LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Friday, April 23, 2021

When the contract did not prohibit the award of interest in respect of delayed payment in local currency component specified therein. - it can be granted .- This being the position, in our opinion, the contrary view expressed by the Arbitration Court in a proceeding under Section 34 of the Act, which view was upheld by the Appellate forum, breaches the permissible boundaries for encroaching upon an award as laid down in Saw Pipes case (supra). When the agreement is silent on the point of rate of interest but provides for payment of interest on delayed payment, simple interest at 8% per annum is a reasonable one - .the Tribunal’s exercise of fixing the rate should have been on the basis of applying the principle laid down in 19 paragraph 43.1. in the case of G.C. Roy (supra). The said principle is applicable in a proceeding under the 1996 Act as well. This principle has been broadly incorporated in Section 31(7) (a) of the 1996 Act. The only difference between the situation contemplated in the aforesaid provision and the facts of this case is that the agreement involved is not silent on interest entitlement of the appellants on delayed payment but the agreement contains provision for such payment. Only the rate at which interest would be payable remained unspecified. In our view, simple interest at the rate of 8% would be just and equitable on the sum left unpaid, calculated otherwise on the basis of sub­paragraphs 1.6. to 1.8 of the award.

 When the contract did not prohibit the award of interest in   respect   of   delayed   payment   in   local   currency   component specified therein.  - it can be granted .- This being the position, in our opinion, the contrary view expressed by the Arbitration Court in a proceeding under   Section   34   of   the   Act,   which   view   was   upheld   by   the Appellate   forum,   breaches   the   permissible   boundaries   for encroaching upon an award as laid down in  Saw   Pipes  case (supra). 

 When the agreement is silent on the point of rate of   interest   but   provides   for   payment   of   interest   on   delayed payment, simple interest at 8% per annum is a reasonable one - .the Tribunal’s exercise of fixing the rate should have been   on   the   basis   of   applying   the   principle   laid   down   in 19 paragraph   43.1.   in   the   case   of  G.C.   Roy  (supra).     The   said principle is applicable in a proceeding under the 1996 Act as well. This principle has been broadly incorporated in Section 31(7) (a) of   the   1996   Act.     The   only   difference   between   the   situation contemplated in the aforesaid provision and the facts of this case is that the agreement involved is not silent on interest entitlement of the appellants on delayed payment but the agreement contains provision for such payment.   Only the rate at which interest would be payable remained unspecified.   In our view, simple interest at the rate of 8% would be just and equitable on the sum left unpaid, calculated otherwise on the basis of sub­paragraphs 1.6. to 1.8 of the award.


REPORTABLE

IN THE SUPREME COURT OF INDIA

   CIVIL APPELLATE JURISDICTION

         CIVIL APPEAL NO. 3454 OF 2011

M/s. Oriental Structural Engineers Pvt. Ltd.  ...Appellant(s)

     Versus

State of Kerala …Respondent(s)

J U D G M E N T

ANIRUDDHA BOSE, J.

The  appellants were awarded a contract by the  State  of

Kerala for upgradation of a State Highway for two stretches, from

Muvattupuzha­Thodupuzha   and   Muvattupuzha–Angamaly.   The

agreement in this regard was executed on 7th  November, 2002.

This appeal originates from disputes on certain issues arising

between the parties primarily relating to making payment to the

appellants   under   certain   heads.     In   the   present   proceeding,

however, the only point of dispute on which arguments have been

advanced before us is over entitlement of the appellants to receive

interest on delayed payment on the subject­heads, which were to

1

be paid by the employer in local currency as per the stipulations

in the said agreement. The agreement had provision for resolution

of disputes by a Disputes Review Board (DRB) which was to make

recommendations at the first instance. If the recommendations

were not acceptable to any of the parties, such disagreeing party

was required to give notice to commence arbitration within a

specified   time   and   thereafter   the   dispute   was   to   be   settled

through arbitration. So far as the controversies out of which this

appeal   arises   are   concerned,   disputes   on   three   counts   arose

between the parties, which could not be resolved at the stage of

DRB recommendations.  Those disputes were referred to a threemember   Arbitral   Tribunal   (the   ‘Tribunal’   in   short).     We   have

already   referred   to   the   scope   of   controversy   involved   in   this

appeal.  This controversy shall be henceforth referred to in this

judgment as dispute on delayed payment. We shall address that

issue only in this judgment. 

