LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Friday, July 23, 2021

whether a subsequent purchaser is not entitled to similar treatment as the original allottee, and can be denied relief which otherwise the original allottee would have been entitled to, had she or he continued with the arrangement

whether a subsequent purchaser is not entitled to similar treatment as the original allottee, and can be denied relief which otherwise the original allottee would have been entitled to, had she or he continued with the arrangement

The original allottee thereafter approached the builder, informing it that the purchaser had stepped into her shoes and would continue with the obligations, and was therefore entitled to possession. Significantly, the builder endorsed and even required the purchaser to execute the letter of undertaking, which he did. With this development, the builder acknowledged that the rights and entitlements of the original allottee relation to the flat were assumed by the purchaser, and signified its obligations, correspondingly to the purchaser, as the consumer

The principal argument of the builder is the rights of a purchaser are not the same as an original allottee. The builder appellant cites Raje Ram and Arifur Rahman Khan (supra).In the first decision Raje Ram, this Court declined to grant interest on a refund claim made by a subsequent purchaser. The original allottee did not continue with the allotment; the statutory authority/developer HUDA re-allotted  the plot. The re-allottee then approached the consumer forum which directed refund with interest. This court was of the opinion that when the subsequent purchaser, i.e. the re-allottee stepped into the shoes of the original allottee, he was aware of the delay in handing over the possession which had occurred and therefore could no longer claim the time of the delay. In Arifur Rahman Khan (supra) several allottees approached the Court. This Court did not grant relief to the subsequent purchasers who stepped into the shoes of the original allottees, citing Raje Ram.

held that 

This court has also ruled, recently9 that proceedings initiated by complainants and resultant actions including of the NCDRC are fully saved by provisions of the Real Estate Regulatory Authority Act, 2019. 31. In view of these considerations, this court is of the opinion that the per se bar to the relief of interest on refund, enunciated by the decision in Raje Ram (supra) which was applied in Wg. Commander Arifur Rehman (supra) cannot be considered good law. The nature and extent of relief, to which a subsequent purchaser can be entitled to, would be fact dependent. However, it cannot be said that a subsequent purchaser who steps into the shoes of an original allottee of a housing project in which the builder has not honoured its commitment to deliver the flat within a stipulated time, cannot expect any – even reasonable time, for the performance of the builder’s obligation Such a conclusion would be arbitrary, given that there may be a large number- possibly thousands of flat buyers, waiting for their promised flats or residences; they surely would be entitled to all reliefs under the Act. In such case, a purchaser who no doubt enters the picture later surely belongs to the same class. Further, the purchaser agrees to buy the flat with a reasonable expectation that delivery of possession would be in accordance within the bounds of the delayed timeline that he has knowledge of, at the time of purchase of the flat. Therefore, in the event the purchaser claims refund, on an assessment that he too can (like the original allottee) no longer wait, and face intolerable burdens, the equities would have to be moulded. It would no doubt be fair to assume that the purchaser had knowledge of the delay. However, to attribute knowledge that such delay would continue indefinitely, based on an a priori assumption, would not be justified. The equities, in the opinion of this court, can properly be moulded by directing refund of the principal amounts, with interest @ 9% per annum from the date the builder acquired knowledge of the transfer, or acknowledged it.

1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 7042 of 2019

M/S LAUREATE BUILDWELL PVT. LTD. ….APPELLANT (S)

VERSUS

CHARANJEET SINGH ....RESPONDENT(S)

ORDER

S. RAVINDRA BHAT, J.

1. The appellant (hereafter called “Laureate” or “the builder”) is aggrieved by

an order of the National Consumer Dispute Redressal Commission 1

(hereafter

“NCDRC”). The respondent (hereafter “the purchaser”) had sought, through his

complaint a direction against the builder, for refund of the consideration amount of

₹1,93,70,883/- received by the latter, as consideration for sale of a flat along with

interest @ 24% p.a. from the date different instalments were paid, as well as

compensation and costs.

2. The relevant facts are that one Ms. Madhabi Venkatraman (hereafter “the

original allottee”) applied on 29.08.2012 for allotment of a residential flat (No. 7013,

(hereafter “the flat”) admeasuring 4545 sq. ft., in Nectarine Tower "PARX

LAUREATE" at Sector- 108, Expressway, Noida. The flat was to be developed by


1

In Consumer case No. 1183/2017, decided on 29-05-2019

2

the builder (Laureate). She paid the registration amount of ₹7,00,000/-. On

16.10.2012, an allotment letter was issued to the original allottee, for the flat after

deposit of ₹32,33,657/- out of the total sale consideration of ₹2,47,29,405/-.

