
herewith for doing the needful at your end.
4. Regarding   Debris   Removal   Bills   in   original,   we   are
enclosing herewith separate letter and contents of the
same   are   self­explanatory.     This   payment   is   to   be
released at later date as per our letter.
5. Full   and   final   settlement   discharge   voucher   for
Rs.2,81,44,413/­   duly   endorsed   by   the   bank   is
attached for doing the needful at your end.
While   hoping   that   you   will   find   above   information/
documents   in   line   of   your   requirement,   we   look
forward to have the immediate transfer of payment of
our claim to our bank.
A line of confirmation in this regard will be highly
appreciated.
Thanking you
Yours faithfully,
For Antique Art Exports Pvt. Ltd.
Ashok Jain
Chairman”
“ANTIQUE ART
Exports Pvt. Ltd.
(A Govt. of India Recognized Export House)
PANIPAT OFFICE: 78 K.M. Stone, G.T. Road, karhans Village, Tehsil
Samalkha, Panipat­132103(INDIA)
T:0091­180­3003300 (100 Lines), F: 0091­180­3003311
E:Info@antiqueartexports.com, :www.antiqueartexports.com
05.05.2016
5
Full and Final Settlement Discharge Voucher
We,   Antique   Art   Exports   Pvt.   Ltd.,   78   KM   Stone,
Karhans   Village,   Tehsil   Samalkha,   Panipat­132103,
Haryana   do   hereby   accept   payment   of
Rs.2,81,44,413/­(Rupees Two Crore Eighty One Lacs
Fourty   Four   Thousand   and   Four   Hundred   Thirteen
only) as full and final settlement against our fire claim
No.:0407001113 C101515001 of loss dated 25.10.2013
without any subjectivity.
For Antique Art Exports Pvt. Ltd.
Sd/­
  Ashok Jain
  Chairman”
5.     Civil Appeal arising out of SLP(C ) No. 23963 of 2017 deals
with the fire taken place on 25th  September, 2013.   It is not
disputed between the parties that the facts are similar except
that the claim was settled for Rs. 2,20,36,840/­.
6. Indisputedly,   both   the   claims   were   accepted   by   the
respondent without any demur or protest, and after full and final
settlement and discharge of claim in reference to both the claims
of the incident dated 25th  September, 2013 and 25th  October,
2013, the respondent later through e­mail dt. 11th  July, 2016
desired   certain   details   and   reports   with   a   break   up   of
computation including copy of the preliminary survey report etc.
and there was no whisper that any coercion or undue influence,
6
etc. was used by the appellant company.  The e­mail was replied
by the appellant on 20th July, 2016 giving all details as desired by
the respondent.  Thereafter on 27th July, 2016 for the first time
nearly almost after 11 weeks of the receipt of claim and full and
final   discharge,   respondent   claimed   that   fraud,   coercion   and
undue influence was exercised and he was forced to sign on the
dotted   lines   without   furnishing   any   prima   facie   evidence   in
support thereof.   In furtherance, application came to be filed
before the High Court on 11th January, 2017 under Section 11(6)
of the Arbitration and Conciliation Act, 1996(hereinafter being
referred to as “the Act”) inter alia that the insurer coerced and
forced the respondent to sign on dotted lines on a pre­signed
discharge voucher and claimed for appointment of an Arbitrator.
7. The   appellant   Insurance   Company   in   their   reply   refuted
such   allegations   and   further   stated   that   the   respondent   had
signed a letter of subrogation in accepting the payment in full
and final settlement of its claim.   Discharge Voucher was sent
without any demur or protest and nothing further survives and
no arbitral dispute subsists for adjudication and so far as the
allegation levelled that the insurer has coerced and put undue
7
force upon the respondent to sign on dotted lines on a pre­signed
standard discharged paper is concerned, there is no prima facie
documentary evidence placed on record except the letter dated
27th  July, 2016 which was sent for the first time after almost
more   than   11   weeks   of   the   claim   being   settled   and   the
application   for   appointment   of   Arbitrator   is   ill   founded   and
deserves to be rejected.