2. The Tribunal passed the award in favour of the appellants

on this point and interest was directed to be paid on delayed

payment in relation to local currency component payable under

the agreement. This was, however, a majority award and not a

unanimous one as one of the members of the Tribunal gave a

2

dissenting view.  In the succeeding paragraphs of this judgment,

whenever we refer to the expression ‘award’, it shall mean the

majority award only. The award of the Tribunal was assailed by

the State of Kerala before the District Court at Ernakulam (the

Arbitration Court) by taking out an application under Section 34

of the Arbitration and Conciliation Act, 1996 (the1996 Act). This

application was allowed in part. Award of the Tribunal in favour

of the appellants on the point of interest on delayed payment was

set aside. The Arbitration Court also adjudicated upon two other

points, but as these points have not been urged before us, we do

not consider it necessary to deal with them here in this judgment.

The decision of the Arbitration Court was sustained in appeal by

a Division Bench of the Kerala High Court.  This appeal is against

the   said   Bench   decision   of   the   High   Court   delivered   on   17th

September, 2009.  The appellants want the award of the Tribunal

allowing   their   claim   for   interest   on   delayed   payment   to   be

restored. 

3. Entitlement of the contractor to interest was provided for in

sub­clause 60.8 of the agreement on delayed interim payment.

This clause has been reproduced in page 38 of the paperbook and

reads:­

3

“ Time of Payment and Interest

(a) The   amount   due   to   the   Contractor   under   any

Interim Payment Certificate issued by the Engineer

pursuant to this Clause or to any other term of the

Contract shall subject to Clauses be paid by the

Employer to the Contractor as follows.

(i) (A) In the case of Interim Payment Certificates

within   42   days   after   the   Contractor’s   monthly

statement has been submitted to the Engineer for

certification pursuant to sub­clause 60.1. Provided

that if the Engineer’s Interim Certificate has not yet

been issued within said 42 days, the Employer shall

pay the amount shown in the Contractor’s monthly

statement and that any discrepancy shall be added

to   or   deducted   from   the   next   payment   to   the

Contractor and

(B) in the case of any monthly statement submitted

by the Contractor at a time when the Bank’s loan or

credit   (from   which   part   of   the   payment   to   the

Contractor are being made) is suspended within 14

days   after   such   monthly   statement   is   submitted.

Provided  that  if  the  Engineer’s  Interim Certificate

has not yet been issued within said 14 days the

Employer   shall   pay   the   amount   shown   in   the

Contractor’s   monthly   statement   and   that   any

discrepancy shall be added to or deducted from the

next payment to the Contractor.

(ii) (A) In the case of the Final Payment Certificate

pursuant to Sub­clause 60.13 within 84 days after

the Final statement and written discharge have been

submitted to the Engineer for certification and

(B) In the case of the Final Statement submitted by

the Contractor at a time when the Bank’s loan or

credit   from   which   part   of   the   payments   to   the

Contractor   are   being   made   is   suspended   or   for

which payment under (ii) (A) becomes due after 63

days of the date of notification of the suspension

notice payment will be made within 63 days after

the date of notification of the suspension pursuant

to Sub Clause 69.6(d) provided that if the Engineer’s

Final Payment Certificate has not been issued within

4

the   said   63   days,   the   Employer   shall   pay   the

undisputed amounts shown in the Final Statement.

