LawforAll
advocatemmmohan
- advocatemmmohan
- since 1985 practicing as advocate in both civil & criminal laws. This blog is only for information but not for legal opinions
Just for legal information but not form as legal opinion
WELCOME TO MY LEGAL WORLD - SHARE THE KNOWLEDGE
Showing posts with label condone delay of 10 years. Show all posts
Showing posts with label condone delay of 10 years. Show all posts
Friday, February 10, 2012
Limitation Act, 1963 - s.5 - Condonation of delay - Appeal by Government Corporation against judgment and decree in civil suit - Also application under for condonation of delay of 4 years - Allowed by Division Bench - Justification of - Held: Not justified - Law Department of the Government Corporation did not approach High Court with clean hands - High Court committed grave error by condoning more than four years' delay in filing of appeal ignoring the judicially accepted parameters for exercise of discretion u/s. 5 - Thus, order of High Court set aside - Application for condonation of delay dismissed - Civil Procedure Code, 1908 - O 41 r. 3A. The question which arose for consideration was whether the Division Bench of High Court was justified in condoning more than four years' delay in filing of appeal by the respondents against judgment and decree passed by the Civil Judge in the Special Civil Suit.
Allowing the appeal, the Court
HELD: 1.1. The law of limitation is founded on public policy. The
legislature does not prescribe limitation with the object of destroying the
rights of the parties but to ensure that they do not resort to dilatory
tactics and seek remedy without delay. The idea is that every legal remedy
must be kept alive for a period fixed by the legislature. To put it
differently, the law of limitation prescribes a period within which legal
remedy can be availed for redress of the legal injury. At the same time,
the courts are bestowed with the power to condone the delay, if sufficient
cause is shown for not availing the remedy within the stipulated time. The
expression "sufficient cause" employed in section 5 of the Limitation Act,
1963 and similar other statutes is elastic enough to enable the courts to
apply the law in a meaningful manner which sub serves the ends of justice.
Although, no hard and fast rule can be laid down in dealing with the
applications for condonation of delay, this Court has justifiably advocated
adoption of a liberal approach in condoning the delay of short duration and
a stricter approach where the delay is inordinate. [Para 8] [1184-c-e]
Collector, Land Acquisition, Anantnag v. Mst. Katiji (1987) 2 SCC 107; N.
Balakrishnan v. M. Krishnamurthy (1998) 7 SCC 123; Vedabai v. Shantaram
Baburao Patil (2001) 9 SCC 106, relied on.
1.2. In dealing with the applications for condonation of delay filed on
behalf of the State and its agencies/instrumentalities this Court has,
while emphasizing that same yardstick should be applied for deciding the
applications for condonation of delay filed by private individuals and the
State, observed that certain amount of latitude is not impermissible in the
latter case because the State represents collective cause of the community
and the decisions are taken by the officers/agencies at a slow pace and
encumbered process of pushing the files from table to table consumes
considerable time causing delay. [Para 8] [1184-f-h; 1185-a]
G. Ramegowda v. Spl. Land Acquisition Officer (1988) 2 SCC 142; State of
Haryana v. Chandra Mani (1996) 3 SCC 132; State of U.P. v. Harish Chandra
(1996) 9 SCC 309; State of Bihar v. Ratan Lal Sahu (1996) 10 SCC 635; State
of Nagaland v. Lipok Ao (2005) 3 SCC 752; State (NCT of Delhi) v. Ahmed
Jaan (2008) 14 SCC 582, relied on.
2.1. A reading of the impugned order makes it clear that the High Court did
make a bald reference to the application for condonation of delay filed by
the respondents but allowed the same without adverting to the averments
contained therein and the reply filed on behalf of the appellant. The High
Court erroneously assumed that the delay was of 1067 days, though, as a
matter of fact, the appeal was filed after more than four years. Another
erroneous assumption made by the High Court was that the appellant had not
filed reply to controvert the averments contained in the application for
condonation of delay. It may have been possible for this Court to ignore
the first error in the impugned order because by deleting the figures and
words "4 years and 28" in paragraphs 2 and 3 of the application and
substituting the same with the figure 1067, the respondents misled the High
Court in believing that the delay was of 1067 days only but it is not
possible to fathom any reason why the Division Bench of the High Court
omitted to consider the detailed reply which had been filed on behalf of
the appellant to contest the prayer for condonation of delay.
Notwithstanding this, the impugned order may have been set aside and
remitted the case to the High Court for fresh disposal of the application
filed by the respondents under section 5 of the Limitation Act but, it is
not proper to adopt that course because the respondents did not approach
the High Court with clean hands. [Para 10] [1185-a-h; 1186-a]
2.2. It is clear that the Law Department of respondent No.1 was very much
aware of the proceedings of the first as well as the second suit. In the
first case, RM was appointed as an advocate and in the second case BR was
instructed to appear on behalf of the respondents, but none of the officers
is shown to have personally contacted either of the advocates for the
purpose of filing written statement and preparation of the case and none
bothered to appear before the trial Court on any of the dates of hearing.
It is a matter of surprise that even though an officer of the rank of
General Manager (Law) had issued instructions to RM to appear and file
vakalat as early as in May 2001 and Manager (Law) had given vakalat to BR
Advocate in the month of May 2005, in the application filed for condonation
of delay, the respondents boldly stated that the Law Department came to
know about the ex parte decree only in the month of January/February 2008.
The respondents went to the extent of suggesting that the parties may have
arranged or joined hands with some employee of the corporation and that may
be the reason why after engaging advocates, nobody contacted them for the
purpose of giving instructions for filing written statement and giving
appropriate instructions which resulted in passing of the ex parte decrees.
The above statement is not only incorrect but is ex facie false and the
High Court committed grave error by condoning more than four years' delay
in filing of appeal ignoring the judicially accepted parameters for
exercise of discretion under section 5 of the Limitation Act. [Para 13]
[1187-g-h; 1188-a]
2.3. The impugned order of the High Court is set aside and the application
for condonation of delay filed by the respondents is dismissed. As a
corollary, the appeal filed by the respondents against judgment and decree
dated 30.10.2004 shall stand dismissed as barred by time. However, it is
made clear that the disposal of the instant appeal shall not absolve the
higher functionaries of respondent No.1 from the responsibility of
conducting a thorough probe into the matter so that accountability of the
defaulting officers/officials may be fixed and the loss, if any, suffered
by respondent No.1 recovered from them after complying with the rules of
natural justice. [Para 14] [1188-b-c]
State of Bihar and others v. Kamleshwar Prasad Singh and another 2000 AIR
SC 2388; Spl. Tehsildars, Land Acquisition, Kerala v. K.V. Ayisumma AIR
1996 SC 2750; Punjab Small Industries and Export Corporation Ltd. and
others v. Union of India and others 1995 Suppl. (4) SCC 681; P.K.
Ramachandran v. State of Kerala and another (1997) 7 SCC 566, referred to.
Case Law Reference:
2000 AIR SC 2388 Referred to Para 5
AIR 1996 SC 2750 Referred to Para 5
1995 Suppl. (4) SCC 681 Referred to Para 5
(1997) 7 SCC 566 Referred to Para 5
(1987) 2 SCC 107 Relied on Para 8
(1998) 7 SCC 123 Relied on Para 8
(2001) 9 SCC 106 Relied on. Para 8
(1988) 2 SCC 142 Relied on Para 8
(1996) 3 SCC 132 Relied on Para 8
(1996) 9 SCC 309 Relied on Para 8
(1996) 10 SCC 635 Relied on Para 8
(2005) 3 SCC 752 Relied on Para 8
(2008) 14 SCC 582 Relied on. Para 8
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2075 of 2010.
From the Judgment & Order dated 25.3.2009 of the High Court of Gujarat at
Ahmedabad in Civil Application No. 14201 of 2008 in First Appeal No. 4180
of 2008.
L.N. Rao, Nikhil Goel, Naveen Goel, Marsoak Bafaki, Sheela Goel for the
Appellant.
Anip Sachthey, Mohit Paul, Shagun Matta, Sherin Daniel for the Respondents.
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No.2075 of 2010
(Arising out of S.L.P. (C) No.10965 of 2009)
Oriental Aroma Chemical Industries Ltd. ...Appellant
Versus
Gujarat Industrial Development Corporation ...Respondents
and another
J U D G M E N T
G.S. Singhvi, J.
1. Leave granted.
2. Whether the Division Bench of Gujarat High Court was justified in
condoning more than four years' delay in filing of appeal by the
respondents against judgment and decree dated 30.10.2004 passed by
Civil Judge (Sr. Division) Gandhinagar (hereinafter referred to as "the trial
Court") in Special Civil Suit No.32 of 2001 is the question which arises for
consideration in this appeal.
2
3. The appellant was allotted a piece of land for setting up an industrial
unit at Ankleshwar subject to the terms and conditions embodied in
agreement of licence dated 2.4.1976 which, among other things, provided
for consumption of specified quantity of water by the appellant. The
agreement also provided for payment of 70% of the cost of agreed quantity
of water irrespective of consumption. In 1982, respondent No.1 demanded
non utilization charges amounting to Rs.4068/-, which were deposited by
the appellant. After some time, respondent No.1 demanded Rs.2,69,895/-
towards water charges. For next 10 years, the parties entered into long
correspondence on the issue of levy of water charges, etc. Finally,
respondent No.1 issued bill dated 13.1.1996 requiring the appellant to pay
Rs.22,96,207/- towards water charges. The appellant challenged the
same in Special Civil Suit No.32 of 2001. The summons issued by the trial
Court were duly served upon the respondents but no written statement
was filed on their behalf to controvert the averments contained in the plaint
and none appeared on the dates of hearing despite the fact that the case
was adjourned on more than one occasion. The suit was finally decreed
on 30.10.2004 and it was declared that the appellant is not liable to pay
Rs.22,96,207/- by way of minimum charges for water for the period
between 1978 and 16.4.2001 and, thereafter, till the water was supplied by
respondent No.1. After few months, the appellant filed another suit which
was registered as Civil Suit No.222 of 2005 and prayed that respondent
3
No.1 be directed to issue no objection certificate in its favour. The
summons of the second suit were also served upon the respondents, but
neither the written statement was filed nor any one appeared on their
behalf. The second suit was also decreed on 12.12.2007 and respondent
No.1 was directed to issue no objection certificate to the appellant. In
compliance of the decree passed in the second suit, the concerned
authority of the Corporation issued no dues certificate dated 9.7.2008.
