Restricting to four floors the height of Wing ‘C’ (providing for public parking lot-
‘PPL’ for short) of the buildings being constructed on Plot No.46 of Town
Planning Scheme-III, - Apex court - gave directions -
Division Bench of the Bombay High Court whereby Writ Petition
No.143/2012 filed by the respondents was allowed, and which quashed the
stop work notice dated 22.12.2011 issued by Executive Engineer (Building
Proposal) City-III, Municipal Corporation of Greater Mumbai, and order
dated 27.4.2012 passed by the Additional Municipal Commissioner restricting
to four floors the height of Wing ‘C’ (providing for public parking lot-
‘PPL’ for short) of the buildings being constructed on Plot No.46 of Town
Planning Scheme-III, N.C.Kelkar Road, Shivaji Park, Dadar, Mumbai. =
In the circumstances we pass the following order:-
(1) The memorandum of settlement dated 18.4.2013, concerning the
Public Parking Lot (PPL) arrived at between the appellant-Municipal
Corporation of Greater Mumbai and the respondents was taken on record, as
noted in Part-I order dated 25.7.2013, in the facts and circumstances of
the present case. Both the parties shall act strictly in accordance with
the same. It is clarified that as held in the said order, the Municipal
circular dated 22.6.2011 is not in any way held to be bad in law.
(2) The four additional issues framed in Part-II of the above order are
decided as follows:-
Issue No. (i) – The minimum recreational space as laid down under
Development Control Regulation (DCR) 23, cannot be reduced on the basis of
DCR 38(34). The recreational space, if any, provided on the podium as per
DCR 38(34)(iv), shall be in addition to that provided as per DCR 23.
Issue Nos. (ii) & (iii) – The Government of Maharashtra, the Development
Plan Drafting Committee, and the appellant-Municipal Corporation shall
consider the suggestions as contained in paragraph Nos.53 and 54 above,
while framing the Development Plan for Greater Mumbai.
Issue No. (iv) – The second proviso to DCR 43(1) (A), concerning fire
protection requirements, is held to be bad in law. We hold that even for
the reconstruction proposals of plots upto the size of 600 sq. mts. under
DCR 33(7), open space of the width of 6 meters at least on one side at
ground level within the plot, accessible from the road side will have to be
maintained for the maneuverability of a fire engine, unless the building
abuts two roads of 6 meters or more on two sides, or another access of 6
meters to the building is available, apart from the road abutting the
building.
(3) The decision as contained in Clauses 2(i) and 2(iv) above, will apply
to those constructions where plans are still not approved, or where the
Commencement Certificate (CC) has not yet been issued. All authorities
concerned are directed to ensure strict compliance accordingly.
(4) The Government of Maharashtra shall issue the necessary notification
within four weeks of this order, re-constituting the ‘Technical Committee
for the High-Rise Buildings’, as directed in paragraph 56, including the
additional terms of reference, as mentioned in paragraph 57 above. The
appellant is directed to render assistance and provide the required
honorarium, as mentioned in paragraph 58 above.
(5) In view of the settlement arrived at between the parties, as well as
Part-I order dated 25.7.2013 mentioned in paragraph (1), and the
determination on the four additional issues as in paragraph (2) above, no
further order is required on this appeal, and the appeal stands disposed
off accordingly.
(6) The parties will bear their own costs.
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.11150 OF 2013
(@ out of SPECIAL LEAVE PETITION (CIVIL) NO. 33402/2012)
Municipal Corporation of Greater Mumbai and Ors. … Appellants
Versus
Kohinoor CTNL Infrastructure Company Private
Limited and another … Respondents
J U D G E M E N T
H.L. Gokhale J.
Leave granted.
2. This appeal is directed against the order dated 9.7.2012 passed
by a Division Bench of the Bombay High Court whereby Writ Petition
No.143/2012 filed by the respondents was allowed, and which quashed the
stop work notice dated 22.12.2011 issued by Executive Engineer (Building
Proposal) City-III, Municipal Corporation of Greater Mumbai, and order
dated 27.4.2012 passed by the Additional Municipal Commissioner restricting
to four floors the height of Wing ‘C’ (providing for public parking lot-
‘PPL’ for short) of the buildings being constructed on Plot No.46 of Town
Planning Scheme-III, N.C.Kelkar Road, Shivaji Park, Dadar, Mumbai.
Dispute between the parties, settlement thereof and Part-I of the order
dated 25.7.2013:-
3. This appeal was initially heard by a bench of G.S. Singhvi and
H.L. Gokhale, JJ. Mr. Harish Salve and Mr. R.P Bhatt, both learned Senior
Counsel appeared for the appellants, and Mr. F.S Nariman, learned Senior
Counsel appeared for the respondent. The appellants wanted to restrict the
PPL up to four floors only, but before the issuance of the restrictive
circular dated 22.6.2011, in this behalf, the respondents had already
consumed higher FSI (Floor Space Index) on the basis of the Commencement
Certificates issued earlier. In view of the discussion in the Court
however, a settlement was arrived at between the appellants and the
respondents on the controversy concerning the PPL. Before passing the
order on the settlement, the bench noted the backdrop of the facts and
circumstances of the case in paragraphs 2 to 5 in Part-I of the order
passed on 25.7.2013 (per Singhvi, J. as he then was). These paragraphs
read as follows:-
“2. The plans submitted by respondent No. 1 for construction
of Wings-‘A’, ‘B’ and ‘C’ of the building were sanctioned by the
competent authority of the Municipal Corporation of Greater
Mumbai (for short, ‘the corporation’) and Intimation of
Disapproval was issued on 15.2.2006. After the Ministry of
Environment and Forests, Government of India granted clearance
for the construction of commercial building, the competent
authority issued commencement certificated dated 13.9.2006. The
Joint Commissioner of Police (Traffic) issued NOC dated
11.12.2009 for the development of a multi-storied public parking
lot and vide letter dated 2.6.2010, the State government granted
in-principle approval under Clause 33(24) of the Development
Control Regulations (DCR) for Greater Mumbai, 1991 for
construction of a multi-storied public parking lot. Thereafter,
the competent authority issued the Letter of Intent dated
27.7.2010.
3. During the construction of the building, the Urban
Development Department of the State Government sent letter dated
4.3.2011 to the Municipal Commissioner requiring him to submit a
proposal for amendment of Clause 33 (24) of the DCR for limiting
the height of parking towers to 4 floors and also for revocation
of all sanctioned proposals where the commencement certificates
had not been issued. In view of that letter, the Corporation
issued circular dated 22.6.2011 prescribing certain conditions
under Clause (iv) of DCR 33(24) and clarified that all proposals
for public parking lots shall be considered subject to those
conditions. The new conditions sought to limit the height of
public parking to ground plus 4 upper floors and 2 basements.
4. As a sequel to the above changes, the Corporation issued
notice dated 29.11.2011 to respondent No. 1 under Section 51 of
the Maharashtra Regional and Town Planning Act, 1966 requiring
it to show cause as to why the commencement certificate may not
be revoked. Respondent No. 1 submitted detailed reply dated
14.12.2011 and pleaded that the amended DCR 33(24) cannot be
made applicable to its buildings because substantial
construction had already been made at a cost of Rs. 167/-
crores. Thereafter, the concerned Executive Engineer issued
stop work notice dated 22.12.2011 and directed respondent No. 1
to restrict the work of public parking to 4 floors instead of 13
floors. After about six months, Additional Municipal
Commissioner passed order dated 27.4.2012, the relevant portion
of which is extracted below:-
“As there is a substantial construction on core part of the
plot, PPL done in this part shall be allowed to the extent of
already executed construction as per report dated 27.12.2011.
In the remaining portion of the plot, where there is no
substantial construction, PPL shall be limited to G + 4,
Developer is to be asked to modify his plans in consonance with
modified DCR.”
5. The respondent challenged the stop work notice and the
order of the Additional Municipal Commissioner in Writ Petition
No. 143/2012, which was allowed by the High Court in the
following terms:-
“In the facts of this case, the admitted position as accepted in
the order of the Additional Municipal Commissioner indicates
that the work of development had substantially progressed by the
time a notice to show cause was issued under Section 51 of the
M.R. & T.P. Act, 1966. The impugned order passed by the
Additional Municipal Commissioner restricting the Petitioners to
a height of a ground floor and four upper floors in deviation of
the permission granted earlier is thereafter contrary to law.
Hence, the impugned order would have to be quashed and set aside
and is accordingly set aside. The stop work notice which has
been issued to the Petitioners on the basis of the notice to
show cause dated 29 November 2011 is to that extent quashed and
set aside. Rule is made absolute in these terms. There shall
be no order as to costs.”
4. The above referred memorandum of settlement arrived at between
the parties contained clauses 1, 2 (a to e) and an annexure thereto with
respect to the modus-operandi in that behalf. Clauses 2 (a) and (b)
thereof are relevant for our purpose. They read as follows:-
“2. In view of the peculiar facts and circumstances of the
present case and without establishing any precedent, it is
agreed between the Petitioners herein and the Respondent No.
1(Kohinoor CTNL) as follows:-
a) In public interest, Public Parking Lot (PPL) will no
longer be on ground + 13 upper floors as initially approved
under amended approval dated 21st September, 2011 in Wing ‘C’ of
the development of composite building on Final Plot No. 46, but
on the ground + 4 upper floors in Wing ‘C’ as well as in three
level basement below Wing ‘A’, ‘B’ and ‘C’ i.e. entire basement,
and the captive parking shall be on 5th to 13 upper floors in
Wing ‘C’.
b) It is also agreed that in the present case of F.P. No.
46, the PPL will be managed and operated by the Petitioner No. 1
(MCGM) or its nominee(s) and common ingress and egress through
the common entry/exist shall be provided in Wing ‘C’ for PPL as
well as captive parking for Municipal Corporation of Greater
Mumbai and Respondent No. 1 (Kohinoor CTNL). The modus-operandi
in that behalf is detailed in Annexure hereto.”
(emphasis supplied)
5. Since the signed memorandum of settlement was filed in the
Court, the Court passed the following operative order in paragraph 9 of
Part-I of the said order dated 25.7.2013:-
“9. Accordingly, the Memorandum of Settlement signed by the
representatives of the parties and their advocates on 18.4.2013
together with the annexure are taken on record. We note that
this settlement is arrived at on the backdrop of the facts and
circumstances of this case. We clarify that we have not in
anyway held the Municipal Circular dated 22.6.2011 to be bad in
law. We direct that the parties shall strictly abide by the
terms of settlement.”
(emphasis supplied)
6. The settlement has brought about the change as desired by the
appellants, while taking care of interest of the respondents. The complex
is going to be on the land which earlier belonged to Kohinoor Textile Mill
at Dadar, Mumbai. Wing ‘A’ is to consist of 3 basements + ground to 5
Floors, and Wing ‘B’ is to consist of 3 basements + ground to 48 floors
with a total height of 195.90 meters. Wing ‘C’ was to be in two parts as
originally proposed. Ground+14 Floors, thereof, were to be meant for PPL,
and 15 to 30 floors were to be kept for residential purposes. Under the
Municipal circular dated 22.6.2011 prescribing conditions under clause (iv)
of DCR 33(24), the public parking building was to be confined only to
ground+4 upper floors. The settlement accepts this position, and now as per
the settlement, public parking is going to be provided in the ground + 4
upper floors in Wing ‘C’ and also in the three level basements below Wings
A’, ‘B’ and ‘C’. The private parking shall be from 5th to 13th floors of
Wing ‘C’.
Part-II of the order dated 25.7.2013 framing four issues:-
7. Although the dispute between the parties, was with respect to
the height of the building consisting of the PPL, it was felt that the
appellants had not applied their mind to some of the issues which, in fact,
did arise in the matter of the grant of permission to this complex on the
said plot No.46 in the heart of Mumbai city. It was noticed that as per
the approved plan, the recreational space available at the ground level was
reduced to only 7.7% of the area of the plot, as against the required
minimum of 15% (where the area of the plot was between 1001 sq. mts. to
2500 sq. mts. as per the DCR 23). In view of the reduction in the
recreational area at the ground level, it was observed in paragraph 13 of
the said order as follows:-
“…..We may add that since the petitioners and respondents
have arrived at a settlement, we do not propose to go into this
issue with respect to the construction of the respondent. We
are, however, surprised that the Municipal Corporation did not
look into the reduction in the recreational area at the ground
level very seriously, probably because the rule permits
recreational space on the podium. If this is treated as a
correct interpretation, then it is quite possible that the
recreational area left at the ground level could simply be zero.
It may leave no space on the ground floor for the
residents/occupants of the apartments constructed in the
particular building, and that will have serious adverse impact
on the right to life not only of the residents/occupants of the
apartments but also of the people in the adjoining areas because
all of them will have to only fall back on the public parks or
play grounds and gardens for their minimum recreational
requirements……”
(emphasis supplied)
It was, therefore, felt that it was necessary to examine the co-relation
between DCR-23, which provides for minimum Recreational/Amenity open
spaces, and DCR-38 (34) concerning the Podium.
8. Secondly, it was noted that in the present matter a higher FSI
has been given in lieu of making a provision for public parking, leading to
a high-rise building. Such high-rise constructions bring along with them
more population and more vehicles on the adjoining narrow roads and into an
already congested area, and that aspect did not appear to have been
examined by the appellant-Municipal Corporation. In the instant case, the
approved complex is bounded on four sides by four roads, and these roads
are not, at all, wide. The height of the complex is going to be quite
disproportionate to the width of these roads, but that has been permitted
amongst other reasons in view of making a provision for public parking.
Under DCR No.31 (1), the height of the building has to be in proportion to
the width of the road which is adjoining a building, but the proviso to
that DCR makes another exception to this rule with respect to construction
schemes under DCRs Nos.33(7), (8) and (9). DCR 33(7) is regarding
reconstruction or redevelopment of cessed buildings in the island city, by
co-operative housing societies, or of old buildings belonging to the
Municipal Corporation or the police department, and it grants FSI of 2.5
plus incentive FSI as specified in Appendix III, whichever is more. DCR
33(8) is regarding construction for housing the dis-housed, by the
Municipal Corporation. DCR 33(9) is regarding reconstruction or
redevelopment of cessed buildings or urban renewal schemes on extensive
areas, where the FSI is 4. These constructions also add to the population
and the vehicles in that very area. A question therefore arose as to
whether these exemptions are justified, valid and legal?
9. Thirdly, the impact of construction of high-rise buildings in
the thickly populated areas on the traffic in the city was also discussed
during the consideration of the SLP. The Court noted in paragraph 14 of
the order, that although additional space for public parking was being
provided, simultaneously higher FSI was also being granted to the
developer, on that count. Consequently, such high-rise buildings would add
more number of vehicles on the adjoining streets. This required
examination of the impact of additional FSI on the traffic situation,
particularly in the island city of Greater Mumbai.
10. Lastly, considering that the height of the complex was going
up to 198.50 meters, it was decided to look into the issue of hazards due
to fire which the occupants of such towers could face. It was noted that
there were provisions with respect to the space to be kept around such
buildings for the movement of fire engines within the compound of such
buildings, but these provisions are not uniform. The fire engines, with
their ladders, available with the Municipal Corporation, do not reportedly
reach anywhere beyond 14th floor. It was also noted that recently the
Secretariat Building of the State of Maharashtra (known as the
‘Mantralaya’) was engulfed with fire. The building is only six storeys,
and yet it took quite a few days to control the fire, and in that exercise
a few lives were unfortunately lost. Therefore, the issue of safety of the
occupants of such high-rise buildings, that of the residents in the
neighbourhood, and the firemen, required urgent consideration.
11. Therefore, in Part-II of its order dated 25.7.2013, the Bench
framed four issues for further consideration. These issues read as
follows:-
“(1) What should be the correlation between DCR 23 and DCR
38(34) regarding the recreational area? Is it permissible to
reduce the minimum recreational area provided under DCR 23 on
any ground?
(2) Whether the exemption from DCR 31(1) under DCR Nos.
33(7), (8), and (9) is justified, valid and legal particularly
in the island city of Greater Mumbai. If so, to what extent and
in which context?
(3) What is the impact of the addition of FSI in the island
city on the traffic situation? How can it be controlled?
(4) Whether the present mechanism for protection against
the fire hazards is adequate and is being implemented
effectively? If not, what should be the mechanism for
enforcement with respect to the provisions concerning the fire
safety?
12. For that purpose, affidavits were sought from the following:-
“(A) From the Municipal Corporation:-
(i) The affidavit of the Chief Engineer, Town Planning on
issues no. 1 and 2.
(ii) The affidavit of the Chief Engineer, concerning
traffic on issued no. 3.
(iii) The affidavit of the Chief Fire Officer on issue no
4.
(B) From the State of Maharashtra:-
(i) By the Secretary, Urban Development Department on
issue nos. 1, 2 and 3 above.
(ii) By the Commissioner of Police (Traffic) on issue no.
3 above.”
13. The excessive construction at the cost of minimum recreational
space, as seen in the present case, required an immediate attention to be
paid to issue no. (1).. Similarly, issue no. (4). concerning the fire
hazards also required urgent attention, and it was thought that the Court
should go into the legality of the relevant provisions in this behalf. As
against that, examination of the other two issues was taken up for the
reason that the development plan for the city of Mumbai is going to be
revised shortly, and certain suggestions in that behalf could be made.
Issue no. (2). arising out of exemptions to the high-rise buildings under
DCR 33(7),(8), (9) and issue no. (3) concerning the impact on traffic,
required a detailed deliberation. At this point, it is relevant to mention
that a similar approach has been adopted by this Court in Municipal
Corporation of Delhi Vs. Association of victims of Uphaar Tragedy & Ors.
reported in AIR 2012 SC 100. That case concerned the compensation to be
paid to the victims of the fire in the ‘Upahaar’ theatre at Delhi. This
Court decided the issue of compensation in paragraph 38 of the judgment.
However, the Court could not ignore that the fire had resulted into the
death of 59 persons and injury to 103 persons, and therefore, this Court
observed in paragraph 39 of the said judgment:-
“39. Normally we would have let the matter rest there.
But having regard to the special facts and circumstances of the
case we propose to proceed a step further to do complete
justice.”
And then, the Court made a number of suggestions in paragraph 45 of its
judgment to the Government for its consideration and implementation.
Similarly, although a settlement is arrived at, on the controversy between
the parties before the Court, considering the acute problems in the city of
Mumbai with respect to shortage of recreational space, the fire hazards and
high density of traffic, a further deliberation on the above referred four
issues was felt necessary.
14. Thereafter, the matter has been heard by the present Bench.
Consequent upon the above order, the necessary affidavits were filed by the
officers of the appellant as well as the State of Maharashtra. A number of
interveners have also assisted the Court. The interveners include (i) The
Urban Design Research Institute (‘UDRI’ for short) & Ors., (ii) Maharashtra
Chamber of Housing Industry, (iii) Practicing Engineers Architects and Town
Planners Association (India) and (iv) Property Redevelopers Association.
They have all assisted in the examination of these four issues. We will
deal with their submissions in the context of the Maharashtra Regional and
Town Planning Act, 1966 (the ‘MRTP’ Act for short), and the Development
Control Regulations for Greater Mumbai, 1991, framed thereunder which
govern these issues.
Issue no.1 concerning the reduction in the minimum recreational space from
the one as required under DCR 23:-
15. The Development Control Regulations are referable to Section
22(m) of the MRTP Act. Section 21 of the said Act requires the planning
authority, i.e. the local authority (appellant no. 1 in the instant case)
to prepare a development plan for the local area within its jurisdiction.
Section 22 of the Act lays down what should be the contents of a
development plan, and in that behalf it provides under sub-section (m) that
it shall contain amongst others:-
“(m) provision for permission to be granted for controlling
and regulating the use and development of land within the
jurisdiction of a local authority…..”