8. The High Court taking note of the rival contentions of the
parties and of sub­section (6A) of Section 11 of the Act which has
been introduced by virtue of Amendment Act, 2015 observed that
once there is existence of arbitration agreement,  acceptance of
the payment disbursed by the appellant company, whether it was
under coercion or undue influence, is a matter to be examined by
the   Arbitrator   and   accordingly   proceeded   to   appoint   the   sole
arbitrator to adjudicate the dispute between the parties. 
9. Shri   Vineet   Malhotra,   learned   counsel   for   the   appellant
submits   that   once   the   claim   was   settled   and   the   claimant
received compensation and issued a discharge voucher in full
and final settlement of its claim, there was a discharge of the
8
contract by accord and satisfaction.   As a result, neither any
contract nor any claim survived.   It was also contended that
having received the payment under the said discharge voucher
without any demur or protest, it was not open for the respondent
after 11 weeks of the receipt of the claim and full and final
discharge, to raise a voice that the discharge was obtained under
coercion and undue influence without furnishing any prima facie
evidence in support thereof and placed reliance of the judgment
of this Court in  New   India  Assurance  Company  Limited  Vs.
Genus  Power   Infrastructure  Limited 2015(2) SCC 424 which
according   to   him   is   almost   on   the   same   set   of   facts   and
circumstances. 
10. Learned counsel for the appellant further submits that subsection (6A) of Section 11 of the Act has been introduced by
Amendment Act, 2015 with a limited purpose for expediting the
arbitral disputes in a time bound manner provided there is a
prima   facie   arbitral   claim/dispute   subsist   under   the   arbitral
agreement for adjudication by the Arbitrator.  In the instant case,
as there was no arbitral dispute subsisting after the claim being
finally settled with consent of the parties with due accord and
9
satisfaction, Section 11(6) was not available to be invoked by the
respondent in raising a dispute after more than 11 weeks of the
settlement of the claim to the satisfaction of the parties. 
11. Per Contra, Shri Dhruv Mehta, learned senior counsel for
the respondent submitted that he is not disputing as far as the
settlement of the claims are concerned but his objection is that
the respondent was not in a bargaining position and being in
financial stress, he had no option but to accept the claim on the
dotted   lines   settled   by   the   appellant   in   an   arbitrary   manner
leaving   no   choice   and   mere   acceptance   in   the   given
circumstances will not take away the right of the respondent to
establish that it was not voluntary but under undue influence
and coercion and since there is a clause of arbitration in the
agreement, it will be for the Arbitrator to examine as to whether
the acceptance of the claim by the respondent has been voluntary
or   under   undue   influence   or   coercion   and   in   the   given
circumstances, no error has been committed by appointing the
Arbitrator under the impugned judgment.
10
12. The existence of an arbitration clause in the contract of
insurance is not in dispute.  The question does arise whether the
discharge   in   the   present   case   upon   acceptance   of   the
compensation and signing of the discharge letter was voluntary
or under coercion or undue influence and the respondent was
justified in invoking Section 11(6) of the Act.   It is true that
execution   of   full   and   final   agreement,   receipt   or   a   discharge
voucher in itself cannot be a bar to arbitration and it has been
observed   by   this   Court   in  National   Insurance   Company
Limited Vs. Boghara Polyfab Private Limited 2009(1) SCC 267
at para 44 as under:­
“44. None   of   the   three   cases   relied   on   by   the
appellant lay down a proposition that mere execution
of a full and final settlement receipt or a Discharge
Voucher is a bar to arbitration, even when the validity
thereof is challenged by the claimant on the ground of
fraud, coercion or undue influence.   Nor do they lay
down   a   proposition   that   even   if   the   discharge   of
contract is not genuine or legal, the claims cannot be
referred to arbitration.  In all the three cases, the Court
examined the facts and satisfied itself that there was
accord and satisfaction or complete discharge of the
contract and that there was no evidence to support the
allegation of coercion/undue influence.”
