REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 9151-9152 OF 2015
(Arising out of S.L.P. (Civil) Nos. 34129-34130 of 2014)
Elektron Lighting Systems …..Appellants
Pvt. Ltd. and Anr.
Versus
Shah Investments Financial Developments
and Consultants Pvt. Ltd and Ors. Etc. .….Respondents
J U D G M E N T
Prafulla C. Pant, J.
These appeals are directed against judgment and order dated
14.10.2014 passed by High Court of Judicature at Bombay, whereby Writ
Petition Nos. 7843 of 2014 and 8211 of 2014, are allowed, and the work
order dated 03.09.2014, and consequential agreement between the appellants
and respondent No. 3, are quashed.
2. Succinctly stated the facts of the case are that on 01.08.2014
respondent no. 3 - Aurangabad Municipal Corporation (for short “municipal
corporation”) invited tenders for replacement of existing street lights by
Light Emitting Diodes (LED) fittings with refurbishment of street light
infrastructure on Build, Operate and Transfer (BOT) basis. The contractor
was required to complete the project within one year and recover the
payment from the municipal corporation through Ninety six Equated Monthly
Installments (EMIs) over a period of eight years. Response to E-tender
notice was required to be made in two separate parts, namely, technical bid
and price bid. As per the tender notice, the tender forms were made
available from 01.08.2014 to 20.08.2014. The period of submission of bids
was extended up to 28.08.2014.
3. The Tender Notice contained inter alia following conditions : -
“(i) Manufactures of LED Lights OR registered Clause A Electrical
Contractors and are eligible to participate in the Tender.
The Class A Electrical Contractors (Lead Partner) may only participate by
having a Joint Venture agreement with the Manufacturer of LED Light
Fittings.
The Manufacturer of LED Light fittings (Lead Partner) may form a Joint
Venture with Class A Electrical Contractor.
The Manufacturer of LED Lights (Lead Partner) may form a Joint Venture with
another Manufacturer of Electrical items, provided that the Lead Partner
has entered into a MOU with a Class A Electrical Contractor towards
execution of the tendered BOT project.
The Bidder should have achieved a minimum turnover of Rs. 25 crores in each
of the three preceding financial years, total 75 crores in three years.
Attested true copies of Sale Tax/VAT registration, Manufacturing
certificate & DD for EMD to be submitted along with tender papers.
xxx xxx xxx
(xiv) Bidder may be Joint Venture of maximum two companies/firms to
jointly meet the commercial and technical conditions.”
xxx xxx xxx
The present appellants and respondent No.1/writ petitioners submitted their
bids but technical bids of the latter were rejected as they did not fulfill
the terms as per the tender notice. The price bid of appellants was
negotiated by the respondent - municipal corporation, and proposal was sent
to the standing committee of the corporation. Whereafter, as per the
resolution, the work order was issued in favour of the appellants.
The two disqualified bidders filed the Writ Petitions (W.P. Nos. 7843 of
2014 and 8211 of 2014) before the High Court of Judicature of Bombay,
Aurangabad Bench, challenging their disqualification, and acceptance of the
appellants’ bid. The High Court vide impugned order held that though
disqualification of writ petitioners was correct but extraordinary favour
was shown to appellants who were awarded work order, as such, the same was
quashed. Hence these appeals.
It is relevant to mention here that the writ petitioners have not
challenged the order of the High Court, whereby their disqualification by
the municipal corporation has been upheld. The disqualification and
rejection of technical bid of the writ petitioners was mainly based on
following three reasons:-
Neither the writ petitioner nor its joint venture partner was a
registered Class-A contractor, nor any one of them was stated to be
manufacturer of LED lights.
None of the writ petitioners had achieved a minimum turnover of Rs. 25
crores in the three preceding financial years.
The writ petitioners failed to submit minimum thirty pieces of different
types of samples for the purposes of testing.
As such, so far as the disqualification of the writ petitioners (present
respondent no. 1) is concerned, it requires no further examination. The
only point to be considered by us is whether the High Court, even after
finding that the technical bids of the writ petitioners were rightly
rejected, was justified in quashing the work order given to the appellants
whose technical bid was accepted by the municipal corporation.
On behalf of the appellants following submissions were made assailing the
impugned order passed by the High Court:-
(1). RE. ABSENCE OF MOU:
That the appellants duly entered into MOU on 14.08.2014 with M/s. Matoshree
Electricals & Winding Works, a Class A Electrical Contractor as required in
Clause 1.1(4) of tender.
That the Technical Evaluation Report by AMC states that MOU had been
duly filed by Petitioners.
That the Writ Petitioners never raised this point in their Writ Petitions
and even in the amended Writ Petitions. That is also the reason why the MOU
was not filed before High Court.
That this being an online tender, all documents filed by all the parties
were accessable to all. Since the MOU had been uploaded, the issue was not
raised in Writ Petition.
(2). RE. NON-SUBMISSION OF ATTESTED COPIES OF VAT RETURNS:
That the appellants had duly filed attested copies of VAT Returns in terms
of Clause 1.2(1)(C) of tender. The Technical Evaluation Report by AMC
states VAT Returns had been duly filed by them.
That the Writ Petitioners never raised this point in their Writ Petitions
and even in the amended Writ Petitions. That is why copies of VAT Returns
were not filed before the High Court.
That this being an online Tender, all documents filed by all parties were
accessable to all. Since the VAT Returns had been uploaded, the issue was
not raised in Writ Petition.
That the High Court erred in assuming that even joint venture partner which
had zero turnover in a particular financial year had to file VAT Returns.
It is submitted that VAT return was required only to establish the turnover
requirement. Thus a joint venture partner had to file VAT returns only if
its turnover exceeded zero.
(3). Re. TURNOVER REQUIRMENT:
That the Clause 1.1(5) requires that bidder should have achieved minimum
turnover of Rs. 25 crores in each of the 3 preceding financial years, total
75 crores in 3 years. Clause 1.1(14) specifies bidder may be a joint
venture of maximum two companies/firms to ‘jointly meet’ the commercial &
technical conditions.
That the joint turnover of the two joint venture partners is in excess of
Rs. 25 crores p.a. and Rs. 75 crores in 3 years. The fact that turnover of
P-1 was nil, is inconsequential since requirement is joint compliance.
That the High Court at para 28 noted that jointly the turnover requirement
is met but erroneously held against the appellants on the ground that
turnover of appellant No.1 is nil.
(4). RE. TREATING LETTER DATED 19.08.2014 AS FINANCIAL OFFER:
That the subject matter of letter dated 19.08.2014 was offer of a separate
product and different period, which was not covered by the present tender.
Hence question of the letter being a financial offer did not arise.
That the letter dated 19.08.2014 had the subject “Additional Suggestions
towards tender- UNCONDITIONAL” and specifically stated that “…..These
suggestions are unconditional and are being made in favour of the
improvement for the City of Aurangabad. It shall be completely at your kind
discretion to accept or reject these suggestions…..”