The present DCR’s for Greater Mumbai, 1991 were sanctioned by the State of
Maharashtra on 20.2.1991 and are enforced from 25.3.1991. The new DCR’s
are shortly to be formulated for the next twenty years.
The DCR 23 on recreational / amenity open spaces:-
16. The DCR 23 with which we are concerned in the first issue reads
as follows:-
“23. Recreational/Amenity Open Spaces:-
(1) Open spaces in residential and commercial layouts—
(a) Extent:—In any layout or sub-division of vacant land in a
residential and commercial zone, open spaces shall be provided
as under:
(i) Area from 1001 sq.m. to 2500 sq.m. 15 per cent
(ii) Areas from 2501 sq.m. to 10000 sq.m. 20 per cent
(iii) Area above 10000 sq.m. 25 per cent.
These open spaces shall be exclusive of areas of
accesses/internal roads/designations or reservations,
development plan roads and areas for road-widening and shall as
far as possible be provided in one place. Where, however, the
area of the layout or sub-division is more than 5000 sq.m., open
spaces may be provided in more than one place, but at least one
such places shall be not less than 1000 sq.m. in size. Such
recreational spaces will not be necessary in the case of land
used for educational institutions with attached independent
playgrounds. Admissibility of FSI shall be as indicated in
Regulation 35.
(b) Minimum area:—No such recreational space shall measure less
than 125 sq.m.
(c) Minimum dimensions:—The minimum dimension of such
recreational space shall not be less than 7.5 m., and if the
average width of such recreational space is less than 16.6 m.,
the length thereof shall not exceed 2'/2 times the average
width.
(d) Access:—Every plot meant for a recreational open space shall
have an independent means of access, unless it is approachable
directly from every building in the layout.
(e) Ownership:—The ownership of such recreational space shall
vest, by provision in a deed of conveyance, in all the property
owners on account of whose holdings the recreational space is
assigned.
(f) Tree growth:—Excepting for the area covered by the
structures permissible under (g) below, the recreational space
shall be kept permanently open to the sky and accessible to all
owners and occupants as a garden or a playground etc. and trees
shall be grown as under :—
(a) at the rate of 5 trees per 100 sq.m. or part thereof of the
said recreational space to be grown within the entire plot.
(b) at the rate of I tree per 80 sq.m. or part thereof to be
grown in a plot for which a sub-division or layout is not
necessary.
(g) Structures/uses permitted in recreational open spaces:—
(i) In a recreational open space exceeding 400 sq.m. in area (
in one piece), elevated/underground water reservoirs, electric
substations, pump houses may be built and shall not utilise more
than 10 per cent of the open space in which they are located.
(ii) In a recreational open space or playground of 1000 sq.m. or
more in area (in one piece and in one place), structures for
pavilions, gymnasia, club houses and other structures for the
purpose of sports and recreation activities may be permitted
with built-up area not exceeding 15 per cent of the total
recreational open spaces in one place. The area of the plinth of
such a structure shall be restricted to 10 per cent of the areas
of the total recreational open space. The height of any such
structure which may be single storey shall not exceed 8 m. A
swimming pool may also be permitted in such a recreational open
space and shall be free of FSI. Structures for such sports and
recreation activities shall conform to the following
requirements:—
(a) The ownership of such structures and other appurtenant users
shall vest, by provision in a deed of conveyance, in all the
owners on account of whose cumulative holdings the recreational
open space is required to be kept as recreational open space or
ground, viz. 'R.G.' in the layout or sub-division of the land.
(b) The proposal for construction of such structure should come
as a proposal from the owner/owners/society/societies or
federation of societies without any profit motive and shall be
meant for the beneficial use of the owner/owners/members of such
society / societies / federation of societies.
(c) Such structures shall not be used for any other purpose,
except for recreational activities, for which a security deposit
as decided by the Commissioner will have to be paid to the
Corporation.
(d) The remaining area of the recreational open space or
playground shall be kept open to sky and properly accessible to
all members as a place of recreation, garden or a playground.
(e) The owner/owners/or society/or societies or federation of
societies shall submit to the Commissioner a registered
undertaking agreeing to the conditions in (a) to (d) above.
(2) Open spaces in industrial plots/layouts of industrial
plots:—
(a) In any industrial plot admeasuring 10,000 sq.m. or more in
area, 10 per cent of the total area shall be provided as an
amenity open space subject to a maximum of 2500 sq.m., and
(i) such open space shall have proper means of access and shall
be so located that it can be conveniently utilised by the person
working in the industry;
(ii) the parking and loading and unloading spaces as required
under these Regulations shall be clearly shown on the plans;
(iii) such open spaces shall be kept permanently open to sky and
accessible to all the owners and occupants and trees shall be
grown therein at the rate of 5 trees for every 100 sq.m. of the
said open space to be grown within the entire plot or at the
rate of 1 tree for every 80 sq.m. to be grown in a plot for
which a sub-division or layout is not necessary.
(b) In case of sub-division of land admeasuring 8000 sq.m. or
more in area in an industrial zone, 5 per cent of the total area
in addition to 10 per cent in (a) above shall be reserved as
amenity open space, which shall also serve as general parking
space. When the additional amenity open space exceeds 1500 sq.m.
the excess area may be used for construction of buildings for
banks, canteens, welfare centers, offices, crèches and other
common purposes considered necessary for industrial users as
approved by the Commissioner.”
The provision regarding the podium:-
17. As has been noted in paragraph 13 of the order dated 25.7.2013,
the appellants did not look into the issue of reduction in recreational
area at the ground level very seriously, probably because the rule permits
recreational space on the podium. Some of the interveners very seriously
canvassed that in view of the provision concerning recreational space on
the podium, the recreational / amenity open space at the ground level could
legitimately be reduced. The provision regarding the podium is seen in DCR
No. 38 (34). DCR 38 lays down the requirements concerning parts of
buildings. DCR 38 (34) reads as follows:-
“(34) Podium.
(i) A podium may be permitted on plot admeasuring 1500 sq.mt. or
more.
(ii) The podium provided with ramp may be permitted in one or
more level, total height not exceeding 24 m. above ground level.
However, podium not provided with ramp but provided with two car
lifts may be permitted in one or more level, total height not
exceeding 9 mt. above ground level.
(iii) The podium shall be used for the parking of vehicles.
(iv) The recreational space prescribed in D.C. Regulation 23 may
be provided either at ground level or on open to sky podium.
(v) Podium shall not be permitted in required front open space.
(vi) Such podium may be extended beyond the building line in
consonance with provision of D.C. Regulation 43(1) on one side
whereas on other side and rear side it shall be not less that
1.5m. from the plot boundary.
(vii) Ramps may be provided in accordance with D.C. Regulation
38(18).
(viii) Adequate area for Drivers rest rooms and sanitary block
may be permitted on podiums by counting in FSI.”
18. As far as the issue no. 1 is concerned, this Court had sought
the affidavit from the Chief Engineer, Town Planning of the appellant-
Municipal Corporation, and from the Secretary, Urban Development Department
of the State of Maharashtra. Shri Manu Kumar Srivastava, Principal
Secretary to the Government of Maharashtra in the Urban Development
Department has filed an affidavit affirmed on 6.9.2013. In para 4.4 he has
stated as follows:-
“4.4) I submit that in quite a few cases, the requirements
of captive parking for the building can be met only by providing
the same in basement or on upper parking floors or podium, which
in turn requires provision of access / ramps etc., which often
makes it difficult to provide the required Recreational /
Amenity open spaces on the ground……”
Thereafter, he has stated that it is to overcome this difficulty that the
DCRs have been amended with effect from 6.1.2012 to allow recreational
spaces on podium in plots admeasuring 1500 sq. mts. or more. In his
affidavit he has pointed out that in the redevelopment projects under DCR
33(7) for reconstruction of cessed buildings, and for the urban renewal
schemes under DCR 33(9), and for the slum rehabilitation projects under DCR
33(10), it is permissible to reduce the Recreational / Amenity open spaces
to the limit prescribed in the respective regulations. He has stated that
this has been done consciously to facilitate these schemes.
19. On behalf of the appellant-Municipal Corporation Shri Rajeev
Kuknur, Chief Engineer (Development Plan) has affirmed his reply on
6.9.2013. In paragraph 6, thereof, he has also stated that the provision
for parking on podium has been made to facilitate the requirement of
parking. He has, however, added “in such situation it may not be possible
for the planner to provide the entire Recreational/Amenity space on the
ground”. Later in paragraph 7, he has pointed out that in certain other
situations the amenity open spaces are permitted to be reduced. Thus,
under DCR 33(1) read with Clause 6.20 of Appendix IV which applies to the
redevelopment schemes for slums, the amenity space can be reduced, but
still a minimum of 8% of the amenity space shall be maintained. Clause 8
of Appendix III applies the same provision to the reconstruction /
redevelopment of cessed buildings under DCR 33(7). As regards the
development under DCR 33 (9), clause 12.14 of Appendix IIIA concerning DCR
33(9), states that, “Even if the recreational open space is reduced to make
the project viable, a minimum of at least 10 percent of plot area shall be
provided as recreational open space. In addition to this, 10 percent of
plot area shall be earmarked for amenity space which can be adjusted
against the DP reservation, if any”.
20. It was canvassed on behalf of Maharashtra Chamber of Housing
Industry by Mr. S. Ganesh, learned Senior Counsel that DCR 38 (34) clearly
provides under clause (iv) thereof, that the recreational space prescribed
in DCR 23 may be provided at the ground level or on open to sky podium. In
his view, this will enable the developers to provide more parking spaces
within the plots concerned since now-a- days, there is a demand for even
two parking spaces per flat. He submitted that, in fact, this will give a
large continuous open space on the podium and in view thereof the
Recreational / Amenity space need not be at the ground level. He submitted
that even trees would be planted on the podium, and movements on the podium
will be safer for elderly people as well as for the children. The areas
for parking and recreation on the podium can be separately ear-marked for
that purpose. A few photographs of such arrangements were also brought to
our notice. He submitted that in view of the necessity of having more
accommodation and more parking spaces that this provision has been made,
and it should be interpreted accordingly.
21. It is very relevant to note that although Mr. F.S. Nariman,
learned senior counsel appeared for the respondents-Kohinoor, he stated
that after the order was passed by this Court on 25.7.2013, he was
appearing to assist the Court on the four issues framed in Part-II of that
order as amicus-curie. He pointed out that sub-clause (iv) of DCR 38(34)
lays down that the recreational space ‘may be provided’ either at the
ground level or on open to sky podium. As against that the Recreational /
Amenity open space contemplated under DCR 23 was mandatory. Sub-clause
(1) (a) of DCR 23 speaks of ‘vacant land’ and the open spaces as far as
possible ‘shall be provided’ at one place. He, therefore, submitted that
whereas the provision under DCR 23 is mandatory, the one under DCR 38(34)
is discretionary, and it cannot prevail over DCR 23.
22. Similarly, though learned Senior Counsel Mr. Harish N Salve,
appeared for the Municipal Corporation, until the passing of the order
dated 25.7.2013, as far as the issue of recreational spaces on podium is
concerned, he submitted a separate note to assist the Court. He pointed out
that as clause (iii) of the DCR 38(34) states, the podium shall be used for
parking of vehicles. Clause (iv) gives a further option to provide
recreational space on the podium, but it links this recreational space on
the podium to the recreational space prescribed in DCR 23, by stating that
the recreational space under DCR 23, may be provided at the ground level,
or on the open-to-sky podium. In his submission, if read as an alternative
to the minimum recreational space on the ground floor, this provision will
lead to the serious erosion of recreational space at the ground level,
affecting the minimum necessities of life, and will therefore lead to
violation of the right to life, and will have to be held as bad in law, as
against the guarantee provided under Article 21 of the Constitution of
India. As against that in his submission clause (iv) can survive only if
this clause is read down as inapplicable and not excluding the recreational
space provided under DCR 23. In other words, it makes an additional
provision for recreational space, over and above the one at the ground
level, and does not in any way reduce the same. This is because the podium
is basically meant to provide parking, as stated in clause (iii). Any
recreational space provided on the podium is entirely discretionary, and
that being so it cannot be read to lead to a reduction in the mandatory
provision under Clause (iii).
23. The UDRI was represented by learned Senior Counsel Mr. Shyam
Divan. He pointed out that DCR 23 providing for recreational space at the
ground level existed since the inception of DCR in 1991, and even prior
thereto since 1967. It was always contemplated that the recreational space
will be at the ground level, and not at an elevated level within buildings.
This is clear from the provision with respect to the trees and playgrounds
contained in DCR 23. Besides, he pointed out that clause (iii) of DCR
38(34) clearly provides that ‘podium shall be used for the parking of
vehicles’, meaning thereby that it is essentially to be used for parking
purposes. That apart, he submitted that there is clearly a risk involved
in providing both parking as well as recreational space on the podium. DCR
38 (34) (iv) has been introduced by way of an amendment only from 6.1.2012,
and it does not contain a non-obstante clause that the provision is
notwithstanding the mandatory requirement under DCR 23. It cannot,
therefore, be read in derogation of the main provision under DCR 23.
24. Mr. Divan then brought to our notice the harsh reality of the
open spaces becoming smaller and smaller in the city of Mumbai. He placed
the following hard statistics for our consideration. Greater Mumbai has
just 1.91 sq. mts. of open space per person. Of this, less than 0.88 sq.
mts. per person is accessible for recreational purpose. This is woefully
inadequate as compared to the norms of 3 sq. mts. per capita as prescribed
by the National Building Code of India 2005 and of 11 sq. mts. per capita
recommended by the Urban Development Plans Formulation and Implementation
Guidelines (1996) of the Ministry of Urban Affairs, Government of India.
He pointed out that pouring of too much of cement and concrete is not
conducive to good human living, and will ultimately affect meaningful
‘life’ within the meaning of Article 21 of the Constitution. Recreational
spaces are intended to ensure that there are green “breathing spaces”
between buildings and properties in the built-up environment. . Trees and
the land around them at the ground level are necessary for controlling the
air pollution from the point of view of health of human beings as well.
The shifting of recreational space from the ground to podiums will result
in higher level of concretization, diminishing green cover, and buildings
being too close to each other, leading to increased city temperature
25. Having noted these submissions, it is seen that podium is
permissible only on plots admeasuring 1500 sq. mts. or more. So this
provision is not applicable to plots smaller than 1500 sq. mts. As can be
seen from DCR 23 (1) (a), it speaks of a lay-out or sub-division of ‘vacant
land’ and open spaces. The open spaces ‘shall as far as possible’ be
provided in one place. If a lay-out or sub-division is more than 5000 sq.
mts., open space can be provided in more than one place, but at least one
such place ‘shall be of not less than 1000 sq. mts.’. These provisions
clearly show that they are mandatory. Besides under sub-clause (f) of DCR
23 there is a requirement of keeping the recreational open space
permanently open to the sky and trees are to be grown in that space as laid
down, i.e. five trees per hundred square meters of the recreational space
within the plot. DCR 2 (64) defines ‘open space’ to mean an area forming
an integral part of a site left open to the sky. A ‘site’ is defined under
DCR 2 (83) to mean a parcel or piece of land enclosed by definite
boundaries. These DCR’s when read together, very much make it clear that
the recreational /amenity space has to be on the land i.e. on ground level
and it has got to be 15%, 20% or 25% of the area depending upon its size.
As rightly pointed out by learned senior counsel Mr. Nariman and Mr.
Salve, the requirement of recreational space on the podium under DCR 38
(34) (iv) is discretionary. Besides, as the above referred clause (iii)
lays down, podium shall be basically used for parking. Besides Clause (iv)
does not contain a non-obstante clause to over-ride the requirement under
DCR 23 making it mandatory to provide recreational space on the ground-
floor. That being so, the provision under DCR 38 (34) cannot be read in
derogation of the requirement under DCR 23 or else it will result into
serious erosion in the basic requirements for a good life affecting the
guarantee of right to life, under Article 21 of the Constitution of India.
We have therefore to read down clause (iv) of the DCR 38(34) as
inapplicable and not excluding the mandatory provision under DCR 23.
26. It is also relevant to note that the development schemes under
DCRs 33(7), 33(9) and 33(10) provide for lesser Recreational area / Amenity
spaces. Thus, under DCR 33(7) and 33(10) reduction in the Amenity open
space is permitted to make the project viable, but still minimum 8 percent
of the project area is required to be maintained as Amenity open space.
Similarly, for the schemes under DCR 33(9) minimum 10 percent of the plot
area is required to be retained as Recreational space. In other properties,
where there are no such constraints to make the development schemes of
rehabilitation or reconstruction of old buildings or slums viable, there is
no reason why the Amenity open space at the ground level should be read as
permissible, to be reduced. The only ground being given is to provide more
parking and more accommodation, meaning thereby more construction,
concretization and financial expediency. Such a purpose cannot be read
into the provisions as they presently exist, nor is it desirable to do so
from the point of view of the requirement of minimum open spaces at the
ground level.
27. Besides, as pointed out by Mr. Divan, the requirement of having
trees and open land around them is necessary from an environmental point of
view, since there is already excessive concretization, and a very serious
reduction in open spaces at the ground level. It must be noted that the
right to a clean and healthy environment is within the ambit of Article
21, as has been noted in Court on its Own Motion v. Union of India reported
in 2012 (12) SCALE 307 in the following words:-
“The scheme under the Indian Constitution unambiguously
enshrines in itself the right of a citizen to life under Article
21 of the Constitution. The right to life is a right to live
with dignity, safety and in a clean environment.”
The right to a clean and pollution free environment, is also a right under
our common-law jurisprudence, as has been held by this Court in Vellore
Citizen’s Welfare Forum v. Union of India and Ors reported in (1996)5SCC647
where this Court held:-
“The Constitutional and statutory provisions protect a
persons right to fresh air, clean water and pollution free
environment, but the source of the right is the inalienable
common law right of a clean environment.”
In the same judgment the Court emphasized the importance of Sustainable
Development, and the need for a balance between development and ecological
considerations, in the following words:-
“The traditional concept that development and ecology are
opposed to each other, is no longer acceptable….
‘Sustainable Development’ is the answer…Sustainable
Development as defined by the Brundtland Report means
"development that meets the needs of the present without
compromising the ability of the future generations to meet their
own needs". We have no hesitation in holding that "Sustainable
Development' as a balancing concept between ecology and
development has been accepted as a part of the Customary
International Law though its salient features have yet to be
finalised by the International Law jurists.”
28. Therefore, after reflecting upon the legal position, we are
clearly of the opinion that having 15%, 20% or 25% of the area (depending
upon the size of the lay-out) as the recreational/amenity area at the
ground level is a minimum requirement, and it will have to be read as such.
We therefore, answer the issue no. 1 by holding that it is not permissible
to reduce the minimum recreational area provided under DCR 23 by relying
upon DCR 38(34). However, if the developers wish to provide recreational
area on the podium, over and above the minimum area mandated by DCR 23 at
the ground level, they can certainly provide such additional recreational
area.
Issue No.4 with respect to the protection against the fire hazards:-
29. As stated earlier, this issue was decided to be gone into
considering that the main building in the present complex is going to be of
48 storeys. This issue was decided to be gone into also in the backdrop of
the recent fire that engulfed the six storey Secretariat building of
Maharashtra, in Mumbai. It took a few days to extinguish the fire which
resulted into a loss of lives. This Court sought the affidavit of the Chief
Fire Officer of the appellant-Municipal Corporation on this issue. Shri
Suhas Vishnu Joshi, Chief Fire Officer, Mumbai Fire Brigade, has affirmed
his reply on 15.9.2013. In paragraph 3 of his affidavit, he has stated
that the Fire Brigade of the appellant-Municipal Corporation has got
special appliances such as Aerial Ladder Platform which can reach up to the
height of 70 meters, and the department is in the process of procuring
special appliances which can reach up to the height of 90 meters. In
paragraph 4, he has accepted that in high-rise buildings above 90 meters,
the fire-fighting operations cannot be carried out from outside the
building alone. They are also to be fought from inside the building with
the help of fire safety and protection measures / installations provided in
the high-rise buildings as per the building by-laws. He has pointed out
the passive safety measures as well as active fire safety measures
necessary for the high-rise buildings in his affidavit. Amongst the fire
safety measures, he has pointed out that the width of the access road and
the open space for maneuverability of fire appliances has to be adequate.
