LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Tuesday, September 4, 2012

The appellant was awarded the work relating to the construction of residential and non-residential building at Central Excavation Training Institute (CETI) vide work order dated 25.2.1987 for an amount of Rs.68,91,589/-. Appellant submits that for want of final drawings and delay in the supply of cement and other construction materials, including supply of water, the work was delayed, but completed on 1.4.1989 and handed over the buildings to the respondent. - We are of the view that the High Court was not justified in interfering with the amount awarded in respect of the water charges which comes to Rs.1,68,890.25. Going by the general terms and conditions of the contract, in our view, the department was bound to supply water, so found by the arbitrator, in our view, rightly. Therefore, that part of the award of the Arbitrator, with regard to the water charges, is upheld. However, the High Court, in our view, rightly denied the claim with regard to plaster of paris, therefore, not interfered with. Appeals are disposed of accordingly, subject to the above modification of the judgment of the High Court. However, there will be no order as to costs.


                                                              Non-Reportable



                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPELLATE JURISDICTION

                      CIVIL  APPEAL  NO. 6262  OF 2012
                @ Special Leave Petition (C) No.24337 of 2009


NAND CONTR. & ENGR. THR G.D. AHUJA      …    Appellant(s)

                                   Versus

NORTHERN COAL FIELD LTD. & ANR.         …    Respondent(s)

                                    WITH

                      CIVIL  APPEAL  NO. 6263  OF 2012
                @ Special Leave Petition (C) No.31125 of 2009

                      CIVIL  APPEAL  NO. 6265  OF 2012
                @ Special Leave Petition (C) No.10681 of 2011

                      CIVIL  APPEAL  NO.  6264  OF 2012
                @ Special Leave Petition (C) No.32878 of 2009
                                     And
                      CIVIL  APPEAL  NO.  6266  OF 2012
                @ Special Leave Petition (C) No.18183 of 2009


                               J U D G M E N T



K.S. Radhakrishnan, J.



1.    Leave granted.

2.    We may take up Civil Appeal arising out of Special Leave Petition  (C)
No.24337 of 2009 as a lead case which arises out of a common judgment  dated
14.11.2007 of the High Court of Madhya Pradesh at Jabalpur.   In  the  first
three appeals, we are concerned with the claim on  interest  alone  and,  in
the other two appeals, the question involved is with  regard  to  the  claim
for interest, water charges and the cost of plaster of paris.



3.    The appellant was awarded the work relating  to  the  construction  of
residential and non-residential  building  at  Central  Excavation  Training
Institute  (CETI)  vide  work  order  dated  25.2.1987  for  an  amount   of
Rs.68,91,589/-.  Appellant submits that  for  want  of  final  drawings  and
delay in the supply of cement and other  construction  materials,  including
supply of water, the work was delayed, but completed on 1.4.1989 and  handed
over the buildings to the respondent.  There was delay on the  part  of  the
respondents in preparing and sanctioning the final bills which gave rise  to
various  disputes  and  ultimately  the  matter  was  referred  to  a   sole
arbitrator.  The arbitrator passed an award dated 30.10.1999 on  the  claims
made by the appellant including claims for  water  charges  and  plaster  of
paris.  So far as the  claim  for  interest  is  concerned,  the  arbitrator
awarded simple interest @ 15% per annum from  six  months  of  the  date  of
completion i.e. 1.4.1989 on  all  the  amounts  awarded  till  the  date  of
payment.  Further, it was also ordered that in case the payment was  delayed
beyond three months of the date of the award, interest be  paid  @  18%  per
annum from the date of payment.  No payment was  made  within  three  months
from the date of the award.  Hence, according to the appellants, as per  the
award he was entitled for 15% interest  from  six  months  of  the  date  of
completion i.e. 1.4.1989 on the amounts awarded by the Arbitrator  till  the
date of payment.



4.    Award passed by  the  Arbitrator  was  challenged  by  the  respondent
before the First Additional District Judge, Sidhi  who  did  not  upset  the
award on merits, but modified the interest awarded  by  the  Arbitrator  and
substituted with 12% per annum simple interest from the date  of  the  award
i.e. 31.10.1999 till the date of payment.   Aggrieved  by  the  said  order,
appeals were preferred by the appellant before the  High  Court.   The  High
Court disposed of all the appeals, reducing the interest to 10%  per  annum.
The High Court has also set aside the award on the claim for  water  charges
and plaster of paris.  Being aggrieved by the judgment, as  already  stated,
these appeals have been preferred by the appellant.



5.    We have heard Shri Rohit Arya and Shri Mahabir Singh,  learned  senior
counsel, appearing for the appellant and  respondents,  respectively.    Mr.
Rohit Arya, learned senior counsel submitted that that  the  High  Court  as
well as the District Court were not justified in interfering with  the  well
considered  award  passed  by  the  Arbitrator.   Learned   senior   counsel
submitted that the reasons stated  by  the  High  Court  are  incorrect  and
contrary to the terms of contract as well as documents produced  before  the
arbitrator.  Learned  senior  counsel  submitted  that  the  Arbitrator  was
justified  in  allowing  the  claim  of  water  charges  to  the   tune   of
Rs.1,68,890.25.   Reference was  also  made  to  clauses  5(a)  and  (b)  of
General Conditions applicable to the contract and submitted that it  is  the
responsibility of the respondents  to  supply  the  water  at  their  costs.
Learned senior counsel also submitted the claim for plaster of  paris  which
was rightly allowed by the arbitrator and there was no reason  to  interfere
with the same.

6.     Shri  Mahabir  Singh,  learned  senior  counsel  appearing  for   the
respondents, on the other  hand,  submitted  that  there  is  no  reason  to
interfere with the judgment of the High Court  which  has  rightly  rejected
the claims on water charges and plaster of paris and also reduced  the  rate
of interest.  Further, no question of law arises for consideration in  these
appeals.

7.    We are of the view that the dispute between  the  parties  lies  in  a
narrow compass.  We find that the arbitrator has awarded simple  interest  @
15% per annum from six months of the date of  completion  i.e.  1.4.1989  on
the amounts awarded till the date of payment.  The  High  Court  thought  it
fit to reduce the rate of interest to  10%  per  annum,  which  we  find  no
reason to disturb.    The period for which the Arbitrator  has  awarded  the
interest will remain the same.  The appellant, therefore, would be  entitled
to get interest at the rate of 10% per annum from 1.4.1989 till the date  of
payment.



8.    We are  of  the  view  that  the  High  Court  was  not  justified  in
interfering with the amount awarded in respect of the  water  charges  which
comes to Rs.1,68,890.25.  Going by the general terms and conditions  of  the
contract, in our view, the department was bound to supply  water,  so  found
by the arbitrator, in our view, rightly.  Therefore, that part of the  award
of the Arbitrator, with regard to the water charges,  is  upheld.   However,
the High Court, in our  view,  rightly  denied  the  claim  with  regard  to
plaster of paris, therefore, not interfered with.     Appeals  are  disposed
of accordingly, subject to the above modification of  the  judgment  of  the
High Court.  However, there will be no order as to costs.


                                      …....................................J
                                                   (K.S. Radhakrishnan)


                                      …....................................J
                                             (Dipak Misra)

New Delhi,
September  4,  2012