Thursday, August 4, 2016
exemption from public consultation/public hearing - not good = If the public consultation/public hearing results in a negative mandate against the expansion of the project, the Authorities would do well to direct and ensure scaling down of the activities to the level that was permitted by Environmental Clearance dated 20.02.2008. If public consultation/public hearing reflects in favour of the expansion of the project, Environmental Clearance dated 27.01.2010 would hold good and be fully operative. =we cannot lose sight of the fact that in pursuance of Environmental Clearance dated 27.01.2010, the expansion of the project has been undertaken and as reported by CPCB in its affidavit filed on 07.07.2014, most of the recommendations made by CPCB are complied with. In our considered view, the interest of justice would be sub-served if that part of the decision exempting public consultation/public hearing is set aside and the matter is relegated back to the concerned Authorities to effectuate public consultation/public hearing. However, since the expansion has been undertaken and the industry has been functioning, we do not deem it appropriate to order closure of the entire plant as directed by the High Court. If the public consultation/public hearing results in a negative mandate against the expansion of the project, the Authorities would do well to direct and ensure scaling down of the activities to the level that was permitted by Environmental Clearance dated 20.02.2008. If public consultation/public hearing reflects in favour of the expansion of the project, Environmental Clearance dated 27.01.2010 would hold good and be fully operative. In other words, at this length of time when the expansion has already been undertaken, in the peculiar facts of this case and in order to meet ends of justice, we deem it appropriate to change the nature of requirement of public consultation/public hearing from pre- decisional to post-decisional. The public consultation/public hearing shall be organized by the concerned authorities in three months from today.
›
Non-Reportable IN THE SUPREME COURT OF INDIA ...
Wednesday, April 3, 2013
environmental clearance= the appellant company applied and obtained ‘No Objection Certificate’ on 01.08.1994 from the Tamil Nadu Pollution Control Board (forPage 2 short ‘the TNPCB’) for setting up a copper smelter plant (for short ‘the plant’) in Melavittan village, Tuticorin. On 16.01.1995, the Ministry of Environment and Forests, Government of India, granted environmental clearance to the setting up of the plant of the appellants at Tuticorin subject to certain conditions including those laid down by the TNPCB and the Government of Tamil Nadu. On 17.05.1995, the Government of Tamil Nadu granted clearance subject to certain conditions and requested the TNPCB to issue consent to the proposed plant of the appellants. Accordingly, on 22.05.1995, the TNPCB granted its consent under Section 21 of the Air (Prevention and Control of Pollution) Act, 1981 (for short ‘the Air Act’) and under Section 25 of the Water (Prevention and Control of Pollution) Act, 1974 (for short ‘the Water Act’) to the appellants to establish the plant in the SIPCOT Industrial Complex, Melavittan village, Tuticorin Taluk.- The environmental clearance granted by the Ministry of Environment and Forests, Government of India, and the consent orders under the Air Act and the Water Act granted by the TNPCB were challenged before the Madras High Court in W.P. Nos.15501, 15502 and 15503 of 1996 by the National Trust for Clean Environment. = There is no doubt that there has been misrepresentation and suppression of material facts made in the special leave petition but to decline relief to the appellants in this case would mean closure of the plant of the appellants. The plant of the appellants contributes substantially to the copper production in India and copper is used in defence, electricity, automobile, construction and infrastructure etc. The plant of the appellants has about 1300 employees and it also provides employment to large number of people through contractors. A number of ancillary industries are also dependent on the plant. Through its various transactions, the plant generates a huge revenue to Central and State Governments in terms of excise, custom duties, income tax and VAT. It also contributes to 10% of the total cargo volume of Tuticorin port. For these considerations of public interest, we do not think it will be a proper exercise of our discretion under Article 136 of the Constitution to refuse relief on the grounds of misrepresentation and suppression of material facts in the special leave petition. - In the result, the appeals are allowed and the impugned common judgment of the High Court is set aside. The appellants, however, are directed to deposit within three months from today a compensation of Rs.100 crores with the Collector of Thoothukudi District, which will be kept in a fixed deposit in a Nationalized Bank for a minimum of five years, renewable as and when it expires, and the interest therefrom will be spent on suitable measures for improvement of the environment, including water and soil, of the vicinity of the plant of the appellants after consultation with TNPCB and approval of the Secretary, Environment, Government of Tamil Nadu. In case the Collector of Thoothukudi District, after consultation with TNPCB, finds the interest amount inadequate, he may also utilize the principal amount or part thereof for the aforesaid purpose after approval from the Secretary, Environment, Government of Tamil Nadu. By this judgment, we have only set aside the directions of the High Court in the impugned common judgment and we make it clear that this judgment will not stand in the way of the TNPCB issuing directions to the appellant-company, including a direction for closure of the plant, for the protection of environment in accordance with law. We also make it clear that the award of damages of Rs. 100 Crores by this judgment against the appellant Company for the period from 1997 to 2012 will not stand in the way of any claim for damages for the aforesaid period or any other period in a civil court or any other forum in accordance with law.
›
Page 1 Reportable IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL Nos. 2776-2783 OF 2013 (Arising out of SLP ...
›