According to the allotment letter, the possession of the flat was to be handed over

within 36 months (from the date of allotment letter) i.e., latest by 15.10.2015. The

original allottee made payment to the tune of ₹1,55,89,329/-, for the first seven

instalments as demanded by Laureate. On 16.02.2015, after noticing the slow pace of

construction, the original allottee decided to sell the flat. The purchaser who was in

search of a residential flat was approached by her through a broker. He was assured

that the possession of the flat would be delivered on time, and he agreed to purchase

the flat and paid an amount of 1,00,000/- as advance towards the total sale

consideration of ₹1,55,89,329/-. The purchaser and the original allottee agreed that

the balance amount of sale consideration would be paid on or before 15.10.2015 and

further that the purchaser would pay the outstanding instalments beyond

₹1,55,89,329/- directly after transfer of the flat to him. Demand letters for two

instalments (Nos. 8 & 9) were issued by Laureate and payment to the tune of ₹21,

68,694/- was made by the original allottee.

3. The purchaser alleged that possession was not delivered in October, 2015 as

promised (in the allotment letter). He decided to wait for the possession and not to

make any payment towards the sale; however, the original allottee insisted upon the

execution of an agreement to sell and demanded payment of instalments, which she

had made to the builder, stating that she could not wait any further and she would

forfeit the earnest money and cancel the deal. The purchaser alleged that he made

enquiries from the officials of the builder, who assured that the possession would be

delivered by June 2016. Therefore, the purchaser, on 17.02.2016, entered into an

agreement of sale with the original allottee, and paid an amount of ₹1,85,00,000/-.

4. The original allottee on 02.04.2016, requested the builder to transfer the flat

in favor of the respondent. The purchaser submitted an undertaking dated 01.04.2016

duly signed and executed by him, to the builder, Laureate. Later, Laureate issued a

3

letter dated 09.05.2016 to the purchaser, confirming the payment of ₹1,93,70,883/-

towards the purchase of the flat. Thereafter, the purchaser visited the site to acquaint

himself with the extent of construction but he was denied entry to the construction

site by the builder’s employees citing security reasons and was informed that the

work was in progress and possession would be delivered shortly. The purchaser

alleges that he made telephonic inquiries from the office of the builder regarding

possession, but unavailingly, without any result. He claims to have visited the

builder’s office in last week of January, 2017 and was informed that possession of

the said flat could not be delivered till the end of year 2017.

5. After this, the purchaser sought for refund of the amount paid, from the

builder. On 08.03.2017, a legal notice was issued to the builder asking for refund of

the amount of ₹1,93,70,883/- with interest @ 24% p.a. from the various dates of

deposit, was sought by the purchaser, but in vain. He claims to have been shocked to

receive the demand letter for the 11th instalment for ₹10,92,628/-. On refusal of the

payment of instalment, the officials of the builder threatened the purchaser of

cancellation and forfeiture of the amounts paid. It is in these circumstances, that the

appellant approached the NCDRC, for direction to the builder to refund the entire

sum of ₹1,93,70,883/- with interest at the rate of 24% from the respective dates when

the instalments were paid to Laureate. In addition, ₹ 5,00,000/- as compensation and

₹ 2,00,000/- as litigation expenses were sought along with other costs.

6. The builder, Laureate denied the claim, stating that for the period 28.03.2013

to January 2016, (i.e. 26 months), there was complete slowdown in the construction

of the projects in all of NOIDA including the buildings in question, due to the order

passed by National Green Tribunal (NGT) in OA/158/2013, and due to a notification

issued by the Ministry of Environment, Forests and Climate Change. The original

allottee was aware of the orders of the NGT, and the builder had sent several

reminders for payment towards the instalments and finally issued a notice on

17.10.2014 for cancellation of the Provisional Allotment of Flat No. 7013. It was

alleged that in view of Clause 13(7) of the agreement neither Ms. Madhabi 

4

Venkatraman, the original allottee nor the purchaser-respondent who is endorsed by

the original allottee was entitled to any amounts for delay in construction. It was also

alleged that on 02.04.2016, the original allottee requested the builder to transfer flat

No. 7013 in favour of the purchaser. The purchaser furnished an undertaking on

01.04.2016 duly signed before the competent authority, which makes it clear that

both the original allottee and the purchaser were aware of the order of the NGT and

the delay in construction were beyond the control of the purchaser. Therefore, their

right to claim compensation is construed to be waived in terms of Clause 13.