(b) In the event of the failure of the Employer to

make payments within the time stated the Employer

shall   pay   to   the   Contractor   interest   compounded

monthly at the rate(s) stated in the Appendix to Bid

upon all sums unpaid from the date upon which the

same should have been paid in the currencies in

which the payment are due. The provisions of the

Sub Clause are without prejudice to the Contractor’s

entitlement under Clause 69 or otherwise.”

4. The relevant provision of the appendix to the bid, the content

of   which   came   for   interpretation   before   the   Tribunal   and

thereafter before the two judicial fora stipulated:­

“ANNEXURE- P-3

Kerala State Transport Project

Volume III

Section 6: Appendix to Bid   Page 7.8

Origin of materials 60.3(a) (v) item Origin Currency

And Plants 60.3 (d) Plant,  USA

Machinery & Germany, or

Spares any other US Dollars

Bitumen & Iran,

   Thermoplastic Singapore or US Dollars

   Paint any other

Bidder to complete

Rates of Interest upon 60.8 ________ percent of payments in local 

Unpaid Sums currency. For other countries, refer to the

table below. 

Currency (as per Sub­Clause 60.1) London Inter­Bank OnLending Rate

(LIBOR) Plus 2 percent

                         USS ­do­ 

The above of interest for foreign currencies shall be supplied by the

Bidder, and these rates are subject to clarification/negotiation before

5

formalizing the Contract.

5. In their bid document, the appellants had left the space for

recording the rate of interest for payment to be made in local

currency   blank.   The   agreement   contemplated   payment   to   the

contractor in foreign currency as also in local currency. So far as

payment by foreign currency was concerned, as would be evident

from the appendix to the bid quoted in the preceding paragraph,

the London Interbank On­lending Rate (LIBOR) plus two per cent

was the specified norm. It was on this basis the State’s stand has

been   that   the   rate   of   interest   on   delayed   payment   (as

contemplated in Clause 60.8) in local currency had to be treated

as “zero” or “nil”. It has also been the position of the State,

referring to certain communications made by the appellants that

there was waiver of the claim of interest by the appellants.  In the

award, the Tribunal had repelled the argument of the State that

the words “zero” or “nil” could be read into the said column of the

“appendix to bid”. Relying on the Constitution Bench judgment of

this   Court   in   the   case   of  Secretary,   Irrigation   Department,

Government of Orissa & Ors. vs. G.C. Roy [(1992) 1 SCC 508],

6

the Tribunal held that a person deprived of the use of money to

which he is legitimately entitled has a right to be compensated

and such compensation may be called interest, compensation or

damages. Two documents originating from the appellants in the

form of written communications were relied upon by the State

before the Tribunal to contend that claim for interest, in any

event, stood waived by claimants on delayed payment of the sum

which was to be made in local currency.   First of these two

documents was a letter of the appellant dated 14th  July, 2004

(Exhibit   R­1   before   the   Tribunal)   and   the   next   was   another

written   communication   dated   3rd  August,   2004   (Exhibit   C­72

before the Tribunal).   The first letter issued by the appellants

addressed to the Chief Executive Officer, Kerala State Transport

Project reads :­

“Dear Madam,

As discussed on the above subject we confirm

that   there   is   no   provision   of   interest   on

delayed payment in the Contract and hence

interest will not be claimed.”

                           (quoted verbatim)

6. The   next   communication   dated   3rd  August,   2004   was

addressed to the same officer of the respondents. The text of this

communication is:­

7

“Dear Sir,

We wish to invite your kind attention to the

issue   of   release   of   payment   against   IPC­1

General Items as recommended by DRB.  As

a   pre­condition   for   release   of   the   said

payment, we were made to issue the above

referred   letter   dated   14.7.2004.   Our

commitment not to claim any interest on the

said   amount   released   by   you   be   treated

purely   as   a   goodwill   gesture   so   that   our

future payments are released to us without

any delay.  The said letter is restricted to the

subject claim/item only.”