4. After four months and fifteen days of taking action in furtherance of
the decree passed in the second suit, the respondents filed an appeal
against judgment and decree dated 30.10.2004 passed in Special Civil
Suit No.32 of 2001. They also filed an application under Order 41 Rule 3A
of the Code of Civil Procedure read with Section 5 of the Limitation Act for
condonation of delay by making the following assertions:
"1. That this appeal is preferred against the judgment and
decree of the learned Civil Judge (SD), Gandhinagar passed
on 30.10.2004. That the suit was filed for permanent
injunction and declaration and on the ground that the
advocate of the GIDC has appeared but no written statement
was filed and, therefore, the learned Judge resorted to Order 8
Rule 11 of the Civil Procedure Code and granted the
declaration as prayed for in the plaint. That after the decree
being passed, the present plaintiff filed another suit being Civil
Suit No.222 of 2005 and in which the decree was passed on
12.12.2007. That particular decree is to be challenged before
this Honourable Court and, therefore, in 2008, after the
second decree was passed, it was brought to the notice of the
Legal Department as well as to the Executive Engineer at
GIDC, Ankleshwar as to how this has happened and it seems
that because of numerous transfers as well as it is also
4
possible that the party might have arranged or joined hands
with some employee of the Corporation and thereby after
engaging advocate, no body has gone to the advocate for the
purpose of giving instruction or filing the written statement and
as a result thereof, decree is passed and only in the month of
January/February, the law department came to know and
therefore, an inquiry was made into the matter but the GIDC
could not trace out as to at whose hands the mistake or
mischief was done, however, when after inquiry everything
was noticed and, therefore, the application for certified copy
was made on 17.11.2008 and on 18.11.2008, the copy was
ready and the same was sent to the advocate and thereafter
the present appeal is preferred.
2. That a long span from 30.10.2004 to 18.11.2008,
practically four years time is passed and this has happened
only because of some mistake or mischief on the part of the
staff and, therefore, the appeal could not be preferred,
otherwise it is a matter of substantial right of the GIDC where
the water charges are leveled in spite of water being used or
not and when the bills were already drawn, there was not
intention on the part of the GIDC not to contest the suit. But it
is difficult to trace out how this has happened and, therefore,
when the inquiry was conducted in detail, the facts were
brought to the notice and on that basis the cause has arisen to
file this appeal and the delay of 1067 days cause in filing the
appeal is required to be condoned in the interest of justice."
On notice, a detailed reply was filed on behalf of the appellant in the form
of an affidavit of its Director, Shri Sanjay Kantilal Shah, paragraphs 4.16, 5
and 6 whereof read as under:
"4.16. That the First Appeal preferred by the appellant
has been preferred with Civil Application No.14201 of 2008
and the said application for condonation of delay under Order
41 Rule (3A) read with Section 5 of the Limitation Act. As a
matter of fact, the petitioner company being a Government
Corporation is bound to follow the rules and regulations as it is
and cannot deviate itself from the provisions of law. As a
matter of fact in filing the present First Appeal there is a delay
of more than 4 years. Moreover, in the second suit, the
5
decree and judgment is already passed and thereafter now
the petitioner has no right to challenge the order of the Civil
Suit No.32/2001. But for the reasons best known to the
appellant the correct number of days has not been mentioned
in the condonation of delay application. As a matter of fact,
the petitioner being a Government Corporation has to follow
the rules and regulations strictly and is required to give proper
explanation as to why the Appeal has not been preferred
within the time frame and if they were so, being aggrieved by
the order passed by the Ld. Civil Judge (SD) Gandhinagar. If
the condonation of delay is taken into consideration the said
page is only a 4 pages wherein no proper explanation as to
what the petitioner was doing for the past year has been given
in the said and thereby also the said application is required to
be dismissed in limine.
5. With regard to para -1 of the Civil Application, I most
humbly and respectfully submit that it is true that the decree
passed by the Ld. Civil Judge (S.D) Gandhinagar on
13.10.2004. It is also true that in the said Suit, the advocate
for the GIDC had appeared but had not filed written statement
and therefore, the Ld. Judge has passed the order under the
provisions of the Code of Civil Procedure and granted
declaration as prayed for in the plaint. It is also true that after
decree was passed, the present respondent filed another suit
being Civil Suit No.222/2005 and the said decree was passed
on 12.12.2007. It is not true that in the year 2008 after the
second decree was passed it was brought to the knowledge of
the Legal Department that the earlier decree was required to
be challenged. Lack of legal knowledge cannot be said to be
ground to condone the delay. If the facts had not been
brought well in time then for the said it cannot be said that the
respondent company is required to be punished. As a matter
of fact nothing has been mentioned on Affidavit as to who did
not give proper instructions or as to who had possibly played
the mischief and as to who had joined the hand with the
respondent company. It is only the blame game which is
being played and allegations are being leveled in order to
save its own skin but there is no truth behind the facts
mentioned therein and thereby there is no way as to how the
present application can ever be allowed. Moreover the
respondent is not knowing any persons of the G.I.D.C. (as on
today or at any time).
6
6. With regard to para-2 of the Civil Application, I most
humbly and respectfully say and submit that it is true that
more than 4 years time has been passed from the date of the
decree but as to who has played the mischief or mistake or
had it been intentionally filed within the time frame that is for
the reasons best known to the appellant corporation and that
is something on which the petitioner company would not like to
comment at this juncture. No proper justification or
explanation has been brought on record as to what was
happening for the past 4 years, has also not given anything in
detail and neither true and correct facts have been mentioned
nor the calculation in respect of the days have been made
properly and thereby also on all the said counts, the present
application is required to be dismissed with exemplary cost."
5. The Division Bench of the High Court referred to the judgments of
this Court in State of Bihar and others v. Kamleshwar Prasad Singh
and another, 2000 AIR SC 2388, N. Balakrishnan v. M. Krishnamurthy,
JT 1998 (6) SC 242, State of Haryana v. Chandra Mani and others AIR
1996 SC 1623, Spl. Tehsildars, Land Acquisition, Kerala v. K.V.
Ayisumma AIR 1996 SC 2750, Punjab Small Industries and Export
Corporation Ltd. and others v. Union of India and others 1995 Suppl.
(4) SCC 681, P.K. Ramachandran v. State of Kerala and another (1997)
7 SCC 566 and Collector, Land Acquisition, Anantnag v. Mst. Katiji
AIR 1987 SC 1353 and condoned the delay by making a cryptic
observation that the cause shown by the respondents is sufficient. The
relevant portion of the High Court's order is reproduced below:
"Applying the principles laid down by the Supreme Court to the
facts of the present case, we are satisfied that sufficient cause
7
is made out by the applicant for condonation of delay. Over
and above, in view of the fact that reasons mentioned in this
application have not been controverted by the other side and
also in view of the principles governing the discretionary
exercise of power under Section 5 of the Limitation Act, 1963,
we are of the view that sufficient cause has been stated for not
filing the appeal in time and hence, delay caused in filing
appeal is to be condoned and the application is required to be
allowed."
(Emphasis supplied)
6. Shri L.N. Rao, learned senior counsel appearing for the appellant
argued that the impugned order is liable to be set aside because the High
Court allowed the application for condonation of delay by erroneously
assuming that the delay was of 1067 days only. Learned senior counsel
pointed out that appeal against judgment and decree dated 30.10.2004
was filed on 24.11.2008 i.e., after more than four years, but by scoring out
the figures and words "4 years and 28" in paragraphs 2 and 3 of the
application and substituting the same with figure "1067", the respondents
misled the High Court in believing that delay was of 1067 days. He then
referred to affidavit dated 16.2.2009 of Shri Sanjay Kantilal Shah to show
that substantial grounds had been put forward on behalf of the appellant
for opposing the respondents' prayer for condonation of delay of more than
four years and submitted that the Division Bench of the High Court
committed serious error in condoning the delay by assuming that no reply
had been filed by the appellant. Learned senior counsel also invited the
Court's attention to affidavits dated 25.11.2009 and 4.2.2010 of Shri Pravin
8
Keshav Lal Modi and Shri Harishbhai Patel respectively filed in this Court
on behalf of the respondents as also the list of events attached with the
second affidavit to show that the functionaries of respondent No.1 were
very much aware of the proceedings of Special Civil Suit No.32 of 2001
and Civil Suit No.222 of 2005 and submitted that the High Court should not
have accepted patently incorrect assertions contained in the application for
condonation of delay, which was supported by an affidavit of none else
than the General Manager of respondent No.1, Shri R.B. Jadeja, that the
Law Department came to know about the judgment of Special Civil Suit
No.32/2001 only in January/February, 2008.
7. Shri Anip Sachthey, learned counsel for the respondents fairly
admitted that the appeal was filed after lapse of more than four years of
judgment dated 30.10.2004 but submitted that this Court should not
interfere with the discretion exercised by the High Court to condone the
delay and the respondents should not be penalized simply because the
advocates appointed by the Corporation did not bother to file written
statement and appear before the trial Court on the dates of hearing.
Learned counsel emphasized that this Court has repeatedly taken
cognizance of the lethargy and callousness with which litigation is
conducted on behalf of the State and its agencies/instrumentalities at
various levels and condoned the delay so as to enable them to contest the
9
matters on merit and submitted that similar approach may be adopted in
the present case and the appellant may be compensated by award of
adequate cost.