30. It is also pointed out in this affidavit that there is a State
Act known as Maharashtra Fire Prevention and Life Safety Measures Act, 2006
under which the developers / society in-charge of the building have to
maintain the fire prevention and life safety measures in good repair and
efficient condition at all times. In paragraph 7 of his affidavit he has
stated that for any high-rise and special type building, No Objection
Certificate from the Chief Fire Officer is required at two stages viz.
prior to the construction of the building and after the compliance of the
requirement. Besides, for buildings having a height above 70 meters, there
is a High Rise Technical Committee under the Chairmanship of a retired
Hon’ble High Court Judge with other experts and the proposal for high rise
buildings has to be cleared by this committee.
31. As far as the maneuverability of the fire appliances is
concerned, fire protection requirements under DCR 43 become relevant. This
DCR 43 is split in two parts (1) General and (2) Exits for every building.
It reads as follows:-
“43. Fire Protection Requirements:-
(1) General:—The planning design and construction of any
building shall be such as to ensure safety from fire. For thi s
purpose, unless otherwise specified in these Regulations, the
provisions of Part-IV; Fire Protection Chapter. National
Building Code shall apply. For multi-storeyed, high rise and
special buildings, additional provisions relating to fire
protection contained in Appendix VIII shall also apply-
(A) For proposal under regulations 33(7) and 33(10), in case of
rehabilitation/composite buildings on plots exceeding 600 sq.
mts. and having height more than 24 m. at least, one side other
than road side shall have clear open space of 6 m. at ground
level, accessible from road side.
Provided, if the building abuts another road of 6 m. or
more this condition shall not be insisted.
Provided further that in case of redevelopment proposals
under DCR 33(7), for plot size upto 600 sq. mt., 1.5 mts open
space will be deemed to be adequate.
(B) For the proposals other than (A) above
(a) Building having height more than 24 m. upto 70 m. at
least one side, accessible from road side, shall have clear open
space of 9 m. at ground level.
Provided however, if podium is proposed it shall not extend
3 m. beyond building so as to have clear open space of 6m.
beyond podium.
Provided further, where podium is accessible, to fire
appliances by a ramp, then above restriction shall not apply.
(b) Buildings having height more than 70 m. at least two
sides accessible from road side, shall have clear open space of
9m. at ground level.
Provided however ramps if podium is proposed it shall not
extend 3m. beyond building line so as to have clear open space
6m. beyond podium. No ramps for the podium shall be provided in
these side open spaces.
Provided further, where podium is accessible to fire
appliances by a ramp then above restriction shall not apply.
(c) Courtyard/ramp podium accessible to fire appliances
shall be capable of taking the load upto 48 tonnes.
(d) These open spaces shall be free from any obstruction
and shall be motorable.
(2) Exits:—Every building meant for human occupancy shall be
provided with exits sufficient to permit safe escape of its
occupants in case of fire or other emergency for which the exits
shall conform to the followings :—
(i) Types:—Exits should be horizontal or vertical. A
horizontal exit may be a door-way, a corridor, a passage-way to
an internal or external stairway or to an adjoining building, a
ramp, a verandah, or a terrace which has access to the street or
to the roof of a building. A vertical exit may be a staircase or
a ramp, but not a lift.
(ii) General requirements.—Exits from all the parts of the
building, except those not accessible for general public use,
shall—
(a) provide continuous egress to the exterior of the
building or to an exterior open space leading to the street;
(b) be so arranged that, except in a residential building,
they can be reached without having to cross another occupied
unit;
(c) be free of obstruction;
(d) be adequately illuminated;
(e) be clearly visible, with the routes reaching them
clearly marked and signs posted to guide any person to the floor
concerned;
(f) be fitted, if necessary, with fire fighting equipment
suitably located but not as to obstruct the passage, clearly
marked and with its location clearly indicated on both sides of
the exit way;
(g) be fitted with a fire alarm device, if it is either a
multi-storeyed, high-use or a special building so as to ensure
its prompt evacuation;
(h) remain unaffected by any alteration of any part of the
building so far as their number, width, capacity and protection
thereof is concerned;
(i) be so located that the travel distance on the floor
does not exceed the following limits :—
(i) Residential, educational, institutional and hazardous
occupancies: 22.5 m.
(ii) Assembly, business, mercantile, industrial and storage
buildings: 30 m.
Note:—The travel distance to an exit from the dead end of a
corridor shall not exceed half the distance specified above.
When more than one exit is required on a floor, the exits shall
be as remote from each other as possible:
Provided that subject to the provision under D.C.
Regulation 44(5) (a) for all multi-storeyed high rise and
special buildings, a minimum of two enclosed type staircases
shall be provided, at least one of them opening directly to the
exterior to an interior, open space or to any open place of
safety.
(iii) Number and width of Exits:—The width of an exit,
stairway/corridor and exit door to be provided at each floor in
occupancies of various types shall be as shown in columns 3 and
5 of Table 21 hereunder. Their number shall be calculated by
applying to every 100 sq.m. of the plinth or covered area of the
occupancy, the relevant multiplier in columns 4 and 6 of the
said Table, fractions being rounded off upward to the nearest
whole number.”
32. Now, what is seen here is that under Clause 1 (B) of DCR 43,
for buildings having heights of more than 24 meters up to 70 meters, at
least one side accessible from road side shall have clear open space of 9
meters at ground level. For buildings which have a height of more 70
meters, at least two sides accessible from road sides, shall have a clear
open space of 9 meters at ground level. In both these cases where podium
is proposed, it shall not extend 3 meters beyond the building line so as to
leave clear open space of 6 meters beyond podium. Similarly Clause 1 (A)
lays down that in case of the proposals under DCR 33(7) (which are for the
cessed building) and those under 33(10) (which are for the slum
rehabilitation), if the plot of the building exceeds 600 sq. mts. and the
building is having height of more than 24 meters, at least one side other
than the road side shall have a clear open space of 6 meters at ground
level accessible from the road side. The first proviso to Clause 1 (A)
makes an exception if the building abuts another road of 6 meters or more.
In that case this condition is not insisted. Thus, as can be seen, a
minimum access of 6 meters to every building from two sides is insisted,
i.e. from a road side and from one side within the property, or from two
road sides so that the fire engine can approach the building at least from
two sides. The second proviso under Clause 1 (A) however states that if
the redevelopment proposal is under DCR 33(7) i.e. for reconstruction or
redevelopment of cessed buildings on plots of size upto 600 sq. mts., only
1.5 meters side open space will be deemed to be adequate. This will mean a
space of just about 5 feet or so, through which a fire engine can certainly
not enter.
33. We asked Mr. R.P. Bhatt, learned Senior Counsel appearing for
the Municipal Corporation as to what would be the height of these buildings
on plots upto 600 sq. mts., and his answer was that it will depend on the
number of flats for the families to be accommodated in such buildings, and
it may as well go up to 20 floors. Mr. Ganesh, learned Senior Counsel
appearing for the Maharashtra Chamber of Housing Industry defended the
existing provision on the ground of economic viability of such projects,
and submitted that for such projects under DCR 33(7), the side space inside
the property will have to be reduced on that count. He submitted that some
of these plots are very small and are in congested areas, and that these
redevelopment schemes are carried out by private developers. Additional
construction is required to be carried out to provide minimum accommodation
to the existing occupants as well as for the newly entering occupants who
pay higher amounts to buy the additional flats. He referred to and relied
upon a judgment of a bench of two judges of this Court in Jayant Achyut
Sathe Vs. Joseph Bain D’souza & Ors. reported in 2008 (13) SCC 547 wherein
the challenge to the 1.5 m. open space (i.e. about 5 feet) in the schemes
under DCR 33 (7) came to be rejected.
34. (i) On the other hand, Mr. Nariman pointed out that although the
ladders / snorkels which the fire department are supposed to go up to the
height of 70 meters, the maximum reach of the snorkel depends on various
factors such as wind velocity, availability of space, and tilt and angle of
the approach. Thus, the reach is always less than the theoretical maximum
height. Besides, there are 33 Fire Brigade Stations in Greater Mumbai, 15
in the city, 12 in Western Suburbs and 6 in Eastern Suburbs. None of these
stations have sufficient equipments (snorkels) in their stations since they
are in limited numbers.
(ii) It was also pointed out by Mr. Nariman that as far as the internal
arrangement in the multi-storey buildings is concerned, a refuge floor is
required to be provided above every 7 floors for buildings crossing the
height of 24 meters. However, these refuge floors are very often not
properly maintained, are not kept vacant, and are used for other purposes.
The consequence is that the effectiveness of the fire protection from
within the building remains in peril. He further pointed out that the Fire
Brigade is supposed to check installations such as sprinklers and other
fire-fighting equipments as provided under Appendix VIII inside the
buildings periodically, but the department is understandably over-worked,
and therefore not in a position to effectively cover all the buildings in
the city.
35. Mr. Shyam Divan, learned Senior Counsel appearing for the UDRI
pointed out that the present fire protection requirements contained in DCR
43(1) if strictly complied with, could be considered as adequate for mid-
rise buildings and structures up to 13 storeys. However, when it comes to
the high-rise buildings, the fire safety requirements are primarily
compromised by relaxation in the access under DCR 17 and the side open /
setback spaces between the buildings under DCR 28. He submitted that the
provision contained in the second proviso of DCR 43(1)(A) could not be
justified.
36. As far as the schemes under DCR 33(7) are concerned, Mr. Shyam
Divan, learned Senior Counsel appearing for the UDRI has pointed out that
there is already a criticism with respect to these schemes viz. that they
are working more for the developers and for the private new entrants who
buy the flats at higher costs, than for providing the accommodation to the
existing occupants. The State Government is also raising its hands on the
ground of financial difficulties to take up such schemes. Consequently,
the inability of fire engines to go into such plots, and thereby
permanently denying the occupants adequate fire protection is not the
concern of either of them. Protection of the environment and human life
are constitutional mandates, and even if the developers and the public
authorities choose to ignore these essentials, this Court cannot.
Adequate access for the fire-engines as an essential requirement:-
37. Having noted the submissions of all the counsel in this behalf,
what we find is that whereas the provisions for the mid-rise buildings up
to 13 floors are somewhat adequate, those beyond are required to be
strictly implemented from within as well. The provisions for the refuge
floor and various requirements from within have to be strictly scrutinized
and insisted upon. That apart the second proviso to DCR 43(1)(A) cannot
stand scrutiny of minimum safety requirement. If the access of 6 meters is
required from at least one side within the property for the fire engine to
enter and move inside, we fail to see as to how in redevelopment proposals
under DCR 33(7) where the plot size is up to 600 sq. mts., open space of
1.5 meters, can be said to be adequate. As fairly pointed out by Mr.
Bhatt, the buildings on such plots can also go up to 20 floors, depending
upon the number of flats for the occupants to be provided for. If that is
so, it is necessary to have an open space of the width of 6 meters within
the property for the fire engine to enter the property at least from one
side which is so provided for every other building.
38. It is true that in Jayant Achyut Sathe (supra) the challenge to
the five feet open space in the schemes under DCR 33(7), came to be
rejected. However, as can be seen from paragraph 49 of the judgment, it
was principally rejected on the ground that the challenge was hopelessly
delayed since this provision restricting the open spaces in these schemes
had been in existence since 1984. The question of fire engines not being
able to go inside such plots, was raised in the Bombay High Court, but this
Court has not gone into that aspect in the said judgment. We are looking
into the issue of the side space on the backdrop of the failure of the fire
brigade to quickly extinguish the fire even in the six storeyed
Secretariate building in Mumbai, which has sufficient side spaces on all
sides. Not providing a minimum space of 6 meters which makes room for the
fire-engine to access the building amounts to violation of the right to
life and equality of the residents of these buildings, by not providing the
same standard of safety to them which is available to residents of all
other buildings. It is true that some of these plots under the DCR 33(7)
schemes are small plots and are in congested areas. But if that is so,
nothing prevents the State Government from taking over such schemes for
which it can finance from the overall cess collection. In such cases, it
may have to accommodate only the existing occupants. This can also be
achieved by calling upon such occupants to partly contribute towards the
construction cost. But human life cannot be made to suffer only on the
ground that in the redevelopment scheme sufficient access cannot be
provided for the fire engine to enter within the plot even from one side.
39. We are, therefore, of the view that the second proviso to DCR
43(1)(A) is discriminatory as against the occupants of the plots up to the
size of 600 sq. mts. and therefore violative of Article 14 of the
Constitution of India. The provision is likely to lead to a hazardous
situation, affecting the life of the occupants, and therefore violative of
Article 21 of the Constitution. We, therefore, hold the provision to be
bad in law. If the fire is to be extinguished at the earliest the fire-
engine must be able to reach the spot of fire, without any delay.
Maneuverability of the fire engine is, therefore, of utmost importance. As
such, most of the city roads are very narrow. On top of that if there is no
adequate space for the fire engine to enter the property, the situation
will become worse. We are clearly of the view that even for redevelopment
proposals of plots up to the size of 600 sq. mts. under DCR 33(7), an open
space of the width of 6 meters within the property which is accessible from
the road on one side, will have to be maintained unless the building abuts
roads of 6 meters or more on two sides, or another appropriate access of 6
meters to the building is available apart from the abutting road. This
will be subject to the decision of the Chief Fire Officer in writing.
Besides, we also feel that it is necessary to direct that the fire
department must insist from the developer/society of all the buildings, to
certify at least once in six months that the access to the building, the
internal exits and the internal fire fighting arrangements are maintained
as per the expectations under the DCR, the norms of the fire department,
and must check them periodically, on its own.
The decision on Issues no. 1 and 4 to apply prospectively:-
40. Although, for the reasons stated above, we are of the view that
the provision under DCR 38 (34) cannot be read in derogation to the one
under DCR 23 with respect to the recreational area, and also that the
second proviso to DCR 43 (1) (A) on fire protection requirements is
hazardous and discriminatory against the occupants of the schemes under DCR
33 (7), we do note the submission by the intervening Practicing Engineers,
Architects, and Town Planners Association that any such declaration/
changes be implemented with prospective effect, namely, where the
commencement certificate (CC) has yet not been granted.
Issue No.2 regarding height of the buildings vis-à-vis the width of the
adjoining road, and Issue No.3 on the impact of additional FSI on the
traffic situation:-
41. As far as the issues no.2 and 3 are concerned, though they are,
in a way, independent issues, they are inter-related also, and therefore,
we will deal with them together. These are issues requiring wider
consideration and consultation amongst planners, and as far as these issues
are concerned, this Court will confine itself to making certain
recommendations for consideration of the planners. This is because this
Court is conscious of the fact that the new development plan for the city
of Mumbai is in the process of being drafted. It is for the planners to
examine these issues. However, since these issues have arisen in the
context of the present matter, this Court has invited the response from the
appellant-Municipal Corporation as well as the State Government. The
concerned interveners have also made their submissions. We shall look into
the submissions in this behalf and make certain suggestions for
consideration in the light thereof.
Issue No. 2-Height of buildings, vis-à-vis width of the roads:-
42. DCR 31 (1) lays down that the height of a building shall not
exceed one and a half times the total of the width of the street on which
it abuts. Issue No. 2 is framed in the backdrop of the fact that in the
present case, a tower of the height of 195.90 meters is being constructed.
This tower is bounded by four roads and the height of the tower is
disproportionately high, as against the width of the adjoining roads. The
first proviso to DCR 31(1) lays down that this restriction shall not be
applicable for construction of buildings undertaken under DCR section
33(7), 33(8) and 33(9). Though, these DCR’s are for the housing re-
development schemes they also add to the population in the particular area
as well as the vehicles. It is from this point of view that the question
has been framed as to whether these exemptions are justified, valid or
legal? DCR 31(1) reads as follows:-
“31. Height of Buildings
(1) Height vis-à-vis the road width.- The height of a building
shall not exceed one and a half times the road of the width of
the street on which it abuts and the required front open space.
The restrictions of height of the building spelt out in
Regulation No. 31(1) shall however, cease to apply in case where
the plot front on road having with more than 18.00 mtrs. And
where front marginal open space of 12 mtrs. Minimum is observed,
provided that open spaces on other sides are made available as
required from the fire safety point of view. For this purpose,
the width of the street may be the prescribed width of the
street, provided the height of the building does not exceed
twice the sum of the width of the existing street and the width
of the prescribed and required open space between the existing
street and the building. The latter width shall be calculated
by dividing the area of land between the street and the building
by the length of the front face of the building.
Explanations-
(i)”Prescribed width” here means the width prescribed in the
development plan or the width resulting from the prescription of
a regular line of the street under the Bombay Municipal
Corporation Act, 1888, whichever is larger.
(ii) If a building abuts two or more streets of different
widths, it shall be deemed for that purpose of this Regulation
to abut the wider street; the height of the building shall be
regulated by the width of that street and may be continued to
this height to a depth of 24m. along the narrower street,
subject to conformity with Regulation 28:
[Provided however, that restrictions on height spelt out in this
regulation shall not be applicable for reconstruction and
redevelopment of old buildings undertaken under Regulation
33(7), 33(8) and 33(9) of these Regulations, which are not
affected by Coastal Regulation Zone Notification dated 19th
February, 1991, issued by the Ministry of Environment and
Forests, Government of India, and orders issued from time to
time.
[Provided however that restrictions on height spelt out in this
Regulation shall not be applicable for construction of buildings
undertaken under regulation 33(10) and 33(14) of these
regulations for implementation of Slum Rehabilitation Scheme.]”
43. As far as this issue is concerned, response was sought from the
Secretary, Urban Development Department, of State of Maharashtra, and the
Chief Engineer Town Planning of the appellant. Shri Manu Kumar Srivastava,
Principal Secretary, Urban Development Department, Government of
Maharashtra has explained these exemptions in his affidavit. He has
pointed out that these schemes under DCR 33(7), 33(8) and 33(9) seek to
achieve free of cost in-situ-rehabilitation of the occupants living in old
and dilapidated buildings. Therefore, to make the scheme viable, incentive
FSI is granted, which the developer uses to construct what is called as a
‘sale component’ that is sold in the open market to recover the cost
incurred by him for constructing the tenements for rehabilitation of the
existing tenants. Therefore, the restriction on the height of these
buildings vis-à-vis the width of the road, is required to be relaxed.
44. Shri Rajiv Kuknur, Chief Engineer, Development (Development
Plan) in his affidavit on this issue on behalf of the appellants,
reiterated that the exemptions under these DCRs are for accommodating
existing tenants which is done with the participation of private
developers. Mr. Ganesh, appearing for the Maharashtra Chamber of Housing
Industry, has similarly justified granting higher FSI and construction of
the high-rise buildings on that footing.
45. The State Government was represented by learned Senior Counsel,
Mr. Shekhar Naphade. He pointed that the city was suffering from some basic
constraints viz. on the one hand, the population was increasing,
particularly in the suburbs, and on the other hand, the land resources
were very limited. There was also the floating population moving from the
northern suburbs to the city everyday and returning back by the evening.