(quoted verbatim)

7. Before the Tribunal, the appellants had taken a point that

the said letter of 14th  July, 2004 was issued under coercion or

duress. Their second plea on this count was that the content of

the   first   letter   was   restricted   to   release   of   withheld   amount

recommended by the Review Board in respect of Interim Payment

Certificate­I   (IPC­I).     The   Tribunal   accepted   the   stand   of   the

appellants (claimants before it).  It was, inter­alia, observed in the

award:­

“The   essential   element   of   waiver   is

intentional relinquishment of known right.

The claimant has stated that the said letter

was   given   by   them   under   coercion.   This

holds   goods   in   view   of   the   fact   and

circumstances of the case. It is also noted

that the said letter dated 14.7.04 (ext. R1) is

not   even   mentioned   in   the   defence

statement dated 29.1.05. Nor has this issue

been   raised   before   the   DRB.   So   the

8

argument of the respondent that the letter

dated 14.7.04 (ext. R1) is a waiver of the

rights of the claimant does not stand. The

fact that this letter was issued at the time of

receiving   payment   in   respect   of   IPC.   I

suggests that this was given under coercion.

The waiver does not  apply to the instant

case. This is corroborated by the fact that

the claimant has been continually agitating

for the payment of interest before and after

the issuance of the said letter.  As discussed

earlier, payment of interest on unpaid sums

was due under the terms of the contract

and under the law. The recommendation of

the DRB made after due deliberations and

discussions with the parties has relevance

in the matter.”

(quoted verbatim)

The   Tribunal   directed   interest   on   delayed   payment   in

paragraphs 1.6 to 1.8 of the award. Extract from the award

containing   these   paragraphs   would   appear   later   in   this

judgment.

8. The majority view of the Tribunal was that the contract itself

provided for payment of interest with regard to local currency and

foreign currency.  The plea of the appellants has been that there

was no waiver and in any event the communication of 14th July,

2004 followed by that of 3rd August, 2004 related to IPC­I only.

This   stand   had   been   broadly   accepted   by   the   Tribunal.   The

9

Tribunal had also accepted the appellants/claimants’ stand that

there was no waiver on claim of interest in respect of all sums

due for which Interim Payment Certificates had been issued.  The

Tribunal’s finding on that aspect was buttressed by the fact that

the   appellants/claimants   had   continued   to   raise   demand   for

interest subsequent to the issue of those two communications.

These were essentially findings on facts. 

9. The Arbitration Court and the Appellate Court in sustaining

the State’s application for setting aside the award were of the view

that the contract could not be construed to contain provisions for

interest on delay in payment with regard to the local currency

component contained in the agreement, as the appellants did not

fill up the blank space with the rate of interest.  Opinion of the

Appellate Bench was that in the event it was intention of the

claimants   to   retain   their   entitlement   to   interest   on   delayed

payment under that head, they ought to have had filled in the

blank space in the “appendix to bid”.  Another facet of the High

Court’s reasoning was that the respondents might have had been

persuaded to accept the appellants’ bid on the basis that the

appellants would claim no interest on delayed payment in such

10

situation,   as   this   factor   could   have   made   their   bid   more

competitive.  

10. This appeal, in substance, is an extension of a proceeding

under Section 34 of the 1996 Act.   To go into the question of

legality of the decisions made by the two judicial fora, we need to

test first if the grounds of challenge to the award met the test laid

down by this Court in the case of Oil Natural Gas Corporation

Ltd. vs. Saw Pipes Ltd.  [(2003) 5 SCC 705].  Contention of the

respondents has been that the Arbitral Tribunal’s order stood

vitiated under the “patent illegality” principle spelt out in that

judgment. This principle came under the broad heading of “Public

Policy” test, applying which an arbitral award could be set aside.