That the letter was considered separately by AMC. This is apparent from the
Work Order. This is also corroborated by AMC’s Additional affidavit before
the High Court.
That the letter was uploaded alongwith the Technical Bid. The High Court
erroneously held that the letter had been disclosed even before opening of
the technical bid, which is contrary to its own recording that letter was
submitted simultaneously with tender offer. In fact Shah Investments’
amended Writ Petition itself records that letter dated 19.08.2014 was
submitted with technical bid.
That the relevant figure for evaluation of tender was under the heading
“TOTAL COST TO AMC for Evaluating the Lowest Bidder = (VI)+(VII)+(VII)”.
This figure was nowhere disclosed either in technical bid or in the letter
dated 19.08.2014. Price bid comprised of 27 pages and none of the pages was
attached as part of Technical Bid.
That without prejudice to the aforesaid, the part of work order relating to
letter dated 19.08.2014 is severable and even if that part is set aside,
the remaining contract stands.
(5). RE. TREATING GRANT OF ADVERTISING RIGHTS ON POLES AS BEYOND THE TERMS
OF THE TENDER:
That the work order is in two parts-one pertaining to award of the
main contract and the other to additional suggestions of the appellants.
It is submitted that the part pertaining to additional suggestions can be
severed from main contract and directed to be removed from the work order.
Thus, work order may be confined to award of main contract only.
(6). RE. THE DECISION MAKING BY AMC BEING HASTY:
That the Notice Inviting Tender was issued on 01.08.2014 and the whole
process was completed on 03.09.2014. There was thus no undue haste.
That the time period for submission of bids was extended twice which
negates the factum of alleged haste.
That the Commissioner of AMC being under orders of transfer had no bearing
on the matter as the ultimate decision was taken by the Standing Committee
of AMC.
That the decision making process shows due application of mind.
(7). OTHER SUBMISSIONS:
That the High Court did not correctly appreciate the judgment of this Court
in Sanjay Kumar Shukla Vs. Bharat Petroleum Corporation Limited [(2014) 3
SCC 493] where this Court reiterated need for caution in entertaining writ
petitions in contractual matters, unless justified by public interest,
since serious consequences could ensue.
That the High Court failed to appreciate that the petitions before it were
not public interest petitions but were petitions of unsuccessful bidders.
That the motives of the writ petitioners, who made bids despite knowing
that they did not fulfill the essential requirements, were not considered.
In fact, Shah Investments was a finance company. It is submitted that the
Writ Petitioners were front men for others.
That writ petitioner Shah Investment’s W.P. No. 7843/2014 did not even
contain any prayer to quash the petitioners’ bid despite amendment.
appellant No. 2 in present appeals was not even made a party in Polycab’s
W.P. No. 8211/2014.
That impugned order imputes mala fides although there were no allegations
of mala fide against any particular person in the writ petitions.
On the other hand, on behalf of the respondent No.1, it is argued that the
work order in question was rightly quashed by the High Court for the
following reasons:-
That the bidding for the present tender was to be conducted by a two-step e-
tendering process. As per Clause 3 of the bid document, at the first stage
the bidders were required to submit their technical bids, and the
acceptable bids amongst these would be sent for field trials. Only the
financial bids of those bidders whose samples qualify the technical stage
were thereafter to be opened.
That Clause 1.2(h) stipulated that in the event a bidder submits the price
offer along with the technical bid, the tender bid shall be treated as
withdrawn and EMD forfeited.
That it was an essential and mandatory condition of the tender as can be
construed from the use of the word “shall” and the consequences attached to
a breach of this clause, i.e., the bid treated to be as withdrawn and the
consequent forfeiture of the EMD deposit.
That it is settled law that where there are essential conditions, the same
must be adhered to. In the present case, the Respondent No. 3 - Corporation
has no power to relax any of the terms of the bid document, and in any
event no such power can be inferred in this context, as no relaxation can
be granted from complying with a mandatory condition of the bid document.
That the contention of the appellants that the offer contained in the
letter dated 19th August, 2014 was an unconditional offer made only for the
consideration and benefit of the Respondent no. 3 - Corporation cannot save
the appellants from the consequences of a breach of the terms of the bid
document.
That the said letter dated 19th August, 2014 admittedly contained the
following offers and suggestions which have a direct bearing on the price
offer made by the appellants:
The letter divulged that the appellants would be offering its services
for the minimum guarantee period under the tender at the rate of Rs.95/-
per fixture per month.
The letter also stated that by implementing the online monitoring system,
the number of control panels to be utilized would be reduced to 600 from
1200 as required by the bid document. Interestingly, no corresponding
reduction in the price was offered by the appellants. However, if the
number of control panels required were to increase over 600, the appellants
would install the same at the additional cost of the Respondent No.3 -
Corporation. This is a kind of offer which clearly exposes the mischievous
intention of the appellants in negotiating a bargain which would be purely
beneficial to itself at the cost of the public exchequer.
The letter also made an offer to implement these new technologies in
consideration for being granted exclusive advertising rights on the street
lights for the entire BOT period.
That the offers and suggestions made in the said letter, be it conditional
or unconditional, were unquestionably a price offer, as is evident from the
work order dated 3rd September, 2014 issued by the Respondent No. 3 -
Corporation.
That the submission of such letter ipso facto renders the bid of the
appellants unresponsive, to be treated as withdrawn and EMD forfeited. The
terms of the bid document do not give the Respondent No.3 - Corporation the
authority to relax its terms unilaterally for any individual bidder, in a
manner which would allow such bidder to circumvent a mandatory and
essential terms of the bid document.
That having submitted such a price offer along with the technical bid, the
appellants stood disqualified at the technical stage and, therefore, no
question arises as to whether the Respondent No.3 - Corporation could
choose to accept or reject these additional offers and suggestions of the
appellants.
That the practice of indulging in post tender negotiations has been
deprecated and labeled as a source of corruption and in pursuance of the
same, the Central Vigilance Commission has issued Circular No.4/3/07 dated
3rd March, 2007 and has mandated that no post tender negotiations be held
with L-1 except in certain exceptional situations as are mentioned therein.
Admittedly, no such situation exists in the present case.
That the acceptance of these additional offers and suggestions as contained
in the Work Order dated 3rd September, 2014 has resulted in
enlarging the scope of the tender. The period of the tender has been
increased from eight years with a two years extended guarantee period to
eight years with a four years extended guarantee period. The answering
respondent/writ petitioner seeks compensation in return for providing the
additional two years of guarantee. The scope of the tendered work has also
been increased to include the grant of exclusive advertising rights for the
entire contract period which now stands revised to twelve years, for no
consideration whatsoever. These are major deviations from the essential
terms of the tender which cannot be permitted.