He submitted that one has to take into consideration the practical
realities. At the time when the development plan was prepared in 1991, the
appellant-Municipal Corporation found that it could not acquire land for
various public projects such as gardens and playgrounds and therefore, the
concept of Transferred Development Rights (TDR) was introduced, whereunder
the land owner surrenders the land required for gardens or playgrounds and
gets the TDR in lieu thereof. He pointed out that the population density
in Mumbai was very high. It was 270 persons per hectare as against 106 of
New York, 83 of Singapore and 64 of Hongkong. The Corporation had to
adjust the competing interests and therefore, at appropriate places the
high-rise buildings had to be permitted.
46. Mr. Shyam Divan, on the other hand, submitted that these tall
structures have affected access to natural light and ventilation and has
created number of health problems. In his submission, there should not be
a blanket exemption for projects involving additional FSI from the height
restrictions under DCR 31. There should be accountability on the part of
the authority and the project developer to whom relaxation is granted. He
submitted that some of these buildings which were reconstructed with high
FSI under DCR 33(7), (8) and (9), had been reduced to vertical slums. The
developers do not bother to look into the maintenance of these schemes, the
construction is poor and a large number of the occupants for whom these
houses are constructed, sell them and the purpose of having the scheme,
gets defeated.
Issue No.3 concerning impact of FSI on the traffic situation:-
47. As far as issue No. 3 viz. impact of FSI on the traffic
situation is concerned, Shri Manu Kumar Srivastava, has pointed that as per
the census of 2011, 30.82 lakhs people were staying in the island city.
Due to the accelerated economic growth, there is a spurt in the vehicles of
the occupants, as well as, those entering the island city. In para 6.3, he
has placed on record the steps taken by the State Government in this
behalf. This paragraph 6.3 reads as follows:-
“6.3 ….
i) Revising the captive parking requirements upwards for
various categories of buildings.
ii) Introducing instruments like Regulation 33(24) for
creating public parking lots.
iii) Taking up construction of mass rapid transit systems
like Metro Rail, Mono Rail etc. so as to wean people
away from the use of personalized means of
transport.”
In para 6.4 he has referred to the suggestions made by a High- Powered
Committee regarding traffic management and that steps were being taken
according to those recommendations. In para 7 of his affidavit, he has
stated that the draft development plan for the period 2014-2034 is under
preparation, wherein many of these difficulties will be taken care of.
48. Shri R.C. Dixit, Chief Engineer, Roads and Traffic of the
appellant-Municipal Corporation has filed his affidavit on issue No. 3. He
has pointed out that the number of vehicles in Greater Mumbai has increased
from 3.08 lakhs from 1981 to 19.38 lakhs in 2011, and the population has
increased during this period from 82.43 lakhs to 124.78 lakhs. Out of
this population, that of the island city is 31.06 lakhs. He has pointed
out in paragraph 16 of his affidavit that the State Government has
constituted a High Powered Committee on 6.6.2012 to suggest corrective and
remedial measures. It has also to prepare an action plan for
recommendations up to 2016-2017. In paragraph 18, he has referred to
various recommendations made by the High Powered Committee and that the
same are being followed.
49. Shri Vivek Phansalkar, Commissioner of Police, Traffic, Mumbai,
has stated in paragraph 9 of his reply that as per information of the State
Transport Department, on an average 450 new vehicles were being added to
the road network every day. The vehicular population by January 2013 was
nearly 21 lakhs. He has stated that Mumbai continues to have a high usage
of public transport, yet there is a relatively sharp increase in use of
cars in the last decade which has pushed Mumbai into a situation of a grid
lock. Increasing vehicles on the roads have led to bottlenecks for traffic
movement. In paragraph 13 he has stated that no definite findings can be
arrived at without a comprehensive study of the impact of additional FSI in
the island city of Mumbai on traffic density. He has however, accepted
that periodical increase in FSI would result in more construction which, in
turn, could lead to the higher tenement density, indicating an increase in
traffic. In paragraph 14, he has suggested various measures to control the
traffic congestion.
50. The UDRI has made various suggestions. Its trustees include
Mr. Charles Correa, an eminent architect and town planner, Shri Dipak
Parekh an eminent economist, Shri D.M. Sukhtankar, retired Municipal
Commissioner and former Secretary to Government of Maharashtra and others.
This institute has made a detailed study of the problems of the city. With
respect to issue No. 2, this institute has submitted as noted above, that
there should not be a blanket relaxation for the high rise buildings, and
it should be examined locality-wise. Absence of any check in this behalf,
has resulted into very tall buildings with no open spaces on extremely
narrow streets. It is often seen that whereas the ordinary FSI is 1.33,
the minimum FSI available to the schemes under DCR 33(7), 33(8) and 33(9)
is 2.5, and there is no upper limit. No assessment is made of the
sustainable carrying capacity of the areas in which these projects are
implemented. There is no transport impact assessment on the neighbourhood
in such projects. A locality-wise approach is therefore required.
51. In its submissions on the issues at hand, UDRI pointed out that
whereas the total open space in Mumbai is 3.8%, if we compare it with
another crowded area viz. Manhattan in US, there the public open space for
recreation is 13.1%. The National Building Code (of India) requires 3 sq.
mts. per capita by way of open space. However, Greater Mumbai has just 1.91
sq. mts. of open space per person, and of this less than 0.88 sq. mts. per
person is accessible for recreation. Each Manhattan resident occupies 11
times as much floor space as a Mumbai resident. Doubling or trebling
Mumbai’s FSI will only make it two or three times denser than Manhattan in
regard to the number of people on the ground. Consequently, the open space
available per person will become even less.
52. Since the project of respondent-Kohinoor is going to be at a
busy road junction near Shivaji Park in the Dadar area of Mumbai, it is
pointed out by UDRI that Dadar, Mahim, and Matunga areas, are essentially
residential areas. Various housing colonies were laid out, as per the town
planning scheme, such as Dadar Parsi Colony and Hindu Colony etc. In fact,
Mr. Divan pointed out that the entire area around Shivaji Park was laid out
systematically as per the norms, for a specified population, and it is like
a heritage area. Requisite provisions for gardens, schools, roads, foot-
paths and play-grounds etc., have been made for a certain density of
population. Now with the reconstruction schemes being proposed, suddenly
tall buildings are coming up even near the school buildings, and adding
further to the density and pressure on the existing infrastructure. The
roads having been laid out much earlier, and being in proper proportion to
the height of the adjoining buildings, these new tall buildings coming up
in the very area are causing congestion and greater traffic. This is
affecting the life of the people around and even the school going children,
with increased traffic and parking on the roads. The roads which were
adequate at one point of time, are now being found to be narrow. Plot
No.46, with which we are concerned, in the present matter, had a textile
mill earlier, and now a huge commercial complex has been approved on it.
But for this construction, there were no such large commercial complexes in
this entire area. Earlier only those commercial activities were permitted
which were necessary for the use of the residents. This huge commercial
complex is going to add tremendous pressure on the traffic in the area and
at an already busy junction.
Suggestions on issue Nos. 3 and 4 for consideration when the new
Development Plan is drafted:-
53. We have noted the submissions on both these issues, and what we
find is that the exemptions from DCR 31 (1) for schemes under Section
33(7), 33(8) and 33(9), though apparently meant for laudable purpose, are
very often resulting into extreme crowding, and traffic congestion. It is
necessary that while granting exemptions from DCR 31(1), there must be a
scheme-wise approach, and there ought to be a proper supervision of the
construction. These development schemes and the additional FSI thereunder,
should be examined locality-wise. The impact of such high-rise buildings
on the adjoining locality as well as on the traffic, is required to be
examined before granting such permission.
54. In our view, there is a need to restrict the additional
pressure on existing infrastructure so that it does not affect the quality
of life. The existing social infrastructure like educational institutions,
open spaces, hospitals etc, and physical infrastructure like water supply
and drainage is already over-burdened. Therefore, wherever possible, the
State Government, the planning authority, and the committee entrusted with
drafting of the new plan should consider contribution by the existing
occupants themselves to a good extent towards the construction cost, or the
State should contribute through its agencies or from the amount of cess-
collected. This will result into curtailing the number of additional
entrants and will not add to the density of the population. This approach
should particularly be examined where the plots are small or are in
congested areas, and particularly where the proposal is under DCR 33(7).
The new Development Plan is to be prepared shortly, and while preparing the
plan these aspects concerning restrictions on blanket exemptions,
contribution by the existing occupants to the reconstruction schemes,
locality-wise consideration and impact of additional FSI on traffic, ought
to be gone into. In areas where the old town planning schemes have
prescribed a uniform lay-out, one can accept some buildings going up to a
certain extent, if necessary, to accommodate the existing occupants in a
reconstruction scheme. However, it should not result into a plethora of
steeply rising buildings, to accommodate outsiders to the building, adding
to the population and traffic, and disturbing the existing order of the lay-
out completely.
Reconstitution of the ‘Technical Committee for High Rise Buildings’:-
55. (i) It has been pointed out on behalf of the Municipal Corporation
that subsequent to a PIL in the Bombay High Court in the case of Tardeo
Haji Ali Residents Welfare Association, the State Government has
constituted a ‘Technical Committee for High-Rise Buildings’ (i.e. Buildings
exceeding 70 meters in height). As per the note submitted by the learned
Senior Counsel for the Municipal Corporation, the terms of reference of the
committee are as follows:-
“(1) The Committee shall be of advisory nature and it will
advise the Municipal Commissioner regarding the feasibility
of the development proposals that might be referred to it
by the Commissioner.
(2) It will be open for the Commissioner to over-rule the
recommendations of the Committee, after giving a proper and
reasonable justification in writing. Such powers will not
be delegated to any subordinate officer.
(3) In specific cases, if the Chairman desires, any expert
from other fields may be invited for the meeting of the
Committee.”
The note points out
1) The building proposals which are to be referred to the
committee
2) The procedure to be followed by the committee
3) The points to be considered by the committee, viz.,
a) Architectural Points:-
1) Clear width of access available.
2) Location, width & No. of staircase.
3) Natural ventilation to staircase and common lobby.
4) Whether benefit of D.C. Rule 33 (24) is availed?
5) The minimum net plot size for High Rise proposal is
prescribed as 1000 Sq.Mt. and 850 Sq.Mts. for
proposals under D.C. R. 33 (7).
6) Depth & Nos. of the basement.
7) Area & location of the refuge floors.
8) Open spaces, podiums, etc.
9) Two wheeler & four wheeler parking provisions in the
building.
10) Width of common lobby & ventilation.
b) Structural and Geotechnical Points:-
1) Soil Report indicating soil strata, depth of the hard
rock, etc.
2) Type of foundation i.e. pile foundation or raft
foundation or open foundation.
3) Design Base Report (D.B.R.) for the proposal.
4) Various type of tests carried on site i.e. wind
tunnel test.
5) Gust factor & deflection.
6) Details of the rock anchors, if any provided for
basement.
7) Details of the soil retaining methods.
c) Environmental Points:-
1) Shadow Analysis.
2) Wind Analysis.
3) Heat Analysis.
4) Traffic Study & Traffic Management.
5) Ecological Study (Tree Plantation, Green area, etc.)
6) Disaster Management Plan.
7) Total Water Requirement.
8) Total waste water sewage generated & disposal (Design
of Sewerage Treatment Plant).
9) Effect of the construction material on environment.
10) Rain Water Harvesting & Storm Water Management.
11) Air environment in construction & operation phase.
12) Solid Waste Management.
13) Energy conservation techniques.
d) The point of view of the C.F.O.:-
1) Height of first refuge floor from ground floor and
also height of subsequent refuge floors.
2) Location of refuge area.
3) Whether refuge area is cantilever.
4) Clear open space along with turning radius for
movement of fire tender around the building.
5) Width & gradient of ramp (one way or two way) leading
to podium.
6) Alternate provision for fighting the fire from
ground.
7) Driveway for fire tender movement on paved R.G.
8) Height of underpass in case fire tender moving below
building.
9) Podium line should be flush with building line on
refuge facing area.
10) Number of staircase and width of staircase.
11) Distance between two staircases, through common
lobbies/passages.
12) Natural ventilation through sidewalls of basements.
13) Compartmentalization of the basements.
(ii) The first committee was appointed by a Resolution of the Urban
Development Department dated 28.7.2004. The composition of the Committee
has changed from time to time. We are informed that the term of the
existing committee, which is the third committee, has expired. The
committee consists of six members and is headed by a retired judge of the
Bombay High Court, as the Chairman. It has two ex-officio members, namely,
the Chief Engineer (Development Plan) of the appellant who is also the
member secretary, and the Chief Fire Officer of the appellant. There are
three expert members. Following are the present expert members:-
“(1) Prof R. S. Jangid, Dept of Civil Engineering, IIT Bombay,
as a Structural Engineering Expert.
(2) Prof. Abhay Bambole, Professor and Head of the Structural
Engineering Department, VJIT, Matunga, as the Soil and Geotech
Expert.
(3) Dr. Rakesh Kumar, Director and Gr. Scientist and Head NEERI
Regional Centre as the Environmental Expert.”
56. It has been suggested that we appoint a new committee, though
the State Government has expressed its willingness to extend the term of
the present committee. Mr. Nariman has, in fact, suggested that the
committee should consist of members who will play a pro-active role. Mr.
Divan submitted that it should be a Development Plan over-sight committee,
and it should at-least look into the grievances with respect to the schemes
under 33(7), (8),(9), and (10). Mr. Joaquim Reis, learned senior counsel
instructing Dr. Abhishek Singhvi, learned senior counsel appearing for the
Property Redevelopers Association, suggested inclusion of an architect in
the committee. Considering that the architectural points as mentioned in
the municipal note, are also to be gone into by the committee, the
suggestion is quite apt. He suggested the inclusion of eminent architect
Mr. Charles Correa, who is associated with UDRI (and which is represented
by Mr. Divan). We are, however, not including his name only for the reason
that we are informed that he is a very busy architect, though the committee
should certainly consult him whenever necessary. In his place, we include
Shri Pankaj Joshi, Architect, Urban Researcher, and consultant to the
appellant-Municipal Corporation, whose name is suggested by Mr. Divan.
Thus, the assistance of an architect will also be available to the
committee. Having taken the consensus of the counsel appearing in the
matter, we are effecting one more change in the committee. We appoint
Hon’ble Mr. Justice P.S. Patankar, former Judge of the Bombay High Court,
to be the Chairman of the committee.
The committee will now consist of the following:-
|1) |Chairman |Mr. Justice P.S Patankar, |
| | |Former Judge of the High Court|
| | |of Bombay |
|2) |Member Secretary |Chief Engineer (Development |
| | |Plan) of Municipal Corporation|
| | |of Greater Mumbai (MCGM) |
|3) |Member |Prof. Department of Civil |
| |(Structural |Engineering, IIT Bombay, |
| |Engineering |Pawai. (presently Professor |
| |Expert) |R.S Jangid or any other |
| | |professor, with the required |
| | |qualifications, nominated by |
| | |the Director IIT Pawai) |
|4) |Member (Soil, |Prof and Head of the |
| |Mech. Geo Tech. |Structural Engineering |
| |Expert) |Department, VJTI, Matunga. |
| | |(presently Prof. Abhay Bambole|
| | |or any other professor, with |
| | |the required qualifications, |
| | |nominated by the principal |
| | |VJTI) |
|5) |Member |Director Gr, Scientist and |
| |(Environmental |Head NEERI regional centre |
| |Expert) |(presently Dr. Rakesh Kumar) |
|6) |Ex-officio member|Chief Fire Officer of MCGM |
|7) |Member (Architect|Mr. Pankaj Joshi (Architect, |
| |and Urban |Urban Researcher, and |
| |Researcher) |Consultant to the MCGM) |
The additional terms of reference for the Committee:-
57. (i) As of now, all new building proposals where the height of the
building exceeds 70 meters is referred to the committee. A scrutiny fee
for Rs 50,000 per proposal is collected at the time of submission of the
proposal. We have already referred to the existing terms of reference. In
view of the discussion in this matter, in our view, it is desirable that
the committee be requested to look into two additional aspects which are as
follows:-
(ii) The committee will also look into the grievances regarding
construction and technical requirements of the development schemes under
DCR 33(7), 33(8), 33(9) and 33(10), whenever brought to the notice of the
committee by concerned persons.
(iii) The committee may as well make recommendations to the State
Government with respect to the new Development Plan which is under
drafting.
58. (i) The committee will have to spend good time for this work. The
honorarium paid to the chairman is presently fixed at Rs. 15000 per month,
and it was fixed much earlier. Now we are widening the terms of reference.
Therefore, we direct that the appellant-Municipal Corporation will pay an
honorarium of Rs. 50,000/- per month to the Chairman. The other members
will be provided with the conveyance charges and attendance charges to
attend the meetings and for site inspections, as per the municipal rules.
The Municipal Corporation will make available an appropriate room in its
headquarters and secretarial staff for the working of the committee.
(ii) The State Government shall issue necessary notification reconstituting
the committee, its terms of reference, and other aspects, such as
honorarium etc, within four weeks hereafter.
59. Before we conclude, we record our appreciation for all the
learned counsel who have assisted us in deciding the issues, and
particularly Senior Counsel Mr. Nariman and Mr. Salve, who appeared for the
respondents and appellants respectively, at the stage of the earlier order
which was passed on 25.7.2013, but assisted the Court in deciding the four
issues.
In the circumstances we pass the following order:-
60. (1) The memorandum of settlement dated 18.4.2013, concerning the
Public Parking Lot (PPL) arrived at between the appellant-Municipal
Corporation of Greater Mumbai and the respondents was taken on record, as
noted in Part-I order dated 25.7.2013, in the facts and circumstances of
the present case. Both the parties shall act strictly in accordance with
the same. It is clarified that as held in the said order, the Municipal
circular dated 22.6.2011 is not in any way held to be bad in law.
(2) The four additional issues framed in Part-II of the above order are
decided as follows:-
Issue No. (i) – The minimum recreational space as laid down under
Development Control Regulation (DCR) 23, cannot be reduced on the basis of
DCR 38(34). The recreational space, if any, provided on the podium as per
DCR 38(34)(iv), shall be in addition to that provided as per DCR 23.
Issue Nos. (ii) & (iii) – The Government of Maharashtra, the Development
Plan Drafting Committee, and the appellant-Municipal Corporation shall
consider the suggestions as contained in paragraph Nos.53 and 54 above,
while framing the Development Plan for Greater Mumbai.
Issue No. (iv) – The second proviso to DCR 43(1) (A), concerning fire
protection requirements, is held to be bad in law. We hold that even for
the reconstruction proposals of plots upto the size of 600 sq. mts. under
DCR 33(7), open space of the width of 6 meters at least on one side at
ground level within the plot, accessible from the road side will have to be
maintained for the maneuverability of a fire engine, unless the building
abuts two roads of 6 meters or more on two sides, or another access of 6
meters to the building is available, apart from the road abutting the
building.
(3) The decision as contained in Clauses 2(i) and 2(iv) above, will apply
to those constructions where plans are still not approved, or where the
Commencement Certificate (CC) has not yet been issued. All authorities
concerned are directed to ensure strict compliance accordingly.
(4) The Government of Maharashtra shall issue the necessary notification
within four weeks of this order, re-constituting the ‘Technical Committee
for the High-Rise Buildings’, as directed in paragraph 56, including the
additional terms of reference, as mentioned in paragraph 57 above. The
appellant is directed to render assistance and provide the required
honorarium, as mentioned in paragraph 58 above.
(5) In view of the settlement arrived at between the parties, as well as
Part-I order dated 25.7.2013 mentioned in paragraph (1), and the
determination on the four additional issues as in paragraph (2) above, no
further order is required on this appeal, and the appeal stands disposed
off accordingly.
(6) The parties will bear their own costs.
…………………………………..J.
[ H.L. Gokhale ]
……………………………………J.