What would constitute patent illegality has been elaborated by

this Court in a later judgment,  Associate   Builders   vs.   Delhi

Development Authority [(2015) 3 SCC 49]. An award would be

invalidated,   as   per   this   authority,   if   the   same   was   in

contravention of substantive law of the country or contravention

of the “Arbitration Act itself”. In paragraph 42.3 of the Report (in

the case of Associate Builders), it has been held:­

11

“42.3 (c) Equally, the third subhead of patent

illegality is really a contravention of Section

28(3) of the Arbitration Act, which reads as

under:

“28.   Rules   applicable   to   substance   of

dispute.­(1)­(2)* * *

(3) In all cases, the Arbitral Tribunal shall

decide in accordance with the terms of the

contract   and   shall   take   into   account   the

usages   of   the   trade   applicable   to   the

transaction.”

This   last   contravention   must   be

understood   with   a   caveat.     An   Arbitral

Tribunal must decide in accordance with the

terms of the contract, but  if an  arbitrator

construes   a   term   of   the   contract   in   a

reasonable manner, it will not mean that the

award   can   be   set   aside   on   this   ground.

Construction of the terms of a contract is

primarily for an arbitrator to decide unless

the arbitrator construes the contract in such

a way that it could be said to be something

that   no   fair­minded   or   reasonable   person

could do.”

11. The High Court in the appeal concurred with the Arbitration

Court and concluded that omission to include the rate of interest

in the bid document, the “appendix to bid” to be specific, had

resulted in creation of contractual term that there would not be

any claim for interest on delayed payment (as per Clause 60.8) so

far as payment in local currency component contained in the

agreement   is   concerned.     In   our   opinion,   however,   the

12

interference   with   the   award   by   the   Arbitration   Court   on   this

ground   was   unwarranted.   The   underlying   reasoning   of   the

Appellate Court and earlier, the Arbitration Court on this point is

that the Tribunal went beyond the contractual term in awarding

interest. The case of G.C. Roy (supra) and a later decision of this

Court, Reliance Cellulose Products Ltd. vs. ONGC Ltd. [(2018)

9 SCC 266], were relied upon before us by the appellants to

sustain the Tribunal’s findings.  These decisions are sought to be

distinguished on behalf of the respondents on the ground that

the former decision related to interest pendente lite and both

these cases were under the Arbitration Act, 1940. Under the said

statute,  an arbitrator  had  power or jurisdiction to  grant  prereference interest under the Interest Act, 1978 as also pendente

lite and future interest. Such jurisdiction stood curbed only if

express   terms   of   the   contract   precluded   payment   of   interest.

Referring to another authority, the  Union   of   India   vs.   Bright

Power Projects   (India)   (P)  Ltd.  [(2015) 9 SCC 695], this Court

highlighted the position of law on grant of interest under Section

31(7) of the 1996 Act. In the case of  Bright   Power   Projects

(supra), it has been opined by this Court that unless otherwise

13

agreed by the parties, the Arbitral Tribunal can award interest at

reasonable rate for a period commencing from that date when the

cause of action arises till the date of the award.  In the dispute

which   forms   the   subject­matter   of   this   appeal,   being   the

agreement, there was no specific exclusion of payment of interest

on delayed payment in relation to the local currency component. 

12. On   the   other   hand,   the   specific   term   of   the   agreement

entered into by and between the parties provided for payment of

interest on delayed payment as terms of the contract.  What was

not specifically agreed upon was the rate at which such interest

would be paid. The blank space in the “appendix to the bid”, in

our opinion, cannot be construed as cancellation of the clause

providing for payment of interest of delayed release of funds. We

do not think the Appellate Court or the Arbitration Court was

right in adopting the approach that by not specifying the blank

space provided for filling in the interest rate. We are of the view

that to come to such an inference, active exclusion of payment of

interest   under   that   head   was   necessary   to   have   been

incorporated in the agreement.   Though the case of  G.C.  Roy

(supra) was delivered in a dispute to which the 1940 Act was

14

applicable, the Constitution Bench of this Court has laid down

certain general proposition or principle on the aspect of grant of

interest. This general proposition was referred to by the Tribunal.