The appellants during the course of arguments have tendered certain
additional documents across the bar, to establish that the acceptance of
the additional offers has been done after due consideration. However, a
mere perusal of said documents such as the appellants’ letter dated 2nd
September, 2104, the minutes of the meeting of the Aurangabad Municipal
Commission chaired by the Commissioner also dated 2nd September, 2014 and
the minutes of the meeting of the Standing Committee of the Aurangabad
Municipal Corporation dated 3rd September, 2014 would indicate the hurried
manner in which the entire process of the tender has been finalized.
Learned counsel for the municipal corporation has in substance supported
the grounds taken by the appellants assailing the impugned orders passed by
the High Court.
We have considered submissions of learned counsel for the parties, and
perused the papers on record.
In Tata Cellular Versus Union of India[1], this court has held following
limitations relating to scope of judicial review of administrative
decisions and exercise of powers awarding contracts. In Para 94 this court
has held as under:-
“94. The principles deducible from the above are:
(1) The modern trend points to judicial restraint in administrative action.
(2) The Court does not sit as a court of appeal but merely reviews the
manner in which the decision was made.
(3) The Court does not have the expertise to correct the administrative
decision. If a review of the administrative decision is permitted it will
be substituting its own decision, without the necessary expertise which
itself may be fallible.
(4) The terms of the invitation to tender cannot be open to judicial
scrutiny because the invitation to tender is in the realm of contract.
Normally speaking, the decision to accept the tender or award the contract
is reached by process of negotiations through several tiers. More often
than not, such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other words, a fair
play in the joints is a necessary concomitant for an administrative body
functioning in an administrative sphere or quasi-administrative sphere.
However, the decision must not only be tested by the application of
Wednesbury principle of reasonableness (including its other facts pointed
out above) but must be free arbitrariness not affected by bias or actuated
by mala fides.
(6) Quashing decisions may impose heavy administrative burden on the
administration and lead to increased and unbudgeted expenditure…….”
In Air India Ltd. Versus Cochin International Airport Ltd. And Others[2],
this court has laid down the principle as to how the discretionary power
under Article 226 should be cautiously exercised in the matters of awarding
contracts keeping in mind the public interest. In Para 7 this court has
held as under:-
“7……..It can enter into negotiations before finally deciding to accept one
of the offers made to it. Price need not always be the sole criterion for
awarding a contract. It is free to grant any relaxation, for bona fide
reasons, if the tender conditions permit such a relaxation. It may not
accept the offer even though it happens to be the highest or the lowest.
But the State, its corporations, instrumentalities and agencies are bound
to adhere to the norms, standards and procedures laid down by them and
cannot depart from them arbitrarily. Though that decision is not amenable
to judicial review, the Court can examine the decision making process and
interfere if it is found vitiated by mala fides, unreasonableness and
arbitrariness. The State, its corporations, instrumentalities and agencies
have the public duty to be fair to all concerned. Even when some defect is
found in the decision-making process the Court must exercise its
discretionary power under Article 226 with great caution and should
exercise it only in furtherance of public interest and not merely on the
making out of a legal point. The Court should always keep the larger public
interest in mind in order to decide whether its intervention is called for
or not. Only when it comes to a conclusion that overwhelming public
interest requires interference, the Court should intervene.”
In Jagdish Mandal Versus State of Orissa and Others[3], this court has held
as under:-
“22. Judicial review of administrative action is intended to prevent
arbitrariness, irrationality, unreasonableness, bias and mala fides. Its
purpose is to check whether choice or decision is made “lawfully” and not
to check whether choice or decision is “sound”. When the power of judicial
review is invoked in matters relating to tenders or award of contracts,
certain special features should be borne in mind. A contract is a
commercial transaction. Evaluating tenders and awarding contracts are
essentially commercial functions. Principles of equity and natural justice
stay at a distance. If the decision relating to award of contract is bona
fide and is in public interest, courts will not, in exercise of power of
judicial review, interfere even if a procedural aberration or error in
assessment or prejudice to a tenderer, is made out. The power of judicial
review will not be permitted to be invoked to protect private interest at
the cost of public interest, or to decide contractual disputes. The
tenderer or contractor with a grievance can always seek damages in a civil
court. Attempts by unsuccessful tenderers with imaginary grievances,
wounded pride and business rivalry, to make mountains out of molehills of
some technical/procedural violation or some prejudice to self, and persuade
courts to interfere by exercising power of judicial review, should be
resisted. Such interferences, either interim or final, may hold up public
works for years, or delay relief and succour to thousands and millions and
may increase the project cost manifold.
In the light of the law laid down by this Court, as above, we examined the
facts of the present case. Admittedly, respondent No. 3 Municipal
Corporation invited online tenders for replacement of existing street
lights by LED fittings. The e-tender was required to be made of technical
bid and price bid. It is not disputed that the appellants and the
respondent No. 1 uploaded their technical bid and submitted price/financial
bid separately on the online portal of the municipal corporation. It is
also admitted between the parties that the last date of submission of
tenders was initially 20.08.2014, which was extended up to 28.08.2014. The
technical evaluation of all the three bidders was carried out in their
presence. It is relevant to mention here that the disqualification of
other two bidders, who filed writ petitions, was found correct by the High
Court, and said fact is not challenged before us. As such, the only issue
required to be examined is as to whether the technical bid of the
appellants was approved in accordance with the settled principle of law
without giving them undue favour, or not.
The High Court has observed in the impugned orders that the MOU between the
appellants and LED manufacturer M/s Matoshree Electricals & Winding Works,
was not placed on the record. However, the High court failed to notice that
none of writ petitioners had challenged acceptance of appellants’ bid on
that ground, and the appellants had no opportunity to place the same on the
record of the court. The MOU was part of tender bid, and finds its mention
in “Tender Committee Evaluation Report”. The another reason to take adverse
view against the appellants, mentioned by the High Court in the impugned
order, is that attested copies of VAT returns were not presented by the
appellants. It is pointed out before us that the statement of the VAT
returns for relevant financial years were duly filed by the appellants with
the technical bid. From the record, it reveals that filing of VAT returns
with technical bids gets corroboration also from “Tender Committee
Evaluation Report”. In said report as to the requirement “VAT Returns of
the Bidder”, the Committee has mentioned - “OK. “10A, 10B, 10C, 10D”, and
acquaint the head - “Tender Condition Compliance” word “Yes” is mentioned.
Regarding the condition of turnover of rupees twenty five crores, the High
Court itself did not find infirmity and observed that the appellants did
fulfill the condition of return of rupees twenty five crores in each of the
preceding financial years as the turnover of the joint venture partner was
to be taken into account.
It is pertinent to mention here that the tender was invited incorporating
the National Lightening Code to ensure the safety of pedestrians and
motorists. The tender also specified the Lux levels to be achieved and to
be maintained for eight years. The power consumption required to be
guaranteed and the contractor was made liable to bear the difference
between the excess of actual energy bill over the quoted energy bill. The
contractor was made responsible for comprehensive maintenance for all
installed equipment over BOT period including any breakage, theft, loss on
any account whatsoever. It is worthwhile to mention here that in the pre-
bid meeting, representatives of eight bidders stated to have participated
and clarified various points regarding the tender notice.