7. The builder further alleged that on commencement of 18th floor and 20th

floor roof slab, the 11th and 12th instalments were demanded from the Complainant

and the same was not paid. Therefore, the builder had a right to cancel the allotment.

It is only on account of the restrictive order dated 28.10.2013 passed by NGT on any

construction within the radius of 10 kilometres from Okhla Bird Sanctuary, that the

builder could not complete the project as the said project comes within the radius of

10 kilometres. In view of clause 13(5), the builder was entitled for extension of time

for offer of possession at such premises on account of force majeure conditions.

Therefore, it is not liable to pay any compensation.

8. The NCDRC, after considering the depositions of the parties, through

affidavits, documentary evidence and the submissions of parties, noticed that the

demand letter for the 11th instalment was dated 24.03.2017, whereas the promised

date of delivery was 15.10.2015. That said letter stated that the construction stage 'on

commencement of 18th floor roof slab' of the tower had been achieved and therefore

the 11th instalment was demanded to be paid. This showed that even as on

24.03.2017, the construction of the said tower was incomplete. The commission

considered that Receipt No. 306 dated 01.03.2016 shows that the original allottee had

paid an amount of ₹5,29,000/- towards penal interest charged by the Developer at the

rate of 24% per annum. The NCDRC rejected the plea that the original allottee was a

defaulter. It thereafter allowed the complaint, reasoning as follows:

5

“20. We find it a fit case to place reliance on the judgement of the

Hon'ble Supreme Court in Kolkata West International City Pvt. Ltd. Vs.

Devasis Rudra, II (2019) CPJ 29 (SC), wherein the Hon'ble Apex Court

has clearly laid down that a flat purchaser cannot be made to wait

indefinitely for seeking possession. Even in the instant case, though the

promised date of delivery was way back in the year 2015, even as on

date, the tower is far from completion.

21. The Learned Counsel for the Complainant relied on the decision

of this Commission dated 11.01.2019 in Manmeet Singh & Anr. Vs.

Unitech Hi-Tech Developers Ltd. & Ors. (Consumer Complaint No.

1285 of 2017), wherein this Commission has allowed refund of the

principal amount with interest @ 10% p.a.

22. For all the aforenoted reasons and the principal laid down by the

Hon'ble Supreme Court in Kolkata West International City Pvt. Ltd.

(Supra) we are of the considered view that the Complaint be allowed in

part and we direct the Developer to refund the amount deposited with

the developer in respect of subject flat No. 7013 with interest @ 10%

p.a. from the respective dates of deposit till the date of realisation

together with the cost of ₹25,000/.”

Arguments of the parties

9. It is argued by Mr. Jayanth Mithras, learned senior counsel on behalf of the

builder that the relief granted by NCDRC is unwarranted. Highlighting that the entire

project had come to a standstill on account of an interim order by the NGT, the

learned senior counsel stressed that these facts were within the knowledge of the

original allottee as well as the purchaser. When they decided to purchase it in 2015, it

was decided that the respondent would purchase the flat and step into the shoes of the

original allottee. Learned senior counsel argued that given these circumstances, the

respondent, as a prudent purchaser, could not have reasonably expected the

construction to be completed till the interim orders were vacated and some time was

allowed for the construction to be completed. Clearly, the purchaser was only an

investor and was not interested in residing in the flat.

10. Learned senior counsel submitted that barely a year after the transaction of

stepping into the shoes of the original allottee – which was endorsed by the builder,

the purchaser made an unreasonable demand for the refund of the entire amount. At 

6

that point in time, the interim order of the NGT had been vacated. Quite naturally,

therefore, the construction had started and the builder made the demand on

23.04.2017 towards subsequent instalments which were not paid. Although the

purchaser sent a legal notice prior to these demands, the fact remained that so long as

he assumed responsibility as an allottee, he could not shy away from fulfilling the

demand towards the instalments.

11. Learned senior counsel argued that the purchaser could not claim the equities

in the same manner that an original allottee could. In the present case, the original

allottee had not paid the instalments in time and was constrained to pay penal interest

– a fact noted by the NCDRC. In these circumstances, there were no equities

compelling the NCDRC to grant any relief over and above a refund of compensation

much less interest @ 10% from the period the deposits were made by the original

allottee.