It has been held in paragraph 43.1 of the Report (in the case of

G.C. Roy):­

“43.   The   question   still   remains   whether

arbitrator   has   the   power   to   award   interest

pendent lite, and if so on what principle. We

must reiterate that we are dealing with the

situation   where   the   agreement   does   not

provide for grant of such interest nor does it

prohibit such grant. In other words, we are

dealing with a case where the agreement is

silent as to award of interest. On a conspectus

of   aforementioned   decisions,   the   following

principles emerge:

(i) A person deprived of the use of money to

which he is legitimately entitled has a right to

be compensated for the deprivation, call it by

any   name.   It   may   be   called   interest,

compensation   or   damages.   This   basic

consideration   is  as  valid   for   the   period   the

dispute is pending before the arbitrator as it is

for the period prior to the arbitrator entering

upon the reference. This is the principle of

Section 34, Civil Procedure Code and there is

no reason or principle to hold otherwise in the

case of arbitrator.....”

13. The underlying principle guiding award of interest is that

interest payment is essentially compensatory in nature. But as

we  have  already  observed,  in  the  case  before  us,  interest  on

delayed   payment   formed   part   of   the   contract   itself.     The

15

agreement   did   not   contain   any   express   exclusion   clause   on

payment of interest on delayed payment whether on component

of payment in foreign currency or local currency. We accept the

reasoning of the Tribunal on the basis of which it rejected the

respondents’   plea   of   waiver.   This   was   a   finding   of   fact   on

appreciation of materials placed before the Tribunal. One of the

reasons   behind   the   decisions   of   the   Appellate   Court   and

Arbitration Court was that the appellants, while bidding, had

given up their claims for interest. In substance, the respondents’

assertion is that the Tribunal went beyond the contractual terms,

and   the   said   two   fora   sought   to   invoke   the   principle   of   law

contained in the third sub­head of the “patent illegality” principle

elaborated in the case of Associate Builders (supra).

14. The   Appeal   Court   accepted   reasoning   of   the   Arbitration

Court that the blank portion in the appendix to the bid would

imply “zero” or “nil”.   This reasoning, in our opinion, is flawed

and such an interpretation of the agreement would actually be

contrary to and beyond the terms of the contract. The Tribunal in

this case had already come to a factual finding on appreciation of

evidence that there was no such implication. Such an exercise on

the part of the Arbitration Court and the Appellate Court would

16

constitute rewriting the contract, which is impermissible.   The

Tribunal rejected the plea of waiver and we have reproduced its

reasoning on that point.  We cannot hold such reasoning to be

perverse or improbable in the factual background of the present

case.  The Tribunal in this case could have had awarded interest

as a compensatory or equitable measure, as there was no clause

providing for exclusion or ouster of interest payment on delayed

payment.   The   Tribunal   determined   the   rate   thereof   in   subparagraphs   1.6   to   1.8   of   the   award.   This   part   of   the   award

specifies:­

“1.6 It is, therefore, held that the Claimants

are entitled to interest on the amount as due

under   any   IPCs   issued   by   the   Engineer   or

failing which, on the amounts as shown in the

Claimants  monthly  statements   submitted  to

the Engineer for certification and when were

not   paid   or   had   been   withheld   by   the

Respondents and such interest shall be paid

by the Respondents for the period as 42 days

after   the   claimants’   respective   monthly

statements   had   been   submitted   to   the

Engineer   for   certification   to   the   date   of

payment thereof in full. The arbitral tribunal

further holds that on the unpaid sums and for

the period of delay in the payment thereof as

stated hereinabove, the Respondents shall pay

to the claimants interest at the rate of 1% per

month compounded monthly such rate being

representative of the prevalent rate of access

to money that the claimants were deprived of.

1.7 The Arbitral Tribunal therefore directs

that   the   Respondents   shall   pay   to   the

claimants interest on the unpaid sum of Rs.