8. We have considered the respective submissions. The law of
limitation is founded on public policy. The legislature does not prescribe
limitation with the object of destroying the rights of the parties but to ensure
that they do not resort to dilatory tactics and seek remedy without delay.
The idea is that every legal remedy must be kept alive for a period fixed by
the legislature. To put it differently, the law of limitation prescribes a period
within which legal remedy can be availed for redress of the legal injury. At
the same time, the courts are bestowed with the power to condone the
delay, if sufficient cause is shown for not availing the remedy within the
stipulated time. The expression "sufficient cause" employed in Section 5 of
the Indian Limitation Act, 1963 and similar other statutes is elastic enough
to enable the courts to apply the law in a meaningful manner which sub
serves the ends of justice. Although, no hard and fast rule can be laid
down in dealing with the applications for condonation of delay, this Court
has justifiably advocated adoption of a liberal approach in condoning the
delay of short duration and a stricter approach where the delay is
inordinate - Collector, Land Acquisition, Anantnag v. Mst. Katiji (1987)
2 SCC 107, N. Balakrishnan v. M. Krishnamurthy (1998) 7 SCC 123 and
10
Vedabai v. Shantaram Baburao Patil (2001) 9 SCC 106. In dealing with
the applications for condonation of delay filed on behalf of the State and its
agencies/instrumentalities this Court has, while emphasizing that same
yardstick should be applied for deciding the applications for condonation of
delay filed by private individuals and the State, observed that certain
amount of latitude is not impermissible in the latter case because the State
represents collective cause of the community and the decisions are taken
by the officers/agencies at a slow pace and encumbered process of
pushing the files from table to table consumes considerable time causing
delay - G. Ramegowda v. Spl. Land Acquisition Officer (1988) 2 SCC
142, State of Haryana v. Chandra Mani (1996) 3 SCC 132, State of U.P.
v. Harish Chandra (1996) 9 SCC 309, State of Bihar v. Ratan Lal Sahu
(1996) 10 SCC 635, State of Nagaland v. Lipok Ao (2005) 3 SCC 752,
and State (NCT of Delhi) v. Ahmed Jaan (2008) 14 SCC 582.
9. In the light of the above, it is to be seen whether the respondents
had offered any plausible/tangible explanation for the long delay of more
than four years in filing of appeal and the High Court was justified in
condoning the delay.
10. A reading of the impugned order makes it clear that the High Court
did make a bald reference to the application for condonation of delay filed
11
by the respondents but allowed the same without adverting to the
averments contained therein and the reply filed on behalf of the appellant.
Not only this, the High Court erroneously assumed that the delay was of
1067 days, though, as a matter of fact, the appeal was filed after more
than four years. Another erroneous assumption made by the High Court
was that the appellant had not filed reply to controvert the averments
contained in the application for condonation of delay. It may have been
possible for this Court to ignore the first error in the impugned order
because by deleting the figures and words "4 years and 28" in paragraphs
2 and 3 of the application and substituting the same with the figure 1067,
the respondents misled the High Court in believing that the delay was of
1067 days only but it is not possible to fathom any reason why the Division
Bench of the High Court omitted to consider the detailed reply which had
been filed on behalf of the appellant to contest the prayer for condonation
of delay. Notwithstanding this, we may have set aside the impugned order
and remitted the case to the High Court for fresh disposal of the application
filed by the respondents under Section 5 of the Limitation Act but, do not
consider it proper to adopt that course, because as will be seen
hereinafter, the respondents did not approach the High Court with clean
hands.
12
11. The statement containing the list of events annexed with the affidavit
of Shri Harishbhai Patel shows that before filing suit, the appellant had
issued notice dated 5.2.2001 to which respondent No.1 sent reply dated
13.3.2001. The summons of Special Civil Suit No. 32/2001 instituted by
the appellant were served upon the respondents sometime in the month of
April/May 2001. On 16.5.2001, General Manager (Law) instructed Ms.
Rekhaben M. Patel to appear on behalf of the respondents. Executive
Engineer, Ankleshwar was also directed to contact the advocate for
preparing the reply affidavit. On 23.5.2001, Deputy Executive Engineer,
Ankleshwar forwarded the comments to Ms. Rekhaben M. Patel. On
18.4.2002, the appellant filed an application for ex parte proceedings
against the respondents. On 30.11.2002, the trial Court directed the
respondents to appear on 12.12.2002 with indication that if they fail to do
so, ex parte proceedings will be held. Thereupon, General Manager (Law)
wrote letter dated 10.12.2002 to Ms. Rekhaben to remain present on the
next date of hearing i.e., 12.12.2002. On 30th December, 2002, Deputy
Executive Engineer, Ankleshwar wrote to the advocate in the matter of
submission of para-wise comments. On 2.1.2003, the Executive Engineer
is said to have sent a letter to the advocate informing her about the next
date of hearing i.e., 10.1.2003 and asked her to remain present. After
almost one year and ten months, the trial Court pronounced the ex parte
judgment and decreed the suit. The summons of the second suit were
13
received sometime in May, 2005. On 20.6.2005, Shri B.R. Sharma,
Advocate was instructed to appear on behalf of the respondents. On
10.1.2006, Deputy Executive Engineer, Ankleshwar informed the new
advocate about the next date of hearing which was 23.1.2006. The
second suit was decreed on 12.12.2007.
12. During the course of hearing, learned counsel for the respondents
fairly conceded that in the second suit filed by the appellant there was a
specific mention of decree dated 30.10.2004 passed in Special Civil Suit
No. 32/2001. He also conceded that even though the first suit remained
pending before the trial Court for three years and five months and the
second suit remained pending for more than two years, none of the officers
of the Law Department or the Engineering Department of respondent No.1
appeared before the Court.
13. From what we have noted above, it is clear that the Law Department
of respondent No.1 was very much aware of the proceedings of the first as
well as the second suit. In the first case, Ms. Rekhaben M. Patel was
appointed as an advocate and in the second case Shri B.R. Sharma was
instructed to appear on behalf of the respondents, but none of the officers
is shown to have personally contacted either of the advocates for the
purpose of filing written statement and preparation of the case and none
14
bothered to appear before the trial Court on any of the dates of hearing. It
is a matter of surprise that even though an officer of the rank of General
Manager (Law) had issued instructions to Ms. Rekhaben M. Patel to
appear and file vakalat as early as in May 2001 and Manager (Law) had
given vakalat to Shri B.R. Sharma, Advocate in the month of May 2005, in
the application filed for condonation of delay, the respondents boldly stated
that the Law Department came to know about the ex parte decree only in
the month of January/February 2008. The respondents went to the extent
of suggesting that the parties may have arranged or joined hands with
some employee of the corporation and that may be the reason why after
engaging advocates, nobody contacted them for the purpose of giving
instructions for filing written statement and giving appropriate instructions
which resulted in passing of the ex parte decrees. In our view, the above
statement contained in para 1 of the application is not only incorrect but is
ex facie false and the High Court committed grave error by condoning
more than four years' delay in filing of appeal ignoring the judicially
accepted parameters for exercise of discretion under Section 5 of the
Limitation Act.
14. In the result, the appeal is allowed. The impugned order of the High
Court is set aside and the application for condonation of delay filed by the
respondents is dismissed. As a corollary, the appeal filed by the
15
respondents against judgment and decree dated 30.10.2004 shall stand
dismissed as barred by time. However, it is made clear that the disposal of
this appeal shall not absolve the higher functionaries of respondent No.1
from the responsibility of conducting a thorough probe into the matter so
that accountability of the defaulting officers/officials may be fixed and the
loss, if any, suffered by respondent No.1 recovered from them after
complying with the rules of natural justice.
......................................J.
[G.S. Singhvi]
......................................J.
[Asok Kumar Ganguly]
New Delhi,
Dated: February 26, 2010.
Thursday, February 9, 2012
CODE OF CIVIL PROCEDURE, 1908: Or. 22,r.4 - Abatement of appeal -Inordinate delay in filing application for bringing legal heirs on record and for setting aside abatement - High Court passed a conditional order giving final opportunity to do the needful, failing which the appeal was to stand dismissed-Order not complied with-Subsequently, High Court allowed all applications condoning 3703 days delay in filing the application to bring the legal heirs on record and 883 days delay in filing petition to set aside the dismissal order-Held: Whilst considering applications for condonation of delay u/s 5 of the Limitation Act, the courts do not enjoy unlimited and unbridled discretionary powers- All discretionary powers, especially judicial powers, have to be exercised within reasonable bounds, known to the law-The discretion has to be exercised in a systematic manner informed by reason-Whims or fancies, prejudices or predilections can not and should not form the basis of exercising discretionary powers-High Court, having recorded its conclusions and findings on the unacceptable explanation for delay, should not have condoned unconscionable delay-Judgment of High Court is unsustainable either in law or in equity and is set aside-Limitation Act, 1963-s. 5. ADMINISTRATION OF JUSTICE: Remarks in judgment of High Court on performance of government pleaders - Appeal filed by State Government, before High court-Inordinate delay on the part of Government pleaders in taking steps to bring heirs and legal representative of the respondent on record-Remarks made by High Court against Government pleaders-Held: High Court has, rather sarcastically, dubbed the government pleaders as without merit and ability-The approach adopted by the High Court tends to show the absence of judicial balance and restraint, which a Judge is required to maintain whilst adjudicating any lis between the parties-The High Court not being satisfied with the use of mere intemperate language, resorted to blatant sarcasms-The use of unduly strong intemperate or extravagant language in a judgment has been repeatedly disapproved by this Court in a number of cases-The order of the High Court is based purely on the personal perceptions and predilections of the Judges on the bench-The latent anger and hostility ingrained in the expressions employed in the judgment have denuded the judgment of impartiality-In its desire to castigate the government pleaders and the Court staff, the High Court has sacrificed the "justice oriented approach", the bedrock of which is fairness and impartiality-The caustic remarks made by the High Court, against the government pleaders and the Court staff clearly exhibit a departure from settled principles- The judgment of the High Court is unsustainable either in law or in equity and, as such, is set aside- Code of Civil Procedure, 1908-Or. 22, r.4 - Strictures - Judicial restraint. During the pendency of the appeal before the High Court against judgment and decree in a suit for declaration of title and permanent injunction, the plaintiff-respondent died on 25.2.1990 and his counsel filed a memo before the High Court giving the said intimation after notice to the advocate for the appellants. When the appeal came up for hearing on 24.4.1997, the counsel for the plaintiff-respondent again brought to the notice of the High Court the factum of death of his client. Since, inspite of the directions of the High Court, no steps were taken to bring the legal heirs and representatives of the plaintiff-respondent on record, on 6.2.1998, it gave one week's time for compliance failing which the appeal would stand dismissed. As the order was not complied with, the appeal stood dismissed in terms of the order dated 6.2.1998. In the year 2000, an application was filed by the judgment-debtors before the High Court seeking condonation of 883 days delay in filing the petition to set aside the dismissal order dated 6.2.1998. On 17.8.2000 another application was filed seeking to condone 3703 days delay to bring the legal representatives on record. It was accompanied by an application under Order 22 , Rule 4, CPC. After several adjournments at the instance of the judgment- debtors, the appeal was listed for hearing on 19.8.2003 on which date the High Court allowed all the applications and restored the appeal and posted it for hearing. Aggrieved, the heirs and legal representatives of the plaintiff filed the appeals.