[ J. Chelameswar ]
New Delhi
Dated: December 17, 2013
-----------------------
67
‘PPL’ for short) of the buildings being constructed on Plot No.46 of Town
Planning Scheme-III, - Apex court - gave directions -
Division Bench of the Bombay High Court whereby Writ Petition
No.143/2012 filed by the respondents was allowed, and which quashed the
stop work notice dated 22.12.2011 issued by Executive Engineer (Building
Proposal) City-III, Municipal Corporation of Greater Mumbai, and order
dated 27.4.2012 passed by the Additional Municipal Commissioner restricting
to four floors the height of Wing ‘C’ (providing for public parking lot-
‘PPL’ for short) of the buildings being constructed on Plot No.46 of Town
Planning Scheme-III, N.C.Kelkar Road, Shivaji Park, Dadar, Mumbai. =
In the circumstances we pass the following order:-
(1) The memorandum of settlement dated 18.4.2013, concerning the
Public Parking Lot (PPL) arrived at between the appellant-Municipal
Corporation of Greater Mumbai and the respondents was taken on record, as
noted in Part-I order dated 25.7.2013, in the facts and circumstances of
the present case. Both the parties shall act strictly in accordance with
the same. It is clarified that as held in the said order, the Municipal
circular dated 22.6.2011 is not in any way held to be bad in law.
(2) The four additional issues framed in Part-II of the above order are
decided as follows:-
Issue No. (i) – The minimum recreational space as laid down under
Development Control Regulation (DCR) 23, cannot be reduced on the basis of
DCR 38(34). The recreational space, if any, provided on the podium as per
DCR 38(34)(iv), shall be in addition to that provided as per DCR 23.
Issue Nos. (ii) & (iii) – The Government of Maharashtra, the Development
Plan Drafting Committee, and the appellant-Municipal Corporation shall
consider the suggestions as contained in paragraph Nos.53 and 54 above,
while framing the Development Plan for Greater Mumbai.
Issue No. (iv) – The second proviso to DCR 43(1) (A), concerning fire
protection requirements, is held to be bad in law. We hold that even for
the reconstruction proposals of plots upto the size of 600 sq. mts. under
DCR 33(7), open space of the width of 6 meters at least on one side at
ground level within the plot, accessible from the road side will have to be
maintained for the maneuverability of a fire engine, unless the building
abuts two roads of 6 meters or more on two sides, or another access of 6
meters to the building is available, apart from the road abutting the
building.
(3) The decision as contained in Clauses 2(i) and 2(iv) above, will apply
to those constructions where plans are still not approved, or where the
Commencement Certificate (CC) has not yet been issued. All authorities
concerned are directed to ensure strict compliance accordingly.
(4) The Government of Maharashtra shall issue the necessary notification
within four weeks of this order, re-constituting the ‘Technical Committee
for the High-Rise Buildings’, as directed in paragraph 56, including the
additional terms of reference, as mentioned in paragraph 57 above. The
appellant is directed to render assistance and provide the required
honorarium, as mentioned in paragraph 58 above.
(5) In view of the settlement arrived at between the parties, as well as
Part-I order dated 25.7.2013 mentioned in paragraph (1), and the
determination on the four additional issues as in paragraph (2) above, no
further order is required on this appeal, and the appeal stands disposed
off accordingly.
(6) The parties will bear their own costs.
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.11150 OF 2013
(@ out of SPECIAL LEAVE PETITION (CIVIL) NO. 33402/2012)
Municipal Corporation of Greater Mumbai and Ors. … Appellants
Versus
Kohinoor CTNL Infrastructure Company Private
Limited and another … Respondents
J U D G E M E N T
H.L. Gokhale J.
Leave granted.
2. This appeal is directed against the order dated 9.7.2012 passed
by a Division Bench of the Bombay High Court whereby Writ Petition
No.143/2012 filed by the respondents was allowed, and which quashed the
stop work notice dated 22.12.2011 issued by Executive Engineer (Building
Proposal) City-III, Municipal Corporation of Greater Mumbai, and order
dated 27.4.2012 passed by the Additional Municipal Commissioner restricting
to four floors the height of Wing ‘C’ (providing for public parking lot-
‘PPL’ for short) of the buildings being constructed on Plot No.46 of Town
Planning Scheme-III, N.C.Kelkar Road, Shivaji Park, Dadar, Mumbai.
Dispute between the parties, settlement thereof and Part-I of the order
dated 25.7.2013:-
3. This appeal was initially heard by a bench of G.S. Singhvi and
H.L. Gokhale, JJ. Mr. Harish Salve and Mr. R.P Bhatt, both learned Senior
Counsel appeared for the appellants, and Mr. F.S Nariman, learned Senior
Counsel appeared for the respondent. The appellants wanted to restrict the
PPL up to four floors only, but before the issuance of the restrictive
circular dated 22.6.2011, in this behalf, the respondents had already
consumed higher FSI (Floor Space Index) on the basis of the Commencement
Certificates issued earlier. In view of the discussion in the Court
however, a settlement was arrived at between the appellants and the
respondents on the controversy concerning the PPL. Before passing the
order on the settlement, the bench noted the backdrop of the facts and
circumstances of the case in paragraphs 2 to 5 in Part-I of the order
passed on 25.7.2013 (per Singhvi, J. as he then was). These paragraphs
read as follows:-
“2. The plans submitted by respondent No. 1 for construction
of Wings-‘A’, ‘B’ and ‘C’ of the building were sanctioned by the
competent authority of the Municipal Corporation of Greater
Mumbai (for short, ‘the corporation’) and Intimation of
Disapproval was issued on 15.2.2006. After the Ministry of
Environment and Forests, Government of India granted clearance
for the construction of commercial building, the competent
authority issued commencement certificated dated 13.9.2006. The
Joint Commissioner of Police (Traffic) issued NOC dated
11.12.2009 for the development of a multi-storied public parking
lot and vide letter dated 2.6.2010, the State government granted
in-principle approval under Clause 33(24) of the Development
Control Regulations (DCR) for Greater Mumbai, 1991 for
construction of a multi-storied public parking lot. Thereafter,
the competent authority issued the Letter of Intent dated
27.7.2010.
3. During the construction of the building, the Urban
Development Department of the State Government sent letter dated
4.3.2011 to the Municipal Commissioner requiring him to submit a
proposal for amendment of Clause 33 (24) of the DCR for limiting
the height of parking towers to 4 floors and also for revocation
of all sanctioned proposals where the commencement certificates
had not been issued. In view of that letter, the Corporation
issued circular dated 22.6.2011 prescribing certain conditions
under Clause (iv) of DCR 33(24) and clarified that all proposals
for public parking lots shall be considered subject to those
conditions. The new conditions sought to limit the height of
public parking to ground plus 4 upper floors and 2 basements.
4. As a sequel to the above changes, the Corporation issued
notice dated 29.11.2011 to respondent No. 1 under Section 51 of
the Maharashtra Regional and Town Planning Act, 1966 requiring
it to show cause as to why the commencement certificate may not
be revoked. Respondent No. 1 submitted detailed reply dated
14.12.2011 and pleaded that the amended DCR 33(24) cannot be
made applicable to its buildings because substantial
construction had already been made at a cost of Rs. 167/-
crores. Thereafter, the concerned Executive Engineer issued
stop work notice dated 22.12.2011 and directed respondent No. 1
to restrict the work of public parking to 4 floors instead of 13
floors. After about six months, Additional Municipal
Commissioner passed order dated 27.4.2012, the relevant portion
of which is extracted below:-
“As there is a substantial construction on core part of the
plot, PPL done in this part shall be allowed to the extent of
already executed construction as per report dated 27.12.2011.
In the remaining portion of the plot, where there is no
substantial construction, PPL shall be limited to G + 4,
Developer is to be asked to modify his plans in consonance with
modified DCR.”
5. The respondent challenged the stop work notice and the
order of the Additional Municipal Commissioner in Writ Petition
No. 143/2012, which was allowed by the High Court in the
following terms:-
“In the facts of this case, the admitted position as accepted in
the order of the Additional Municipal Commissioner indicates
that the work of development had substantially progressed by the
time a notice to show cause was issued under Section 51 of the
M.R. & T.P. Act, 1966. The impugned order passed by the
Additional Municipal Commissioner restricting the Petitioners to
a height of a ground floor and four upper floors in deviation of
the permission granted earlier is thereafter contrary to law.
Hence, the impugned order would have to be quashed and set aside
and is accordingly set aside. The stop work notice which has
been issued to the Petitioners on the basis of the notice to
show cause dated 29 November 2011 is to that extent quashed and
set aside. Rule is made absolute in these terms. There shall
be no order as to costs.”
4. The above referred memorandum of settlement arrived at between
the parties contained clauses 1, 2 (a to e) and an annexure thereto with
respect to the modus-operandi in that behalf. Clauses 2 (a) and (b)
thereof are relevant for our purpose. They read as follows:-
“2. In view of the peculiar facts and circumstances of the
present case and without establishing any precedent, it is
agreed between the Petitioners herein and the Respondent No.
1(Kohinoor CTNL) as follows:-
a) In public interest, Public Parking Lot (PPL) will no
longer be on ground + 13 upper floors as initially approved
under amended approval dated 21st September, 2011 in Wing ‘C’ of
the development of composite building on Final Plot No. 46, but
on the ground + 4 upper floors in Wing ‘C’ as well as in three
level basement below Wing ‘A’, ‘B’ and ‘C’ i.e. entire basement,
and the captive parking shall be on 5th to 13 upper floors in
Wing ‘C’.
b) It is also agreed that in the present case of F.P. No.
46, the PPL will be managed and operated by the Petitioner No. 1
(MCGM) or its nominee(s) and common ingress and egress through
the common entry/exist shall be provided in Wing ‘C’ for PPL as
well as captive parking for Municipal Corporation of Greater
Mumbai and Respondent No. 1 (Kohinoor CTNL). The modus-operandi
in that behalf is detailed in Annexure hereto.”
(emphasis supplied)
5. Since the signed memorandum of settlement was filed in the
Court, the Court passed the following operative order in paragraph 9 of
Part-I of the said order dated 25.7.2013:-
“9. Accordingly, the Memorandum of Settlement signed by the
representatives of the parties and their advocates on 18.4.2013
together with the annexure are taken on record. We note that
this settlement is arrived at on the backdrop of the facts and
circumstances of this case. We clarify that we have not in
anyway held the Municipal Circular dated 22.6.2011 to be bad in
law. We direct that the parties shall strictly abide by the
terms of settlement.”
(emphasis supplied)
6. The settlement has brought about the change as desired by the
appellants, while taking care of interest of the respondents. The complex
is going to be on the land which earlier belonged to Kohinoor Textile Mill
at Dadar, Mumbai. Wing ‘A’ is to consist of 3 basements + ground to 5
Floors, and Wing ‘B’ is to consist of 3 basements + ground to 48 floors
with a total height of 195.90 meters. Wing ‘C’ was to be in two parts as
originally proposed. Ground+14 Floors, thereof, were to be meant for PPL,
and 15 to 30 floors were to be kept for residential purposes. Under the
Municipal circular dated 22.6.2011 prescribing conditions under clause (iv)
of DCR 33(24), the public parking building was to be confined only to
ground+4 upper floors. The settlement accepts this position, and now as per
the settlement, public parking is going to be provided in the ground + 4
upper floors in Wing ‘C’ and also in the three level basements below Wings
A’, ‘B’ and ‘C’. The private parking shall be from 5th to 13th floors of
Wing ‘C’.
Part-II of the order dated 25.7.2013 framing four issues:-
7. Although the dispute between the parties, was with respect to
the height of the building consisting of the PPL, it was felt that the
appellants had not applied their mind to some of the issues which, in fact,
did arise in the matter of the grant of permission to this complex on the
said plot No.46 in the heart of Mumbai city. It was noticed that as per
the approved plan, the recreational space available at the ground level was
reduced to only 7.7% of the area of the plot, as against the required
minimum of 15% (where the area of the plot was between 1001 sq. mts. to
2500 sq. mts. as per the DCR 23). In view of the reduction in the
recreational area at the ground level, it was observed in paragraph 13 of
the said order as follows:-
“…..We may add that since the petitioners and respondents
have arrived at a settlement, we do not propose to go into this
issue with respect to the construction of the respondent. We
are, however, surprised that the Municipal Corporation did not
look into the reduction in the recreational area at the ground
level very seriously, probably because the rule permits
recreational space on the podium. If this is treated as a
correct interpretation, then it is quite possible that the
recreational area left at the ground level could simply be zero.
It may leave no space on the ground floor for the
residents/occupants of the apartments constructed in the
particular building, and that will have serious adverse impact
on the right to life not only of the residents/occupants of the
apartments but also of the people in the adjoining areas because
all of them will have to only fall back on the public parks or
play grounds and gardens for their minimum recreational
requirements……”
(emphasis supplied)
It was, therefore, felt that it was necessary to examine the co-relation
between DCR-23, which provides for minimum Recreational/Amenity open
spaces, and DCR-38 (34) concerning the Podium.
8. Secondly, it was noted that in the present matter a higher FSI
has been given in lieu of making a provision for public parking, leading to
a high-rise building. Such high-rise constructions bring along with them
more population and more vehicles on the adjoining narrow roads and into an
already congested area, and that aspect did not appear to have been
examined by the appellant-Municipal Corporation. In the instant case, the
approved complex is bounded on four sides by four roads, and these roads
are not, at all, wide. The height of the complex is going to be quite
disproportionate to the width of these roads, but that has been permitted
amongst other reasons in view of making a provision for public parking.
Under DCR No.31 (1), the height of the building has to be in proportion to
the width of the road which is adjoining a building, but the proviso to
that DCR makes another exception to this rule with respect to construction
schemes under DCRs Nos.33(7), (8) and (9). DCR 33(7) is regarding
reconstruction or redevelopment of cessed buildings in the island city, by
co-operative housing societies, or of old buildings belonging to the
Municipal Corporation or the police department, and it grants FSI of 2.5
plus incentive FSI as specified in Appendix III, whichever is more. DCR
33(8) is regarding construction for housing the dis-housed, by the
Municipal Corporation. DCR 33(9) is regarding reconstruction or
redevelopment of cessed buildings or urban renewal schemes on extensive
areas, where the FSI is 4. These constructions also add to the population
and the vehicles in that very area. A question therefore arose as to
whether these exemptions are justified, valid and legal?
9. Thirdly, the impact of construction of high-rise buildings in
the thickly populated areas on the traffic in the city was also discussed
during the consideration of the SLP. The Court noted in paragraph 14 of
the order, that although additional space for public parking was being
provided, simultaneously higher FSI was also being granted to the
developer, on that count. Consequently, such high-rise buildings would add
more number of vehicles on the adjoining streets. This required
examination of the impact of additional FSI on the traffic situation,
particularly in the island city of Greater Mumbai.
10. Lastly, considering that the height of the complex was going
up to 198.50 meters, it was decided to look into the issue of hazards due
to fire which the occupants of such towers could face. It was noted that
there were provisions with respect to the space to be kept around such
buildings for the movement of fire engines within the compound of such
buildings, but these provisions are not uniform. The fire engines, with
their ladders, available with the Municipal Corporation, do not reportedly
reach anywhere beyond 14th floor. It was also noted that recently the
Secretariat Building of the State of Maharashtra (known as the
‘Mantralaya’) was engulfed with fire. The building is only six storeys,
and yet it took quite a few days to control the fire, and in that exercise
a few lives were unfortunately lost. Therefore, the issue of safety of the
occupants of such high-rise buildings, that of the residents in the
neighbourhood, and the firemen, required urgent consideration.
11. Therefore, in Part-II of its order dated 25.7.2013, the Bench
framed four issues for further consideration. These issues read as
follows:-
“(1) What should be the correlation between DCR 23 and DCR
38(34) regarding the recreational area? Is it permissible to
reduce the minimum recreational area provided under DCR 23 on
any ground?
(2) Whether the exemption from DCR 31(1) under DCR Nos.
33(7), (8), and (9) is justified, valid and legal particularly
in the island city of Greater Mumbai. If so, to what extent and
in which context?
(3) What is the impact of the addition of FSI in the island
city on the traffic situation? How can it be controlled?
(4) Whether the present mechanism for protection against
the fire hazards is adequate and is being implemented
effectively? If not, what should be the mechanism for
enforcement with respect to the provisions concerning the fire
safety?
12. For that purpose, affidavits were sought from the following:-
“(A) From the Municipal Corporation:-
(i) The affidavit of the Chief Engineer, Town Planning on
issues no. 1 and 2.
(ii) The affidavit of the Chief Engineer, concerning
traffic on issued no. 3.
(iii) The affidavit of the Chief Fire Officer on issue no
4.
(B) From the State of Maharashtra:-
(i) By the Secretary, Urban Development Department on
issue nos. 1, 2 and 3 above.
(ii) By the Commissioner of Police (Traffic) on issue no.
3 above.”
13. The excessive construction at the cost of minimum recreational
space, as seen in the present case, required an immediate attention to be
paid to issue no. (1).. Similarly, issue no. (4). concerning the fire
hazards also required urgent attention, and it was thought that the Court
should go into the legality of the relevant provisions in this behalf. As
against that, examination of the other two issues was taken up for the
reason that the development plan for the city of Mumbai is going to be
revised shortly, and certain suggestions in that behalf could be made.
Issue no. (2). arising out of exemptions to the high-rise buildings under
DCR 33(7),(8), (9) and issue no. (3) concerning the impact on traffic,
required a detailed deliberation. At this point, it is relevant to mention
that a similar approach has been adopted by this Court in Municipal
Corporation of Delhi Vs. Association of victims of Uphaar Tragedy & Ors.
reported in AIR 2012 SC 100. That case concerned the compensation to be
paid to the victims of the fire in the ‘Upahaar’ theatre at Delhi. This
Court decided the issue of compensation in paragraph 38 of the judgment.
However, the Court could not ignore that the fire had resulted into the
death of 59 persons and injury to 103 persons, and therefore, this Court
observed in paragraph 39 of the said judgment:-
“39. Normally we would have let the matter rest there.
But having regard to the special facts and circumstances of the
case we propose to proceed a step further to do complete
justice.”
And then, the Court made a number of suggestions in paragraph 45 of its
judgment to the Government for its consideration and implementation.
Similarly, although a settlement is arrived at, on the controversy between
the parties before the Court, considering the acute problems in the city of
Mumbai with respect to shortage of recreational space, the fire hazards and
high density of traffic, a further deliberation on the above referred four
issues was felt necessary.
14. Thereafter, the matter has been heard by the present Bench.
Consequent upon the above order, the necessary affidavits were filed by the
officers of the appellant as well as the State of Maharashtra. A number of
interveners have also assisted the Court. The interveners include (i) The
Urban Design Research Institute (‘UDRI’ for short) & Ors., (ii) Maharashtra
Chamber of Housing Industry, (iii) Practicing Engineers Architects and Town
Planners Association (India) and (iv) Property Redevelopers Association.
They have all assisted in the examination of these four issues. We will
deal with their submissions in the context of the Maharashtra Regional and
Town Planning Act, 1966 (the ‘MRTP’ Act for short), and the Development
Control Regulations for Greater Mumbai, 1991, framed thereunder which
govern these issues.
Issue no.1 concerning the reduction in the minimum recreational space from
the one as required under DCR 23:-
15. The Development Control Regulations are referable to Section
22(m) of the MRTP Act. Section 21 of the said Act requires the planning
authority, i.e. the local authority (appellant no. 1 in the instant case)
to prepare a development plan for the local area within its jurisdiction.
Section 22 of the Act lays down what should be the contents of a
development plan, and in that behalf it provides under sub-section (m) that
it shall contain amongst others:-
“(m) provision for permission to be granted for controlling
and regulating the use and development of land within the
jurisdiction of a local authority…..”