12. Learned senior counsel submits that since the complainant was not the original

allottee but a subsequent purchaser, he could not claim any interest. He relied upon

two rulings of this Court in HUDA v. Raje Ram2

and the recent judgment of this

Court in Wing Commander Arifur Rahman Khan and Anr. v. DLF Southern Homes

Pvt. Ltd.3

. It is submitted that in both these cases, this Court had categorically ruled

that when the allottee in a housing project transfers his or her rights in favour of

another, such a third party cannot claim equities to the same extent as the original

allottee, especially as regards a claim for interest. It was submitted by the learned

senior counsel that there is a sound public policy rationale in support of such a rule

which is that a subsequent purchaser is deemed to be aware of the nature of

construction and the delay which occurred till the time he or she steps into the shoes

of the allottee. The NCDRC overlooked these binding rulings and directed payment

of interest for the entire period and clearly the respondent purchaser was not entitled

to any interest at all.


2 2008 (17) SCC 407

3 2020 SCC Online 667 (SC)

7

13. Mr. M.L. Lahoty, learned counsel for the respondent urged this Court not to

interfere with the findings and directions of the NCDRC. He highlighted that even if

they were notified about the transfer by the original allottee in respect of the

respondent, the builder had made demands towards penal interest, for various

periods. A total amount of ₹ 5.9 lakhs was in fact paid during the period 01.03.2016

to 18.04.2016. The builder was made aware of the agreement to sell when its

endorsement with respect to the transfer was sought. Further, it was only after

receiving the amounts towards the so-called penal interest that the endorsement letter

was ultimately issued on 09.05.2016 by the builder. This clearly confirmed

₹1,93,70,883/- was paid towards the flat. This endorsement letter also confirmed that

the respondent purchaser would be entitled to the delivery of the flat.

14. It is submitted that the purchaser had entered into an understanding and paid

the amounts towards the previous instalments as well as settled the later penal

interest component to the original allottee and also paid penal interest upto October

2016. In these circumstances, it was not unreasonable for him to expect that project

would be complete and the flat would be handed over at least in the first part of

2017. However, upon visiting the site and noticing that there was practically no

progress, the respondent/purchaser was constrained to move the NCDRC for the

relief of direction of refunding the entire amount.

15. Mr. Lahoty pointed to the findings and observations of the NCDRC which had

noticed the facts that although the NGT’s interim order had subsisted for a while, and

the builder had taken shelter under it to say that construction could not take place, the

record indicated that the builder had sought for instalments from the original allottee,

including demanding penal interest. Given these facts, there were no equities in

favour of the builder; it was not open to it to claim that force majeure conditions

operated and prevented it from going ahead with the construction.

16. It was submitted that upon the endorsement by the builder of all the

transactions, and its acknowledgment, the purchaser had become entitled to seek

delivery. There was no impediment in the purchaser claiming any kind of relief. Mr. 

8

Lahoty submitted that if for instance, there were to be any defect or deficiency in

service, the purchaser could not be discriminated against and an application or a

plaint in that regard cannot be dismissed as not maintainable. Likewise, the mere fact

that a subsequent purchaser steps into the shoes of an original allottee who might

have at an earlier point of time sought allotment but because of the delay in the

construction, being unable to withstand economic pressures withdrew, does not mean

that the builder’s default could be glossed over. Learned counsel urged that there is

no rule or principle to support the judgment in Raje Ram (supra) or Wing

Commander Arifur Rahman Khan and Anr. (supra) to say that subsequent purchasers

should never be given the relief of interest on refunds. It was submitted that the

refusal of the Court to grant relief have to be seen in the light of the peculiar

circumstances of those cases.

Analysis and Conclusions:

17. The allotment letter dated 16.10.2012 assured the original allottee that the

possession of the flat would be handed over within 36 months i.e. on or before

15.10.2015. The original allotee made payment to the tune of ₹1,55,89,329/-,

towards the first seven instalments as and when demanded. Apparently, the allottee

due to her own compulsions could not continue to wait indefinitely for delivery of

the flat, having regard to the slow pace of construction. She therefore felt compelled

to sell the flat. It was then that the purchaser stepped in, and an agreement to sell

was executed between the parties on 17.02.2016. The original allottee thereafter

approached the builder, informing it that the purchaser had stepped into her shoes

and would continue with the obligations, and was therefore entitled to possession.

Significantly, the builder endorsed and even required the purchaser to execute the

letter of undertaking, which he did. With this development, the builder

acknowledged that the rights and entitlements of the original allottee relation to the

flat were assumed by the purchaser, and signified its obligations, correspondingly to

the purchaser, as the consumer.