In our opinion, there appears to be no hurry on the part of the municipal
corporation, in awarding contract as the tender had been issued on
01.08.2014 and the same was finalized only on 03.09.2014, i.e. after a
period of more than one month. Pre-bid meetings were held and the last
date for submission of tender was extended twice from 20.08.2014 to
25.08.2014 and thereafter to 28.08.2014, which by itself shows that the
process was not carried out in haste. Exhaustive pre-bid meeting was held
on 12.08.2014, which was stated to have been attended by eight prospective
bidders and the minutes of the pre-bid meetings running into several pages
changed many terms in favour of the respondent Corporation to ensure even
stricter contract execution responsibilities and thus became part of the
tender through issuance of two corrigenda. The pre-bid meeting was held to
understand the requirements of the contract viz. the opinion of the
prospective bidders, to give sufficient time for bid preparation,
evaluation of bids and award of contract. One month was consumed in
carrying out the said activities and in no way can it be termed as a
hurried process, as held by the High Court.
Therefore, in our opinion, the High Court has erred in law in holding that
the work order was illegally given to the appellants in respect of
replacement of street lights by LED fittings and refurbishment of street
light infrastructure on BOT basis.
Now, we come to that part of work order and consequential agreement by
which advertising rights were also granted to the appellants on the basis
of letter dated 19.8.2014 sent by the appellants to the Municipal
Corporation. The High Court has taken serious note of the letter dated
19.08.2014 (a day before submission of technical bid) in which the
appellants has made “certain suggestions” to the municipal corporation.
Copy of said letter is reproduced below: -
“The Commissioner,
Aurangabad Municipal Corporation
Aurangabad, Maharashtra
Sub: Additional Suggestions toward Tender-UNCONDITIONAL
Respected Sir,
We are participating in the tender for the LED Street Lighting due to be
opened on 21st August, 2014, & there are some additional suggestions
towards the same for your kind consideration. These suggestions are
unconditional & are being made in favour of the improvement for the City of
Aurangabad. It shall be completely at your kind discretion to accept or
reject these suggestions.
We can offer to implement the Online Internet based Control & Monitoring of
the Street Lights from the Switching point. The suitable systems shall use
GSM based modems to control the switching ON & OFF of the street lights, to
be installed in each control Panel. Though the cost of such a system is
quite high, however we are hereby offering to implement the solution at a
reduced price of Rs. 36,000/- per Control Panel along with the recurring
costs of the GSM communication & software to Online monitor it, provided
the Exclusive Advertising rights for all the Street Lights Poles are
extended to us.
The stipulated number of Control Panels is about 1200, as per the Tender.
In case it is decided to implement the New Technology Online control
System, we may mutually plan to reduce the number of existing Control
Panels to about 600, as the Switching Point system load shall get
substantially reduced after implementation of LED Lights. Thus we may
offset the cost of reduced Control Panels by using Online Technology
without burden of AMC. In case due to logistic issues, the Street Lighting
cannot be controlled by the proposed 600 Panels, then whatever additional
nos. may be required, cost for the same shall be borne by AMC.
As a reciprocal towards implementation of the Online Monitoring & Control,
we seek the Exclusive Advertising Rights for all the Street Light Poles.
2. Additional Extended Guarantee Period of Two Years:-
We can extend the Additional Guarantee Period from Two Years to Four Years,
if required by AMC, on the same terms of Cost as per Part D, i.e. on
payment of Rs.95/- per fixture per month. This offer has.
Joint Venture Bidder
(Electron Lighting System (P) Ltd.
& Paragon Cable India)
Sd/-
Authorized Signatory”
The above letter discloses that the suggestions were unconditional, leaving
it open for the municipal corporation to accept or not to accept the same.
Through the above quoted letter the appellants suggested that if exclusive
advertising rights are given to the bidder on the street lights pole, the
bidder would reduce price by Rs. 36,000/- per control panel. The stipulated
number of control panel was 1,200/-, which could be reduced through mutual
plan to 600/-. We are of the view that the above offer relating to
advertising rights was uncalled for and severable, and not a part of the
work for which tender was floated. Learned counsel for the appellants
submitted that the appellants are ready to execute the work without taking
benefit of said letter as per the work contract relating to replacement of
street lights by LED on BOT basis.
It is submitted on behalf of the respondent No.3 that though revenue from
advertising in city of Aurangabad from other sources, for the financial
years 2011-2012, 2012-2013 and 2013-2014 was Rs. 81,31,091=00, 81,15,438=00
and 89,03,976=00 respectively, but the same from advertising on Street
Light Poles was nil for each of the three years. As such, the municipal
Corporation did not commit any illegality in negotiating the matter with
the appellants while awarding the work order to it.
In our opinion, the matter regarding advertising rights was separate, and
the municipal corporation which is a statutory body and instrumentality of
the State should have acted fairly by making it open for all eligible to
submit their offers. As such, we think that the respondent No.3 was not
justified in giving the advertisement rights to the appellants without
inviting tender for it. To that extent, in our opinion, respondent No.3 has
not acted fairly. As such, the manner in which the advertising rights are
given to the appellants with the work order cannot be said to be fair and
contract to that extent was liable to be quashed without interfering with
rest of the work order.
Explaining the doctrine of severability contained in Section 57 of Indian
Contract Act, 1872, in B.O.I. Finance Ltd., v. Custodian and others[4], a
three Judge Bench of this Court has held that question of severance arises
only in the case of a composite agreement consisting of reciprocal
promises. In Shin Satellite Public Co. Ltd. V. Jain Studios Ltd.[5], this
Court has observed that the proper test for deciding validity or otherwise
of an order or agreement is “substqantial severability” and not “textual
divisibility”. It was further held by this Court that it is the duty of
the Court to sever and separate trivial and technical parts by retaining
the main or substantial part and by giving effect to the latter if it is
legal, lawful and otherwise enforceable.
Therefore, in the facts and circumstances and for the reasons as discussed
above, the appeals deserve to be partly allowed. Accordingly, we set aside
the impugned orders passed by the High Court to the extent it has quashed
the work contract given to the appellants regarding replacement of existing
street lights by LED fittings and refurbishment of street light
infrastructure on BOT basis. The work order dated 03.09.2014, to that
extent given to the appellants shall stand valid. However, the
advertisement rights given to the appellants, in the work contract, shall
remain quashed. As to the advertisement rights, respondent No.3 may invite
tenders before awarding contract in respect thereof. The appeals stand
disposed of.
No order as to costs.
……………….....…………J.
[Dipak Misra]
.……………….……………J.
New Delhi; [Prafulla C. Pant]
November 20, 2015.
-----------------------
[1] (1994) 6 SCC 651
[2] (2000) 2 SCC 617
[3] (2007) 14 SCC 517
[4] (1997) 10 SCC 488
[5] (2006) 2 SCC 628
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 9151-9152 OF 2015
(Arising out of S.L.P. (Civil) Nos. 34129-34130 of 2014)
Elektron Lighting Systems …..Appellants
Pvt. Ltd. and Anr.