The present DCR’s for Greater Mumbai, 1991 were sanctioned by the State of
Maharashtra on 20.2.1991 and are enforced from 25.3.1991. The new DCR’s
are shortly to be formulated for the next twenty years.
The DCR 23 on recreational / amenity open spaces:-
16. The DCR 23 with which we are concerned in the first issue reads
as follows:-
“23. Recreational/Amenity Open Spaces:-
(1) Open spaces in residential and commercial layouts—
(a) Extent:—In any layout or sub-division of vacant land in a
residential and commercial zone, open spaces shall be provided
as under:
(i) Area from 1001 sq.m. to 2500 sq.m. 15 per cent
(ii) Areas from 2501 sq.m. to 10000 sq.m. 20 per cent
(iii) Area above 10000 sq.m. 25 per cent.
These open spaces shall be exclusive of areas of
accesses/internal roads/designations or reservations,
development plan roads and areas for road-widening and shall as
far as possible be provided in one place. Where, however, the
area of the layout or sub-division is more than 5000 sq.m., open
spaces may be provided in more than one place, but at least one
such places shall be not less than 1000 sq.m. in size. Such
recreational spaces will not be necessary in the case of land
used for educational institutions with attached independent
playgrounds. Admissibility of FSI shall be as indicated in
Regulation 35.
(b) Minimum area:—No such recreational space shall measure less
than 125 sq.m.
(c) Minimum dimensions:—The minimum dimension of such
recreational space shall not be less than 7.5 m., and if the
average width of such recreational space is less than 16.6 m.,
the length thereof shall not exceed 2'/2 times the average
width.
(d) Access:—Every plot meant for a recreational open space shall
have an independent means of access, unless it is approachable
directly from every building in the layout.
(e) Ownership:—The ownership of such recreational space shall
vest, by provision in a deed of conveyance, in all the property
owners on account of whose holdings the recreational space is
assigned.
(f) Tree growth:—Excepting for the area covered by the
structures permissible under (g) below, the recreational space
shall be kept permanently open to the sky and accessible to all
owners and occupants as a garden or a playground etc. and trees
shall be grown as under :—
(a) at the rate of 5 trees per 100 sq.m. or part thereof of the
said recreational space to be grown within the entire plot.
(b) at the rate of I tree per 80 sq.m. or part thereof to be
grown in a plot for which a sub-division or layout is not
necessary.
(g) Structures/uses permitted in recreational open spaces:—
(i) In a recreational open space exceeding 400 sq.m. in area (
in one piece), elevated/underground water reservoirs, electric
substations, pump houses may be built and shall not utilise more
than 10 per cent of the open space in which they are located.
(ii) In a recreational open space or playground of 1000 sq.m. or
more in area (in one piece and in one place), structures for
pavilions, gymnasia, club houses and other structures for the
purpose of sports and recreation activities may be permitted
with built-up area not exceeding 15 per cent of the total
recreational open spaces in one place. The area of the plinth of
such a structure shall be restricted to 10 per cent of the areas
of the total recreational open space. The height of any such
structure which may be single storey shall not exceed 8 m. A
swimming pool may also be permitted in such a recreational open
space and shall be free of FSI. Structures for such sports and
recreation activities shall conform to the following
requirements:—
(a) The ownership of such structures and other appurtenant users
shall vest, by provision in a deed of conveyance, in all the
owners on account of whose cumulative holdings the recreational
open space is required to be kept as recreational open space or
ground, viz. 'R.G.' in the layout or sub-division of the land.
(b) The proposal for construction of such structure should come
as a proposal from the owner/owners/society/societies or
federation of societies without any profit motive and shall be
meant for the beneficial use of the owner/owners/members of such
society / societies / federation of societies.
(c) Such structures shall not be used for any other purpose,
except for recreational activities, for which a security deposit
as decided by the Commissioner will have to be paid to the
Corporation.
(d) The remaining area of the recreational open space or
playground shall be kept open to sky and properly accessible to
all members as a place of recreation, garden or a playground.
(e) The owner/owners/or society/or societies or federation of
societies shall submit to the Commissioner a registered
undertaking agreeing to the conditions in (a) to (d) above.
(2) Open spaces in industrial plots/layouts of industrial
plots:—
(a) In any industrial plot admeasuring 10,000 sq.m. or more in
area, 10 per cent of the total area shall be provided as an
amenity open space subject to a maximum of 2500 sq.m., and
(i) such open space shall have proper means of access and shall
be so located that it can be conveniently utilised by the person
working in the industry;
(ii) the parking and loading and unloading spaces as required
under these Regulations shall be clearly shown on the plans;
(iii) such open spaces shall be kept permanently open to sky and
accessible to all the owners and occupants and trees shall be
grown therein at the rate of 5 trees for every 100 sq.m. of the
said open space to be grown within the entire plot or at the
rate of 1 tree for every 80 sq.m. to be grown in a plot for
which a sub-division or layout is not necessary.
(b) In case of sub-division of land admeasuring 8000 sq.m. or
more in area in an industrial zone, 5 per cent of the total area
in addition to 10 per cent in (a) above shall be reserved as
amenity open space, which shall also serve as general parking
space. When the additional amenity open space exceeds 1500 sq.m.
the excess area may be used for construction of buildings for
banks, canteens, welfare centers, offices, crèches and other
common purposes considered necessary for industrial users as
approved by the Commissioner.”
The provision regarding the podium:-
17. As has been noted in paragraph 13 of the order dated 25.7.2013,
the appellants did not look into the issue of reduction in recreational
area at the ground level very seriously, probably because the rule permits
recreational space on the podium. Some of the interveners very seriously
canvassed that in view of the provision concerning recreational space on
the podium, the recreational / amenity open space at the ground level could
legitimately be reduced. The provision regarding the podium is seen in DCR
No. 38 (34). DCR 38 lays down the requirements concerning parts of
buildings. DCR 38 (34) reads as follows:-
“(34) Podium.
(i) A podium may be permitted on plot admeasuring 1500 sq.mt. or
more.
(ii) The podium provided with ramp may be permitted in one or
more level, total height not exceeding 24 m. above ground level.
However, podium not provided with ramp but provided with two car
lifts may be permitted in one or more level, total height not
exceeding 9 mt. above ground level.
(iii) The podium shall be used for the parking of vehicles.
(iv) The recreational space prescribed in D.C. Regulation 23 may
be provided either at ground level or on open to sky podium.
(v) Podium shall not be permitted in required front open space.
(vi) Such podium may be extended beyond the building line in
consonance with provision of D.C. Regulation 43(1) on one side
whereas on other side and rear side it shall be not less that
1.5m. from the plot boundary.
(vii) Ramps may be provided in accordance with D.C. Regulation
38(18).
(viii) Adequate area for Drivers rest rooms and sanitary block
may be permitted on podiums by counting in FSI.”
18. As far as the issue no. 1 is concerned, this Court had sought
the affidavit from the Chief Engineer, Town Planning of the appellant-
Municipal Corporation, and from the Secretary, Urban Development Department
of the State of Maharashtra. Shri Manu Kumar Srivastava, Principal
Secretary to the Government of Maharashtra in the Urban Development
Department has filed an affidavit affirmed on 6.9.2013. In para 4.4 he has
stated as follows:-
“4.4) I submit that in quite a few cases, the requirements
of captive parking for the building can be met only by providing
the same in basement or on upper parking floors or podium, which
in turn requires provision of access / ramps etc., which often
makes it difficult to provide the required Recreational /
Amenity open spaces on the ground……”
Thereafter, he has stated that it is to overcome this difficulty that the
DCRs have been amended with effect from 6.1.2012 to allow recreational
spaces on podium in plots admeasuring 1500 sq. mts. or more. In his
affidavit he has pointed out that in the redevelopment projects under DCR
33(7) for reconstruction of cessed buildings, and for the urban renewal
schemes under DCR 33(9), and for the slum rehabilitation projects under DCR
33(10), it is permissible to reduce the Recreational / Amenity open spaces
to the limit prescribed in the respective regulations. He has stated that
this has been done consciously to facilitate these schemes.
19. On behalf of the appellant-Municipal Corporation Shri Rajeev
Kuknur, Chief Engineer (Development Plan) has affirmed his reply on
6.9.2013. In paragraph 6, thereof, he has also stated that the provision
for parking on podium has been made to facilitate the requirement of
parking. He has, however, added “in such situation it may not be possible
for the planner to provide the entire Recreational/Amenity space on the
ground”. Later in paragraph 7, he has pointed out that in certain other
situations the amenity open spaces are permitted to be reduced. Thus,
under DCR 33(1) read with Clause 6.20 of Appendix IV which applies to the
redevelopment schemes for slums, the amenity space can be reduced, but
still a minimum of 8% of the amenity space shall be maintained. Clause 8
of Appendix III applies the same provision to the reconstruction /
redevelopment of cessed buildings under DCR 33(7). As regards the
development under DCR 33 (9), clause 12.14 of Appendix IIIA concerning DCR
33(9), states that, “Even if the recreational open space is reduced to make
the project viable, a minimum of at least 10 percent of plot area shall be
provided as recreational open space. In addition to this, 10 percent of
plot area shall be earmarked for amenity space which can be adjusted
against the DP reservation, if any”.
20. It was canvassed on behalf of Maharashtra Chamber of Housing
Industry by Mr. S. Ganesh, learned Senior Counsel that DCR 38 (34) clearly
provides under clause (iv) thereof, that the recreational space prescribed
in DCR 23 may be provided at the ground level or on open to sky podium. In
his view, this will enable the developers to provide more parking spaces
within the plots concerned since now-a- days, there is a demand for even
two parking spaces per flat. He submitted that, in fact, this will give a
large continuous open space on the podium and in view thereof the
Recreational / Amenity space need not be at the ground level. He submitted
that even trees would be planted on the podium, and movements on the podium
will be safer for elderly people as well as for the children. The areas
for parking and recreation on the podium can be separately ear-marked for
that purpose. A few photographs of such arrangements were also brought to
our notice. He submitted that in view of the necessity of having more
accommodation and more parking spaces that this provision has been made,
and it should be interpreted accordingly.
21. It is very relevant to note that although Mr. F.S. Nariman,
learned senior counsel appeared for the respondents-Kohinoor, he stated
that after the order was passed by this Court on 25.7.2013, he was
appearing to assist the Court on the four issues framed in Part-II of that
order as amicus-curie. He pointed out that sub-clause (iv) of DCR 38(34)
lays down that the recreational space ‘may be provided’ either at the
ground level or on open to sky podium. As against that the Recreational /
Amenity open space contemplated under DCR 23 was mandatory. Sub-clause
(1) (a) of DCR 23 speaks of ‘vacant land’ and the open spaces as far as
possible ‘shall be provided’ at one place. He, therefore, submitted that
whereas the provision under DCR 23 is mandatory, the one under DCR 38(34)
is discretionary, and it cannot prevail over DCR 23.
22. Similarly, though learned Senior Counsel Mr. Harish N Salve,
appeared for the Municipal Corporation, until the passing of the order
dated 25.7.2013, as far as the issue of recreational spaces on podium is
concerned, he submitted a separate note to assist the Court. He pointed out
that as clause (iii) of the DCR 38(34) states, the podium shall be used for
parking of vehicles. Clause (iv) gives a further option to provide
recreational space on the podium, but it links this recreational space on
the podium to the recreational space prescribed in DCR 23, by stating that
the recreational space under DCR 23, may be provided at the ground level,
or on the open-to-sky podium. In his submission, if read as an alternative
to the minimum recreational space on the ground floor, this provision will
lead to the serious erosion of recreational space at the ground level,
affecting the minimum necessities of life, and will therefore lead to
violation of the right to life, and will have to be held as bad in law, as
against the guarantee provided under Article 21 of the Constitution of
India. As against that in his submission clause (iv) can survive only if
this clause is read down as inapplicable and not excluding the recreational
space provided under DCR 23. In other words, it makes an additional
provision for recreational space, over and above the one at the ground
level, and does not in any way reduce the same. This is because the podium
is basically meant to provide parking, as stated in clause (iii). Any
recreational space provided on the podium is entirely discretionary, and
that being so it cannot be read to lead to a reduction in the mandatory
provision under Clause (iii).
23. The UDRI was represented by learned Senior Counsel Mr. Shyam
Divan. He pointed out that DCR 23 providing for recreational space at the
ground level existed since the inception of DCR in 1991, and even prior
thereto since 1967. It was always contemplated that the recreational space
will be at the ground level, and not at an elevated level within buildings.
This is clear from the provision with respect to the trees and playgrounds
contained in DCR 23. Besides, he pointed out that clause (iii) of DCR
38(34) clearly provides that ‘podium shall be used for the parking of
vehicles’, meaning thereby that it is essentially to be used for parking
purposes. That apart, he submitted that there is clearly a risk involved
in providing both parking as well as recreational space on the podium. DCR
38 (34) (iv) has been introduced by way of an amendment only from 6.1.2012,
and it does not contain a non-obstante clause that the provision is
notwithstanding the mandatory requirement under DCR 23. It cannot,
therefore, be read in derogation of the main provision under DCR 23.
24. Mr. Divan then brought to our notice the harsh reality of the
open spaces becoming smaller and smaller in the city of Mumbai. He placed
the following hard statistics for our consideration. Greater Mumbai has
just 1.91 sq. mts. of open space per person. Of this, less than 0.88 sq.
mts. per person is accessible for recreational purpose. This is woefully
inadequate as compared to the norms of 3 sq. mts. per capita as prescribed
by the National Building Code of India 2005 and of 11 sq. mts. per capita
recommended by the Urban Development Plans Formulation and Implementation
Guidelines (1996) of the Ministry of Urban Affairs, Government of India.
He pointed out that pouring of too much of cement and concrete is not
conducive to good human living, and will ultimately affect meaningful
‘life’ within the meaning of Article 21 of the Constitution. Recreational
spaces are intended to ensure that there are green “breathing spaces”
between buildings and properties in the built-up environment. . Trees and
the land around them at the ground level are necessary for controlling the
air pollution from the point of view of health of human beings as well.
The shifting of recreational space from the ground to podiums will result
in higher level of concretization, diminishing green cover, and buildings
being too close to each other, leading to increased city temperature
25. Having noted these submissions, it is seen that podium is
permissible only on plots admeasuring 1500 sq. mts. or more. So this
provision is not applicable to plots smaller than 1500 sq. mts. As can be
seen from DCR 23 (1) (a), it speaks of a lay-out or sub-division of ‘vacant
land’ and open spaces. The open spaces ‘shall as far as possible’ be
provided in one place. If a lay-out or sub-division is more than 5000 sq.
mts., open space can be provided in more than one place, but at least one
such place ‘shall be of not less than 1000 sq. mts.’. These provisions
clearly show that they are mandatory. Besides under sub-clause (f) of DCR
23 there is a requirement of keeping the recreational open space
permanently open to the sky and trees are to be grown in that space as laid
down, i.e. five trees per hundred square meters of the recreational space
within the plot. DCR 2 (64) defines ‘open space’ to mean an area forming
an integral part of a site left open to the sky. A ‘site’ is defined under
DCR 2 (83) to mean a parcel or piece of land enclosed by definite
boundaries. These DCR’s when read together, very much make it clear that
the recreational /amenity space has to be on the land i.e. on ground level
and it has got to be 15%, 20% or 25% of the area depending upon its size.
As rightly pointed out by learned senior counsel Mr. Nariman and Mr.
Salve, the requirement of recreational space on the podium under DCR 38
(34) (iv) is discretionary. Besides, as the above referred clause (iii)
lays down, podium shall be basically used for parking. Besides Clause (iv)
does not contain a non-obstante clause to over-ride the requirement under
DCR 23 making it mandatory to provide recreational space on the ground-
floor. That being so, the provision under DCR 38 (34) cannot be read in
derogation of the requirement under DCR 23 or else it will result into
serious erosion in the basic requirements for a good life affecting the
guarantee of right to life, under Article 21 of the Constitution of India.
We have therefore to read down clause (iv) of the DCR 38(34) as
inapplicable and not excluding the mandatory provision under DCR 23.
26. It is also relevant to note that the development schemes under
DCRs 33(7), 33(9) and 33(10) provide for lesser Recreational area / Amenity
spaces. Thus, under DCR 33(7) and 33(10) reduction in the Amenity open
space is permitted to make the project viable, but still minimum 8 percent
of the project area is required to be maintained as Amenity open space.
Similarly, for the schemes under DCR 33(9) minimum 10 percent of the plot
area is required to be retained as Recreational space. In other properties,
where there are no such constraints to make the development schemes of
rehabilitation or reconstruction of old buildings or slums viable, there is
no reason why the Amenity open space at the ground level should be read as
permissible, to be reduced. The only ground being given is to provide more
parking and more accommodation, meaning thereby more construction,
concretization and financial expediency. Such a purpose cannot be read
into the provisions as they presently exist, nor is it desirable to do so
from the point of view of the requirement of minimum open spaces at the
ground level.
27. Besides, as pointed out by Mr. Divan, the requirement of having
trees and open land around them is necessary from an environmental point of
view, since there is already excessive concretization, and a very serious
reduction in open spaces at the ground level. It must be noted that the
right to a clean and healthy environment is within the ambit of Article
21, as has been noted in Court on its Own Motion v. Union of India reported
in 2012 (12) SCALE 307 in the following words:-
“The scheme under the Indian Constitution unambiguously
enshrines in itself the right of a citizen to life under Article
21 of the Constitution. The right to life is a right to live
with dignity, safety and in a clean environment.”
The right to a clean and pollution free environment, is also a right under
our common-law jurisprudence, as has been held by this Court in Vellore
Citizen’s Welfare Forum v. Union of India and Ors reported in (1996)5SCC647
where this Court held:-
“The Constitutional and statutory provisions protect a
persons right to fresh air, clean water and pollution free
environment, but the source of the right is the inalienable
common law right of a clean environment.”
In the same judgment the Court emphasized the importance of Sustainable
Development, and the need for a balance between development and ecological
considerations, in the following words:-
“The traditional concept that development and ecology are
opposed to each other, is no longer acceptable….
‘Sustainable Development’ is the answer…Sustainable
Development as defined by the Brundtland Report means
"development that meets the needs of the present without
compromising the ability of the future generations to meet their
own needs". We have no hesitation in holding that "Sustainable
Development' as a balancing concept between ecology and
development has been accepted as a part of the Customary
International Law though its salient features have yet to be
finalised by the International Law jurists.”
28. Therefore, after reflecting upon the legal position, we are
clearly of the opinion that having 15%, 20% or 25% of the area (depending
upon the size of the lay-out) as the recreational/amenity area at the
ground level is a minimum requirement, and it will have to be read as such.
We therefore, answer the issue no. 1 by holding that it is not permissible
to reduce the minimum recreational area provided under DCR 23 by relying
upon DCR 38(34). However, if the developers wish to provide recreational
area on the podium, over and above the minimum area mandated by DCR 23 at
the ground level, they can certainly provide such additional recreational
area.
Issue No.4 with respect to the protection against the fire hazards:-
29. As stated earlier, this issue was decided to be gone into
considering that the main building in the present complex is going to be of
48 storeys. This issue was decided to be gone into also in the backdrop of
the recent fire that engulfed the six storey Secretariat building of
Maharashtra, in Mumbai. It took a few days to extinguish the fire which
resulted into a loss of lives. This Court sought the affidavit of the Chief
Fire Officer of the appellant-Municipal Corporation on this issue. Shri
Suhas Vishnu Joshi, Chief Fire Officer, Mumbai Fire Brigade, has affirmed
his reply on 15.9.2013. In paragraph 3 of his affidavit, he has stated
that the Fire Brigade of the appellant-Municipal Corporation has got
special appliances such as Aerial Ladder Platform which can reach up to the
height of 70 meters, and the department is in the process of procuring
special appliances which can reach up to the height of 90 meters. In
paragraph 4, he has accepted that in high-rise buildings above 90 meters,
the fire-fighting operations cannot be carried out from outside the
building alone. They are also to be fought from inside the building with
the help of fire safety and protection measures / installations provided in
the high-rise buildings as per the building by-laws. He has pointed out
the passive safety measures as well as active fire safety measures
necessary for the high-rise buildings in his affidavit. Amongst the fire
safety measures, he has pointed out that the width of the access road and
the open space for maneuverability of fire appliances has to be adequate.