9

18. In the meanwhile, there was a slowdown in construction, apparently, on

account of orders made by NGT. The builder alleged that the slowdown in

construction was due to the NGT’s interim orders. However, what transpired was

that on 28.10.2013, the NGT imposed certain restrictions within 10 km radius of the

Okhla Bird Sanctuary. The application before the NGT was disposed on 03.04.2014.

Consequently, there were no directions after that date. A review application was filed

before the NGT which remained pending for some time; however, even at that stage

there were no interim orders requiring stoppage of construction. On 19.08.2015 the

Ministry of Environment and Forests issued a notification. The appellant is unclear

as to the effect of this notification; apparently, it did not impede construction; the

notification was challenged. It is only on 05.07.2016, on account of an application

preferred by an occupant of an adjoining area that the NGT directed the builder not

to carry on with the construction. This, the builder informs in its appeal, was finally

disposed of in January 2016.

19. The facts set out in the preceding paragraph demonstrate that on the one hand

the builder/appellant is not categorical with respect to the existence of interim orders

enjoining it not to construct further. Rather, it appears that there was no construction

of the project for about six months. However, despite this position, it continued to

demand and received instalments. The purchaser entered the scene in 2016, waited

for some time and demanded refund of the entire amount with interest from the dates

that deposits were made. After receiving notice, the builder demanded further

instalments. It was in this background that the purchaser approached the NCDRC

successfully with the claim for refund. The claim for interest was allowed to the

extent of 10% on the entire amounts deposited from the respective dates of deposits.

20. The principal argument of the builder is the rights of a purchaser are not the

same as an original allottee. The builder appellant cites Raje Ram and Arifur

Rahman Khan (supra).In the first decision Raje Ram, this Court declined to grant

interest on a refund claim made by a subsequent purchaser. The original allottee did

not continue with the allotment; the statutory authority/developer HUDA re-allotted 

10

the plot. The re-allottee then approached the consumer forum which directed refund

with interest. This court was of the opinion that when the subsequent purchaser, i.e.

the re-allottee stepped into the shoes of the original allottee, he was aware of the

delay in handing over the possession which had occurred and therefore could no

longer claim the time of the delay. In Arifur Rahman Khan (supra) several allottees

approached the Court. This Court did not grant relief to the subsequent purchasers

who stepped into the shoes of the original allottees, citing Raje Ram.

21. The relevant discussion in Raje Ram is as follows:

“14. The appellants challenged the said orders of the State Commission

contending that no interest was payable. The National Consumer

Disputes Redressal Commission by its non-speaking orders dated 27-8-

2002, 30-9-2002 and 27-8-2002, disposed of the said revisions filed by

the Development Authority, in terms of its earlier decision

in HUDA v. Darsh Kumar [ RP No. 1197 of 1998 decided on 31-8-2001

(NC)] by merely observing that it had upheld the award of interest up to

18% per annum in similar circumstances. The National Commission did

not refer to or consider the facts of these cases. The said orders are

challenged in these appeals by special leave. The common issue in all

these cases is whether interest could have been awarded against the

appellant, and if so whether the rate of interest is excessive.

15. The decision of the National Commission in Darsh Kumar [ RP No.

1197 of 1998 decided on 31-8-2001 (NC)] , followed in the impugned

orders, did not find favour of this Court in HUDA v. Darsh

Kumar [(2005) 9 SCC 449] . This Court observed that (at SCC p. 451,

para 7) where possession is given at the old rate, the party has got the

benefit of escalation in price of land, and therefore, there cannot and

should not be award of interest on the amounts paid by the allottee on

the ground of delay in allotment. On the special facts of that case, this

Court however awarded compensation for harassment/mental agony.

16. The respondents in the three appeals are not the original allottees.

They are re-allottees to whom reallotment was made by the appellant in

the years 1994, 1997 and 1996 respectively. They were aware, when the

plots were reallotted to them, that there was delay (either in forming the

layout itself or delay in delivering the allotted plot on account of

encroachment, etc). In spite of it, they took reallotment. Their cases

cannot be compared to the cases of the original allottees who were

made to wait for a decade or more for delivery and thus put to mental

agony and harassment. They were aware that time for performance was 

11

not stipulated as the essence of the contract and the original allottees

had accepted the delay.”