Versus
Shah Investments Financial Developments
and Consultants Pvt. Ltd and Ors. Etc. .….Respondents
J U D G M E N T
Prafulla C. Pant, J.
These appeals are directed against judgment and order dated
14.10.2014 passed by High Court of Judicature at Bombay, whereby Writ
Petition Nos. 7843 of 2014 and 8211 of 2014, are allowed, and the work
order dated 03.09.2014, and consequential agreement between the appellants
and respondent No. 3, are quashed.
2. Succinctly stated the facts of the case are that on 01.08.2014
respondent no. 3 - Aurangabad Municipal Corporation (for short “municipal
corporation”) invited tenders for replacement of existing street lights by
Light Emitting Diodes (LED) fittings with refurbishment of street light
infrastructure on Build, Operate and Transfer (BOT) basis. The contractor
was required to complete the project within one year and recover the
payment from the municipal corporation through Ninety six Equated Monthly
Installments (EMIs) over a period of eight years. Response to E-tender
notice was required to be made in two separate parts, namely, technical bid
and price bid. As per the tender notice, the tender forms were made
available from 01.08.2014 to 20.08.2014. The period of submission of bids
was extended up to 28.08.2014.
3. The Tender Notice contained inter alia following conditions : -
“(i) Manufactures of LED Lights OR registered Clause A Electrical
Contractors and are eligible to participate in the Tender.
The Class A Electrical Contractors (Lead Partner) may only participate by
having a Joint Venture agreement with the Manufacturer of LED Light
Fittings.
The Manufacturer of LED Light fittings (Lead Partner) may form a Joint
Venture with Class A Electrical Contractor.
The Manufacturer of LED Lights (Lead Partner) may form a Joint Venture with
another Manufacturer of Electrical items, provided that the Lead Partner
has entered into a MOU with a Class A Electrical Contractor towards
execution of the tendered BOT project.
The Bidder should have achieved a minimum turnover of Rs. 25 crores in each
of the three preceding financial years, total 75 crores in three years.
Attested true copies of Sale Tax/VAT registration, Manufacturing
certificate & DD for EMD to be submitted along with tender papers.
xxx xxx xxx
(xiv) Bidder may be Joint Venture of maximum two companies/firms to
jointly meet the commercial and technical conditions.”
xxx xxx xxx
The present appellants and respondent No.1/writ petitioners submitted their
bids but technical bids of the latter were rejected as they did not fulfill
the terms as per the tender notice. The price bid of appellants was
negotiated by the respondent - municipal corporation, and proposal was sent
to the standing committee of the corporation. Whereafter, as per the
resolution, the work order was issued in favour of the appellants.
The two disqualified bidders filed the Writ Petitions (W.P. Nos. 7843 of
2014 and 8211 of 2014) before the High Court of Judicature of Bombay,
Aurangabad Bench, challenging their disqualification, and acceptance of the
appellants’ bid. The High Court vide impugned order held that though
disqualification of writ petitioners was correct but extraordinary favour
was shown to appellants who were awarded work order, as such, the same was
quashed. Hence these appeals.
It is relevant to mention here that the writ petitioners have not
challenged the order of the High Court, whereby their disqualification by
the municipal corporation has been upheld. The disqualification and
rejection of technical bid of the writ petitioners was mainly based on
following three reasons:-
Neither the writ petitioner nor its joint venture partner was a
registered Class-A contractor, nor any one of them was stated to be
manufacturer of LED lights.
None of the writ petitioners had achieved a minimum turnover of Rs. 25
crores in the three preceding financial years.
The writ petitioners failed to submit minimum thirty pieces of different
types of samples for the purposes of testing.
As such, so far as the disqualification of the writ petitioners (present
respondent no. 1) is concerned, it requires no further examination. The
only point to be considered by us is whether the High Court, even after
finding that the technical bids of the writ petitioners were rightly
rejected, was justified in quashing the work order given to the appellants
whose technical bid was accepted by the municipal corporation.
On behalf of the appellants following submissions were made assailing the
impugned order passed by the High Court:-
(1). RE. ABSENCE OF MOU:
That the appellants duly entered into MOU on 14.08.2014 with M/s. Matoshree
Electricals & Winding Works, a Class A Electrical Contractor as required in
Clause 1.1(4) of tender.
That the Technical Evaluation Report by AMC states that MOU had been
duly filed by Petitioners.
That the Writ Petitioners never raised this point in their Writ Petitions
and even in the amended Writ Petitions. That is also the reason why the MOU
was not filed before High Court.
That this being an online tender, all documents filed by all the parties
were accessable to all. Since the MOU had been uploaded, the issue was not
raised in Writ Petition.
(2). RE. NON-SUBMISSION OF ATTESTED COPIES OF VAT RETURNS:
That the appellants had duly filed attested copies of VAT Returns in terms
of Clause 1.2(1)(C) of tender. The Technical Evaluation Report by AMC
states VAT Returns had been duly filed by them.
That the Writ Petitioners never raised this point in their Writ Petitions
and even in the amended Writ Petitions. That is why copies of VAT Returns
were not filed before the High Court.
That this being an online Tender, all documents filed by all parties were
accessable to all. Since the VAT Returns had been uploaded, the issue was
not raised in Writ Petition.
That the High Court erred in assuming that even joint venture partner which
had zero turnover in a particular financial year had to file VAT Returns.
It is submitted that VAT return was required only to establish the turnover
requirement. Thus a joint venture partner had to file VAT returns only if
its turnover exceeded zero.
(3). Re. TURNOVER REQUIRMENT:
That the Clause 1.1(5) requires that bidder should have achieved minimum
turnover of Rs. 25 crores in each of the 3 preceding financial years, total
75 crores in 3 years. Clause 1.1(14) specifies bidder may be a joint
venture of maximum two companies/firms to ‘jointly meet’ the commercial &
technical conditions.
That the joint turnover of the two joint venture partners is in excess of
Rs. 25 crores p.a. and Rs. 75 crores in 3 years. The fact that turnover of
P-1 was nil, is inconsequential since requirement is joint compliance.
That the High Court at para 28 noted that jointly the turnover requirement
is met but erroneously held against the appellants on the ground that
turnover of appellant No.1 is nil.
(4). RE. TREATING LETTER DATED 19.08.2014 AS FINANCIAL OFFER:
That the subject matter of letter dated 19.08.2014 was offer of a separate
product and different period, which was not covered by the present tender.
Hence question of the letter being a financial offer did not arise.
That the letter dated 19.08.2014 had the subject “Additional Suggestions
towards tender- UNCONDITIONAL” and specifically stated that “…..These
suggestions are unconditional and are being made in favour of the
improvement for the City of Aurangabad. It shall be completely at your kind
discretion to accept or reject these suggestions…..”