30. It is also pointed out in this affidavit that there is a State
Act known as Maharashtra Fire Prevention and Life Safety Measures Act, 2006
under which the developers / society in-charge of the building have to
maintain the fire prevention and life safety measures in good repair and
efficient condition at all times. In paragraph 7 of his affidavit he has
stated that for any high-rise and special type building, No Objection
Certificate from the Chief Fire Officer is required at two stages viz.
prior to the construction of the building and after the compliance of the
requirement. Besides, for buildings having a height above 70 meters, there
is a High Rise Technical Committee under the Chairmanship of a retired
Hon’ble High Court Judge with other experts and the proposal for high rise
buildings has to be cleared by this committee.
31. As far as the maneuverability of the fire appliances is
concerned, fire protection requirements under DCR 43 become relevant. This
DCR 43 is split in two parts (1) General and (2) Exits for every building.
It reads as follows:-
“43. Fire Protection Requirements:-
(1) General:—The planning design and construction of any
building shall be such as to ensure safety from fire. For thi s
purpose, unless otherwise specified in these Regulations, the
provisions of Part-IV; Fire Protection Chapter. National
Building Code shall apply. For multi-storeyed, high rise and
special buildings, additional provisions relating to fire
protection contained in Appendix VIII shall also apply-
(A) For proposal under regulations 33(7) and 33(10), in case of
rehabilitation/composite buildings on plots exceeding 600 sq.
mts. and having height more than 24 m. at least, one side other
than road side shall have clear open space of 6 m. at ground
level, accessible from road side.
Provided, if the building abuts another road of 6 m. or
more this condition shall not be insisted.
Provided further that in case of redevelopment proposals
under DCR 33(7), for plot size upto 600 sq. mt., 1.5 mts open
space will be deemed to be adequate.
(B) For the proposals other than (A) above
(a) Building having height more than 24 m. upto 70 m. at
least one side, accessible from road side, shall have clear open
space of 9 m. at ground level.
Provided however, if podium is proposed it shall not extend
3 m. beyond building so as to have clear open space of 6m.
beyond podium.
Provided further, where podium is accessible, to fire
appliances by a ramp, then above restriction shall not apply.
(b) Buildings having height more than 70 m. at least two
sides accessible from road side, shall have clear open space of
9m. at ground level.
Provided however ramps if podium is proposed it shall not
extend 3m. beyond building line so as to have clear open space
6m. beyond podium. No ramps for the podium shall be provided in
these side open spaces.
Provided further, where podium is accessible to fire
appliances by a ramp then above restriction shall not apply.
(c) Courtyard/ramp podium accessible to fire appliances
shall be capable of taking the load upto 48 tonnes.
(d) These open spaces shall be free from any obstruction
and shall be motorable.
(2) Exits:—Every building meant for human occupancy shall be
provided with exits sufficient to permit safe escape of its
occupants in case of fire or other emergency for which the exits
shall conform to the followings :—
(i) Types:—Exits should be horizontal or vertical. A
horizontal exit may be a door-way, a corridor, a passage-way to
an internal or external stairway or to an adjoining building, a
ramp, a verandah, or a terrace which has access to the street or
to the roof of a building. A vertical exit may be a staircase or
a ramp, but not a lift.
(ii) General requirements.—Exits from all the parts of the
building, except those not accessible for general public use,
shall—
(a) provide continuous egress to the exterior of the
building or to an exterior open space leading to the street;
(b) be so arranged that, except in a residential building,
they can be reached without having to cross another occupied
unit;
(c) be free of obstruction;
(d) be adequately illuminated;
(e) be clearly visible, with the routes reaching them
clearly marked and signs posted to guide any person to the floor
concerned;
(f) be fitted, if necessary, with fire fighting equipment
suitably located but not as to obstruct the passage, clearly
marked and with its location clearly indicated on both sides of
the exit way;
(g) be fitted with a fire alarm device, if it is either a
multi-storeyed, high-use or a special building so as to ensure
its prompt evacuation;
(h) remain unaffected by any alteration of any part of the
building so far as their number, width, capacity and protection
thereof is concerned;
(i) be so located that the travel distance on the floor
does not exceed the following limits :—
(i) Residential, educational, institutional and hazardous
occupancies: 22.5 m.
(ii) Assembly, business, mercantile, industrial and storage
buildings: 30 m.
Note:—The travel distance to an exit from the dead end of a
corridor shall not exceed half the distance specified above.
When more than one exit is required on a floor, the exits shall
be as remote from each other as possible:
Provided that subject to the provision under D.C.
Regulation 44(5) (a) for all multi-storeyed high rise and
special buildings, a minimum of two enclosed type staircases
shall be provided, at least one of them opening directly to the
exterior to an interior, open space or to any open place of
safety.
(iii) Number and width of Exits:—The width of an exit,
stairway/corridor and exit door to be provided at each floor in
occupancies of various types shall be as shown in columns 3 and
5 of Table 21 hereunder. Their number shall be calculated by
applying to every 100 sq.m. of the plinth or covered area of the
occupancy, the relevant multiplier in columns 4 and 6 of the
said Table, fractions being rounded off upward to the nearest
whole number.”
32. Now, what is seen here is that under Clause 1 (B) of DCR 43,
for buildings having heights of more than 24 meters up to 70 meters, at
least one side accessible from road side shall have clear open space of 9
meters at ground level. For buildings which have a height of more 70
meters, at least two sides accessible from road sides, shall have a clear
open space of 9 meters at ground level. In both these cases where podium
is proposed, it shall not extend 3 meters beyond the building line so as to
leave clear open space of 6 meters beyond podium. Similarly Clause 1 (A)
lays down that in case of the proposals under DCR 33(7) (which are for the
cessed building) and those under 33(10) (which are for the slum
rehabilitation), if the plot of the building exceeds 600 sq. mts. and the
building is having height of more than 24 meters, at least one side other
than the road side shall have a clear open space of 6 meters at ground
level accessible from the road side. The first proviso to Clause 1 (A)
makes an exception if the building abuts another road of 6 meters or more.
In that case this condition is not insisted. Thus, as can be seen, a
minimum access of 6 meters to every building from two sides is insisted,
i.e. from a road side and from one side within the property, or from two
road sides so that the fire engine can approach the building at least from
two sides. The second proviso under Clause 1 (A) however states that if
the redevelopment proposal is under DCR 33(7) i.e. for reconstruction or
redevelopment of cessed buildings on plots of size upto 600 sq. mts., only
1.5 meters side open space will be deemed to be adequate. This will mean a
space of just about 5 feet or so, through which a fire engine can certainly
not enter.
33. We asked Mr. R.P. Bhatt, learned Senior Counsel appearing for
the Municipal Corporation as to what would be the height of these buildings
on plots upto 600 sq. mts., and his answer was that it will depend on the
number of flats for the families to be accommodated in such buildings, and
it may as well go up to 20 floors. Mr. Ganesh, learned Senior Counsel
appearing for the Maharashtra Chamber of Housing Industry defended the
existing provision on the ground of economic viability of such projects,
and submitted that for such projects under DCR 33(7), the side space inside
the property will have to be reduced on that count. He submitted that some
of these plots are very small and are in congested areas, and that these
redevelopment schemes are carried out by private developers. Additional
construction is required to be carried out to provide minimum accommodation
to the existing occupants as well as for the newly entering occupants who
pay higher amounts to buy the additional flats. He referred to and relied
upon a judgment of a bench of two judges of this Court in Jayant Achyut
Sathe Vs. Joseph Bain D’souza & Ors. reported in 2008 (13) SCC 547 wherein
the challenge to the 1.5 m. open space (i.e. about 5 feet) in the schemes
under DCR 33 (7) came to be rejected.
34. (i) On the other hand, Mr. Nariman pointed out that although the
ladders / snorkels which the fire department are supposed to go up to the
height of 70 meters, the maximum reach of the snorkel depends on various
factors such as wind velocity, availability of space, and tilt and angle of
the approach. Thus, the reach is always less than the theoretical maximum
height. Besides, there are 33 Fire Brigade Stations in Greater Mumbai, 15
in the city, 12 in Western Suburbs and 6 in Eastern Suburbs. None of these
stations have sufficient equipments (snorkels) in their stations since they
are in limited numbers.
(ii) It was also pointed out by Mr. Nariman that as far as the internal
arrangement in the multi-storey buildings is concerned, a refuge floor is
required to be provided above every 7 floors for buildings crossing the
height of 24 meters. However, these refuge floors are very often not
properly maintained, are not kept vacant, and are used for other purposes.
The consequence is that the effectiveness of the fire protection from
within the building remains in peril. He further pointed out that the Fire
Brigade is supposed to check installations such as sprinklers and other
fire-fighting equipments as provided under Appendix VIII inside the
buildings periodically, but the department is understandably over-worked,
and therefore not in a position to effectively cover all the buildings in
the city.
35. Mr. Shyam Divan, learned Senior Counsel appearing for the UDRI
pointed out that the present fire protection requirements contained in DCR
43(1) if strictly complied with, could be considered as adequate for mid-
rise buildings and structures up to 13 storeys. However, when it comes to
the high-rise buildings, the fire safety requirements are primarily
compromised by relaxation in the access under DCR 17 and the side open /
setback spaces between the buildings under DCR 28. He submitted that the
provision contained in the second proviso of DCR 43(1)(A) could not be
justified.
36. As far as the schemes under DCR 33(7) are concerned, Mr. Shyam
Divan, learned Senior Counsel appearing for the UDRI has pointed out that
there is already a criticism with respect to these schemes viz. that they
are working more for the developers and for the private new entrants who
buy the flats at higher costs, than for providing the accommodation to the
existing occupants. The State Government is also raising its hands on the
ground of financial difficulties to take up such schemes. Consequently,
the inability of fire engines to go into such plots, and thereby
permanently denying the occupants adequate fire protection is not the
concern of either of them. Protection of the environment and human life
are constitutional mandates, and even if the developers and the public
authorities choose to ignore these essentials, this Court cannot.
Adequate access for the fire-engines as an essential requirement:-
37. Having noted the submissions of all the counsel in this behalf,
what we find is that whereas the provisions for the mid-rise buildings up
to 13 floors are somewhat adequate, those beyond are required to be
strictly implemented from within as well. The provisions for the refuge
floor and various requirements from within have to be strictly scrutinized
and insisted upon. That apart the second proviso to DCR 43(1)(A) cannot
stand scrutiny of minimum safety requirement. If the access of 6 meters is
required from at least one side within the property for the fire engine to
enter and move inside, we fail to see as to how in redevelopment proposals
under DCR 33(7) where the plot size is up to 600 sq. mts., open space of
1.5 meters, can be said to be adequate. As fairly pointed out by Mr.
Bhatt, the buildings on such plots can also go up to 20 floors, depending
upon the number of flats for the occupants to be provided for. If that is
so, it is necessary to have an open space of the width of 6 meters within
the property for the fire engine to enter the property at least from one
side which is so provided for every other building.
38. It is true that in Jayant Achyut Sathe (supra) the challenge to
the five feet open space in the schemes under DCR 33(7), came to be
rejected. However, as can be seen from paragraph 49 of the judgment, it
was principally rejected on the ground that the challenge was hopelessly
delayed since this provision restricting the open spaces in these schemes
had been in existence since 1984. The question of fire engines not being
able to go inside such plots, was raised in the Bombay High Court, but this
Court has not gone into that aspect in the said judgment. We are looking
into the issue of the side space on the backdrop of the failure of the fire
brigade to quickly extinguish the fire even in the six storeyed
Secretariate building in Mumbai, which has sufficient side spaces on all
sides. Not providing a minimum space of 6 meters which makes room for the
fire-engine to access the building amounts to violation of the right to
life and equality of the residents of these buildings, by not providing the
same standard of safety to them which is available to residents of all
other buildings. It is true that some of these plots under the DCR 33(7)
schemes are small plots and are in congested areas. But if that is so,
nothing prevents the State Government from taking over such schemes for
which it can finance from the overall cess collection. In such cases, it
may have to accommodate only the existing occupants. This can also be
achieved by calling upon such occupants to partly contribute towards the
construction cost. But human life cannot be made to suffer only on the
ground that in the redevelopment scheme sufficient access cannot be
provided for the fire engine to enter within the plot even from one side.
39. We are, therefore, of the view that the second proviso to DCR
43(1)(A) is discriminatory as against the occupants of the plots up to the
size of 600 sq. mts. and therefore violative of Article 14 of the
Constitution of India. The provision is likely to lead to a hazardous
situation, affecting the life of the occupants, and therefore violative of
Article 21 of the Constitution. We, therefore, hold the provision to be
bad in law. If the fire is to be extinguished at the earliest the fire-
engine must be able to reach the spot of fire, without any delay.
Maneuverability of the fire engine is, therefore, of utmost importance. As
such, most of the city roads are very narrow. On top of that if there is no
adequate space for the fire engine to enter the property, the situation
will become worse. We are clearly of the view that even for redevelopment
proposals of plots up to the size of 600 sq. mts. under DCR 33(7), an open
space of the width of 6 meters within the property which is accessible from
the road on one side, will have to be maintained unless the building abuts
roads of 6 meters or more on two sides, or another appropriate access of 6
meters to the building is available apart from the abutting road. This
will be subject to the decision of the Chief Fire Officer in writing.
Besides, we also feel that it is necessary to direct that the fire
department must insist from the developer/society of all the buildings, to
certify at least once in six months that the access to the building, the
internal exits and the internal fire fighting arrangements are maintained
as per the expectations under the DCR, the norms of the fire department,
and must check them periodically, on its own.
The decision on Issues no. 1 and 4 to apply prospectively:-
40. Although, for the reasons stated above, we are of the view that
the provision under DCR 38 (34) cannot be read in derogation to the one
under DCR 23 with respect to the recreational area, and also that the
second proviso to DCR 43 (1) (A) on fire protection requirements is
hazardous and discriminatory against the occupants of the schemes under DCR
33 (7), we do note the submission by the intervening Practicing Engineers,
Architects, and Town Planners Association that any such declaration/
changes be implemented with prospective effect, namely, where the
commencement certificate (CC) has yet not been granted.
Issue No.2 regarding height of the buildings vis-à-vis the width of the
adjoining road, and Issue No.3 on the impact of additional FSI on the
traffic situation:-
41. As far as the issues no.2 and 3 are concerned, though they are,
in a way, independent issues, they are inter-related also, and therefore,
we will deal with them together. These are issues requiring wider
consideration and consultation amongst planners, and as far as these issues
are concerned, this Court will confine itself to making certain
recommendations for consideration of the planners. This is because this
Court is conscious of the fact that the new development plan for the city
of Mumbai is in the process of being drafted. It is for the planners to
examine these issues. However, since these issues have arisen in the
context of the present matter, this Court has invited the response from the
appellant-Municipal Corporation as well as the State Government. The
concerned interveners have also made their submissions. We shall look into
the submissions in this behalf and make certain suggestions for
consideration in the light thereof.
Issue No. 2-Height of buildings, vis-à-vis width of the roads:-
42. DCR 31 (1) lays down that the height of a building shall not
exceed one and a half times the total of the width of the street on which
it abuts. Issue No. 2 is framed in the backdrop of the fact that in the
present case, a tower of the height of 195.90 meters is being constructed.
This tower is bounded by four roads and the height of the tower is
disproportionately high, as against the width of the adjoining roads. The
first proviso to DCR 31(1) lays down that this restriction shall not be
applicable for construction of buildings undertaken under DCR section
33(7), 33(8) and 33(9). Though, these DCR’s are for the housing re-
development schemes they also add to the population in the particular area
as well as the vehicles. It is from this point of view that the question
has been framed as to whether these exemptions are justified, valid or
legal? DCR 31(1) reads as follows:-
“31. Height of Buildings
(1) Height vis-à-vis the road width.- The height of a building
shall not exceed one and a half times the road of the width of
the street on which it abuts and the required front open space.
The restrictions of height of the building spelt out in
Regulation No. 31(1) shall however, cease to apply in case where
the plot front on road having with more than 18.00 mtrs. And
where front marginal open space of 12 mtrs. Minimum is observed,
provided that open spaces on other sides are made available as
required from the fire safety point of view. For this purpose,
the width of the street may be the prescribed width of the
street, provided the height of the building does not exceed
twice the sum of the width of the existing street and the width
of the prescribed and required open space between the existing
street and the building. The latter width shall be calculated
by dividing the area of land between the street and the building
by the length of the front face of the building.
Explanations-
(i)”Prescribed width” here means the width prescribed in the
development plan or the width resulting from the prescription of
a regular line of the street under the Bombay Municipal
Corporation Act, 1888, whichever is larger.
(ii) If a building abuts two or more streets of different
widths, it shall be deemed for that purpose of this Regulation
to abut the wider street; the height of the building shall be
regulated by the width of that street and may be continued to
this height to a depth of 24m. along the narrower street,
subject to conformity with Regulation 28:
[Provided however, that restrictions on height spelt out in this
regulation shall not be applicable for reconstruction and
redevelopment of old buildings undertaken under Regulation
33(7), 33(8) and 33(9) of these Regulations, which are not
affected by Coastal Regulation Zone Notification dated 19th
February, 1991, issued by the Ministry of Environment and
Forests, Government of India, and orders issued from time to
time.
[Provided however that restrictions on height spelt out in this
Regulation shall not be applicable for construction of buildings
undertaken under regulation 33(10) and 33(14) of these
regulations for implementation of Slum Rehabilitation Scheme.]”
43. As far as this issue is concerned, response was sought from the
Secretary, Urban Development Department, of State of Maharashtra, and the
Chief Engineer Town Planning of the appellant. Shri Manu Kumar Srivastava,
Principal Secretary, Urban Development Department, Government of
Maharashtra has explained these exemptions in his affidavit. He has
pointed out that these schemes under DCR 33(7), 33(8) and 33(9) seek to
achieve free of cost in-situ-rehabilitation of the occupants living in old
and dilapidated buildings. Therefore, to make the scheme viable, incentive
FSI is granted, which the developer uses to construct what is called as a
‘sale component’ that is sold in the open market to recover the cost
incurred by him for constructing the tenements for rehabilitation of the
existing tenants. Therefore, the restriction on the height of these
buildings vis-à-vis the width of the road, is required to be relaxed.
44. Shri Rajiv Kuknur, Chief Engineer, Development (Development
Plan) in his affidavit on this issue on behalf of the appellants,
reiterated that the exemptions under these DCRs are for accommodating
existing tenants which is done with the participation of private
developers. Mr. Ganesh, appearing for the Maharashtra Chamber of Housing
Industry, has similarly justified granting higher FSI and construction of
the high-rise buildings on that footing.
45. The State Government was represented by learned Senior Counsel,
Mr. Shekhar Naphade. He pointed that the city was suffering from some basic
constraints viz. on the one hand, the population was increasing,
particularly in the suburbs, and on the other hand, the land resources
were very limited. There was also the floating population moving from the
northern suburbs to the city everyday and returning back by the evening.