22. In Arifur Rahman Khan, the court observed as follows:

“43. Similarly, the three appellants who have transferred their title,

right and interest in the apartments would not be entitled to the benefit

of the present order since they have sold their interest in the apartments

to third parties. The written submissions which have been filed before

this Court indicate that “the two buyers stepped into the shoes of the

first buyers” as a result of the assignment of rights and liabilities by the

first buyer in favour of the second buyer. In HUDA v. Raje

Ram [HUDA v. Raje Ram, (2008) 17 SCC 407 : (2009) 5 SCC (Civ)

889] , this Court while holding that a claim of compensation for delayed

possession by subsequent transferees is unsustainable, observed that:

(SCC p. 410, para 16)

“16. The respondents in the three appeals are not the

original allottees. They are re-allottees to whom

reallotment was made by the appellant in the years 1994,

1997 and 1996 respectively. They were aware, when the

plots were reallotted to them, that there was delay (either

in forming the layout itself or delay in delivering the

allotted plot on account of encroachment, etc.). In spite of

it, they took reallotment. Their cases cannot be compared

to the cases of the original allottees who were made to

wait for a decade or more for delivery and thus put to

mental agony and harassment. They were aware that time

for performance was not stipulated as the essence of the

contract and the original allottees had accepted the

delay.”

Even if the three appellants who had transferred their interest in the

apartments had continued to agitate on the issue of delay of

possession, we are not inclined to accept the submission that the

subsequent transferees can step into the shoes of the original buyer for

the purpose of benefiting from this order. The subsequent transferees

in spite of being aware of the delay in delivery of possession the flats,

had purchased the interest in the apartments from the original buyers.

Further, it cannot be said that the subsequent transferees suffered any

agony and harassment comparable to that of the first buyers, as a

result of the delay in the delivery of possession in order to be entitled

to compensation.”

12

23. The builder does not deny that upon issuance of the endorsement letter, the

purchaser not only stepped into the shoes of the original allottee but also became

entitled to receive possession of the flat. There is no denial that the purchaser fulfils

the description of the complainant/ consumer and is entitled to move any forum

under the Consumer Protection Act for any deficiency in service. The question then

is whether a subsequent purchaser is not entitled to similar treatment as the original

allottee, and can be denied relief which otherwise the original allottee would have

been entitled to, had she or he continued with the arrangement. An individual such

as the original allottee, enters into an agreement to purchase the flat in an on-going

project where delivery is promised. The terms of the agreement as well as the

assurance by the builder are that the flat would be made available within a timeframe. It is commonplace that in a large number of such transactions, allottees are

not able to finance the flat but seek advances and funds from banks or financial

institutions, to which they mortgage the property. The mortgage pay-outs start

initially after an agreed period, commencing in a span of about 15 to 24 months after

the agreement. This would mean that in most cases, allottees start repaying the bank

or financial institutions with instalments (mostly equated monthly instalments)

towards the principal and the interest spread over a period of time, even before the

flats are ready. If these facts are taken into consideration, prolongation of the project

would involve serious economic repercussions upon such original allottees who are

on the one hand compelled to pay instalments and, in addition, quite often -if she or

he is in want of a house -also pay monthly rents. Such burdens become almost

intolerable. It is at this point that an indefinite wait is impossible and allottees prefer

to find purchasers who might step into their shoes. That such purchasers take over

the obligations of the original allottee – either to pay the balance instalments or to

wait for sometime, would not per se exclude them from the description of a

consumer. All that then happens is that the consumer forum or commission – or

even courts have to examine the relative equities having regard to the time frame in

each case.

13

24. In a larger five judge bench ruling in Economic Transport Organization v.

Charan Spinning Mills (P) Ltd4

, the question was whether an insurer, who honours

its contract, and pays the insured the agreed money, in the event of an insurable

incident such as an accident, can maintain a consumer complaint against the carrier,

who is responsible for the accident. This court held that such complaints are not

barred:

“29. In all three types of subrogation, the insurer can sue the

wrongdoer in the name of the assured. This means that the insurer

requests the assured to file the suit/complaint and has the option of

joining as co-plaintiff. Alternatively, the insurer can obtain a

special power of attorney from the assured and then to sue the

wrongdoer in the name of the assured as his attorney.

****************** **************

37. Whether the document executed by the assured in favour of the

insurer is a subrogation simpliciter, or a subrogation-cumassignment is relevant only in a dispute between the assured and

the insurer. It may not be relevant for deciding the maintainability

of a complaint under the Act. If the complaint is filed by the assured

(who is the consumer), or by the assured represented by the insurer

as its attorney holder, or by the assured and the insurer jointly as

complainants, the complaint will be maintainable, if the presence of

insurer is explained as being a subrogee. Whether the amount

claimed is the total loss or only the amount for which the claim was

settled would make no difference for the maintainability of the

complaint, so long as the consumer is the complainant (either

personally or represented by its attorney-holder) or is a cocomplainant along with his subrogee.