17

2,15,72,150/­ for the period of the due dates

of   payment   till   the   actual   dates   of   full

payment of such amount at the rate stated in

para 1.6 above in respect of IPCs No. 2 & IPC

No. 4.

1.8 The Respondents shall further pay to

the   claimants   such   interest   on   the   unpaid

sums in respect  of other IPCs No. 5 to 14

issued   by   the   Engineer   or   the   Claimants

monthly statements submitted to the Engineer

for certification for the period from the due

dates of payment till the actual dates of full

payment at the rate as stated in hereinabove.

The respondents are also directed to pay

further interest at the rate of 12% per annum

on the interest amount determined pursuant

to para 1.7 and 1.8 hereinabove from such

dates of payment of the principal amount to

the date of award.”

15. The   Appellate   Court’s   rationale   that   such   blank   interest

column might have had resulted in acceptance of the bid of the

appellants as their bid could have been more competitive on the

assumption that the other bidders might have had pressed for

interest in that column is not acceptable to us. We do not find

any material from which such a conclusion could be reached. No

material has been shown to us from which it can be inferred that

omission to fill in the blank space gave the appellants some kind

of competitive edge in the bid process. We also do not know if

other bidders had left the space blank or filled the same with

18

specified rate. The Arbitration Court’s view, sustained by the High

Court is tainted with an element of speculation on this point. 

16. We do not find any flaw in the reasoning of the Arbitral

Tribunal that the contract did not prohibit the award of interest

in   respect   of   delayed   payment   in   local   currency   component

specified therein.   This being the position, in our opinion, the

contrary view expressed by the Arbitration Court in a proceeding

under   Section   34   of   the   Act,   which   view   was   upheld   by   the

Appellate   forum,   breaches   the   permissible   boundaries   for

encroaching upon an award as laid down in  Saw   Pipes  case

(supra). 

17. In   our   opinion,   the   view   taken   by   the   Tribunal   on

consideration of the contract was both reasonable and possible

view.   We, however, are of the opinion that the rate at which

interest has been directed to be paid as contained in paragraphs

1.6 and 1.8 of the award, which we have reproduced above, are

rather excessive.  As the agreement is silent on the point of rate

of   interest   but   provides   for   payment   of   interest   on   delayed

payment, the Tribunal’s exercise of fixing the rate should have

been   on   the   basis   of   applying   the   principle   laid   down   in

19

paragraph   43.1.   in   the   case   of  G.C.   Roy  (supra).     The   said

principle is applicable in a proceeding under the 1996 Act as well.

This principle has been broadly incorporated in Section 31(7) (a)

of   the   1996   Act.     The   only   difference   between   the   situation

contemplated in the aforesaid provision and the facts of this case

is that the agreement involved is not silent on interest entitlement

of the appellants on delayed payment but the agreement contains

provision for such payment.   Only the rate at which interest

would be payable remained unspecified.   In our view, simple

interest at the rate of 8% would be just and equitable on the sum

left unpaid, calculated otherwise on the basis of sub­paragraphs

1.6. to 1.8 of the award. We, accordingly, set aside the judgment

of the Division Bench of the High Court of Kerala impugned in

this appeal on the point of entitlement of the appellants to receive

interest   on   delayed   payment   in   relation   to   local   currency

component of the contract.  As a consequence, judgment of the

Sixth   Additional   District   Judge,   Ernakulam,   shall   also   stand

invalidated. The award of the Tribunal shall stand sustained so

far as direction to pay interest on delayed payment of the local

currency component of the agreement is concerned, but the rate

of   interest   on   the   sum   shall   be   computed   in   the   manner

20

prescribed in paragraphs 1.6, 1.7 and 1.8 and shall be at 8%

simple interest per annum. 

18. The appeal is allowed in the above terms.

19. There shall be no order as to costs. 

      .................................J.

(SURYA KANT)

...............................J.

 (ANIRUDDHA BOSE)

NEW DELHI

APRIL 22, 2021

21