Allowing the appeals, the Court
HELD: 1.1. This Court while issuing notice in the SLP had directed
proceedings in the appeal pending in the High Court to remain stayed
meanwhile. Therefore, it is evident that the situation as on date is as it
was when the order was passed on 06.02.1998 i.e. , appeal filed by
respondent Nos. 1 and 2 stood abated and, as such, dismissed. [Para 16]
[229-C]
1.2. Generally speaking, the courts including this Court, adopt a liberal
approach in considering the application for condonation of delay on the
ground of sufficient cause u/s 5 of the Limitation Act. [para 19] [230-C]
Balwant Singh (dead) Vs. Jagdish Singh, 2010 (8) SCR597= (2010) 8 SCC
685; N. Balakrishnan Vs. M. Krishnamurthy 1998 (1) Suppl. SCR 403=
(1998) 7 SCC 123; Mithailal Dalsangar Singh & Ors. Vs. Annabai Devram Kini
& Ors. (2003) 10 SCC 691; and Sardar Amarjit Singh Kalra (dead) by LRs Vs.
Pramod Gupta (dead) by LRs. 2002 (5) Suppl. SCR350= (2003) 3 SCC 272;
and Collector, Land Acquisition, Anantnag & Ors. Vs. Katiji & Ors. 1987 (2)
SCR 387= (1987) 2 SCC 107 - referred to.
1.3. Whilst considering applications for condonation of delay u/s 5 of the
Limitation Act, 1963, the courts do not enjoy unlimited and unbridled
discretionary powers. All discretionary powers, especially judicial powers,
have to be exercised within reasonable bounds, known to the law. The
discretion has to be exercised in a systematic manner informed by reason.
Whims or fancies, prejudices or predilections can not and should not form
the basis of exercising discretionary powers. [para 26] [234-G-H; 235-A]
1.4. The High Court, in the instant case, graphically narrated the clear
dereliction of duty by the government pleaders concerned in not pursuing
the appeal before it diligently, and set out the different stages at which
the government pleaders had exhibited almost culpable negligence in
performance of their duties. It found the justification given by the
government pleaders to be unacceptable. Having recorded such conclusions,
inexplicably, the High Court proceeds to condone the unconscionable delay.
Such a course was not open to the High Court, given the pathetic
explanation offered by the respondents in the application seeking
condonation of delay. There does not seem to be any logic or rationale,
which could have impelled the High Court to condone the delay after holding
the same to be unjustifiable. The concepts such as "liberal approach",
"justice oriented approach", "substantial justice" cannot be employed to
jettison the substantial law of limitation. Especially, in cases where the
court concludes that there is no justification for the delay. [para 24,
25-26] [234-B-C; 235-F; 234-D]
2.1. In the opening paragraph of the impugned order the High Court has,
rather sarcastically, dubbed the government pleaders as without merit and
ability. The approach adopted by the High Court tends to show the absence
of judicial balance and restraint, which a Judge is required to maintain
whilst adjudicating any lis between the parties. The High Court, not being
satisfied with the use of mere intemperate language, resorted to blatant
sarcasms. The use of unduly strong intemperate or extravagant language in a
judgment has been repeatedly disapproved by this Court in a number of
cases. [para 25-26] [233-G; 234-F]
2.2. The order of the High Court is based purely on the personal
perceptions and predilections of the Judges on the bench. The latent anger
and hostility ingrained in the expressions employed in the judgment have
denuded the judgment of impartiality. In its desire to castigate the
government pleaders and the Court staff, the High Court has sacrificed the
"justice oriented approach", the bedrock of which is fairness and
impartiality. It is also well known that anger deprives a human being of
his ability to reason. Judges being human are not immune to such
disability. It is of utmost importance that in expressing their opinions,
Judges and Magistrates be guided only by the considerations of doing
justice. The caustic remarks made by the High Court, against the government
pleaders and the Court staff clearly exhibit a departure from the well
established principles. [para 27-28] [235-B-D; 236-D]
State of U.P. Vs. Mohammad Naim (1964)2 SCR 363 - relied on.
3. The judgment of the High Court is unsustainable either in law or in
equity and, as such, is set aside. [para 29] [236-E]
Case Law Reference:
2010 (8) SCR597 referred to para 18
1998 ( 1 ) Suppl. SCR 403 referred to para 18
(2003) 10 SCC 691 referred to para 18
2002 (5 ) Suppl. SCR350 referred to para 18
1987 ( 2 ) SCR 387 referred to para 19
(1964)2 SCR 363 relied on para 27
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2909-2913 of 2005.
From the Judgment & Order dated 19.08.2003 of the High Court Judicature
Andhra Pradesh at Hyderabad in CMP Nos. 21114-21118 of 2003.
P.S. Narasimha and R. Sundaravardan, M. Srinivas R. Rao, K. Parameshwar,
Sudhu Gupta, G.N. Reddy, V. Pattabhi Ram, C.K. Sucharita and V. Mohana for
the appearing parties.
REPORTABL
E
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2909-2913 OF 2005
Lanka Venkateswarlu (D) by LRs. .. Appellants
VERSUS
State of A.P. & Ors ..Respondents
J U D G M E N T
SURINDER SINGH NIJJAR, J.
1. These appeals are directed against the order passed
by a Division Bench of the High Court of Judicature of
Andhra Pradesh at Hyderabad in CMP Nos. 21114,
21115, 21116, 21117 and 21118 of 2003 dated 19th
August, 2003. By the aforesaid order, the High Court
has allowed all the petitions/applications.
2. In the applications/petitions, respondent No.3,
herein, had sought the following directions:-
"
CMP
No. 21114/2003: Petition under
Order 22 Rule 4 of the CPC praying that in
the circumstances stated in the affidavit titled
therewith, the High Court will be pleased to
permit the petitioners to bring the above stated
persons as legal representatives of the
deceased sole respondent in Appeal
No. 8 of 1985 on the file of the High Court.
CMP No. 21115/2003: Petition U/s praying
that the High Court may be pleased to set
aside the dismissal Order dated 6.2.98 in AS
No.8 of 1985 and to restore the appeal to file.
CMP No. 21116/2003: Petition Under Order 9
Rule 9 read with section 151 CPC, praying that
the High Court may be pleased to set aside the
abatement caused due to the death of sole
respondent i.e. Lanka Venkateswarlu.
CMP No. 21117/2003:
Between
Sri D.E.V Apparao ...Petitioner/impleaded
Petitioner in AS No.8 of 1985 on the file of
High Court
And:
1. The State of A.P. rep. by District
Collector, Visakhapatnam.
2. The Tahsildar, Visakhpatnam
...Respondent/Appellants
3. Lanka Venkateswarlu (died)
...Respondent
2
Petition under Order 1 Rule 10 CPC, prays this
Hon'ble Court may be pleased to permit the
petitioners society to be impleaded as
appellant No.3 along with the appellants No. 1
and 2 in AS. 8 of 1985 on the file of the
Hon'ble Court to prosecute the appeal.
CMP No. 21118/2003: Petition U/s 5 of
Limitation Act praying the High Court may be
pleased to condone the delay of 883 days in
filing the petition seeking to set aside the
dismissal order dated 6.2.1998.
These petitions coming on for hearing, upon
perusing the petition and the affidavit filed in
support thereof and upon hearing the
arguments of Govt. pleader for Appeal for
Petitioners in CMP Nos. 21114, 21115, 21116,
21118 of 2003 and of Mr. K. Sarva Bhouma
Rao, Advocate for petitioner in CMP
No. 21117 of 2003 and of Mr. M.S.R.
Subramanyam, Advocate for the respondents
in CMP Nos. 21114, 21115, 21116, 21118 of
2003 and G.P. for Appeal for the respondents
in CMP No. 21117 of 2003."
3. We may now briefly notice the relevant facts as
stated in the pleadings of the parties and the impugned
order of the High Court. The predecessor of the
appellants, i.e., Shri Lanka Venkateswarlu, (hereinafter
referred to as `original plaintiff'), brought a suit O.S. No.
72 of 1979 before the subordinate judge Visakhapatnam
3
for the declaration of his title as the absolute owner of
the suit schedule property and for permanent injunction
restraining respondents Nos. 1 and 2 from interfering
with his peaceful possession. The suit schedule property,
to the extent of 2 acres was, according to the original
plaintiff, covered by survey No. 73/12 in Thokada village.
