LawforAll

advocatemmmohan

My photo
since 1985 practicing as advocate in both civil & criminal laws

WELCOME TO LEGAL WORLD

WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE

Sunday, October 12, 2025

Arbitration and Conciliation Act, 1996 – Section 9 – Availability of alternative remedy – Writ jurisdiction – When the contract between the parties contains a clause providing for resolution of disputes by arbitration, and the petitioner has already invoked the arbitration clause, the remedy for interim protection against invocation of Bank Guarantee lies under Section 9 of the Arbitration and Conciliation Act, 1996. The writ jurisdiction under Article 226 of the Constitution of India is therefore not to be ordinarily invoked in such contractual disputes. Performance Bank Guarantee – Invocation – Challenge under Article 226 – Maintainability – The action of respondent authority in invoking the Performance Bank Guarantee cannot be examined on merits by this Court when the contract provides for a specific dispute resolution mechanism through arbitration. Petitioner relegated to avail remedy under the Arbitration and Conciliation Act, 1996. Contract – Short closure – Invocation of Bank Guarantee – Respondent-authorities stated that the contract was short closed by notice dated 15.09.2025 and only thereafter the Performance Bank Guarantee was sought to be encashed for delay in completion of the project. Interim protection – Exercise of equitable jurisdiction – Considering the peculiar facts and circumstances of the case and the intervening Court vacations, the respondents were directed not to take any coercive steps for invocation of the Performance Bank Guarantee for one week from the date of order, to enable the petitioner to move the competent Court under Section 9 of the Arbitration and Conciliation Act, 1996. Writ Petition – Disposal – Liberty – Writ petition disposed of granting liberty to the petitioner to avail appropriate remedy under the Arbitration and Conciliation Act, 1996; miscellaneous petitions, if any, dismissed as infructuous; no costs. Result: Writ Petition disposed of – Liberty granted to avail arbitration remedy – Respondents restrained for one week from invoking Bank Guarantee – No costs.


Arbitration and Conciliation Act, 1996 – Section 9 – Availability of alternative remedy – Writ jurisdiction –

When the contract between the parties contains a clause providing for resolution of disputes by arbitration, and the petitioner has already invoked the arbitration clause, the remedy for interim protection against invocation of Bank Guarantee lies under Section 9 of the Arbitration and Conciliation Act, 1996. The writ jurisdiction under Article 226 of the Constitution of India is therefore not to be ordinarily invoked in such contractual disputes.


Performance Bank Guarantee – Invocation – Challenge under Article 226 – Maintainability –

The action of respondent authority in invoking the Performance Bank Guarantee cannot be examined on merits by this Court when the contract provides for a specific dispute resolution mechanism through arbitration. Petitioner relegated to avail remedy under the Arbitration and Conciliation Act, 1996.


Contract – Short closure – Invocation of Bank Guarantee –

Respondent-authorities stated that the contract was short closed by notice dated 15.09.2025 and only thereafter the Performance Bank Guarantee was sought to be encashed for delay in completion of the project.


Interim protection – Exercise of equitable jurisdiction –

Considering the peculiar facts and circumstances of the case and the intervening Court vacations, the respondents were directed not to take any coercive steps for invocation of the Performance Bank Guarantee for one week from the date of order, to enable the petitioner to move the competent Court under Section 9 of the Arbitration and Conciliation Act, 1996.


Writ Petition – Disposal – Liberty –

Writ petition disposed of granting liberty to the petitioner to avail appropriate remedy under the Arbitration and Conciliation Act, 1996; miscellaneous petitions, if any, dismissed as infructuous; no costs.


Result:


Writ Petition disposed of – Liberty granted to avail arbitration remedy – Respondents restrained for one week from invoking Bank Guarantee – No costs.APHC010531232025

IN THE HIGH COURT OF ANDHRA PRADESH

AT AMARAVATI

(Special Original Jurisdiction)

[0]

FRIDAY,THE THIRD DAY OF OCTOBER

TWO THOUSAND AND TWENTY FIVE

PRESENT

THE HONOURABLE SRI JUSTICE CHALLA GUNARANJAN

WRIT PETITION NO: 27157/2025

Between:

1. AIR CONTROL AND CHEMICAL ENGINEERING CO LTD, HAVING

ITS HEAD OFFICE AT 63, THE CHAMBERS, NR. GOYAL PALACE,

OPP-GURUDWARA, S.G. HIGHWAY, BODAKDEV, AHMEDABAD,

GUJARAT - 380054. REPRESENTED BY ITS MANAGING

DIRECTOR, SRI VISHAL DAGA.