13. It further laid down the illustrations as to when claims are
arbitrable and when they are not.  This may be illustrative (not
11
exhaustive) but beneficial for the authorities in taking a decision
as to  whether in a given  situation  where no claim/discharge
voucher has been furnished what will be its legal effect and still
there is any arbitral dispute subsists to be examined by the
arbitrator in the given facts and circumstances and held in para
52   of  National   Insurance   Co.   Ltd.  Vs.  Boghara   Polyfab
Private Limited (supra) as follows:­
“52. Some   illustrations   (not   exhaustive)   as   to   when
claims are arbitrable and when they are not, when
discharge of contract by accord and satisfaction are
disputed, to round up the discussion on this subject
are:
(i) A claim is referred to a conciliation or a pre­litigation
Lok   Adalat.   The   parties   negotiate   and   arrive   at   a
settlement. The terms of settlement are drawn up and
signed   by   both   the   parties   and   attested   by   the
conciliator or the members of the Lok Adalat. After
settlement by way of accord and satisfaction, there can
be no reference to arbitration.
(ii) A claimant makes several claims. The admitted or
undisputed claims are paid. Thereafter negotiations are
held for settlement of the disputed claims resulting in
an agreement in writing settling all the pending claims
and disputes. On such settlement, the amount agreed
is   paid   and   the   contractor   also   issues   a   discharge
voucher/no­claim   certificate/full   and   final   receipt.
After the contract is discharged by such accord and
satisfaction,   neither   the   contract   nor   any   dispute
survives   for   consideration.   There   cannot   be   any
reference of any dispute to arbitration thereafter.
(iii) A contractor executes the work and claims payment
of say rupees ten lakhs as due in terms of the contract.
The   employer   admits   the   claim   only   for   rupees   six
lakhs and informs the contractor either in writing or
12
orally   that   unless   the   contractor   gives   a   discharge
voucher   in   the   prescribed   format   acknowledging
receipt of rupees six lakhs in full and final satisfaction
of the contract, payment of the admitted amount will
not be released. The contractor who is hard­pressed for
funds and keen to get the admitted amount released,
signs on the dotted line either in a printed form or
otherwise, stating that the amount is received in full
and final settlement. In such a case, the discharge is
under   economic   duress   on   account   of   coercion
employed by the employer. Obviously, the discharge
voucher cannot be considered to be voluntary or as
having resulted in discharge of the contract by accord
and satisfaction. It will not be a bar to arbitration.
(iv) An insured makes a claim for loss suffered. The
claim is neither admitted nor rejected. But the insured
is   informed   during   discussions   that   unless   the
claimant gives a full and final voucher for a specified
amount (far lesser than the amount claimed by the
insured),  the  entire claim  will  be  rejected.  Being  in
financial   difficulties,   the   claimant   agrees   to   the
demand and issues an undated discharge voucher in
full and final settlement. Only a few days thereafter,
the admitted amount mentioned in the voucher is paid.
The   accord   and   satisfaction   in   such   a   case   is   not
voluntary but under duress, compulsion and coercion.
The   coercion   is   subtle,   but   very   much   real.   The
“accord”   is   not   by   free   consent.   The   arbitration
agreement can thus be invoked to refer the disputes to
arbitration.
(v) A claimant makes a claim for a huge sum, by way of
damages.   The   respondent   disputes   the   claim.   The
claimant who is keen to have a settlement and avoid
litigation, voluntarily reduces the claim and requests
for settlement. The respondent agrees and settles the
claim and obtains a full and final discharge voucher.
Here   even   if   the   claimant   might   have   agreed   for
settlement   due   to   financial   compulsions   and
commercial pressure or economic duress, the decision
was his free choice. There was no threat, coercion or
compulsion by the respondent. Therefore, the accord
and satisfaction is binding and valid and there cannot
be any subsequent claim or reference to arbitration.”