He submitted that one has to take into consideration the practical
realities. At the time when the development plan was prepared in 1991, the
appellant-Municipal Corporation found that it could not acquire land for
various public projects such as gardens and playgrounds and therefore, the
concept of Transferred Development Rights (TDR) was introduced, whereunder
the land owner surrenders the land required for gardens or playgrounds and
gets the TDR in lieu thereof. He pointed out that the population density
in Mumbai was very high. It was 270 persons per hectare as against 106 of
New York, 83 of Singapore and 64 of Hongkong. The Corporation had to
adjust the competing interests and therefore, at appropriate places the
high-rise buildings had to be permitted.
46. Mr. Shyam Divan, on the other hand, submitted that these tall
structures have affected access to natural light and ventilation and has
created number of health problems. In his submission, there should not be
a blanket exemption for projects involving additional FSI from the height
restrictions under DCR 31. There should be accountability on the part of
the authority and the project developer to whom relaxation is granted. He
submitted that some of these buildings which were reconstructed with high
FSI under DCR 33(7), (8) and (9), had been reduced to vertical slums. The
developers do not bother to look into the maintenance of these schemes, the
construction is poor and a large number of the occupants for whom these
houses are constructed, sell them and the purpose of having the scheme,
gets defeated.
Issue No.3 concerning impact of FSI on the traffic situation:-
47. As far as issue No. 3 viz. impact of FSI on the traffic
situation is concerned, Shri Manu Kumar Srivastava, has pointed that as per
the census of 2011, 30.82 lakhs people were staying in the island city.
Due to the accelerated economic growth, there is a spurt in the vehicles of
the occupants, as well as, those entering the island city. In para 6.3, he
has placed on record the steps taken by the State Government in this
behalf. This paragraph 6.3 reads as follows:-
“6.3 ….
i) Revising the captive parking requirements upwards for
various categories of buildings.
ii) Introducing instruments like Regulation 33(24) for
creating public parking lots.
iii) Taking up construction of mass rapid transit systems
like Metro Rail, Mono Rail etc. so as to wean people
away from the use of personalized means of
transport.”
In para 6.4 he has referred to the suggestions made by a High- Powered
Committee regarding traffic management and that steps were being taken
according to those recommendations. In para 7 of his affidavit, he has
stated that the draft development plan for the period 2014-2034 is under
preparation, wherein many of these difficulties will be taken care of.
48. Shri R.C. Dixit, Chief Engineer, Roads and Traffic of the
appellant-Municipal Corporation has filed his affidavit on issue No. 3. He
has pointed out that the number of vehicles in Greater Mumbai has increased
from 3.08 lakhs from 1981 to 19.38 lakhs in 2011, and the population has
increased during this period from 82.43 lakhs to 124.78 lakhs. Out of
this population, that of the island city is 31.06 lakhs. He has pointed
out in paragraph 16 of his affidavit that the State Government has
constituted a High Powered Committee on 6.6.2012 to suggest corrective and
remedial measures. It has also to prepare an action plan for
recommendations up to 2016-2017. In paragraph 18, he has referred to
various recommendations made by the High Powered Committee and that the
same are being followed.
49. Shri Vivek Phansalkar, Commissioner of Police, Traffic, Mumbai,
has stated in paragraph 9 of his reply that as per information of the State
Transport Department, on an average 450 new vehicles were being added to
the road network every day. The vehicular population by January 2013 was
nearly 21 lakhs. He has stated that Mumbai continues to have a high usage
of public transport, yet there is a relatively sharp increase in use of
cars in the last decade which has pushed Mumbai into a situation of a grid
lock. Increasing vehicles on the roads have led to bottlenecks for traffic
movement. In paragraph 13 he has stated that no definite findings can be
arrived at without a comprehensive study of the impact of additional FSI in
the island city of Mumbai on traffic density. He has however, accepted
that periodical increase in FSI would result in more construction which, in
turn, could lead to the higher tenement density, indicating an increase in
traffic. In paragraph 14, he has suggested various measures to control the
traffic congestion.
50. The UDRI has made various suggestions. Its trustees include
Mr. Charles Correa, an eminent architect and town planner, Shri Dipak
Parekh an eminent economist, Shri D.M. Sukhtankar, retired Municipal
Commissioner and former Secretary to Government of Maharashtra and others.
This institute has made a detailed study of the problems of the city. With
respect to issue No. 2, this institute has submitted as noted above, that
there should not be a blanket relaxation for the high rise buildings, and
it should be examined locality-wise. Absence of any check in this behalf,
has resulted into very tall buildings with no open spaces on extremely
narrow streets. It is often seen that whereas the ordinary FSI is 1.33,
the minimum FSI available to the schemes under DCR 33(7), 33(8) and 33(9)
is 2.5, and there is no upper limit. No assessment is made of the
sustainable carrying capacity of the areas in which these projects are
implemented. There is no transport impact assessment on the neighbourhood
in such projects. A locality-wise approach is therefore required.
51. In its submissions on the issues at hand, UDRI pointed out that
whereas the total open space in Mumbai is 3.8%, if we compare it with
another crowded area viz. Manhattan in US, there the public open space for
recreation is 13.1%. The National Building Code (of India) requires 3 sq.
mts. per capita by way of open space. However, Greater Mumbai has just 1.91
sq. mts. of open space per person, and of this less than 0.88 sq. mts. per
person is accessible for recreation. Each Manhattan resident occupies 11
times as much floor space as a Mumbai resident. Doubling or trebling
Mumbai’s FSI will only make it two or three times denser than Manhattan in
regard to the number of people on the ground. Consequently, the open space
available per person will become even less.
52. Since the project of respondent-Kohinoor is going to be at a
busy road junction near Shivaji Park in the Dadar area of Mumbai, it is
pointed out by UDRI that Dadar, Mahim, and Matunga areas, are essentially
residential areas. Various housing colonies were laid out, as per the town
planning scheme, such as Dadar Parsi Colony and Hindu Colony etc. In fact,
Mr. Divan pointed out that the entire area around Shivaji Park was laid out
systematically as per the norms, for a specified population, and it is like
a heritage area. Requisite provisions for gardens, schools, roads, foot-
paths and play-grounds etc., have been made for a certain density of
population. Now with the reconstruction schemes being proposed, suddenly
tall buildings are coming up even near the school buildings, and adding
further to the density and pressure on the existing infrastructure. The
roads having been laid out much earlier, and being in proper proportion to
the height of the adjoining buildings, these new tall buildings coming up
in the very area are causing congestion and greater traffic. This is
affecting the life of the people around and even the school going children,
with increased traffic and parking on the roads. The roads which were
adequate at one point of time, are now being found to be narrow. Plot
No.46, with which we are concerned, in the present matter, had a textile
mill earlier, and now a huge commercial complex has been approved on it.
But for this construction, there were no such large commercial complexes in
this entire area. Earlier only those commercial activities were permitted
which were necessary for the use of the residents. This huge commercial
complex is going to add tremendous pressure on the traffic in the area and
at an already busy junction.
Suggestions on issue Nos. 3 and 4 for consideration when the new
Development Plan is drafted:-
53. We have noted the submissions on both these issues, and what we
find is that the exemptions from DCR 31 (1) for schemes under Section
33(7), 33(8) and 33(9), though apparently meant for laudable purpose, are
very often resulting into extreme crowding, and traffic congestion. It is
necessary that while granting exemptions from DCR 31(1), there must be a
scheme-wise approach, and there ought to be a proper supervision of the
construction. These development schemes and the additional FSI thereunder,
should be examined locality-wise. The impact of such high-rise buildings
on the adjoining locality as well as on the traffic, is required to be
examined before granting such permission.
54. In our view, there is a need to restrict the additional
pressure on existing infrastructure so that it does not affect the quality
of life. The existing social infrastructure like educational institutions,
open spaces, hospitals etc, and physical infrastructure like water supply
and drainage is already over-burdened. Therefore, wherever possible, the
State Government, the planning authority, and the committee entrusted with
drafting of the new plan should consider contribution by the existing
occupants themselves to a good extent towards the construction cost, or the
State should contribute through its agencies or from the amount of cess-
collected. This will result into curtailing the number of additional
entrants and will not add to the density of the population. This approach
should particularly be examined where the plots are small or are in
congested areas, and particularly where the proposal is under DCR 33(7).
The new Development Plan is to be prepared shortly, and while preparing the
plan these aspects concerning restrictions on blanket exemptions,
contribution by the existing occupants to the reconstruction schemes,
locality-wise consideration and impact of additional FSI on traffic, ought
to be gone into. In areas where the old town planning schemes have
prescribed a uniform lay-out, one can accept some buildings going up to a
certain extent, if necessary, to accommodate the existing occupants in a
reconstruction scheme. However, it should not result into a plethora of
steeply rising buildings, to accommodate outsiders to the building, adding
to the population and traffic, and disturbing the existing order of the lay-
out completely.
Reconstitution of the ‘Technical Committee for High Rise Buildings’:-
55. (i) It has been pointed out on behalf of the Municipal Corporation
that subsequent to a PIL in the Bombay High Court in the case of Tardeo
Haji Ali Residents Welfare Association, the State Government has
constituted a ‘Technical Committee for High-Rise Buildings’ (i.e. Buildings
exceeding 70 meters in height). As per the note submitted by the learned
Senior Counsel for the Municipal Corporation, the terms of reference of the
committee are as follows:-
“(1) The Committee shall be of advisory nature and it will
advise the Municipal Commissioner regarding the feasibility
of the development proposals that might be referred to it
by the Commissioner.
(2) It will be open for the Commissioner to over-rule the
recommendations of the Committee, after giving a proper and
reasonable justification in writing. Such powers will not
be delegated to any subordinate officer.
(3) In specific cases, if the Chairman desires, any expert
from other fields may be invited for the meeting of the
Committee.”
The note points out
1) The building proposals which are to be referred to the
committee
2) The procedure to be followed by the committee
3) The points to be considered by the committee, viz.,
a) Architectural Points:-
1) Clear width of access available.
2) Location, width & No. of staircase.
3) Natural ventilation to staircase and common lobby.
4) Whether benefit of D.C. Rule 33 (24) is availed?
5) The minimum net plot size for High Rise proposal is
prescribed as 1000 Sq.Mt. and 850 Sq.Mts. for
proposals under D.C. R. 33 (7).
6) Depth & Nos. of the basement.
7) Area & location of the refuge floors.
8) Open spaces, podiums, etc.
9) Two wheeler & four wheeler parking provisions in the
building.
10) Width of common lobby & ventilation.
b) Structural and Geotechnical Points:-
1) Soil Report indicating soil strata, depth of the hard
rock, etc.
2) Type of foundation i.e. pile foundation or raft
foundation or open foundation.
3) Design Base Report (D.B.R.) for the proposal.
4) Various type of tests carried on site i.e. wind
tunnel test.
5) Gust factor & deflection.
6) Details of the rock anchors, if any provided for
basement.
7) Details of the soil retaining methods.
c) Environmental Points:-
1) Shadow Analysis.
2) Wind Analysis.
3) Heat Analysis.
4) Traffic Study & Traffic Management.
5) Ecological Study (Tree Plantation, Green area, etc.)
6) Disaster Management Plan.
7) Total Water Requirement.
8) Total waste water sewage generated & disposal (Design
of Sewerage Treatment Plant).
9) Effect of the construction material on environment.
10) Rain Water Harvesting & Storm Water Management.
11) Air environment in construction & operation phase.
12) Solid Waste Management.
13) Energy conservation techniques.
d) The point of view of the C.F.O.:-
1) Height of first refuge floor from ground floor and
also height of subsequent refuge floors.
2) Location of refuge area.
3) Whether refuge area is cantilever.
4) Clear open space along with turning radius for
movement of fire tender around the building.
5) Width & gradient of ramp (one way or two way) leading
to podium.
6) Alternate provision for fighting the fire from
ground.
7) Driveway for fire tender movement on paved R.G.
8) Height of underpass in case fire tender moving below
building.
9) Podium line should be flush with building line on
refuge facing area.
10) Number of staircase and width of staircase.
11) Distance between two staircases, through common
lobbies/passages.
12) Natural ventilation through sidewalls of basements.
13) Compartmentalization of the basements.
(ii) The first committee was appointed by a Resolution of the Urban
Development Department dated 28.7.2004. The composition of the Committee
has changed from time to time. We are informed that the term of the
existing committee, which is the third committee, has expired. The
committee consists of six members and is headed by a retired judge of the
Bombay High Court, as the Chairman. It has two ex-officio members, namely,
the Chief Engineer (Development Plan) of the appellant who is also the
member secretary, and the Chief Fire Officer of the appellant. There are
three expert members. Following are the present expert members:-
“(1) Prof R. S. Jangid, Dept of Civil Engineering, IIT Bombay,
as a Structural Engineering Expert.
(2) Prof. Abhay Bambole, Professor and Head of the Structural
Engineering Department, VJIT, Matunga, as the Soil and Geotech
Expert.
(3) Dr. Rakesh Kumar, Director and Gr. Scientist and Head NEERI
Regional Centre as the Environmental Expert.”
56. It has been suggested that we appoint a new committee, though
the State Government has expressed its willingness to extend the term of
the present committee. Mr. Nariman has, in fact, suggested that the
committee should consist of members who will play a pro-active role. Mr.
Divan submitted that it should be a Development Plan over-sight committee,
and it should at-least look into the grievances with respect to the schemes
under 33(7), (8),(9), and (10). Mr. Joaquim Reis, learned senior counsel
instructing Dr. Abhishek Singhvi, learned senior counsel appearing for the
Property Redevelopers Association, suggested inclusion of an architect in
the committee. Considering that the architectural points as mentioned in
the municipal note, are also to be gone into by the committee, the
suggestion is quite apt. He suggested the inclusion of eminent architect
Mr. Charles Correa, who is associated with UDRI (and which is represented
by Mr. Divan). We are, however, not including his name only for the reason
that we are informed that he is a very busy architect, though the committee
should certainly consult him whenever necessary. In his place, we include
Shri Pankaj Joshi, Architect, Urban Researcher, and consultant to the
appellant-Municipal Corporation, whose name is suggested by Mr. Divan.
Thus, the assistance of an architect will also be available to the
committee. Having taken the consensus of the counsel appearing in the
matter, we are effecting one more change in the committee. We appoint
Hon’ble Mr. Justice P.S. Patankar, former Judge of the Bombay High Court,
to be the Chairman of the committee.
The committee will now consist of the following:-
|1) |Chairman |Mr. Justice P.S Patankar, |
| | |Former Judge of the High Court|
| | |of Bombay |
|2) |Member Secretary |Chief Engineer (Development |
| | |Plan) of Municipal Corporation|
| | |of Greater Mumbai (MCGM) |
|3) |Member |Prof. Department of Civil |
| |(Structural |Engineering, IIT Bombay, |
| |Engineering |Pawai. (presently Professor |
| |Expert) |R.S Jangid or any other |
| | |professor, with the required |
| | |qualifications, nominated by |
| | |the Director IIT Pawai) |
|4) |Member (Soil, |Prof and Head of the |
| |Mech. Geo Tech. |Structural Engineering |
| |Expert) |Department, VJTI, Matunga. |
| | |(presently Prof. Abhay Bambole|
| | |or any other professor, with |
| | |the required qualifications, |
| | |nominated by the principal |
| | |VJTI) |
|5) |Member |Director Gr, Scientist and |
| |(Environmental |Head NEERI regional centre |
| |Expert) |(presently Dr. Rakesh Kumar) |
|6) |Ex-officio member|Chief Fire Officer of MCGM |
|7) |Member (Architect|Mr. Pankaj Joshi (Architect, |
| |and Urban |Urban Researcher, and |
| |Researcher) |Consultant to the MCGM) |
The additional terms of reference for the Committee:-
57. (i) As of now, all new building proposals where the height of the
building exceeds 70 meters is referred to the committee. A scrutiny fee
for Rs 50,000 per proposal is collected at the time of submission of the
proposal. We have already referred to the existing terms of reference. In
view of the discussion in this matter, in our view, it is desirable that
the committee be requested to look into two additional aspects which are as
follows:-
(ii) The committee will also look into the grievances regarding
construction and technical requirements of the development schemes under
DCR 33(7), 33(8), 33(9) and 33(10), whenever brought to the notice of the
committee by concerned persons.
(iii) The committee may as well make recommendations to the State
Government with respect to the new Development Plan which is under
drafting.
58. (i) The committee will have to spend good time for this work. The
honorarium paid to the chairman is presently fixed at Rs. 15000 per month,
and it was fixed much earlier. Now we are widening the terms of reference.
Therefore, we direct that the appellant-Municipal Corporation will pay an
honorarium of Rs. 50,000/- per month to the Chairman. The other members
will be provided with the conveyance charges and attendance charges to
attend the meetings and for site inspections, as per the municipal rules.
The Municipal Corporation will make available an appropriate room in its
headquarters and secretarial staff for the working of the committee.
(ii) The State Government shall issue necessary notification reconstituting
the committee, its terms of reference, and other aspects, such as
honorarium etc, within four weeks hereafter.
59. Before we conclude, we record our appreciation for all the
learned counsel who have assisted us in deciding the issues, and
particularly Senior Counsel Mr. Nariman and Mr. Salve, who appeared for the
respondents and appellants respectively, at the stage of the earlier order
which was passed on 25.7.2013, but assisted the Court in deciding the four
issues.
In the circumstances we pass the following order:-
60. (1) The memorandum of settlement dated 18.4.2013, concerning the
Public Parking Lot (PPL) arrived at between the appellant-Municipal
Corporation of Greater Mumbai and the respondents was taken on record, as
noted in Part-I order dated 25.7.2013, in the facts and circumstances of
the present case. Both the parties shall act strictly in accordance with
the same. It is clarified that as held in the said order, the Municipal
circular dated 22.6.2011 is not in any way held to be bad in law.
(2) The four additional issues framed in Part-II of the above order are
decided as follows:-
Issue No. (i) – The minimum recreational space as laid down under
Development Control Regulation (DCR) 23, cannot be reduced on the basis of
DCR 38(34). The recreational space, if any, provided on the podium as per
DCR 38(34)(iv), shall be in addition to that provided as per DCR 23.
Issue Nos. (ii) & (iii) – The Government of Maharashtra, the Development
Plan Drafting Committee, and the appellant-Municipal Corporation shall
consider the suggestions as contained in paragraph Nos.53 and 54 above,
while framing the Development Plan for Greater Mumbai.
Issue No. (iv) – The second proviso to DCR 43(1) (A), concerning fire
protection requirements, is held to be bad in law. We hold that even for
the reconstruction proposals of plots upto the size of 600 sq. mts. under
DCR 33(7), open space of the width of 6 meters at least on one side at
ground level within the plot, accessible from the road side will have to be
maintained for the maneuverability of a fire engine, unless the building
abuts two roads of 6 meters or more on two sides, or another access of 6
meters to the building is available, apart from the road abutting the
building.
(3) The decision as contained in Clauses 2(i) and 2(iv) above, will apply
to those constructions where plans are still not approved, or where the
Commencement Certificate (CC) has not yet been issued. All authorities
concerned are directed to ensure strict compliance accordingly.
(4) The Government of Maharashtra shall issue the necessary notification
within four weeks of this order, re-constituting the ‘Technical Committee
for the High-Rise Buildings’, as directed in paragraph 56, including the
additional terms of reference, as mentioned in paragraph 57 above. The
appellant is directed to render assistance and provide the required
honorarium, as mentioned in paragraph 58 above.
(5) In view of the settlement arrived at between the parties, as well as
Part-I order dated 25.7.2013 mentioned in paragraph (1), and the
determination on the four additional issues as in paragraph (2) above, no
further order is required on this appeal, and the appeal stands disposed
off accordingly.
(6) The parties will bear their own costs.
…………………………………..J.
[ H.L. Gokhale ]
……………………………………J.
[ J. Chelameswar ]
New Delhi
Dated: December 17, 2013
-----------------------
67