That the letter was considered separately by AMC. This is apparent from the
Work Order. This is also corroborated by AMC’s Additional affidavit before
the High Court.
That the letter was uploaded alongwith the Technical Bid. The High Court
erroneously held that the letter had been disclosed even before opening of
the technical bid, which is contrary to its own recording that letter was
submitted simultaneously with tender offer. In fact Shah Investments’
amended Writ Petition itself records that letter dated 19.08.2014 was
submitted with technical bid.
That the relevant figure for evaluation of tender was under the heading
“TOTAL COST TO AMC for Evaluating the Lowest Bidder = (VI)+(VII)+(VII)”.
This figure was nowhere disclosed either in technical bid or in the letter
dated 19.08.2014. Price bid comprised of 27 pages and none of the pages was
attached as part of Technical Bid.
That without prejudice to the aforesaid, the part of work order relating to
letter dated 19.08.2014 is severable and even if that part is set aside,
the remaining contract stands.
(5). RE. TREATING GRANT OF ADVERTISING RIGHTS ON POLES AS BEYOND THE TERMS
OF THE TENDER:
That the work order is in two parts-one pertaining to award of the
main contract and the other to additional suggestions of the appellants.
It is submitted that the part pertaining to additional suggestions can be
severed from main contract and directed to be removed from the work order.
Thus, work order may be confined to award of main contract only.
(6). RE. THE DECISION MAKING BY AMC BEING HASTY:
That the Notice Inviting Tender was issued on 01.08.2014 and the whole
process was completed on 03.09.2014. There was thus no undue haste.
That the time period for submission of bids was extended twice which
negates the factum of alleged haste.
That the Commissioner of AMC being under orders of transfer had no bearing
on the matter as the ultimate decision was taken by the Standing Committee
of AMC.
That the decision making process shows due application of mind.
(7). OTHER SUBMISSIONS:
That the High Court did not correctly appreciate the judgment of this Court
in Sanjay Kumar Shukla Vs. Bharat Petroleum Corporation Limited [(2014) 3
SCC 493] where this Court reiterated need for caution in entertaining writ
petitions in contractual matters, unless justified by public interest,
since serious consequences could ensue.
That the High Court failed to appreciate that the petitions before it were
not public interest petitions but were petitions of unsuccessful bidders.
That the motives of the writ petitioners, who made bids despite knowing
that they did not fulfill the essential requirements, were not considered.
In fact, Shah Investments was a finance company. It is submitted that the
Writ Petitioners were front men for others.
That writ petitioner Shah Investment’s W.P. No. 7843/2014 did not even
contain any prayer to quash the petitioners’ bid despite amendment.
appellant No. 2 in present appeals was not even made a party in Polycab’s
W.P. No. 8211/2014.
That impugned order imputes mala fides although there were no allegations
of mala fide against any particular person in the writ petitions.
On the other hand, on behalf of the respondent No.1, it is argued that the
work order in question was rightly quashed by the High Court for the
following reasons:-
That the bidding for the present tender was to be conducted by a two-step e-
tendering process. As per Clause 3 of the bid document, at the first stage
the bidders were required to submit their technical bids, and the
acceptable bids amongst these would be sent for field trials. Only the
financial bids of those bidders whose samples qualify the technical stage
were thereafter to be opened.
That Clause 1.2(h) stipulated that in the event a bidder submits the price
offer along with the technical bid, the tender bid shall be treated as
withdrawn and EMD forfeited.
That it was an essential and mandatory condition of the tender as can be
construed from the use of the word “shall” and the consequences attached to
a breach of this clause, i.e., the bid treated to be as withdrawn and the
consequent forfeiture of the EMD deposit.
That it is settled law that where there are essential conditions, the same
must be adhered to. In the present case, the Respondent No. 3 - Corporation
has no power to relax any of the terms of the bid document, and in any
event no such power can be inferred in this context, as no relaxation can
be granted from complying with a mandatory condition of the bid document.
That the contention of the appellants that the offer contained in the
letter dated 19th August, 2014 was an unconditional offer made only for the
consideration and benefit of the Respondent no. 3 - Corporation cannot save
the appellants from the consequences of a breach of the terms of the bid
document.
That the said letter dated 19th August, 2014 admittedly contained the
following offers and suggestions which have a direct bearing on the price
offer made by the appellants:
The letter divulged that the appellants would be offering its services
for the minimum guarantee period under the tender at the rate of Rs.95/-
per fixture per month.
The letter also stated that by implementing the online monitoring system,
the number of control panels to be utilized would be reduced to 600 from
1200 as required by the bid document. Interestingly, no corresponding
reduction in the price was offered by the appellants. However, if the
number of control panels required were to increase over 600, the appellants
would install the same at the additional cost of the Respondent No.3 -
Corporation. This is a kind of offer which clearly exposes the mischievous
intention of the appellants in negotiating a bargain which would be purely
beneficial to itself at the cost of the public exchequer.
The letter also made an offer to implement these new technologies in
consideration for being granted exclusive advertising rights on the street
lights for the entire BOT period.
That the offers and suggestions made in the said letter, be it conditional
or unconditional, were unquestionably a price offer, as is evident from the
work order dated 3rd September, 2014 issued by the Respondent No. 3 -
Corporation.
That the submission of such letter ipso facto renders the bid of the
appellants unresponsive, to be treated as withdrawn and EMD forfeited. The
terms of the bid document do not give the Respondent No.3 - Corporation the
authority to relax its terms unilaterally for any individual bidder, in a
manner which would allow such bidder to circumvent a mandatory and
essential terms of the bid document.
That having submitted such a price offer along with the technical bid, the
appellants stood disqualified at the technical stage and, therefore, no
question arises as to whether the Respondent No.3 - Corporation could
choose to accept or reject these additional offers and suggestions of the
appellants.
That the practice of indulging in post tender negotiations has been
deprecated and labeled as a source of corruption and in pursuance of the
same, the Central Vigilance Commission has issued Circular No.4/3/07 dated
3rd March, 2007 and has mandated that no post tender negotiations be held
with L-1 except in certain exceptional situations as are mentioned therein.
Admittedly, no such situation exists in the present case.
That the acceptance of these additional offers and suggestions as contained
in the Work Order dated 3rd September, 2014 has resulted in
enlarging the scope of the tender. The period of the tender has been
increased from eight years with a two years extended guarantee period to
eight years with a four years extended guarantee period. The answering
respondent/writ petitioner seeks compensation in return for providing the
additional two years of guarantee. The scope of the tendered work has also
been increased to include the grant of exclusive advertising rights for the
entire contract period which now stands revised to twelve years, for no
consideration whatsoever. These are major deviations from the essential
terms of the tender which cannot be permitted.