He had purchased the suit schedule property by a
registered sale deed dated 15th July, 1961 from one
Gonna Appanna son of Venkataswamy of China Gantyda
village. The original plaintiff was constrained to file the
aforesaid suit on coming to know that respondent Nos. 1
and 2 were claiming the suit schedule land to be "banjar
land" which vested in the Government. He had also
learned that the land was in imminent danger of being
illegally alienated by the respondent Nos. 1 and 2. They
were claiming that the land was required to issue Pattas
to weaker sections of society.
4. Respondent Nos. 1 and 2 were impleaded as the
defendants to the suit. Subsequently, the suit was
4
transferred to the Court of IVth Additional District Judge,
Visakhapatnam and renumbered as O.S. No. 83 of 1981.
5. The aforesaid averments of the original plaintiffs
were controverted by the respondent Nos. 1 and 2. It was
claimed that the plaint schedule property was not
covered by old survey No. 73/12 of the original village of
Thokada. The boundaries as well as survey number were
stated to be fictitious, forged and imaginary. Even the
ownership of the ancestors of the vendor of the original
plaintiff of the suit schedule land was denied. Further,
the alleged sale deed dated 15th July, 1961 between the
original plaintiff and the vendor was denied. It was also
stated that the original plaintiff was not in possession
and enjoyment of the plaint schedule property.
6. On the pleadings of the parties, the trial court
framed six issues. Issue No. 1 pertains to the title of the
original plaintiff to the schedule property. Issues No.2 &
3 were with regard to, whether the original plaintiff was
5
entitled to relief of declaration and injunction as prayed
for. Issue No.4 was whether the suit is not maintainable.
A perusal of the judgment of the trial court shows that
the suit was hotly contested on each and every issue.
Issues 1, 2, 3, 4 and 6 were decided in favour of the
original plaintiff and against the defendants, i.e.,
respondent Nos. 1 and 2. Issue No.5 with regard to
valuation of the suit was not pressed by the government
pleader. The suit was decreed by judgment dated
24th September, 1982.
7. The respondents challenged the aforesaid judgment
and decree by filing an appeal before the High Court of
Andhra Pradesh being A.S. No. 8 of 1985. The sole
respondent, i.e., original plaintiff died on 25th February,
1990. Therefore, the Advocate appearing for the
deceased original plaintiff being the `sole respondent' in
the appeal filed a memo before the High Court giving
intimation about the death of his client. The memo was
filed after giving notice to the advocate for respondent
6
Nos. 1 and 2, who were appellants in the aforesaid
appeals. In spite of such intimation, respondent Nos. 1
and 2 failed to bring the legal representatives of the
deceased original plaintiff on record.
8. From the judgment of the High Court it is apparent
that the appeal came up for hearing on 24th April, 1997.
At that stage, the counsel for the appellants again
brought to the notice of the Court that his client has
passed away on 25th February, 1990. The High Court
directed the government pleader to take steps to bring on
the record the legal representatives of the original
plaintiff and posted the matter for hearing on 16th June,
1997. It appears that no actions were taken by the
respondents to comply with the order passed by the High
Court on 24th April, 1997. Therefore, on 6th February,
1998, Justice V. Rajagopala Reddy, J. passed the
following order:-
"Appeal under Section 96 CPC against the
order of the Court of the IV Addl. District
Judge, Visakhapatnam dt.24.09.1982 in O.S.
No. 83/81.
7
This appeal coming on for orders under
Rule 64 of the Appellate Side Rules of the High
Court on the failure of the Appellant herein.
1. To take steps to bring on record the LRs. of
the deceased sole respondent.
In the presence of G./P. for Excise for the
Appellant and of Mr. M.S.R. Subramanyam,
Advocate for the respondent No.1.
It is ordered as follows:
1. That the Appellant do within one week from
the date of this order comply with the
requisitions of the Office referred to above
and;
2. That in default of compliance with the said
requisitions within the time prescribed in
clause 1 supra, the Appeal shall stand
dismissed as against the sole respondent
herein."
9. The aforesaid order was admittedly not complied
with. Consequently, the appeal stood abated in terms of
the order dated 6th February, 1998. It appears that
thereafter CMPSR No. 49656 of 2000 was moved by
respondent Nos. 1 and 2 seeking condonation of 883
days delay in filing the petition to set aside the dismissal
order dated 6th February, 1998. The application was
8
accompanied by an affidavit where it is candidly admitted
by respondent No.2 that the order dated 6th February,
1998 was not complied with. It was further admitted
that as the order dated 6th February, 1998 was not
complied with, the default order came into force and the
appeal stood dismissed.
10. In this affidavit, the explanation given is that the
predecessors of the officer, who affirmed the affidavit
dated 11th July, 2000 came to know about the dismissal
of the appeal during the course of investigation in
original O.S. No. 6 of 2000 which had been filed by the
widow and the children of the deceased original plaintiff,
i.e., sole respondent in the appeal. It is also admitted
that thereafter, an application was filed for setting aside
the order of abatement dated 6th February, 1998, but,
without any application seeking condonation of delay of
883 days in filing the petition. To cover the foresaid
lapse, CMP No. 21118 of 2003 was filed seeking
condonation of delay of 883 days in filing the petition.
9
11. Thereafter CMPSR No. 58644 of 2000 was filed on
17th August, 2000 with a prayer to condone the delay of
3703 days to bring the legal representatives on record.
CMPSR No. 58646 of 2000 was filed to bring the legal
representatives of the deceased original plaintiff on
record and CMPSR No. 58645 of 2000 to set aside the
order of dismissal in AS No. 8 of 1985 dated 6th February,
1998 was filed. These applications were subsequently
numbered as noted in the heading of the impugned
judgment.
12. It appears from the impugned order of the High
Court and CMPSR No. 58644 of 2000 was numbered as
CMP no. 17186 of 2000 on 17th August, 2000 and listed
before the Court on 27th September, 2000. The High
Court granted two weeks time for filing the counter. The
aforesaid CMP was posted for hearing before the bench
on 16th October, 2000 (Venkatanarayan,J.). At that time,
counsel for the deceased original plaintiff submitted that
1
his client had died in 1990 and he had no instructions.
Therefore, the Court directed to issue notice to the
parties on the petition. Even at that stage the
government pleader did not bring to the notice of the
Court that the applications filed by respondent Nos. 1
and 2 to set aside the order of dismissal and to bring the
legal representatives on record were pending
consideration.
13. Thereafter it appears the matter was adjourned on a
number of occasions from 27th June, 2001 to 9th April,
2002. Surprisingly, on 3rd June, 2002 the government
pleader again took time from the Court to verify whether
any separate application was filed for restoration of the
appeal and whether any such application was pending or
not. Thereafter the matter was not pursued by the
government pleader.
14. In the meantime, the alleged beneficiaries to whom
Pattas had been granted by the Government Poramboke
1
in the year 1979 filed CMP No. 21705 of 2000, seeking
permission of the Court to come on record as the third
appellant in the appeal. In the impugned order, it is also
pointed out that the pendency of the applications had
come to the notice of the Court intermittently. It appears
that the application to condone the delay in filing the
petition for setting aside the order of dismissal was filed,
when the lapse was pointed by the Court.
15. Thereafter, it seems that without the adjudication of
any of the applications on merits, the appeal was listed
for hearing before the Bench, which culminated into
passing the judgment and order dated 19th August, 2003,
subject matter of the present appeal. By the aforesaid
judgment, the High Court has allowed all the applications
restored the appeal posted it for hearing on 25th August,
2003.
16. This Court while issuing notice in the SLP
on 15th December, 2003 directed that "in the meantime,
1
proceedings in the appeal pending in the High Court
shall remain stayed". Therefore, it is evident that the
situation today is as it was when the order was passed on
6th February, 1998, i.e., appeal filed by the respondent
Nos. 1 and 2 stood abated and hence dismissed.
17. We have heard the learned counsel for parties.
Mr. P.S. Narasimha, senior advocate, appearing for the
appellant submitted that the impugned order of the High
Court cannot be justified on any legal ground. He
submits that the High Court having itself recorded the
utter negligence of the respondents in pursuing the
appeal at every stage, without any justification, condoned
the delay. The learned senior counsel pointed out that
there was no explanation, much less any plausible
explanation to justify the delay of 3703 days in filing the
application for bringing on record the LRs. of the sole
respondent or for the delay in filing the application for
setting aside the order dated 6th February, 1998. It was
further submitted that there was no justification to
1
permit the respondent No.3 to be impleaded as a party in
the appeal. Learned counsel relied on the judgment of
this Court in the case of Balwant Singh (dead) Vs.
Jagdish
Singh1
in support of the submission that the
law of limitation has to be enforced in its proper
prospective. Even though the Courts have power to
condone the delay, it can not be condoned without any
justification. Such an approach would result in rendering
the provisions contained in the Limitation Act redundant
and inoperative.
18. On the other hand, learned counsel for the
respondents relied on the judgments of this Court in the
case of N. Balakrishnan Vs. M.
Krishnamurthy2
,
Mithailal Dalsangar Singh & Ors. Vs. Annabai Devram
Kini & Ors.3 and Sardar Amarjit Singh Kalra (dead) by
LRs Vs. Pramod
Gupta (dead) by LRs.4
and submitted
1 (2010)8 SCC 685
2 (1998) 7 SCC 123
3 (2003) 10 SCC 691
4 (2003) 3 SCC 272
1
that the High Court in condoning the delay has merely
advanced the cause of substantial justice.
19. We have considered the submissions made by the
learned counsel. At the outset, it needs to be stated that
generally speaking, the courts in this country, including
this Court, adopt a liberal approach in considering the
application for condonation of delay on the ground of
sufficient cause under Section 5 of the Limitation Act.
This principle is well settled and has been set out
succinctly in the case of Collector, Land Acquisition,
Anantnag & Ors. Vs. Katiji & Ors.5
20. In the case of M. Balakrishnan (supra), this Court
again reiterated the principle that rules of limitation are
not meant to destroy the rights of parties. They are
meant to see that the parties do not resort to dilatory
tactics, but seek their remedy promptly.