38. On the other hand, if the assured (who is the consumer) is not

the complainant, and the insurer alone files the complaint in its own

name, the complaint will not be maintainable, as the insurer is not a

“consumer”, nor a person who answers the definition of

“complainant” under the Act. The fact that it seeks to recover from

the wrongdoer (service provider) only the amount paid to the

assured and not any amount in excess of what was paid to the

assured will also not make any difference, if the assured-consignor

is not the complainant or co-complainant. The complaint will not be

maintainable unless the requirements of the Act are fulfilled. The

remedy under the Act being summary in nature, once the consumer

is the complainant or is a co-complainant, it will not be necessary


4

(2010) 4 SCC 114

14

for the Consumer Forum to probe the exact nature of relationship

between the consumer (assured) and the insurer, in a complaint

against the service provider.

****************** **************

40. If in a summary proceedings by a consumer against a service

provider, the insurer is added as a co-complainant or if the insurer

represents the consumer as a power-of-attorney, there is no need to

examine the nature of rights inter se between the consumer and his

insurer. When the complaint is by the consignor-consumer, with or

without the insurer as a co-complainant, the service provider

cannot require the Consumer Forum to consider the nature of

relationship between the assured and the insurer or the nature and

true purport of the document produced as a letter of subrogation. A

wrongdoer cannot side-track the issue before the Consumer Forum.

Once the “consumer”, that is the assured, is the complainant, the

complaint will be maintainable subject to fulfilment of the

requirements of the Act.”

25. In another decision, Canara Bank v. United India Insurance Co. Ltd.5

the issue

which this court had to consider was whether the insurer could repudiate liability in

respect of a fire which destroyed farm produce kept in a cold storage, when the

farmers had no privity with the insurer, but with the cold storage, and who availed

credit on the security of the crop. The court held as follows:

“28. Taking the issue of privity of contract, we are of the considered

view that as far as the Act is concerned, it is not necessary that there

should be privity of contract between the Insurance Company and the

claimants. The definition of “consumer” under Section 2(d) quoted

hereinabove is in two parts. Sub-clause (i) of Section 2(1)(d) deals with

a person who buys any goods and includes any user of such goods other

than the person who buys such goods as long as the use is made with the

approval of such person. Therefore, the definition of consumer even in

the first part not only includes the person who has purchased but

includes any user of the goods so long as such user is made with the

approval of the person who has purchased the goods. As far as the

definition of “consumer” in relation to hiring or availing of services is

concerned, the definition, in our view, is much wider. In this part of the

section, consumer includes not only the person who has hired or availed

of the services but also includes any beneficiary of such services.

Therefore, an insured could be a person who hires or avails of the


5

(2020) 3 SCC 455

15

services of the Insurance Company but there could be many other

persons who could be the beneficiaries of the services. It is not

necessary that those beneficiaries should be parties to the contract of

insurance. They are the consumers not because they are parties to the

contract of insurance but because they are the beneficiaries of the policy

taken out by the insured.

29. The definition of “consumer” under the Act is very wide and it

includes beneficiaries who can take benefit of the insurance availed by

the insured. As far as the present case is concerned, under the tripartite

agreement entered between the Bank, the cold store and the farmers, the

stock of the farmers was hypothecated as security with the Bank and the

Bank had insisted that the said stock should be insured with a view to

safeguard its interest..”

26. If one also considers the broad objective of the Consumer Protection Act,

which is to provide for better protection of the interests of consumers and for that

purpose, provide for the establishment of Consumer Councils and other authorities

for the settlement of consumer disputes and for matters connected therewith, as

evident from the Statement of Objects and Reasons of the Act. The Statement further

seeks inter alia to promote and protect the rights of consumers such as—

“(a) The right to be protected against marketing of goods which are

hazardous to life and property;

(b) the right to be informed about the quality, quantity, potency, purity,

standard and price of goods to protect the consumer against unfair

trade practices;

(c) the right to be assured, wherever possible, access to variety of goods

at competitive prices;

(d) the right to be heard and to be assured that consumers' interests will

receive due consideration at appropriate forums;

(e) the right to seek redressal against unfair trade practice or

unscrupulous exploitation of consumers; and

(f) right to consumer education.”