13
14. It is true that there cannot be a rule of thumb and each
case has to be looked into on its own facts and circumstances,
taking note of the broad principles, it was observed by this Court
in  Union   of   India  and  Others  Vs.  Master   Construction   Co.
2011(12) SCC 349 at para 18 as under:­
“18. In our opinion, there is no rule of the absolute
kind.   In a case where the claimant contends that a
discharge   voucher   or   no­claim   certificate   has   been
obtained by fraud, coercion, duress or undue influence
and the other side contests the correctness thereof, the
Chief Justice/his designate must look into this aspect
to find out at least, prima facie, whether or not the
dispute is bona fide and genuine.  Where the dispute
raised by the claimant with regard to validity of the
discharge voucher or no­claim certificate or settlement
agreement,   prima   facie,   appears   to   be   lacking   in
credibility, there may not be a necessity to refer the
dispute for arbitration at all.”
15. From the proposition which has been laid down by this
Court, what reveals is that a mere plea of fraud, coercion or
undue influence in itself is not enough and the party who alleged
is under obligation to prima facie establish the same by placing
satisfactory material on record before the Chief Justice or his
Designate to exercise power under Section 11(6) of the Act, which
has been considered by this Court in  New   India   Assurance
Company Ltd. case (supra) as follows:­
14
“9.  It is therefore clear that a bald plea of fraud,
coercion, duress or undue influence is not enough
and the party who sets up a plea, must prima
facie establish the same by placing material before
the Chief Justice/his designate…..”
16. In the instant case averment was made for the first time
after 11 weeks of the settlement of claim & release of discharge
voucher   in   the   petition   filed   by   the   respondent   seeking
appointment   of   Arbitrator   of   undue   influence/coercion   being
used by the appellant in signing the papers on dotted lines is
reproduced as under:­
“xiii. It is stated that the Respondent occupying a
bargaining position as an Insurer coerced and forced
the Petitioner to sign on dotted lines on a Pre­signed
Standard   Discharge   Voucher.     The   petitioner   facing
severe financial distress gave in to the pressure tactics
of the Respondent and was made to sign a purported
Discharge Voucher dated 24.06.2016 for an amount of
Rs.   2,20,36,840/­(Rupees   Two   Crore   Twenty   Lakhs
Thirty Six Thousand, Eight Hundred Forty Only) as
against the Claim of Rs. 5,12,49,241/­ (Rupees Five
Crore Twelve Lakhs Forty Nine Thousand Two Hundred
Forty   One   Only)   as   a   pre­condition   for   release   of
money.
xvii. It is stated that Petitioner vide its Letter dated
27.07.2016   rescinded   the   purported   Discharge
Voucher as illegal and void as it was forced on coerced
into signing the same in the face of extreme financial
duress.     The   petitioner   vide   the   said   letter   dated
27.07.2016   called   upon   the   Respondent   to   pay   the
balance   amount   of   Rs.   2,92,12,401/­   (Rupees   Two
Crore   Ninety   Two   Lakhs   Twelve   Thousand   Four
Hundred and One Only) on account of loss suffered by
the  petitioner  as  result   of  fire.    The   petitioner  also
claimed an interest @ 18% per annum from the date of
incident as well as on the paid amount till date of
payment i.e. up to 06.07.2016.”
15
17. It is true that there cannot be a rule of its kind that mere
allegation   of   discharge   voucher   or   no   claim   certificate   being
obtained by fraud/coercion/undue influence practised by other
party   in   itself   is   sufficient   for   appointment   of   the   arbitrator
unless the claimant who alleges that execution of the discharge
agreement or no claim certificate was obtained on account of
fraud/coercion/undue influence practised by the other party is
able to produce prima facie evidence to substantiate the same,
the correctness thereof may be open for the Chief Justice/his
Designate to look into this aspect to find out at least prima facie
whether the dispute is bonafide and genuine in taking a decision
to invoke Section 11(6) of the Act.