5 (1987) 2 SCC 107
1
21. In the case of Sardar Amarjit Singh Kalra (supra),
this Court again emphasized that provisions contained in
the Order 22 CPC were devised to ensure continuation
and culmination in an effective adjudication and not to
retard further progress of the proceedings. The provisions
contained in the Order 22 are not to be construed as a
rigid matter of principle, but must ever be viewed as a
flexible tool of convenience in the administration of
justice. It was further observed that laws of procedure
are meant to regulate effectively, assist and aid the object
of doing a substantial and real justice and not to
foreclose even adjudication on merits of substantial
rights of citizen under personal, property and other laws.
In the case of Mithailal Dalsangar Singh and Ors. Vs.
Annabai Devram Kini & Ors, (Supra), this Court again
reiterated that in as much as abatement results in denial
of hearing on the merits of the case, the provision of an
abatement has to be construed strictly. On the other
hand, the prayer of setting aside abatement and the
1
dismissal consequent upon abatement had to be
considered liberally. It was further observed as follows:-
"The Courts have to adopt a justice oriented
approach dictated by the uppermost
consideration that ordinarily a litigant ought
not to be denied an opportunity of having a lis
determined on merits unless he has, by gross
negligence, deliberate inaction or something
akin to misconduct, disentitled himself from
seeking the indulgence of the court."
22. The concepts of liberal approach and
reasonableness in exercise of the discretion by the Courts
in condoning delay, have been again stated by this Court
in the case of Balwant Singh (supra), as follows:-
"25. We may state that even if the term
"sufficient cause" has to receive liberal
construction, it must squarely fall within the
concept of reasonable time and proper conduct
of the party concerned. The purpose of
introducing liberal construction normally is to
introduce the concept of "reasonableness" as it
is understood in its general connotation."
"26. The law of limitation is a substantive law
and has definite consequences on the right
and obligation of party to arise. These
principles should be adhered to and applied
appropriately depending on the facts and
circumstances of a given case. Once a
valuable right has accrued in favour of one
party as a result of the failure of the other
party to explain the delay by showing sufficient
1
cause and its own conduct, it will be
unreasonable to take away that right on the
mere asking of the applicant, particularly
when the delay is directly a result of
negligence, default or inaction of that party.
Justice must be done to both parties equally.
Then alone the ends of justice can be achieved.
If a party has been thoroughly negligent in
implementing its rights and remedies, it will be
equally unfair to deprive the other party of a
valuable right that has accrued to it in law as
a result of his acting vigilantly."
23. Let us now examine as to whether the High Court
was justified in condoning the delay in the peculiar facts
of the presence case. The High Court in its judgment
records the following conclusions:-
"(1) The Government Pleader having filed the
appeal on 18.2.1983 has taken three long
years to get the appeal numbered.
(2) The sole respondent died in 1990. The
learned counsel for the respondent submits
that he served a letter on the learned
Government Pleader bringing to his notice
about the death of his client in 1990 itself.
Since the letter is not traced we are not giving
much importance to that fact. But at the same
time this fact was brought to the notice of the
Government Pleader on 24.2.1997 when the
appeal was listed for hearing.
(3) Even though the Court gave sufficient time
the Government Pleader has not taken any
steps to bring LRs. on record.
1
(4) After one year the Court passed a
Conditional Order on 6.2.1998 and the appeal
was dismissed for not bringing the LRs. on
record.
(5) After two more years the concerned
officials of the Government and the
Government Pleader in office at the relevant
point of time, filed some applications, which
are not in order.
(6) Even then they have not bestowed any
attention either to comply with the defects in
filing the application or in getting the orders
are passed on these applications. But at the
same time they went on taking time without
knowing for what purpose they were taking
time.
In the result an appeal which would have been
disposed of in 1997 remained pending all these
years mainly due to the negligence on the part
of the Government Pleader in office.
Thereafter at the two stages, the High Court records
that:-
"In the normal course we would have thrown
out these applications without having second
thought in the matter.............."
"We have already observed that in the normal
course we would have dismissed the
applications for severe latches on the part of
the appellants and their counsel."
1
24. Having recorded the aforesaid conclusions, the High
Court proceeded to condone the delay. In our opinion,
such a course was not open to the High Court, given the
pathetic explanation offered by the respondents in the
application seeking condonation of delay.
25. This is especially so in view of the remarks made by
the High Court about the delay being caused by the
inefficiency and ineptitude of the government pleaders.
The displeasure of the Court is patently apparent from
the impugned order itself. In the opening paragraph of
the impugned order the High Court has, rather
sarcastically, dubbed the government pleaders as without
merit and ability. Such an insinuation is clearly
discernable from the observation that "This is a classic
case, how the learned government pleaders appointed on
the basis of merit and ability (emphasis supplied) are
discharging their function protecting the interest of their
clients". Having said so, the High Court, graphically
narrated the clear dereliction of duty by the concerned
2
government pleaders in not pursuing the appeal before
the High Court diligently. The High Court has set out the
different stages at which the government pleaders had
exhibited almost culpable negligence in performance of
their duties. The High Court found the justification given
by the government pleaders to be unacceptable. Twice in
the impugned order, it was recorded that in the normal
course, the applications would have been thrown out
without having a second thought in the matter. Having
recorded such conclusions, inexplicably, the High Court
proceeds to condone the unconscionable delay.
26. We are at a loss to fathom any logic or rationale,
which could have impelled the High Court to condone the
delay after holding the same to be unjustifiable. The
concepts such as "liberal approach", "justice oriented
approach", "substantial justice" can not be employed to
jettison the substantial law of limitation. Especially, in
cases where the Court concludes that there is no
justification for the delay. In our opinion, the approach
2
adopted by the High Court tends to show the absence of
judicial balance and restraint, which a Judge is required
to maintain whilst adjudicating any lis between the
parties. We are rather pained to notice that in this case,
not being satisfied with the use of mere intemperate
language, the High Court resorted to blatant sarcasms.
The use of unduly strong intemperate or extravagant
language in a judgment has been repeatedly disapproved
by this Court in a number of cases. Whilst considering
applications for condonation of delay under Section 5 of
the Limitation Act, the Courts do not enjoy unlimited and
unbridled discretionary powers. All discretionary powers,
especially judicial powers, have to be exercised within
reasonable bounds, known to the law. The discretion
has to be exercised in a systematic manner informed by
reason. Whims or fancies; prejudices or predilections
can not and should not form the basis of exercising
discretionary powers.
2
27. The order of the High Court, in our opinion, is
based purely on the personal perceptions and
predilections of the Judges on the bench. The latent
anger and hostility ingrained in the expressions employed
in the judgment have denuded the judgment of
impartiality. In its desire to castigate the government
pleaders and the Court staff, the High Court has
sacrificed the "justice oriented approach", the bedrock of
which is fairness and impartiality. Judges at all levels in
this country subscribe to an oath when entering upon
office of Judgeship, to do justice without fear or favour, ill
will or malice. This commitment in form of a solemn oath
is to ensure that Judges base their opinions on
objectivity and impartiality. The first casualty of
prejudice is objectivity and impartiality. It is also well
known that anger deprives a human being of his ability
to reason. Judges being human are not immune to such
disability. It is of utmost importance that in expressing
their opinions, Judges and Magistrates be guided only by
the considerations of doing justice. We may notice here
2
the observations made by a Constitution Bench of this
Court in the case of State of U.P. Vs. Mohammad
Naim
6
, which are of some relevance in the present
context. In Paragraph 11 of the judgment, it was
observed as follows:-
"If there is one principle of cardinal importance
in the administration of justice, it is this: the
proper freedom and independence of Judges
and Magistrates must be maintained and they
must be allowed to perform their functions
freely and fearlessly and without undue
interference by any body, even by this Court.
At the same time it is equally necessary that in
expressing their opinions Judges and
Magistrates must be guided by considerations
of justice, fair-play and restraint. It is not
infrequent that sweeping generalisations defeat
the very purpose for which they are made. It
has been judicially recognised that in the
matter of making disparaging remarks against
persons or authorities whose conduct comes
into consideration before courts of law in cases
to be decided by them, it is relevant to
consider (a) whether the party whose conduct
is in question is before the court or has an
opportunity of explaining or defending himself;
(b) whether there is evidence on record bearing
on that conduct, justifying the remarks; and
(c) whether it is necessary for the decision of
the case, as an integral part thereof, to
animadvert on that conduct. It has also been
recognised that judicial pronouncements must
be judicial in nature, and should not normally
depart from sobriety, moderation and reserve."
6 (1964) 2 SCR 363
2
28. We are of the considered opinion that the caustic
remarks made by the High Court, against the government
pleaders and the Court staff clearly exhibits a departure
from the principles quoted above.
29. We are of the considered opinion that the judgment
of the High Court is unsustainable either in law or in
equity. Consequently, the appeals are allowed. The
impugned judgment of the High Court is set aside with
no order as to costs.
...................................J.
[B.Sudershan Reddy]
...................................J.
[Surinder Singh Nijjar]
New Delhi;
February 24, 2011.
2
Delay -6500- On the part of Government litigant - Condonation of - Land ceiling proceeding - Land Tribunal holding that declarants were holding lands in excess of the ceiling limit - Writ petitions challenging the order of Tribunal by declarants and also by State - Writ by declarants withdrawn - State's writ dismissed - Review filed by State alleging fraud on the part of declarant and the Secretary of Land Tribunal - Delay of 14 years in filing the Review - Dismissal of Review Petition - Special Leave Petition - Delay in filing of 6500 days against original order and 300 days against order in Review
Held: Delay, specially in cases where large tracts of land and large sums
of revenue involved, is done to protect unscrupulous litigants at the cost
of public interest/public exchequer - Courts though take liberal attitude
in delay by Government, yet such attitude can be extended upto a certain
limit - s.5 of Limitation Act must receive liberal construction so as to
advance substantial justice - In the instant case, in order to protect
public justice, delay condoned, subject to payment of exemplary cost of
Rs.10 Lakhs - SLP to be admitted subject to payment of the cost -
Limitation Act, 1963 - s.5 - Cost - Imposition of as a condition for
condonation of delay - Constitution of India, 1950 - Article 136 -
Admission of SLP, subject to payment of cost - Practice and Procedure -
Karnataka Land Reforms Act, 1961 - s.66(4) - Administration of justice.