16

27. In Lucknow Development Authority v. M.K. Gupta6

this Court held:

“The importance of the Act lies in promoting welfare of the society by

enabling the consumer to participate directly in the market economy. It

attempts to remove the helplessness of a consumer which he faces

against powerful business, described as, ‘a network of rackets’ or a

society in which, ‘producers have secured power’ to ‘rob the rest’ and

the might of public bodies which are degenerating into storehouses of

inaction where papers do not move from one desk to another as a matter

of duty and responsibility but for extraneous consideration leaving the

common man helpless, bewildered and shocked.”

28. It was further held that

“The Act thus aims to protect the economic interest of a consumer as

understood in commercial sense as a purchaser of goods and in the

larger sense of user of services. … It is a milestone in history of socioeconomic legislation and is directed towards achieving public benefit.”

29. This court has further observed in State of Karnataka v. Vishwabharathi

House Building Coop. Society,

7

that (the) “provisions of the said Act are required to

be interpreted as broadly as possible. It has jurisdiction to entertain a complaint

despite the fact that other forums/courts would also have jurisdiction to adjudicate

upon the lis”8

30. It is therefore evident that the Consumer Protection Act, 1986 was conceived

as a legislation to address complaints of consumers (an expression defined and

interpreted widely) and provide a forum for their quick redressal, and, furthermore,

wherever third parties have claimed relief, technicalities have been brushed aside

consistently, by this court. Thus, even after an original consumer is indemnified for a

fire accident, the insurer can maintain a complaint against the carrier/service

provider, and claim damages (of course along with the insured party). Likewise,

absence of privity of contract is not a bar for maintaining a complaint against a

service provider, by a third party who suffers an incident, which is otherwise covered


6

(1994) 1 SCC 243

7

(2003) 2 SCC 412

8This court also relied on Fair Air Engineers (P) Ltd. v. N.K. Modi [(1996) 6 SCC 385] and Satpal

Mohindra v. Surindra Timber Stores [(1999) 5 SCC 696

17

by an agreement. This court has also ruled, recently9

that proceedings initiated by

complainants and resultant actions including of the NCDRC are fully saved by

provisions of the Real Estate Regulatory Authority Act, 2019.

31. In view of these considerations, this court is of the opinion that the per se bar

to the relief of interest on refund, enunciated by the decision in Raje Ram (supra)

which was applied in Wg. Commander Arifur Rehman (supra) cannot be considered

good law. The nature and extent of relief, to which a subsequent purchaser can be

entitled to, would be fact dependent. However, it cannot be said that a subsequent

purchaser who steps into the shoes of an original allottee of a housing project in

which the builder has not honoured its commitment to deliver the flat within a

stipulated time, cannot expect any – even reasonable time, for the performance of the

builder’s obligation. Such a conclusion would be arbitrary, given that there may be a

large number- possibly thousands of flat buyers, waiting for their promised flats or

residences; they surely would be entitled to all reliefs under the Act. In such case, a

purchaser who no doubt enters the picture later surely belongs to the same class.

Further, the purchaser agrees to buy the flat with a reasonable expectation that

delivery of possession would be in accordance within the bounds of the delayed

timeline that he has knowledge of, at the time of purchase of the flat. Therefore, in

the event the purchaser claims refund, on an assessment that he too can (like the

original allottee) no longer wait, and face intolerable burdens, the equities would

have to be moulded. It would no doubt be fair to assume that the purchaser had

knowledge of the delay. However, to attribute knowledge that such delay would

continue indefinitely, based on an a priori assumption, would not be justified. The

equities, in the opinion of this court, can properly be moulded by directing refund of

the principal amounts, with interest @ 9% per annum from the date the builder

acquired knowledge of the transfer, or acknowledged it.

32. In the present case, there is material on the record suggestive of the

circumstance that even as on the date of presentation of the present appeal, the


9

Imperia Structures Ltd. v. Anil Patni, (2020) 10 SCC 783

18

occupancy certificate was not forthcoming. In these circumstances, given that the

purchaser/respondent had stepped into the shoes of the original allottee, and

intimated Laureate about this fact in April 2016, the interests of justice demand that

interest at least from that date should be granted, in favour of the respondent. The

directions of the NCDRC are accordingly modified in the above terms.

33. The impugned order of the NCDRC is modified in the above terms; the appeal

is partly allowed. There shall be no order on costs.

……………………………….J

[UDAY UMESH LALIT]

……...........................................J

 [HEMANT GUPTA]

……...........................................J

 [S. RAVINDRA BHAT]

New Delhi,

July 22, 2021.