18. In the instant case, the facts are not in dispute that for the
two incidents of fire on 25th September, 2013 and 25th October,
2013, the appellant Company based on the Surveyor’s report sent
e­mails on 5th May, 2016 & 24th June, 2016 for settlement of the
claims for both the fires dated 25th  September, 2013 and 25th
October, 2013 which was responded by the respondent through
e­mail   on   the   same   date   itself   providing   all   the   necessary
16
information   to   the   Regional   Office   of   the   Company   and   also
issued   the   discharge   voucher   in   full   &   final   settlement   with
accord   and   satisfaction.     Thereafter,   on   12th  July,   2016,   the
respondent desired certain information with details that too was
furnished and for the first time on 27th July, 2016, it took a Uturn and raised a voice of undue influence/coercion being used
by the appellant stating that being in financial distress left with
no   option   than   to   proceed   to   sign   on   the   dotted   lines.     As
observed, the phrase in itself is not sufficient unless there is a
prima facie evidence to establish the allegation of coercion/undue
influence, which is completely missing in the instant case.
19. In the given facts and circumstances, we are satisfied that
the   discharge   and   signing   the   letter   of   subrogation   was   not
because of any undue influence or coercion as being claimed by
the   respondent   and   we   find   no   difficulty   to   hold   that   upon
execution of the letter of subrogation, the claim was settled with
due accord and satisfaction leaving no arbitral dispute to be
examined by an Arbitrator to be appointed under Section 11(6) of
the Act.
17
20. The submission of the learned counsel for the respondent
that   after   insertion   of   sub­section   (6A)   to   Section   11   of
Amendment Act, 2015 the jurisdiction of this Court is denuded
and the limited mandate of the Court is to examine the factum of
existence of an arbitration and relied on the judgment in Duro
Felguera S.A. Vs. Gangavaram Port Limited 2017(9) SCC 729.
The exposition in this decision is a general observation about the
effect of the amended provisions which came to be examined
under reference to six arbitrable agreements (five agreements for
works   and   one   corporate   guarantee)   and   each   agreement
contains a provision for arbitration and there was serious dispute
between   the   parties   in   reference   to   constitution   of   Arbitral
Tribunal whether there has to be Arbitral Tribunal pertaining to
each agreement.  In the facts and circumstances, this Court took
note of sub­section (6A) introduced by Amendment Act, 2015 to
Section   11   of  the   Act   and  in   that   context   observed  that  the
preliminary disputes are to be examined by the arbitrator and are
not   for   the   Court   to   be   examined   within   the   limited   scope
available for appointment of arbitrator under Section 11(6) of the
Act.   Suffice it to say that appointment of an arbitrator is a
judicial power and is not a mere administrative function leaving
18
some   degree   of   judicial   intervention   when   it   comes   to   the
question to examine the existence of a prima facie arbitration
agreement, it is always necessary to  ensure that  the dispute
resolution process does not become unnecessarily protracted.
21. In the instant case, prima facie no dispute subsisted after
the discharge voucher being signed by the respondent without
any demur or protest and claim being finally settled with accord
and satisfaction and after 11 weeks of the settlement of claim a
letter was sent on 27th July, 2016 for the first time raising a voice
in the form of protest that the discharge voucher was signed
under undue influence and coercion with no supportive prima
facie evidence being placed on record in absence thereof, it must
follow   that   the   claim   had   been   settled   with   accord   and
satisfaction   leaving   no   arbitral   dispute   subsisting   under   the
agreement to be referred to the Arbitrator for adjudication.
22. In our considered view, the High Court has committed a
manifest error in passing the impugned order and adopting a
mechanical   process   in   appointing   the   Arbitrator   without   any
supportive evidence on record to prima facie substantiate that an
19
arbitral dispute subsisted under the agreement which needed to
be referred to the arbitrator for adjudication.
23. Consequently, the appeals are allowed and the order passed
by the High Court is accordingly set aside.  No costs.
24. Pending application(s), if any, also stand disposed of.
…………………………J.
(A.M. KHANWILKAR)
…………………………J.
(AJAY RASTOGI)
NEW DELHI
March 28, 2019
20