G. Ramegowda, Major etc. v. The Special Land Acquisition Officer, Bangalore
AIR 1988 SC 897 - relied on.
State (NCT of Delhi) v. Ahmed Jaan 2008 (11) SCALE 455; Nand Kishore v.
State of Punjab 1995(6) SCC 614 - referred to.
Case Law Reference
2008(11)SCALE 455 Referred to. Para 15
1995 (6) SCC 614 Referred to. Para 16
AIR 1988 SC 897 Relined on. Para 19
CIVIL APPELLATE JURISDICTION : Special Leave Petiton (C ) Nos. 11398-11400
of 2009
From the Judgement and Order dated 07.11.1990 of the High Court of
Karnataka at Bangalore in W.P. No. 40425 of 1982, W.P. No. 10920 of 1983
and order dated 26.09.2007 in R.P. 817 of 2004 in WP No. 40425 of 1982, C/W
WP No. 10920 of 1983
Sanjay R. Hegde, for the Appellant(s).
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE PETITON (C ) NOS. OF 2009
(Arising out of CC Nos. 3324-3326 OF 2009)
State of Karnataka ...Petitioner
Versus
Y. Moideen Kunhi( dead) by Lrs. And Ors. ...respondents
JUDGMENT
Dr. ARIJIT PASAYAT, J
1. The special leave petitions are directed against the judgment and order
dated 7.11.1990 in Writ Petition No.40425 of 1982 and Writ Petition
No.10920 of 1983 and order dated 26.9.2007 in Review Petition No.817 of
2004 passed by a learned Single Judge of the Karnataka High Court. It
appears that there is a delay of more than nearly 6500 days against the
original order and about 300 days so far as the review petition is concerned.
2. Before dealing with the question of delay it is necessary to take note
of the State's case before the High Court.
3. The records disclose that the agricultural lands to the extent of 50.89
acres, 30.00 acres, 462.00 acres, 3485.83 were purchased through registered
partnership firm M/s Y. Moideen Kunhi & Company. All the lands are sub-
divisions of Sy. No.146 of Neriya Village, Puttur Taluk.
4. The declaration under Section 66 (4) of the Karnataka Land Reforms
Act, 1961(hereinafter referred to as the `Act') was filed by the three
partners of the firm i.e.. respondent Nos. 1,2 and 3 herein for determination
of the excess holding. In the very declaration it is stated that the lands being
the plantation lands, are exempted under Section 104 of the Act. It is further
mentioned therein that all the declarants are the partners of the firm, having
1/3rd share in the properties purchased and that the declarants have furnished
the declaration without prejudice to their contentions that the provision of
the Act and the provisions of the Karnataka Ordinance No. 11 of 1975 are
not applicable to the aforesaid lands. The Land Tribunal, Belthangady by the
2
order dated 27.9.1982, held that the declarants are holding the lands to an
extent of 368.16 acres in excess of the ceiling limit. The tribunal opined that
2820 acres are exempted lands. After deducting the tenanted lands and
exempted lands, the Tribunal ultimately held that an area of 530.16 acres has
to be taken into consideration for the purpose of determining excess holding.
After deducting 10 units for each of the declarants, the Tribunal held that an
area of 368.16 acres is the excess land. Thereafter the Land Tribunal suo
motu initiated review proceedings under Section 122 A of the Act for
reviewing its order dated 27.9.1982. The review proceedings were also
dropped on 10.11.1982.
5. The order of the Land Tribunal was questioned before the High Court
by the three declarants in W.P. no. 40425/1982. So also the State of
Karnataka challenged the order of the Land Tribunal by filing W.P. No.
10920 of 1983. During the course of hearing, the three declarants withdrew
W.P. No, 40425/1982. However, W.P. No. 10920/1983 filed by the State of
Karnataka was dismissed by the High Court on 7.11.1990 on merits holding
that there is no error in the order passed by the Land Tribunal.
3
6. It was contended on behalf of the State that the Tahsildar being the
Secretary of the Land Tribunal should have sent the declaration filed under
Section 66 of the Act by the three declarants, to the Deputy Commissioner to
be dealt with under the provision of Section 79B of the Act, to consider the
question by the registered partnership firm is valid or not; instead he
proceeded to submit the report to the Land Tribunal which has no
jurisdiction to decide the question about the lands purchased by the firm, the
Tahsildar should not have been merely dependant upon the certificates of the
Cardamom Board and Rubber Board to conclude that the lands in question
are plantation lands, the Tahsildar has fraudulently prepared the inspection
report according to which he visited the lands in question within a day and
that he could not visit every nook and corner of the lands in question, that
the Land Tribunal should also not have entertained the declaration filed
under Section 66 of the Act as the lands have been purchased and held by
the registered firm, that the Tribunal also says that the members of the Land
Tribunal inspected the lands within one day, which is a make believe affair;
that the statement made before the High Court in W.P. No. 42774/1982 that
the excess lands have been surrendered, is also a fraud practiced on the
Court inasmuch as the declarants have not actually surrendered the excess
lands; that the learned Judge who decided W.P. No. 10920/1983 has opined
4
that the Tahsildar being the Government official, there was no need to send
notice to the State or other officials, that when the Tahsildar who is directly
concerned with the case has practiced fraud, learned Judge should have
issued notice to the Deputy Commissioner or Revenue Secretary; that the
learned Judge while disposing of W.P. No. 10920/1983 has opined that the
declarants claim the lands not as partners but in their personal capacity
which is an error apparent on the face of the record as the declaration itself
has been filed as the partners of firm; that fraud vitiates everything and
therefore the order passed by the Tribunal as well as by the High Court in
W.P. No. 10920/1983 are null and void as they are obtained by the
declarants by practicing fraud. Therefore the review petition was filed.
7. Stand of the respondents on the other hand was that no fraud was
committed by the respondents or by the Secretary of the Land Tribunal.
Error of judgment cannot be equated to fraud and since there was a delay of
14 years in filing the review petition even after the Deputy Commissioner
allegedly discovered the alleged fraud on 10.2.2003 the delay in filing the
review petition which was in fact filed on 8.10.2004 has not been explained.
It was their stand that non filing of the appeal by the State will not amount to
fraud by the officials of the State.
5
8. The High Court found that there was no element of fraud and,
therefore, the review petition was dismissed. However, liberty was given to
the State or the Tribunal to get the land to the extent of 368.16 acres
surrendered in accordance with law.
9. The State found that the allegation of fraud related to non surrender of
the land. Stand of the respondents was that lands were surrendered by the
declarants before the surveyor of the State who had accepted the possession.
The High Court accepted that the land was surrendered before the Tribunal
as is required under law. It was further observed that if the State felt that the
lands surrendered by the respondents are not suitable, it is open to the State
to initiate action under Section 67 (3A) of the Act. Liberty was given to the
Tribunal or the State to initiate steps for getting the land surrendered in
accordance with Section 67 by initiating necessary proceedings.
10. It is submitted by learned counsel for the appellant that this Court
while dealing with an application for condonation of delay especially those
filed by governments, has held that adoption of strict standard of proof
sometimes fails to protect public justice, and it would result in public
mischief by skilful management of delay in the process of filing an appeal.
6
11. It is submitted that many government matters are delayed by either
the nature of the bureaucratic process or by deliberate manipulation of the
same by taking advantage of loopholes in the conduct of litigation.
12. By way of an example only reference is invited to Chapter 3 of a
report for the year 2003 of the Comptroller and Auditor General of India.
The chapter entitled REVIEW ON HANDLING OF APPEAL CASES IN
THE CENTRAL EXCISE DEPARTMENT reads in pertinent part as under:
3.5 Analysis of adverse decisions due to departmental lapses
3.5.1 Dismissal of Appeals on account of delay
in filing of appeals
13. As per instructions issued by the Board in October 1991, the
Commissioner of Central Excise, must ensure that all the documents
including the original certified copy of the CEGAT order, photocopies of
the order-in-original & order-in-appeal alongwith application for
condonation of delay are enclosed with the proposal sent to the Board for
filing civil appeal before the this court. The time limit prescribed for
review by the Commissionerate is 10 days from the date of receipt of
certified copy of the order. The processing of case at the Board's office
includes drafting, vetting and finalisation of appeal. The jurisdictional
7
Commissioner within 60 days may file the appeal from the date of receipt
of the CEGAT orders in the Commissionerate of Central Excise.
14. Test check of the records, in 16 Commissionerates of Central Excise,
revealed that 32 appeals filed by the department involving revenue of
Rs.50.41 crore were dismissed by this Court and 3 cases involving Rs.2.00
crore by CEGAT on account of abnormal delays in filing of the appeals.
Audit scrutiny revealed that delays had occurred at all the stages viz. receipt
of certified copy, submission of papers to the Board, examination of papers
at Board's office, drafting of appeal by the Panel Counsel; and filing of
appeal by the CCE. The total period of delay varied. from 119 to 691 days.
Some of the illustrative cases are discussed below: -
(i) Delay by Panel Counsel
The CEGAT set aside (March 1997) an order issued by CCE in April
1992 confirming demand of Rs.29.13 crore and penalty of Rs.2 crore,
against M/s. National Organic Chemicals. India Limited, in Mumbai VI
Commissionerate of Central Excise, for invoking Section 11A without
adequate evidence of intention to evade duty. This Court on 15 January,
1999 dismissed the appeal filed by the department against the CEGAT order
dated 5 March 1997, on account of delay in filing of appeal by seven
8
months. The period of delay included four months taken by the Panel
Counsel in drafting the appeal.