The appellants during the course of arguments have tendered certain
additional documents across the bar, to establish that the acceptance of
the additional offers has been done after due consideration. However, a
mere perusal of said documents such as the appellants’ letter dated 2nd
September, 2104, the minutes of the meeting of the Aurangabad Municipal
Commission chaired by the Commissioner also dated 2nd September, 2014 and
the minutes of the meeting of the Standing Committee of the Aurangabad
Municipal Corporation dated 3rd September, 2014 would indicate the hurried
manner in which the entire process of the tender has been finalized.
Learned counsel for the municipal corporation has in substance supported
the grounds taken by the appellants assailing the impugned orders passed by
the High Court.
We have considered submissions of learned counsel for the parties, and
perused the papers on record.
In Tata Cellular Versus Union of India[1], this court has held following
limitations relating to scope of judicial review of administrative
decisions and exercise of powers awarding contracts. In Para 94 this court
has held as under:-
“94. The principles deducible from the above are:
(1) The modern trend points to judicial restraint in administrative action.
(2) The Court does not sit as a court of appeal but merely reviews the
manner in which the decision was made.
(3) The Court does not have the expertise to correct the administrative
decision. If a review of the administrative decision is permitted it will
be substituting its own decision, without the necessary expertise which
itself may be fallible.
(4) The terms of the invitation to tender cannot be open to judicial
scrutiny because the invitation to tender is in the realm of contract.
Normally speaking, the decision to accept the tender or award the contract
is reached by process of negotiations through several tiers. More often
than not, such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other words, a fair
play in the joints is a necessary concomitant for an administrative body
functioning in an administrative sphere or quasi-administrative sphere.
However, the decision must not only be tested by the application of
Wednesbury principle of reasonableness (including its other facts pointed
out above) but must be free arbitrariness not affected by bias or actuated
by mala fides.
(6) Quashing decisions may impose heavy administrative burden on the
administration and lead to increased and unbudgeted expenditure…….”
In Air India Ltd. Versus Cochin International Airport Ltd. And Others[2],
this court has laid down the principle as to how the discretionary power
under Article 226 should be cautiously exercised in the matters of awarding
contracts keeping in mind the public interest. In Para 7 this court has
held as under:-
“7……..It can enter into negotiations before finally deciding to accept one
of the offers made to it. Price need not always be the sole criterion for
awarding a contract. It is free to grant any relaxation, for bona fide
reasons, if the tender conditions permit such a relaxation. It may not
accept the offer even though it happens to be the highest or the lowest.
But the State, its corporations, instrumentalities and agencies are bound
to adhere to the norms, standards and procedures laid down by them and
cannot depart from them arbitrarily. Though that decision is not amenable
to judicial review, the Court can examine the decision making process and
interfere if it is found vitiated by mala fides, unreasonableness and
arbitrariness. The State, its corporations, instrumentalities and agencies
have the public duty to be fair to all concerned. Even when some defect is
found in the decision-making process the Court must exercise its
discretionary power under Article 226 with great caution and should
exercise it only in furtherance of public interest and not merely on the
making out of a legal point. The Court should always keep the larger public
interest in mind in order to decide whether its intervention is called for
or not. Only when it comes to a conclusion that overwhelming public
interest requires interference, the Court should intervene.”
In Jagdish Mandal Versus State of Orissa and Others[3], this court has held
as under:-
“22. Judicial review of administrative action is intended to prevent
arbitrariness, irrationality, unreasonableness, bias and mala fides. Its
purpose is to check whether choice or decision is made “lawfully” and not
to check whether choice or decision is “sound”. When the power of judicial
review is invoked in matters relating to tenders or award of contracts,
certain special features should be borne in mind. A contract is a
commercial transaction. Evaluating tenders and awarding contracts are
essentially commercial functions. Principles of equity and natural justice
stay at a distance. If the decision relating to award of contract is bona
fide and is in public interest, courts will not, in exercise of power of
judicial review, interfere even if a procedural aberration or error in
assessment or prejudice to a tenderer, is made out. The power of judicial
review will not be permitted to be invoked to protect private interest at
the cost of public interest, or to decide contractual disputes. The
tenderer or contractor with a grievance can always seek damages in a civil
court. Attempts by unsuccessful tenderers with imaginary grievances,
wounded pride and business rivalry, to make mountains out of molehills of
some technical/procedural violation or some prejudice to self, and persuade
courts to interfere by exercising power of judicial review, should be
resisted. Such interferences, either interim or final, may hold up public
works for years, or delay relief and succour to thousands and millions and
may increase the project cost manifold.
In the light of the law laid down by this Court, as above, we examined the
facts of the present case. Admittedly, respondent No. 3 Municipal
Corporation invited online tenders for replacement of existing street
lights by LED fittings. The e-tender was required to be made of technical
bid and price bid. It is not disputed that the appellants and the
respondent No. 1 uploaded their technical bid and submitted price/financial
bid separately on the online portal of the municipal corporation. It is
also admitted between the parties that the last date of submission of
tenders was initially 20.08.2014, which was extended up to 28.08.2014. The
technical evaluation of all the three bidders was carried out in their
presence. It is relevant to mention here that the disqualification of
other two bidders, who filed writ petitions, was found correct by the High
Court, and said fact is not challenged before us. As such, the only issue
required to be examined is as to whether the technical bid of the
appellants was approved in accordance with the settled principle of law
without giving them undue favour, or not.
The High Court has observed in the impugned orders that the MOU between the
appellants and LED manufacturer M/s Matoshree Electricals & Winding Works,
was not placed on the record. However, the High court failed to notice that
none of writ petitioners had challenged acceptance of appellants’ bid on
that ground, and the appellants had no opportunity to place the same on the
record of the court. The MOU was part of tender bid, and finds its mention
in “Tender Committee Evaluation Report”. The another reason to take adverse
view against the appellants, mentioned by the High Court in the impugned
order, is that attested copies of VAT returns were not presented by the
appellants. It is pointed out before us that the statement of the VAT
returns for relevant financial years were duly filed by the appellants with
the technical bid. From the record, it reveals that filing of VAT returns
with technical bids gets corroboration also from “Tender Committee
Evaluation Report”. In said report as to the requirement “VAT Returns of
the Bidder”, the Committee has mentioned - “OK. “10A, 10B, 10C, 10D”, and
acquaint the head - “Tender Condition Compliance” word “Yes” is mentioned.
Regarding the condition of turnover of rupees twenty five crores, the High
Court itself did not find infirmity and observed that the appellants did
fulfill the condition of return of rupees twenty five crores in each of the
preceding financial years as the turnover of the joint venture partner was
to be taken into account.
It is pertinent to mention here that the tender was invited incorporating
the National Lightening Code to ensure the safety of pedestrians and
motorists. The tender also specified the Lux levels to be achieved and to
be maintained for eight years. The power consumption required to be
guaranteed and the contractor was made liable to bear the difference
between the excess of actual energy bill over the quoted energy bill. The
contractor was made responsible for comprehensive maintenance for all
installed equipment over BOT period including any breakage, theft, loss on
any account whatsoever. It is worthwhile to mention here that in the pre-
bid meeting, representatives of eight bidders stated to have participated
and clarified various points regarding the tender notice.