...PETITIONER

AND

1. UNION OF INDIA, REPRESENTED BY ITS SECRETARY, MINISTRY

OF DEFENCE, SOUTH BLOCK NEW DELHI-110001

2. THE EASTERN NAVAL COMMAND, REPRESENTED BY THE FLAG

OFFICER COMMANDING IN CHIEF 2ND FLOOR NAVAL BASE,

VISAKHAPATNAM - 530014

3. FLEET MAINTENANCE UNIT, REP. BY THE OFFICER IN-CHARGE,

C/O. FLEET MAIL OFFICE, NAVAL DOCKYARD VISHAKAPATNAM -

530014

4. THE INDIAN OVERSEAS BANK, KALUPUR CIRCLE BRANCH,

GROUND FLOOR, BSNL BUILDING, OPPOSITE KALUPUR

RAILWAY STATION, KALUPUR, AHMEDABAD, GUJARAT - 380002

...RESPONDENT(S):

Petition under Article 226 of the Constitution of India praying that in the

circumstances stated in the affidavit filed therewith, the High Court may be

pleased topleased to issue a writ, order or direction more particularly one in

2025:APHC:41067

the nature of the Writ of Mandamus declaring the action of the Respondent

No.3 herein invoking the Performance Bank Guarantee vide PBG Number

000371124000026 dated 31.07.2024, as extended up to 15.10.2025,

amounting to Rs. 19,00, 894/- (Rupees Nineteen Lakh Eight Hundred and

Ninety Four only), vide Letter No. PC/303/H E/RAN A/24 dated 25.09.2025,

alleging breach of terms and conditions under Work Order bearing No.

PC/303/HE/RANA/24 dated 17.07.2024 as illegal, arbitrary, unjust, contrary to

the terms and conditions under Work Order bearing No. PC/303/H E/RAN

A/24 dated 17.07.2024 and principles of natural justice, besides being

violative of Articles 14, 19(1)g and 300A of the Constitution of India and/or

pass

IA NO: 1 OF 2025

Petition under Section 151 CPC praying that in the circumstances stated

in the affidavit filed in support of the petition, the High Court may be pleased

pleased direct the Respondents No. 4 herein not to honor the Performance

Bank Guarantee vide PBG Number 000371124000026 dated 31.07.2024, as

extended up to 15.10.2025, amounting to Rs. 19,00,894/- (Rupees Nineteen

Lakh Eight Hundred and Ninety Four only), pursuant to the Letter No.

PC/303/H E/RAN A/24 dated 25.09.2025 issued by the Respondent No.3

herein and pass

Counsel for the Petitioner:

1.K KOUTILYA

Counsel for the Respondent(S):

1.

The Court made the following:

2025:APHC:41067

THE HONOURABLE SRI JUSTICE CHALLA GUNARANJAN

WRIT PETITION NO: 27157/2025

ORDER:

The present writ petition is filed assailing the action of respondent No.3

invoking the Performance Bank Guarantee vide PBG number

000371124000026 dated 31.07.2024, which is extended upto 15.10.2025 to

be arbitrary, illegal and violation of principles of natural justice.

2. The petitioner has entered into the contract with respondent No.3 on

17.07.2024. The same was awarded in pursuance to tender process initiated

by respondent No.3. The total value of work awarded was for Rs.6,33,63,140/-

as per the work order. The petitioner was supposed to complete the same

within the period of six months. The petitioner was also required to furnish the

performance bank guarantee for a value of Rs.19,00,894/- as condition

precedent. The same has been complied by the petitioner on 31.07.2024

which is in force till 15.10.2025. In the process of execution of contract,

respondent No.3 had issued impugned proceeding dated 25.09.2025 for

encashment of Performance Bank Guarantee.

3. Learned counsel for the petitioner tried to advance the arguments on

merits of the matter. The contract provided for a specific dispute resolution

mechanism of invoking arbitration, the petitioner had already issued notice

dated 01.10.2025 invoking the arbitration clause under the contract. In as

much as the disputes are agreed to be resolved through arbitration, under the

provisions of Arbitration and conciliation Act, 1996, there is a specific remedy

2025:APHC:41067

for securing interim measure by way of Section 9 application. The petitioner is

therefore required to avail such remedy.

4. Learned counsel for respondent Nos.1 to 3 on instructions submitted

that by notice dated 15.09.2025, the contract has been short closed and only

thereafter, the Performance Bank Guarantee was sought to be encashed for

delay in completion of the project.

5. Since, this Court is inclined to relegate the petitioner to prefer remedy of

filing application under Arbitration and Conciliation Act, it is not proposing to

examine the merits or otherwise of the respective contentions. In peculiar

facts and circumstances of the case, considering that due to intervening

vacations, the jurisdictional Court is not functioning, the writ petition is

disposed of by granting petitioner liberty to avail appropriate remedy. The

respondents are directed not to take any coercive steps in pursuance to the

said proceedings for invocation of Bank Guarantee for a period of one week

from today. In case the petitioner prefers appropriate application before

competent Court, the same shall be considered and disposed of inaccordance

with law without being influence by any of observations made herein. No costs.

As a sequel, Miscellaneous Petitions pending, if any, shall stand

dismissed as infructuous.

_______________________

CHALLA GUNARANJAN,J

Dated: 03.10.2025

AG

2025:APHC:41067

THE HONOURABLE SRI JUSTICE CHALLA GUNARANJAN

WRIT PETITION NO: 27157/2025

Dated: 03.10.2025

AG

2025:APHC:41067