(ii) Delay by the Board
In the case of M/s. Time Pharma, involving revenue of Rs.1.83 crore ,
the Commissionerate of Central Excise Mumbai II (now Mumbai III)
received certified copy of the CEGAT's order after 14 days on 4 February
1997 and sent comments to the Board after 23 days as against prescribed
period of 10 days. Although the Board decided before 17 April 1997 to go in
appeal, the appeal was filed only on 5 June 1998. This court dismissed the
appeal on the ground that there was an inordinate delay of about 360 days in
filing the appeal without giving any satisfactory explanation. The
Commmissionerate of Central Excise attributed the delay to the Board.
(iii) Supplementary appeal filed after six years Mumbai II
Commissionerate of Central Excise, filed an appeal in CEGAT on 14 June,
1993 against an order of the Commissioner dated 31 March 1992 regarding
irregular availment of SSI exemption and consequent availment of Modvat
credit at higher rates by a group of six assessees (M/s. Azo Dye Chem and
five others). The appeal was, however, filed in respect of only one assessee
9
whereas the case was against all the six manufacturing units and fourteen
others being Directors and Managers of the said units. After six years, on the
instructions from Junior Departmental Representative, the supplementary
appeals alongwith application for condonation of delay in filing appeals
against the others were filed in CEGAT on 11 October 1999 under section
35 E (4) of the Act. However, CEGAT dismissed these appeals on 21 July,
2000 borrowing a Larger Bench decision dated 12 July, 2000 in the same
case where it was held that CEGAT has no power to condone the delay.
The main appeal filed in time (14 June 1993) was also dismissed by CEGAT
on 21 July, 2000 on the ground that no appeal had been filed against the
other noticee. The revenue involved in this case was Rs.1.18 crore.
(iv) Frivolous reasons for condonation
In Hyderabad I Commissionerate of Central Excise, two appeals filed
by the department against order of Commissioner (Appeals) on whether
certain products manufactured by the assessees (M/s.Neyland Laboratories
Limited and M/s. Aurbindo Pharma Ltd.) are bulk drugs under `Drugs and
Cosmetics Act', were dismissed (17 August 2002) by CEGAT as time
barred as there was a delay of 48 days in filing the appeals. The reasons put
forth by the department that the new Collector of Central Excise needed time
to familiarize to the work were not accepted. Failure to file an appeal before
10
CEGAT in time resulted in dismissal of the appeal involving revenue of
Rs.81.81 lakh.
15. It is submitted that even with the introduction of safeguards against
delay in the process, in an occasional case delay occurs which is inexplicable
in normal circumstances. The question is whether such delay, should result
in the negation of the state's claim and at the cost of the interest of the
members of the public whose cause has not been carefully espoused. It is
submitted by the appellant-State that in such cases, delay must be visited
with consequences but the interest of the inhabitants of the State must be
protected.
In State (NCT of Delhi) v. Ahmed Jaan 2008 (11) SCALE 455 it was
held as follows:
....It is axiomatic that decisions are taken by officers/ agencies
proverbially at slow pace and encumbered process of pushing
the files from table to table and keeping it on table for
considerable time causing delay - intentional or otherwise - is a
routine. Considerable delay of procedural red-tape in the
process of their making decision is a common feature.
Therefore, certain amount of latitude is not impermissible. If
the appeals brought by the State are lost for such default no
person is individually affected but what in the ultimate analysis
suffers, is public interest. .....In the event of decision to file
appeal needed prompt action should be pursued by the officer
responsible to file the appeal and he should be made personally
11
responsible for lapses, if any. Equally, the State cannot be put
on the same footing as an individual. The individual would
always be quick in taking the decision whether he would pursue
the remedy by way of an appeal or application since he is a
person legally injured while State is an impersonal machinery
working through its officers or servants"
Further at para 15 this court held that:
"... The above position was highlighted in State of Haryana v.
Chandra Mani and Ors. 1996 (3) SCC 132; Special Tehsildar,
Land Acquisition, Kerala v. K V.Ayisumma (1996 (10) SCC
634) and State of Nagaland v. Lipok AO and Ors. (2005 (3)
SCC 752). It was noted that adoption of strict standard of
proof sometimes fail to protract public justice, and, it would
result in public mischief by skilful management of delay in the
process of filing an appeal."
16. This Court has in appropriate cases even condoned delays of over
30 years in filing of SLPs. In Nand Kishore v. State of Punjab 1995 (6)
SCC 614 this court held:
".........13. The step of the three-member Bench so taken reveal its mind
as reflected in the above proceedings. Their Lordships wanted to do
substantial justice. It was thought better to advise the petitioner to file
special leave petition. As we view this order, having invited the
petitioner to file the special leave petition, it is no longer advisable or
appropriate for us to retrace back the step put forward by the three-
member Bench. It is significant to recall that the writ application was
dismissed on 5-2-1962 and the moment Moti Ram Deka case appeared
on the scene, the appellant or 24-2-1964, within limitation, brought
forward his suit which got strengthened by Gurdev Singh case appearing
within a couple of months of its filing. The appellant-special leave
petitioner was thus bona fide pursuing an appropriate remedy for all
these years. In these circumstances, we think that an appropriate case for
12
condonation of delay of the intervening period has been made out. We,
therefore, allow CC 11644 of 1991 and condone the long durated delay
in these exceptional circumstances. On doing so, we grant leave to
appeal. The appeal thus arising and the Civil Appeal No. 632 of 1975
may now be disposed of together...."
17. On perusal of the explanation offered it is clear that the officials who
were dealing with the matter have either deliberately or without
understanding the implications dealt with the matter in a very casual and
lethargic manner. It is a matter of concern that in very serious matters action
is not taken as required under law and the appeals/petitions are filed after
long lapse of time. It is a common grievance that it is so done to protect
unscrupulous litigants at the cost of public interest or public exchequer.
This stand is more noticeable where vast tracts of lands or large sums of
revenue are involved. Even though the courts are liberal in dealing with the
belated presentation of appeals/applications, yet there is a limit upto which
such liberal attitude can be extended. Many matters concerning the State
Government and the Central Government are delayed either by the nature of
bureaucratic process or by deliberate manipulation of the same by taking
advantage of loopholes in the conduct of litigation. Several instances have
come to the notice of this Court where as noted above appeals have been
filed where the revenue involved runs to several crores of rupees. It is true
13
that occasionally delay occurs which is inexplicable in normal
circumstances.
18. The case at hand is a classic example where the circumstances are the
same. More than 4000 acres of land are involved out of which, according to
the State, nearly 3500 acres constitute forest land. Ultimately, the Court has
to protect the public justice. The same cannot be rendered ineffective by
skillful management of delay in the process of making challenge to the order
which prima facie does not appear to be legally sustainable.
19. The expression `sufficient cause' as appearing in Section 5 of the
Indian Limitation Act, 1963 (in short the `Limitation Act') must receive a
liberal construction so as to advance substantial justice as was noted by this
Court in G. Ramegowda, Major etc. v. The Special Land Acquisition
Officer, Bangalore (AIR 1988 SC 897). Para 8 of the judgment reads as
follows:
"8. .......The law of limitation is, no doubt, the same for a
private citizen as for governmental authorities. Government,
like any other litigant must take responsibility for the acts or
omissions of its officers. But a somewhat different complexion
is imparted to the matter where Government makes out a case
where public interest was shown to have suffered owing to acts
of fraud or bad faith on the part of its officers or agents and
where the officers were clearly at cross-purposes with it.
14
Therefore, in assessing what, in a particular case,
constitutes "sufficient cause" for purposes of Section 5, it
might, perhaps, be somewhat unrealistic to exclude from the
considerations that go into the judicial verdict, these factors
which are peculiar to and characteristic of the functioning of the
government. Governmental decisions are proverbially slow
encumbered, as they are, by a considerable degree of procedural
red tape in the process of their making. A certain amount of
latitude is, therefore, not impermissible. It is rightly said that
those who bear responsibility of Government must have "a little
play at the joints". Due recognition of these limitations on
governmental functioning -- of course, within reasonable limits
-- is necessary if the judicial approach is not to be rendered
unrealistic. It would, perhaps, be unfair and unrealistic to put
government and private parties on the same footing in all
respects in such matters. Implicit in the very nature of
governmental functioning is procedural delay incidental to the
decision-making process. In the opinion of the High Court, the
conduct of the law officers of the Government placed the
Government in a predicament and that it was one of those cases
where the mala fides of the officers should not be imputed to
Government. It relied upon and trusted its law officers. Lindley,
M.R., in the In re National Bank of Wales Ltd. (1899) 2 Ch. 629
at p.673 observed, though in a different context:
"Business cannot be carried on upon principles of
distrust. Men in responsible positions must be trusted by
those above them, as well as by those below them, until
there is reason to distrust them."
20. Keeping in view the importance of questions of law which are
involved we are inclined to condone the delay subject to payment of
exemplary costs which we fix at rupees ten lakhs to be paid within a period
15
of 8 weeks to the respondents. The delay is condoned subject to the
payment of the aforesaid amount as costs. After making the payment the
receipt thereof shall be filed before this Court alongwith an affidavit. Only
after the payment is made the special leave petitions shall be listed for
admission. We make it clear that we have not expressed any opinion on
the merits of the case.
21. It is imperative that the State shall immediately initiate action as
available in law against every person responsible for the alleged fraud and
delay in persuing the remedies, fix responsibility and recover the amount
paid as costs from them. Needless to say orders shall be passed in this
regard by the competent authority after grant of opportunity to the concerned
person(s). If any, action under criminal law(s) is to be taken, same shall be
taken.
..........................................J.
(Dr. ARIJIT PASAYAT)
..........................................J.
(ASOK KUMAR GANGULY)
New Delhi,
May 04, 2009
16
Subscribe to:
Comments (Atom)