In our opinion, there appears to be no hurry on the part of the municipal
corporation, in awarding contract as the tender had been issued on
01.08.2014 and the same was finalized only on 03.09.2014, i.e. after a
period of more than one month. Pre-bid meetings were held and the last
date for submission of tender was extended twice from 20.08.2014 to
25.08.2014 and thereafter to 28.08.2014, which by itself shows that the
process was not carried out in haste. Exhaustive pre-bid meeting was held
on 12.08.2014, which was stated to have been attended by eight prospective
bidders and the minutes of the pre-bid meetings running into several pages
changed many terms in favour of the respondent Corporation to ensure even
stricter contract execution responsibilities and thus became part of the
tender through issuance of two corrigenda. The pre-bid meeting was held to
understand the requirements of the contract viz. the opinion of the
prospective bidders, to give sufficient time for bid preparation,
evaluation of bids and award of contract. One month was consumed in
carrying out the said activities and in no way can it be termed as a
hurried process, as held by the High Court.
Therefore, in our opinion, the High Court has erred in law in holding that
the work order was illegally given to the appellants in respect of
replacement of street lights by LED fittings and refurbishment of street
light infrastructure on BOT basis.
Now, we come to that part of work order and consequential agreement by
which advertising rights were also granted to the appellants on the basis
of letter dated 19.8.2014 sent by the appellants to the Municipal
Corporation. The High Court has taken serious note of the letter dated
19.08.2014 (a day before submission of technical bid) in which the
appellants has made “certain suggestions” to the municipal corporation.
Copy of said letter is reproduced below: -
“The Commissioner,
Aurangabad Municipal Corporation
Aurangabad, Maharashtra
Sub: Additional Suggestions toward Tender-UNCONDITIONAL
Respected Sir,
We are participating in the tender for the LED Street Lighting due to be
opened on 21st August, 2014, & there are some additional suggestions
towards the same for your kind consideration. These suggestions are
unconditional & are being made in favour of the improvement for the City of
Aurangabad. It shall be completely at your kind discretion to accept or
reject these suggestions.
We can offer to implement the Online Internet based Control & Monitoring of
the Street Lights from the Switching point. The suitable systems shall use
GSM based modems to control the switching ON & OFF of the street lights, to
be installed in each control Panel. Though the cost of such a system is
quite high, however we are hereby offering to implement the solution at a
reduced price of Rs. 36,000/- per Control Panel along with the recurring
costs of the GSM communication & software to Online monitor it, provided
the Exclusive Advertising rights for all the Street Lights Poles are
extended to us.
The stipulated number of Control Panels is about 1200, as per the Tender.
In case it is decided to implement the New Technology Online control
System, we may mutually plan to reduce the number of existing Control
Panels to about 600, as the Switching Point system load shall get
substantially reduced after implementation of LED Lights. Thus we may
offset the cost of reduced Control Panels by using Online Technology
without burden of AMC. In case due to logistic issues, the Street Lighting
cannot be controlled by the proposed 600 Panels, then whatever additional
nos. may be required, cost for the same shall be borne by AMC.
As a reciprocal towards implementation of the Online Monitoring & Control,
we seek the Exclusive Advertising Rights for all the Street Light Poles.
2. Additional Extended Guarantee Period of Two Years:-
We can extend the Additional Guarantee Period from Two Years to Four Years,
if required by AMC, on the same terms of Cost as per Part D, i.e. on
payment of Rs.95/- per fixture per month. This offer has.
Joint Venture Bidder
(Electron Lighting System (P) Ltd.
& Paragon Cable India)
Sd/-
Authorized Signatory”
The above letter discloses that the suggestions were unconditional, leaving
it open for the municipal corporation to accept or not to accept the same.
Through the above quoted letter the appellants suggested that if exclusive
advertising rights are given to the bidder on the street lights pole, the
bidder would reduce price by Rs. 36,000/- per control panel. The stipulated
number of control panel was 1,200/-, which could be reduced through mutual
plan to 600/-. We are of the view that the above offer relating to
advertising rights was uncalled for and severable, and not a part of the
work for which tender was floated. Learned counsel for the appellants
submitted that the appellants are ready to execute the work without taking
benefit of said letter as per the work contract relating to replacement of
street lights by LED on BOT basis.
It is submitted on behalf of the respondent No.3 that though revenue from
advertising in city of Aurangabad from other sources, for the financial
years 2011-2012, 2012-2013 and 2013-2014 was Rs. 81,31,091=00, 81,15,438=00
and 89,03,976=00 respectively, but the same from advertising on Street
Light Poles was nil for each of the three years. As such, the municipal
Corporation did not commit any illegality in negotiating the matter with
the appellants while awarding the work order to it.
In our opinion, the matter regarding advertising rights was separate, and
the municipal corporation which is a statutory body and instrumentality of
the State should have acted fairly by making it open for all eligible to
submit their offers. As such, we think that the respondent No.3 was not
justified in giving the advertisement rights to the appellants without
inviting tender for it. To that extent, in our opinion, respondent No.3 has
not acted fairly. As such, the manner in which the advertising rights are
given to the appellants with the work order cannot be said to be fair and
contract to that extent was liable to be quashed without interfering with
rest of the work order.
Explaining the doctrine of severability contained in Section 57 of Indian
Contract Act, 1872, in B.O.I. Finance Ltd., v. Custodian and others[4], a
three Judge Bench of this Court has held that question of severance arises
only in the case of a composite agreement consisting of reciprocal
promises. In Shin Satellite Public Co. Ltd. V. Jain Studios Ltd.[5], this
Court has observed that the proper test for deciding validity or otherwise
of an order or agreement is “substqantial severability” and not “textual
divisibility”. It was further held by this Court that it is the duty of
the Court to sever and separate trivial and technical parts by retaining
the main or substantial part and by giving effect to the latter if it is
legal, lawful and otherwise enforceable.
Therefore, in the facts and circumstances and for the reasons as discussed
above, the appeals deserve to be partly allowed. Accordingly, we set aside
the impugned orders passed by the High Court to the extent it has quashed
the work contract given to the appellants regarding replacement of existing
street lights by LED fittings and refurbishment of street light
infrastructure on BOT basis. The work order dated 03.09.2014, to that
extent given to the appellants shall stand valid. However, the
advertisement rights given to the appellants, in the work contract, shall
remain quashed. As to the advertisement rights, respondent No.3 may invite
tenders before awarding contract in respect thereof. The appeals stand
disposed of.
No order as to costs.
……………….....…………J.
[Dipak Misra]
.……………….……………J.
New Delhi; [Prafulla C. Pant]
November 20, 2015.
-----------------------
[1] (1994) 6 SCC 651
[2] (2000) 2 SCC 617
[3] (2007) 14 SCC 517
[4] (1997) 10 SCC 488
[5] (2006) 2 SCC 628